www.avangridrenewables.com 1
Deubrook Elementary SchoolToronto, Deuel County, South Dakota
Tatanka Ridge Wind ProjectSouth Dakota Public Utilities
Commission
Public Input Hearing
August 7th, 2019
AVANGRID RENEWABLES
www.avangridrenewables.com 2
Introduction
Tatanka Ridge Wind Project
• Project Developer – Jesse Bermel• Legal Counsel – Brett Koenecke• Engineer – Mark Mullen• Permitting Manager – Amanda Bohnenblust
AVANGRID RENEWABLES
www.avangridrenewables.com 3
Introduction
Tatanka Ridge Wind Project
Permitting• Janelle Rieland• Dan Flo• Mark Bastasch
AVANGRID RENEWABLES
www.avangridrenewables.com 4
Avangrid Renewables, LLC
…focused on operational excellence and selective growth
A collection of exceptional assets…One of the largest wind project
owners in the U.S. with more than 6 GWs owned and contracted
636 MW of CCGT & peaking capacity on the strategic CA-OR border
Tatanka Ridge is a subsidiary of AVANGRID, NYSE: AGR
More than $32 billion of U.S. assets operating in 24 states
725+ employees at the end of 2018, compared with 12 in 1999
U.S. Renewables
and clean gas generation
Wind Power Solar & Biomass
6,000+ MW 536 MW CCGT100 MW peaking
116 MW Solar55 MW Biomass
Rev.April 2019
Tatanka Ridge Wind Project AVANGRID RENEWABLES
rllllll\W
avangridrenewables.com
U.S. Power Assets
Tatanka Ridge Wind Project 4
Wind generation
Thermal generation
Biomass generation
Solar generation
Mountain View III 22.4 MW
Pleasant Valley144 MW PPA
Twin Buttes75 MW
Colorado Green162 MW
Elk River150 MW
1 - Klondike IIIa76.5 MW
2 - Hay Canyon 100.8 MW
3 – Klondike I24 MW
4 - Klondike III 223.6 MW
5 - Star Point98.7 MW
6 - Klondike II75 MW
7 - Big Horn I199.5 MW
8 - Big Horn II50 MW
9 - Juniper Canyon151.2 MW
10 - Pebble Springs98.7 MW
11 - Leaning Juniper II201.3 MW
Peñascal II 201.6 MW
Barton Chapel120 MW
Locust Ridge I26 MW
Casselman34.5 MW
Rugby149.1 MW
Farmers City 146 MW
Providence Heights72 MW
Peñascal I 201.6 MW
Tacoma 55 MW PPA
WINDPROJECTS
1
4 3 6 85 7
2
9 10 11 12
1 - Buffalo Ridge I 50.4 MW2 - Buffalo Ridge II 210 MW3 - MinnDakota 150 MW4 - Moraine I 51 MW5 - Moraine II 49.5 MW
6 - Elm Creek I 99 MW 7 - Elm Creek II 148.8 MW8 - Trimont 101 MW9 - Flying Cloud 43.5 MW
10 - Winnebago 20 MW11 - Top of Iowa II 80 MW12 - Barton 160 MW13 - New Harvest 100 MW
Maple Ridge II45.4 MW owned(91 MW JV project)
Maple Ridge I115.5 MW owned
(231 MW JV project)
Hardscrabble 74 MW
1 2 3 4
8
5 6 1097
11
Dry Lake I63 MW
Dry Lake II65.1 MW
South Chestnut46 MW
Blue Creek304 MW
StreatorCayuga Ridge300 MW
13
Lempster 24 MW
Hoosac28.5 MW
Groton48 MW
Shiloh 150 MW
Manzana189 MW
High Winds 162 MW PPA
Baffin202 MW
Dillon 45 MW
Amazon Wind Farm NC208 MW
Locust Ridge II102 MW
South TexasCoast Complex
Klamath EnergyCogeneration 536 MWPeakers 100 MW
Copper Crossing20 MW
El Cabo 298 MW
Twin Buttes II75 MW
Deerfield 30 MW
Tule 131.1 MW
San Luis30 MW
Gala56 MW
Wy’East10 MW
Rev. 5/8/19
AVANGRID .,. RENEWABLES 11111
www.avangridrenewables.com 6
South Dakota Experience
Tatanka Ridge Wind Project
• MinnDakota, 54 MW in SD, 36 turbines in Brookings County• Buffalo Ridge 1, 50.4 MW, 24 turbines in Brookings County• Buffalo Ridge 2, 210 MW, 105 turbines in Brookings and Deuel County• Coyote Ridge (under construction) 96.7 MW, 39 turbines in Brookings
County
l l l
m
www.avangridrenewables.com 7Tatanka Ridge Wind Project
Project Boundaries of Avangrid Wind Farms in the Local Area
AVANGRID RENEWABLES
111 1"1'
BR00KIN
,t862ft He n:lrtckS
Bru::e
B,oo k,ng< I I MinnDakota I
Avangrid Renewables CJ Buffa lo Ridg~ Boundary CJ Tatanka Ridge Boundary Facilities .---,
f-- - ---,--------, L.....J Buffalo Ridge II Boundary = Interstate
OUTH AKCTA
CJ Coyote Ridge Boundary
CJ MinnDakota Boundary
km 10
Data Source: World Topo Map Coordinate System: UTM, NAD83. zn 14N
Map produced on 0312612019 by A. L. Dah l
0
!!'
