balrampur chini mills ltd, chemical division...
TRANSCRIPT
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
1 | P a g e
UPDATED FORM – 1
SUBMISSION
TO
MINISTRY OF ENVIRONMENT & FORESTS & CLIMATE CHANGE,
NEW DELHI
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
[AMENDMENT TO ENVIRONMENTAL CLEARANCE]
VILLAGE : BISHUNAPUR
TEHSIL : BALRAMPUR
DISTRICT : BALRAMPUR
STATE : UTTAR PRADESH
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
2 | P a g e
FORM – 1
Sl.
No.
Information/ Checklist
Confirmation
Details thereof (with approximate
quantities/rates, wherever possible) with
source of information data
1 Name of the Project Balrampur Chini Mills Ltd; Chemical Division,
Distt. Balrampur (UP)- 271201
2 Project Sector Industrial Project (Industry - II)
3 Sr. No in the Schedule Schedule 5(g) under category–A of EIA
Notification dated 14th September 2006.
4 Proposed
capacity/Area/length/tonnage
to be handled/command
area/lease area/number of
wells to be drilled.
The present proposal is Amendment in EC of
160 KLPD Distillery Plant :
Increase in no. of operational days of
Distillery from 270 to 330
Amendment of Spent wash treatment
system along with energy recovery.
5 New/Expansion/Modernization The present proposal is request for
1) Increase in no. of operational days of
Distillery from 270 to 330.
2) Amendment of Spent wash treatment system
along with energy recovery.
6 Existing capacity / Area Etc EC has been accorded by MOEF to the 160
KLPD Distillery plant vide order no. J–
11011/151/2006 – IA II (I) dated June 20,
2006.
7 Category of project i.e. ‘A’ or ‘B’. A
8 Does it attract the General
condition? If yes, please specify.
NO
9 Does it attract the specific
condition? If yes, please specify
NO
10 Location
Village
Tehsil
Block
District
State
Bishunapur
Balrampur
Balrampur
Balrampur
Uttar Pradesh
11 Nearest railway station/airport
along with distance in Kms.
Railway Station: Balrampur Railway station :
2.9 km in north direction.
Airport : Gorakhpur Airport : 168.7 km in NEE
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
3 | P a g e
12 Nearest town, City, District
Headquarters along with
distance in Kms.
Balrampur : 4.1 km in North .
13 Village Panchayats,
ZillaParishad, Municipal
Corporation, Local body
(Complete postal addresses with
telephone nos to be given)
Municipal Board Balrampur
14 Name of the applicant Balrampur Chini Mills ; Chemical Division ,
Balrampur
15 Registered address Village : Bishunapur, P.O. Balrampur, Distt. :
Balrampur UP
FAX : 05263-235051
Phone No : 05263 - 235052
16
Address for correspondence Village : Bishunapur, P.O. Balrampur, Distt. :
Balrampur UP
Name Mr Jitendar Malik
Designation General manager
Address Village : Bishunapur, P.O. Balrampur, Distt. :
Balrampur UP
Pin Code 271201
E-mail [email protected]
Telephone No. +919559788888
17 Details of Alternatives sites
examined, if any. Location of
these sites should be shown on
a topo sheet.
No alternate sites are considered as the present
proposal is only request for amendment to EC
accorded vides reference cited above.
18 Interlinked Project No
19 Whether separate application of
interlinked project has been
submitted?
No
20 If yes, date of submission Not applicable
21 If no, reason Present proposal only for amendment to EC
22 Whether the proposal involves
approval/clearance under: If
yes, details of the same and
their status to be given.
The forest (Conservation)
Act, 1980.
No any
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
4 | P a g e
The wildlife (Protection)
Act, 1972
The C.R.Z. Notification,
1992
23 Whether there is any
Government Order/Policy
relevant/relation to the site
No any
24 Forest land involved
(Hectares)
No any
25 Whether there is any litigation
pending against the project
and/or land in which the
project is propose to be set
up?
