Badenoch & Strathspey Re-design of Services Communications and Engagement Public Consultation Activities 21 st April to 21 st July 2014 NHS Highland is engaging with service users, members of the public, staff and partner agencies on the need to change the way some services are organized in Badenoch and Strathspey. This includes looking at options for location of hospital services. This is prompted by the poor condition of the hospital buildings, challenges to provide in-patient medical cover out-of-hours and the need to consider where best to invest resources and services to meet the future needs of the population. Activities, as part of the formal public consultation, are set out in the plan below. This plan builds on an earlier communications and engagement plan which guided the case for change, options appraisal process and development of consultation materials. It should be noted that the independence referendum's purdah period starts on 21 August and the referendum is on 18 September 2014. Maimie Thompson Head of Public Relations and Engagement June 2014 www.nhshighland.scot.nhs.uk

Upload: others

Post on 22-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

Badenoch & Strathspey Re-design of Services

Communications and Engagement Public Consultation Activities

21st April to 21

st July 2014

NHS Highland is engaging with service users, members of the public, staff and partner agencies on the need to change the way some services are organized in Badenoch and Strathspey. This includes looking at options for location of hospital services. This is prompted by the poor condition of the hospital buildings, challenges to provide in-patient medical cover out-of-hours and the need to consider where best to invest resources and services to meet the future needs of the population. Activities, as part of the formal public consultation, are set out in the plan below. This plan builds on an earlier communications and engagement plan which guided the case for change, options appraisal process and development of consultation materials. It should be noted that the independence referendum's purdah period starts on 21 August and the referendum is on 18 September 2014.

Maimie Thompson Head of Public Relations and Engagement June 2014

www.nhshighland.scot.nhs.uk

Page 2: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

2 (of 16)

Version Control The plan will be updated to report on actions and any new updates on meetings and events. Version 1.1 at 21st April 2014, published on website on 28th April 2014 Version 1.2 at 14th June 2014, published on website on 16th June 014 Dates of events will be published on the website and via twitter @NHSHighland #strathchat All the consultation materials are available on the NHS Highland website via the Home Page

Page 3: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

3 (of 16)

Local Publications Badenoch and Strathspey Herald (weekly) Editor Gavin Musgrove [email protected] BOG Standard - [email protected] Carrbridge News - [email protected] (online) Ceilidh (Kingussie) Kincraig Church Newsletter – [email protected] Laggan Newsletter – The Splash [email protected] [email protected] NQ Newtonmore Community Council Newsletter [email protected] [email protected] and [email protected] Spotlight [email protected] The Nethy - [email protected] (x 4 times per year) Radio Speyside -01479 811 888 Local Twitter @boatofgarten @cairngormsnews @carrbridge @Carrbridgenews @davytmsp @Kingussietweets @newtonmore10 @StrathyHerald @visitscotland @NHSHighland #strathchat Facebook Grantownonspey https://www.facebook.com/BoatofGarten https://www.facebook.com/BoatofGartenCommunityHall https://www.facebook.com/carrbridge https://www.facebook.com/NethyBridge https://www.facebook.com/NewtonmoreBusinessAssociation

Page 4: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

4 (of 16)

Websites - Requests to establish links http://cairngorms.co.uk/ http://visitcairngorms.com/whatsonlist http://www.alvieandinshchurch.org.uk/contactus.html - [email protected]

http://www.boatofgarten.com/community/bog-standard/ http://www.carrbridge.com/index.php/Info/ http://www.highland.gov.uk/ http://www.newtonmore.com/our-community/newtonmore-community-council.html http://www.newtonmore.com/village-hall.html

http://www.spotlighton.co.uk/pg_strathspey.php www.davethompsonmsp.org/ www.kingussie.co.uk www.speysoundradio.co.uk

GP Practices all have websites – Information already displayed Aviemore - Iain Gray [email protected] Grantown-on-Spey Kathy Cockman [email protected] Kingussie (also covers Laggan) Mairi Henderson [email protected]

Page 5: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

5 (of 16)

Code Theme Activity Date Lead Comments Status

1.1 Briefing Scottish

Government

Confirm consultation dates April M Thompson Confirmed 10th April Cab Sec briefed via SG officials