" I
\
www.avangridrenewables.com 8
Tatanka Ridge Wind Project
Project Developer• Tatanka Ridge Wind, LLC, a wholly owned subsidiary of
Avangrid Renewables, LLCProject Details• Up to 155 MW• Up to 56 turbines (GE)• Maximum height of 499 feet• Maximum rotor diameter of 417 feet• Underground 34.5 kV collection system• Access roads• MET tower• Operations and maintenance building• Substation
Tatanka Ridge Wind Project AVANGRID RENEWABLES
www.avangridrenewables.com 9
Tatanka Ridge Wind Project – Summary
Tatanka Ridge Wind Project
In-service date• December 1, 2020
Off-take• Two Power Purchase
Agreements for 100% of the output
Land agreements• 100% for all facilities
Participating landowners• Over 100
AVANGRID RENEWABLES
www.avangridrenewables.com 10
Tatanka Ridge Wind – Project Location/Schedule
Located north of Toronto in Blom, Brandt, Grange, Hidewood, and Scandinavia Townships
• Project facilities will be located on ~52 acres, less than 1% of project• Targeting construction as early as the first quarter of 2020• ~12 months to construct• COD end of 2020
Tatanka Ridge Wind Project AVANGRID RENEWABLES
www.avangridrenewables.com 11
Met ower Locooion
Laydovm 1rea
M llld l'I
s.tib ttr I n
(rane ath
Und rgro1,md
Ol.·erhe.adl/Unci\e.grou d ---....__, 10 F-oo Contour
Fin,al A!igm1en~ To Dete.r ·ned CSJI Project Boundar:,,
E:c" ·ng l..!lnderg ound Pip,el"ne c::iJ Mumcipaliily
11 · ng 0-.,erh~d Tr~n~ ]~on Line I PuLii1. L 111.l 5u on r~--i l __ ! Ci'l'il Township Ba , ;:: '/
! County Botmdar)'
www.avangridrenewables.com 12
Overview of Project Benefits
Tatanka Ridge Wind Project
• Brings jobs, taxes, and landowner payments to the project area• We expect about $1 million annually in direct landowner payments• We’ve budgeted approximately ~$700k annually in taxes• ~$260k to two local school districts, ~$180k to the county, ~$75k to all
townships• About 12 to 15 permanent jobs created • Up to 200 construction jobs for 9 months
- -
= DEUEL COUNTY ....... ~ FARMERS UNION
Uliiiiiiiiiili OIL co. ~1.,L=I~==-=
www.avangridrenewables.com 13
Project Development Status
Land Agreements• Secured all agreements for facilities
Meteorological Data• Over 5 years of continuous data collection
Interconnection Agreement• Existing agreements allow project to connect to the transmission grid
Constraints Analysis• Identified constraints, roads, electrical, beam paths…
Field Studies• On schedule for COD, 90% complete
Tatanka Ridge Wind ProjectAVANGRID RENEWABLES
www.avangridrenewables.com 14
• Site characterization study
• Wetland and waterbody
• Birds
• Bats
• Dakota skipper
• Poweshiek skipperling
• Raptor nest
• Cultural resources
Environmental Surveys
Tatanka Ridge Wind ProjectAVANGRID RENEWABLES
www.avangridrenewables.com 15
Project Development Status
Landowner Input To Date• Multiple landowner meetings
and coordinationPermitting• Local permit approved• State permit ongoingPower Purchase Agreements• Secured 2 agreements• 100% of output
Tatanka Ridge Wind ProjectAVANGRID RENEWABLES
www.avangridrenewables.com 16
Wind Farm Construction
• Procurement• Contracts• Access roads• Foundations• Delivery of equipment• Erection of turbines• Electrical system• Post-construction
activities (roads/tile)
Tatanka Ridge Wind ProjectAVANGRID RENEWABLES
www.avangridrenewables.com 17
Decommissioning
At the end of commercial operation, project owner is responsible for decommissioning:
Turbine removal• Foundations removed to 4 feet below gradeRemove below ground equipment to 42 inches per county requirementsRemove above ground facilitiesAccess roads• Landowner has option to keep roadFinancial assurance
Tatanka Ridge Wind ProjectAVANGRID RENEWABLES
www.avangridrenewables.com 18
Summary
Tatanka Ridge Wind Project
• South Dakota partnerships• Wind resource• Fit with agriculture
• Landowner payments• School investment• Total investment of ~$218M
AVANGRID RENEWABLES
www.avangridrenewables.com 19Tatanka Ridge Wind Project
Thank You!
AVANGRID RENEWABLES