Name of the Court
Case No
Orders/directions of the
court, if any and its
relevance with the
proposed project.
No any
26 Project Cost 5739.95 Lakhs (This cost for change in spent
wash treatment strategy )
(II) ACTIVITY
1. Construction, operation or decommissioning of the Project involving
actions, which will cause physical changes in the locality (topography, land
use, changes in water bodies, etc.)
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.1 Permanent or temporary change
in land use, land cover or
topography including increase
in intensity of land use (with
respect to local land use plan)
No The total land acquired for the Chemical
Division is 90.0 Acre.
The above proposal involves minor
construction activities for installation for
treatment of spent wash.
For the above unit, Environmental
Clearance was accorded by Honorable
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
5 | P a g e
Ministry vide order no. J-
11011/151/2006-IA II (I) dated 20-06-
2006.
1.2 Clearance of existing land,
vegetation and buildings?
No The proposed increase in no. of
operational days of existing Distillery
and amendment of Spent wash
treatment system does not involve any
clearance of existing land, vegetation
and buildings.
1.3 Creation of new land uses? No No other land use other than industrial
will be created in the existing plant
premises
1.4 Pre-construction investigations
e.g. bore houses, soil testing?
No As plant has already been constructed
and in operation, no such investigations
or tests are envisaged.
1.5 Construction works? Yes Only minor construction activities will
be taken up for installing new
incineration boiler.
1.6 Demolition works? No No demolition works are envisaged as
the present proposal is only request for
amendments to increase of no. of
operational days of existing Distillery &
change in spent wash treatment
technology.
1.7 Temporary sites used for
construction works or Housing
of construction workers?
No Only minor construction activities will
be taken up for installing incineration
boiler.
Hence no temporary sites for
construction workers will be
constructed.
1.8 Above ground buildings,
structures or earthworks
including linear structures, cut
and fill or excavations
Yes Additional buildings, structures or
earthworks will be involved in
installation of new incineration boiler for
spent wash treatment.
1.9 Underground works including
mining or tunneling?
No No underground works will be involved
in present proposal.
Only foundation work will be done.
1.10 Reclamation works? No No such work will be involved in present
proposal.
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
6 | P a g e
1.11 Dredging? No No such work will be involved in present
proposal.
1.12 Offshore structures? No No such work will be involved in present
proposal.
1.13 Production and manufacturing
processes?
No The process of Fermentation &
Distillation already exists and there is
no change. Only the spent wash
treatment system is proposed to be
changed.
1.14 Facilities for storage of goods or
materials?
No No additional storage of goods or
materials is envisaged.
1.15 Facilities for treatment or
disposal of solid waste or liquid
effluents?
Yes The present treatment is Bio-
methanation then RO plant followed by
Bio-composting.
Now we proposed 1280 KLPD spent
wash treatment strategy: Multiple Effect
Evaporator (MEE) and then Slop will be
burn in incineration boiler (Slop fired
travelling grate).
Due to the above proposed treatment
system we can operate distillery during
rainy season also.
In view of the above, we request
Honorable Ministry to permit us to
operate Distillery for 330 days.
The proposed treatment scheme is
enclosed as ANNEXURE– I for your kind
perusal.
1.16 Facilities for long term housing
of operational workers?
Yes The existing housing colonies of the
factory shall be utilized.
1.17 New road, rail or sea traffic
during construction or
operation?
No Already existing roads to the factory are
being utilized. No new roads envisaged
as a part of this proposed amendments.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes
and stations, ports, airports
etc?
No Already existing roads to the factory are
being utilized. No new roads envisaged
as a part of this proposed amendments.
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
7 | P a g e
1.19 Closure or diversion of existing
transport routes or
infrastructure leading to
changes in traffic movements?
No Already existing roads to the factory are
being utilized. No closure of roads or
diversion is envisaged as a part of this
proposed amendments.
1.20 New or diverted transmission
lines or pipelines?
No New or diversion of transmission lines or
pipelines is proposed as a part of this
proposed amendments.