GREEN

1.2 Confirm consultation underway April M Thompson Email 25th April GREEN

1.3 Arrange for local meeting 14th May M Thompson Actioned GREEN

1.4 Set-up mid-way review 9th June M Thompson As part of Annual Review GREEN

1.5 Send mid-way review report 11th June M Thompson Up to 6th June GREEN

1.6 Keep informed of any developments and progress

Ongoing M Thompson

1.7 Provide update before Purdah End of July M Thompson 21st August, update to August Board Meeting

2.1 Briefing Scottish Health

Council

Confirm consultation dates April M Thompson Confirmed 10th April GREEN

2.2 Sign off consultation materials and go ahead

April D Connelly Confirmed 16th April GREEN

2.3 Sign off evaluation April D Connelly / M Thompson

Before first event GREEN

2.4 Set up regular meetings 8th May S Blackhurst M Thompson GREEN

20th May M Thompson / N Small GREEN

4th June Thompson / N Small GREEN

18th June

7th July

6th August

26th August

5th Sept

17th Sept

1st Oct

2.5 Produce action note of meetings ongoing SHC Include as part of mid-way review

GREEN

2.6 Confirm mid-way review May M Thompson Held on 4th June GREEN

Page 6: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

6 (of 16)

2.7 Confirm after consultation meeting and next steps

tbc M Thompson

2.8 Confirm turn-a-round time for Assurance Report

May D Connelly Will fit with NHS Highland time-table, for Dec Board

GREEN

2.9 Send mid-way review report 11th June M Thompson Up to 6th June GREEN

3.1 Steering Group (includes SHC)

Consult over feed-back response form

April MT Thompson PDSA to develop form and test.

GREEN

3.2 Regular update to Steering Group with:

Dates of events/ meetings

Issues and ideas log emerging from the process

Weekly/ fort-nightly

M Thompson

Start w/b 21st April GREEN

3.3 Arrange Mid-way Review June N Small Arranged for 5th June GREEN

3.4 Mid-way Review Meeting 5th June N Small Reviewed draft report and identified further actions

GREEN

3.5 Issue Mid-way review report 11th June M Thompson Circulated GREEN

3.6 Rep to attend Annual Review 9th June M Thompson Marie Brown GREEN

3.7 Set up date to complete options appraisal on sites

S Blackhurst Agree to do this at mid-way review

3.8 Complete options appraisal on sites

J Bogle Can’t take place until after consultation closes

4.1 Information at public venues Distribution of Consultation

materials, posters and dates of events

CAB

Care Homes

Day Care services

Dental Practices

GP Practices

Hospitals

Libraries

Local Groups

NHS Highland main offices

Pharmacies

Post offices

Service point

w/b 6th May M Thompson/S Blackhurst

3 Service Points 3 Local Libraries University Library Steering Group to be contacted to support Extended dissemination as part of Walk about

GREEN

Page 7: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

7 (of 16)

4.2 Posters and dates of events and consultation forms

Walk about: Newtonmore, Kingussie, Aviemore and Grantown

27th May A Devlin To check awareness, shops, post office, service points etc

GREEN

Walk about Grantown 12 June A Devlin GREEN

4.3 Link in with local groups to produce their own posters and disseminate

Ongoing M Thompson Carrrbridge, Boat of Garten, Newtonmore, Kingussie

GREEN

5.1 List of contacts to send consultation materials

Issue link of consultation materials to contacts

E-mailed on 25th April

M Thompson List prepared by M Thompson and N Small

GREEN

5.2 Issue link to contacts we have contracts with

May M Thompson List from contacts GREEN

5.3 CEO follow up letter to CEO 30th May M Morrison CNP, SAS, THC, Police, Fire, SNH etc

GREEN

6.1 Media, social media and website

Issue Media Releases at Key stages

15 April T Davison/ Thompson

GREEN

16 April T Davison/ Thompson

GREEN

6 May T Davison/ Thompson

GREEN

20 May T Davison/ Thompson

GREEN

4 June T Davison/ Thompson

GREEN

10 June GREEN

w/b 23rd June Photos of sites

w/b 30th June Transport Survey

w/b 7th July Final call for responses

6.2 Advert of Events and how to respond

5th May List of consultation activities

GREEN

20th May List of consultation activities

GREEN

19th June List of how to respond GREEN

w/b 7th July Final call

Page 8: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

8 (of 16)

