![Page 1: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/1.jpg)
Aurora Highlands
Civic Association MeetingArlington County
Department of Environmental Services
May 9, 2018
1
![Page 2: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/2.jpg)
Agenda
Overview
Neighborhood Projects
Arlington Ridge Rd Project
Future Project
2
![Page 3: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/3.jpg)
Drinking Water Overview
Source Water: Potomac River
Treatment plant: Washington aqueduct
Distribution System:
525 miles of water main4 to 48 inch
Ductile or Cast Iron, Steel, Concrete, Plastic
16,000 water valves
37,200 water services
3,700 fire hydrants
5 water pump stations
8 water storage tanks32 Million Gallons (MG)
3
![Page 4: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/4.jpg)
Water Main Age
0
20
40
60
80
100
120
Decade 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
Mile
s
Length of Water Mains By Decade
Diameter 8
Diameter 6
Over 50% of the water system is comprised of unlined cast iron pipes 8 & 6-inches in diameter built before 1960
![Page 5: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/5.jpg)
Water Main Rehabilitation & Replacement
Cleaning and Lining Water Main Replacement
5
![Page 6: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/6.jpg)
60% design – Fall
2018/Winter 2019
• 20th St S – S Kent St to
S Hayes St
• 22nd St S – S Ives St to
S Fern St
Expected construction
start date Mid-May 2018
• 26TH Pl S – 26th St S to S
Hayes St
• S Hayes St – 26th St S to
Fort Scott Dr.
• 17TH St S –S Lynn St to
S Ives St
Neighborhood Projects
![Page 7: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/7.jpg)
What to ExpectNeighborhood Projects:
Working hours
8AM to 4PM Monday through Friday
Parking Impacts
Occur in phases throughout project
Notice will be given at least 72
hours in advance
Traffic
Temporary traffic detour and/or
street closure during the day
Driveway access will be impacted
but accessible at all times
Water service disruption
Notices will be distributed 48 hours
in advance
All shutdowns will be limited to the
same daily construction hours.
Construction impacts
Dust, mud, noise & debris
Notification
Detailed letter will be sent to
Civic Associations presidents
and residents who will be
directly impacted by the
project.
7
![Page 8: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/8.jpg)
S Arlington Ridge Water Main Project
Project limits
S Oakcrest St to S Nash
St.
Existing condition
8inch main
Built in 1927
Maintenance issues
Proposed Install ~5300 feet of new
12inch and 8inch main
Improve fire flow
Timeline
Summer 2018 – Fall 2019
8
![Page 9: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/9.jpg)
What to Expect
S Arlington Ridge Project:Working hours
9AM – 4PM Monday through
Friday
Possible weekend work
Traffic impact
Flagging operation
Variable message signs – 2 weeks
before construction start
Sidewalk will be open at all times
Water service disruption
Notices will be distributed 48 hours
in advance
All shutdowns will be limited to the
same daily construction hours.
Construction impact Dust, mud, noise & debris
Notification Detailed letter will be sent
to Civic Associations
presidents and residents
who will be directly
impacted by the project.
9
![Page 10: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/10.jpg)
What to Expect
Water Quality Tuberculation (iron oxide, discolored water,
rust)
Corrosion byproducts in pipes – iron oxide
deposits
Light yellow to dark brown temporary
discoloration
Cloudy/Whitish water
Drinking water naturally contains a certain
amount of dissolved air.
Air dissolved in water can result in tiny bubbles
similar to those in carbonated beverages.
Run your cold water tap for 5 to 10 minutes, the
water should clear.
If it doesn’t, call the 24-hour line at 703-228-6555
and a crew will be sent to flush the line.
10
![Page 11: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/11.jpg)
Future Project
23rd Street South Project Limits
S Lynn St to S Eads St
Scope of work
Replace existing ~ 4200 feet of 8 inch 1927 main with a new
12 inch
Status/timeline
60% design
Expected construction start – Fall 2019/Winter 2020
11
![Page 12: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/12.jpg)
Questions?
24 Hour Emergency Number: 703-228-6555
12
![Page 13: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/13.jpg)
Drinking Water Quality Report
13
https://water.arlingtonva.us/water/water-quality-reports/
![Page 14: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/14.jpg)
Drinking Water Quality
Monitor drinking water at the entry
point into the distribution system
Monitoring/Testing the distribution
system
Bacteriological: Total Coliforms Rule
(TCR)
Disinfection By Products
Water Quality Parameters
Nitrification
Meets/exceeds all regulations
14
![Page 15: Aurora Highlands Civic Association Meeting · Cleaning and Lining Water Main Replacement 5. 60% design –Fall 2018/Winter 2019 • 20th St S –S Kent St to S Hayes St • 22nd St](https://reader034.vdocuments.mx/reader034/viewer/2022050223/5f68319a7fd7d55c67451ebf/html5/thumbnails/15.jpg)
Due to consistent compliance and results
below the Action Level, EPA requires Arlington
to sample only once every three years.
Next scheduled sampling will start June 2016
Per LCR sampling is required for specific
homes built between 1982 -1986.
Orthophosphate
Corrosion control added at the treatment Plant
Acts as a corrosion inhibitor by forming a
protective film on the interior of the pipes. This
film protects the pipe from the corrosive effects
of water
Arlington does not have lead pipes for water
distribution
Drinking Water Quality – Lead and Copper Rule (LCR)
15