1.21 Impoundment, damming,
culverting, realignment or other
changes to the hydrology of
watercourses or aquifers?
No No impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or aquifers is
envisaged.
1.22 Stream crossings? No Not Applicable as no stream crossings
exists in the Plant site.
1.23 Abstraction or transfers of water
form ground or surface waters?
Yes The total water requirement for the
Distillery unit is 2880 m3/day @ 18.00
KL/KL of alcohol.
Industrial Purposes : 2830 m3/day
Domestic : 50 m3/day
There will not be any increase in water
requirement. In fact the water
requirement is being reduced due to
extraction and recycle of water (MEE
condensate) from Evaporator.
1.24 Changes in water bodies or the
land surface affecting drainage
or run-off?
No There will not be any change in water
bodies or the land surface affecting
drainage or run-off due to the proposed
amendments.
1.25 Transport of personnel or
materials for construction,
operation or decommissioning?
Yes There will be slight increase in traffic
during construction activity.
There will not be increase in traffic
during operation as no capacity
enhancement is proposed.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No No dismantling or decommissioning or
restoration works are envisaged.
1.27 Ongoing activity during
decommissioning which could
have an impact on the
environment?
No No decommissioning activities are
involved as a part of this proposed
amendments
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
8 | P a g e
1.28 Influx of people to an area in
either temporarily or
permanently?
No No Influx of people to an area in either
temporarily or permanently is
anticipated
1.29 Introduction of alien species? No There will not be any introduction of
alien species
1.30 Loss of native species or genetic
diversity?
No There will not be loss of native species or
Genetic diversity.
1.31 Any other actions? No Nil
2. Use of natural resources for construction or operation of the Project
(such as land, water, materials or energy, especially any resources which
are non-renewable or in short supply)
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
2.1 Land especially undeveloped or
agricultural land (ha)
No No additional land is envisaged for the
proposed amendment of increase in no.
of operational days and change of
treatment system.
2.2 Water (expected source &
competing users) unit: KLD
Yes The total water requirement for the
existing Distillery unit is 2880 m3/day
@ 18.00 KL/KL of alcohol.
Industrial Purposes : 2830 m3/day
Domestic : 50 m3/day
The water required which is being met
from ground water for the plant.
After installation of Evaporator in Spent
wash treatment system, recycling of
waste water will be increased so that
water requirement for the plant will
further reduce.
2.3 Minerals (MT) No No usage of minerals is envisaged
2.4 Construction material – stone,
aggregates, sand / soil
(expected source – MT)
Yes Construction materials will be procured
from nearby areas
2.5 Forests and timber (source –
MT)
No -
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
9 | P a g e
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW) \
Yes Power generation : 6 MW
Power requirement: 2.5 – 3.0 MW use in
self consumption and surplus power will
be export to state power grid.
Fuel : Bagasse : 204 TPD
SLOP: 312 TPD
The power requirement increases due to
installation of MEE (Multi effect
evaporator) and Incineration boiler as a
part of Spent wash treatment system.
2.7 Any other natural resources
(use appropriate standard units)
No Nil
3. Use, storage, transport, handling or production of substances or
materials, which could be harmful to human health or the environment
or raise concerns about actual or perceived risks to human health
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health
or the environment (flora, fauna,
and water supplies) .
Yes Used oil generated is being given to
SPCB authorized recyclers.
3.2 Changes in occurrence of
disease or affect disease vectors
(e.g. insect or water borne
diseases)
No No effect envisaged
3.3 Affect the welfare of people e.g.
by changing living conditions?
Yes The existing unit enabled local villagers
to get employment and improved the
business opportunities to the locals.
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patients,
children, the elderly etc.,
No No any
3.5 Any other causes No --
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
10 | P a g e
4. Production of solid wastes during construction or operation or
decommissioning (MT/month)
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
4.1 Spoil, overburden or mine
wastes.