6.3 Collate articles and letters during consultation period

Ongoing E Greig Underway; include in mid-way report

Ongoing

6.4 Use twitter and facebook to promote dates of events, media releases ETC

Ongoing K Burnett & E Grieg

#strathchat Included channels used by Mumsnet and breastfeeding peer volunteers

6.5 Asses reach from social media July K Burnett

6.6 Link with local social media channels

Ongoing M Thompson

6.7 Have all information on website and keep up to date including: Consultation documents, on-line diary and consultation response forms

21st April to 21st July

K Burnett GREEN

6.8 At half way stage make Major Service re-design main focus on Home Page including how to respond

6th June N Henderson Actioned GREEN

7.1 Provide updates in NHS Highland regular communications

Board Media Briefing Bi Monthly T Davison GREEN

7.2 HighLights Monthly T Davison Staff magazine GREEN

7.3 GP Practice Newsletters Ongoing Practice Manager/ M Thompson

GREEN

7.4 NHS Highland Annual Review Report

9th June M Thompson GREEN

8.1 Mail Drop Co-ordinate mail drop to every home and business in B&S via Royal Mail

May M Thompson Scheduled for w/b 19th May; sample checks done and copies received

GREEN

9.1 Consultation Response Form and other feed-

Develop Web version May M Thompson To go live after 1st event 1st May

GREEN

Page 9: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

9 (of 16)

9.2 back Develop paper copies May M Thompson Available for 1st event GREEN

Correction to paper copies June M Thompson Form updated following feed-back

GREEN

9.3 Set up system for collating ad hoc comments and responses (letters, emails, meetings

21st April to 21st July

M Thompson/ N Small

GREEN

9.4 Set up system for capturing feed-back from meetings etc

21st April to 21st July

M Thompson/ K Rodgers

Notes of all meetings to be captured in Blue Book

GREEN

9.5 Monitor number of responses 21st April to 21st July

M Thompson As at mid-way <50 GREEN

9.6 Liaise with SHC over patterns and number of responses at half way stage

10th June M Thompson/ SHC

Information received GREEN

10.1 Link in with existing Forums and structures and provide regular updates and incorporate views and ideas as part of consultation

District Partnership – Nairn Ardersier, Badenoch and Strathspey

24th April N Small Item on Agenda Liaise with Liz Cowie

GREEN

10.2 11th June M Walker Further update on progress – meeting in Nairn. Mid-way Review circulated

GREEN

25th Sept

4th Dec

10.3 Scottish Ambulance Service 21st May N Small

10.4 Cairngorms National Park N Small and J Bogle

Informal meet with CEO GREEN

30 May N Small Meet with Board?? GREEN

27 June N Small Board Meeting

10.5 Transport Scotland 12 June J Bogle GREEN

10.6 Attend Access Panel Meetings May-June N Small Invited onto Steering Group

11.1 MSPs/ Local Councillors E-mail to confirm consultation underway

w/b 21st April M Thompson 25th April GREEN

11.2 Formal Meetings arranged for 28 May 14 GC/EM/MT GREEN

Page 10: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

10 (of 16)

Garry Coutts and Elaine Mead to meet with MSPs

25 Aug 14 GC/EM/MT

19 Nov 14 GC/EM/MT

11.3 Ensure ongoing briefings with MSP in between meetings

Ongoing N Small / M Thompson

Circulated Board Media Briefing and Media Statements

GREEN

11.4 Meet / brief elected members: Bill Lobban

Ongoing N Small/ B Peters/ M Thompson

All are part of Steering Group. Formally emailed as part of wider communication THC on 25th April

GREEN

Jaci Douglas Ongoing GREEN

Dave Fallows Ongoing GREEN

Gregor Rimell Ongoing

12.1 Provide regular briefings to Community Councils to ensure they are fully informed and engaged with the process in advance of key stages and decisions. Arrange specific meetings as part of formal public consultation. Meetings to be arranged as soon as formal consultation confirmed