No Not applicable as it is a Distillery unit
4.2 Municipal waste (domestic and
or commercial wastes)
No Municipal waste generated is being
disposed to authorized Municipal
authorities.
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
Yes
Used oil is being disposed to SPCB
authorized recyclers.
Other Industrial Wastes
4.4 Surplus product No No any
4.5 Sewage sludge or other sludge
from effluent treatment.
Yes Sewage sludge is being treated in septic
tank and soak pit.
Secondary ETP sludge: 0.11 KLPD, used
as manure for horticulture purposes.
4.6 Construction and demolition
wastes
No NA
4.7 Redundant machinery or
equipment
No NA
4.8 Contaminated soil and other
materials
No NA
4.9 Contaminated soils and other
materials
No NA
4.10 Agriculture Waste No NA
4.11 Other solid waste Yes Fermenter Sludge : 40 – 45 Ton/Day
Total Fly ash generation : 59 Ton/Day
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
11 | P a g e
5. Release of pollutants or any hazardous, toxic or noxious substances to air
(Kg/hr)
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
5.1 Emissions from combustion
of fossil fuels from stationary
or mobile sources
Yes A 40 TPH slop fired Travelling grate
Boiler is proposed. Boiler operations
shall result in emissions. A 70 m stack
along with 40 TPH boiler, with ESP as
APCS. The stack shall be of RCC with
internal fire-brick lining.
The exhaust gases from the ESP will be
discharged into the atmosphere through
a stack of adequate height for effective
dispersion of gases into the atmosphere
as per CPCB norms for effective
dispersion of PM, emissions into the
atmosphere.
5.2 Emissions from production
processes
Yes PM ,NOX,SO2,CO
5.3 Emissions from materials
handling including storage or
transport
Yes Dust emissions and fugitive emissions
shall arise from material handling and
transport. The control measures shall
include concrete/asphalt road
construction, water sprinkling, tarpaulin
cover on trucks carrying materials and
covered storage yard for fuel.
5.4 Emissions from construction
activities including plant and
equipment
Yes The present proposal involves
installation of Evaporator & a new Boiler
which requires minor construction
activities.
5.5 Dust or odours from handling
of materials including
construction materials,
sewage and waste
Yes Dust shall be generated during civil
construction and movement of vehicles.
These activities shall be for a short
duration and their impact shall be
minimized by taking the following
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
12 | P a g e
measures:
Water sprinkling
Use of dust arresting panels/ sheets
Regular removal of construction
waste material
Proper storage of construction
material
Use of cover on trucks
Speed limit for vehicles
Earlier some minor odour generation
during fermentation and Bio composting
process. However Now due to proposed
spent wash treatment no such odour
generate.
There is no dust generation as ESP are
installed to the new boiler.
5.6 Emissions from incineration
of waste
No ESP will be install along with 70 Meter
proposed Stack. Hence no emissions will
occur.
5.7 Emissions from burning of
waste in open air (e.g. slash
materials, construction
debris)
No Not applicable
5.8 Emissions from any other
sources
No Not Applicable
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
13 | P a g e
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
6.1 From operation of equipment
e.g. engines, ventilation plant,
crushers
No All equipment’s installed in the unit are
of standard make manufactured as per
noise regulations stipulated by MoEF.
During operation phase, noise shall be
generated by the operation of pumps, air
compressors, boilers, TG set etc. as open
structure is there, no abnormal sound
level is expected. Persons working in the
high noise area will be provided the
required earplugs & earmuffs.
6.2 From industrial or similar
processes
No All equipment’s installed in the unit are
of standard make manufactured as per
noise regulations stipulated by MoEF.
The ambient noise levels in the plant are
well within the standards stipulated by
MoEF.
6.3 From construction or
demolition.
No The proposed installation of Multi Effect
Evaporator and a new Boiler involves
only minor construction activity. Hence
there will not be any much noise
generation during construction activity.
6.4 From blasting or piling No Not Applicable.
6.5 From construction or
operational traffic
No The proposed installation of Multi effect
Evaporator and new boiler involves only
minor construction activity. Hence there
will not be major vehicular movement.
6.6 From lighting or cooling
systems
No Not applicable
6.7 From any other sources No Not applicable
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
14 | P a g e
7. Risks of contamination of land or water from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the
sea
Sl.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
7.1 From handling, storage, use
or spillage of hazardous
materials
No Used oil is being disposed to SPCB
authorized recyclers
7.2 From discharge of sewage or
other effluents to water or the
land (expected mode and
place of discharge)
No It is ZERO discharge unit.
No waste water is disposed to outside
plant premise. Sanitary waste water
generated is being treated in septic tank
followed by soak pit.
Spent wash generated is being treated
by Bio-methanation < RO plant followed
by Bio-composting. Now we proposes,
after Multiple Effect Evaporator (MEE)
followed by Incineration (Slop fired
boiler).
7.3 By deposition of pollutants
emitted to air into the land or
into water
No Proposed 70m stack with ESP shall be
provided for the boiler.
7.4 From any other sources No
7.5 Is there a risk of long term
build up of pollutants in the
environment from these
sources?
No
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
15 | P a g e
8. Risk of accidents during construction or operation of the Project, which
could affect human health or the environment
Sl.
No.
Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
8.1 From explosions, spillages,
fires etc from storage
handling, use or production of
hazardous substances
No No such hazardous substances which lead
to explosions, spillages, fires etc from
storage, handling are being utilized or
produced in the existing unit
8.2 From any other causes No Not applicable
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides,
cloudburstetc)?
Yes There are very less chances of natural
disaster causing environmental changes
but as per our proper Disaster
management Plan & Environment
Management Plan if it will occur then we
will try to minimize the impacts of Natural
Disaster on project.
9. Factors which should be considered (such as consequential development)
which could lead to environmental effects or the potential for cumulative
impacts with other existing or planned activities in the locality
Sl.No
.
Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
9.1 Lead to development of
supporting facilities,
ancillary development or
development stimulated
by the project which
could have impact on the
environment e.g.:
-Supporting
No The existing unit has enabled the local to
get employment and also increased the
business opportunities to the locals
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
16 | P a g e
infrastructure
(roads, power supply,
waste or
waste water treatment,
etc.)
- housing development
- extractive industries
- supply industries.
- other
9.2 Lead to after-use of the
site, which could have an
impact on the
environment
No All precautionary measures are being taken
in the unit to avoid any impact on plant site.
9.3 Set a precedent for later
developments
Yes It will increase Ethanol production of the
country, which in turn in the long run could
lead to further industrial development and
considerable savings of Petrol.
9.4 Have cumulative effects
due to proximity to other
existing or planned
projects with similar
effects.
No The existing unit is an isolated industry and
not in cluster. A better planned and
executed project has to yield a better result
individually.
(III) ENVIRONMENTAL SENSITIVITY
Sl.
No.
Areas Name/
Identity
Aerial distance (within 15 km.) of
proposed project location boundary
1 Areas protected under
international conventions
national or local
legislation for their
ecological, landscape
No No any
BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION
17 | P a g e
cultural or other related
value
2 Areas which are
important or sensitive for
ecological reasons
(Wetlands, watercourses
or other water bodies,
coastal zone, biospheres,
mountains, forests)
No River Rapti : 7.57Km in North
direction.
3 Areas used by protected,
important or sensitive
species of flora or fauna
for breeding, nesting,
foraging, resting, over
wintering, migration
No No any
4 Inland, coastal, marine or
underground waters
No
5 State, National
boundaries
No
6 Routes or facilities used
by the public for access to
recreation or other
tourist, pilgrim areas
No
7 Defense installations No
8 Densely populated or
built-up area
No The proposed project site lies in the
vicinity of city : Balrampur – 4.1 km
9 Areas occupied by
sensitive man-made land
uses (hospitals, schools,
places of worship,
community facilities)
No Some such areas exist in city :