Aviemore and Vicinity Community Council

8th May M Thompson/ B Peters

GREEN

Boat of Garten CC 2nd June M Thompson/ B Peters

GREEN

Carrbridge CC 29th May N Small GREEN

Cromdale and Advie (*) Being arranged

Dulnain 14th May N Small/ B Peters

GREEN

Grantown-on-Spey 20th May B Peters/N Small

GREEN

Kincraig and Vicinity 10th June K Rodgers/M Thompson

GREEN

Kingussie & Vicinity CC 6th May M Thompson/K Rodgers

GREEN

NethyBridge and Vicinity CC 1 May N Small/ B Peters

GREEN

5 June N Small/ B Peters

GREEN

12.2 Community Councils - Strategic

Inform NHS Highland about progress with setting up Association of Community Hospitals

2014/15 Liz Cowie Not likely to be imminent but could be important going forward

Page 11: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

11 (of 16)

13.1 Drop-in Events Aviemore 11th June M Thompson/A Devlin

10-2.30, as part of A9 Public Exhibition

GREEN

12th June M Thompson 5-8PM GREEN

Boat of Garten 2nd June B Peters 4-7PM GREEN

Carrbridge 29th May N Small and M Walker

4-7PM GREEN

Dulnain 14th May N Small and K Rodgers

4-7PM GREEN

Grantown-on-Spey 20th May M Walker and K Rodgers

4-7PM GREEN

Kincraig 10th June M Walker and K Rodgers

4-7PM GREEN

NethyBridge 5th June M Thompson 4-7PM GREEN

Newtonmore 19th June M Thompson 12-3PM

Laggan 19th June M Thompson 4-7PM

14.1 Public Meetings Kingussie 25th June Core Group 7PM

Aviemore 1st July Core Group 7PM

Grantown-on-Spey 2nd July Core Group 7PM

15.1 Meet / speak with local groups and individuals

Continue discussion with Duchaidh

21st April – 21st July

N Small Ongoing GREEN

15.2

Friends of St Vincent’s AGM 23rd April Str Group Rep GREEN

28th May N Small GREEN

15.3 Friends of Ian Charles 23rd June B Peters/M Thompson

GREEN

15.4 Kingussie Lunch Club 19th May M Thompson GREEN

15.5 Dalwhinnie Community Group 28th May B Peters/K Rodgers

GREEN

15.6 Presbytery of COS 17 June N Small

15.7 Sunshine Club 23 June Core

15.8 B&S Access Panel 23 June Core

Badenoch Arthritis Club 23 June Core

15.9 Rotary TBC B Peters

15.10 Walk about Newtonmore 27 May A Devlin GREEN

Page 12: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

12 (of 16)

15.11 Walk about Aviemore 27 May A Devlin GREEN

15.12 Walk about Kingussie 27 May A Devlin GREEN

15.13

Walk about Grantown-on-Spey 27 May A Devlin GREEN

12 June A Devlin GREEN

15.14 Individuals 21 April-21 July

Core Various

15.15 Liaise with Local RCOP Officer 21 April-21 July

N Small/ M Thompson

Ongoing

15.16 Consider providing information at Leisure Centres to coincide with classes

21 April-21 July

M Thompson In discussion with HighLife Highland

15.17 Invite HighLife Highland onto Steering Group

21 April-21 July

N Small Attended as part of Mid-way Review

GREEN

15.18 Attend local “mother and toddler” groups

21 April-21 July

16.1 Opportunities for schools/ Youth Group to be informed and involved

Contact Head Teachers and then agree next steps

w/b 8th April M Thompson All schools contacted: Inter-generational work Promote careers in health and social care in the area

16.3 Liaise with Highland Youth Forum

20th June Highland Conference

16.4

17.1 Transport and Access Liaise with B&S Transport Group to review their data

April K Rodgers Available on website GREEN

17.2 Mileage and Travel times in B&S

21st April K Rodgers In full document and on website

GREEN

17.3 Mileage and Travel times to Aviemore

21st April K Rodgers In full document and on website

GREEN

17.4 Walking times to potential sites 21st April K Rodgers In full document and on website

GREEN

17.5 Stagecoach bus route map 21st April K Rodgers Website GREEN

17.6 Set up Transport Survey May M Thompson w/b 5th May; hard copy and on-line

GREEN

Page 13: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

13 (of 16)

17.7 Prepare interim results June Clinical Governance

17.8 Promote results and continue date gathering

w/b 30th June M Thompson Media; social media and local website

17.9 Discuss Access and Transport Group

5th June N Small Discussed at mid-way review; agreed NHSH not to chair and that group will work over next 3 years

GREEN

17.10 Set up meeting June/July N Small Access Panel, B&S Transport, Service users, THC, Transport providers

17.11 Agree who to chair group Agree at first meeting

18.1 Provide regular briefings to staff and key NHS Highland Groups

Drop-in events for staff across B&S

23rd April N Small Actioned (Others to be arranged)

GREEN

18.2 Item of Local Partnership Forum April N Small Confirm dates

18.3 B&S Locality Meeting Monthly M Walker

18.4 Raigmore Senior Management Team

Monthly N Small/ L Kirkland

Ongoing

Prepare Mid-way Review Report 10th June M Thompson Available on web GREEN

18.5 NHS Highland Board Meetings

(Meetings are held in Public and webcast)

3 Jun 14 N Small Updates via CEO Report GREEN

12 Aug14 N Small

7 Oct 14 N Small

2 Dec 14 N Small

18.6

18.7 Highland Social Care Committee

(Meetings are held in Public and webcast)

1 May 14 N Small Verbal update + sent link on 1 May to consultation materials and engagement plans

GREEN

11 June M Thompson Members sent mid-way review and asked to comment

GREEN

10 Jul 14 N Small Update

11 Sep 14 N Small

6 Nov 14 N Small

Page 14: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

14 (of 16)

18.8 Asset Management Group

25th April M Thompson Chair notified consultation underway

GREEN

11 June M Thompson Members sent mid-way review and asked to comment

GREEN

18.9 Staff Governance 25th April M Thompson Chair notified consultation underway

GREEN

11 June M Thompson Members sent mid-way review and asked to comment

GREEN

18.10 Area Clinical Forum 25th April M Thompson Chair notified consultation underway

GREEN

11 June M Thompson Members sent mid-way review and asked to comment

GREEN

18.11 Partnership Forum 25th April M Thompson Chair notified consultation underway

GREEN

11 June M Thompson Members sent mid-way review and asked to comment

GREEN

19.1 Other Outside eyes 21st April-21st July

M Thompson Link with x2 non execs and senior manager to provide “critical analysis on the process

GREEN

19.2 Link with other NHSH Boards with experience of Major Service Change

21st April-21st July

M Thompson GREEN

19.3 Link in with Master Plan and NHSH Clinical Strategy

21st April-21st July

N Small/ M Thompson/ B Peters

GREEN

19.4 Link in with Major Consultation in Skye and share learning

21st April-21st July

N Small/M Thompson

GREEN

Page 15: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

15 (of 16)

20.1 Governance, Planning for Fairness and Risks

Ensure systems in place to plan and evidence CEL 2 (2010) being fully followed

2013/14 and 2014/15

N Small/ M Thompson

This plan and monitoring of plan supports this process

Reporting to HHSC

Meetings with SHC

Meeting with SG

Walk about to check awareness

Series of mid-way review meetings

Preparation and dissemination of Mid-way-review

Use of outside eyes

Briefing Board Members

Briefing MSPs

20.2 Regular review and update of planning for fairness

2013/14 and 2014/15

N Small/ M Thompson

Reflect feed-back from groups, responses and transport survey

20.3 Discuss with SG, SHC, Steering Group and Chair of HHSC any risks and take mitigating actions. Biggest risks are:

2013/14 and 2014/15

N Small/ M Thompson

This plan and monitoring of plan supports this process, including actions identified under 20.1 above

20.4 Capacity of core team to oversee consultation and maintain consistency

21st April to 21st July

As above

20.5 Insufficient actions to raise awareness

21st April to 21st July

As above

20.6 Not able to demonstrate awareness

21st April to 21st July

As above

20.7 Low response rate reflects weakness in process

21st April to 21st July

As above

Page 16: Badenoch & Strathspey Re-design of Services · SHC) Consult over feed-back response form April MT Thompson PDSA to develop form and test. GREEN 3.2 Regular update to Steering Group

16 (of 16)

20.1 Reporting on Feed-Back from Public Consultation (This section will be fully developed as part of the post consultation plan)

Workshop to score sites

20.2 Analysis of public consultation

20.3 Analysis of Transport Survey

20.4 Analysis of other feed-back and reports

20.5 Write up Evaluation

20.6 SHC Assurance Report to NHS Board

Paper to HHSC

20.7 Paper to NHS Highland Board

20.8 Board to make recommendation

[email protected] 01463 704722 @nhshmt