Page 1: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

1

Page 2: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• The last part (Part D) of the Phase 3 renovation project is scheduled for completion August 11, 2017.  The Part D work includes the interior demolition and reconstruction of the D2200 wing and part of the D2100 wing.  This summer’s work included approximately 12,000 sf.

• Installation of ceiling tile, floor tile and final painting is underway.

• Casework doors installation and trim out on going.

• Final roofing trim out over the D wing is underway.

• New furniture and equipment is stored on site.  Installation of furniture and equipment into renovated spaces will begin 8/14.

• The project is approximately 90% complete.

2

Page 3: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Interior Restrooms, PE Lockers Rooms and new Bleachers are complete. • Agricultural Science Classrooms and Barn are now occupied by teachers• Permanent air is to be running on Aug 10th.  The main building mechanical room 

renovation for 3 boilers and 3 chillers is being renovated (GMP#4) and near completion.   The new cooling tower is installed and piping is connected and operational to the mechanical room.  Admin has relocated to the main building Aug 8.

• Sanitary sewer line with lift station from Concessions Building to Ag Science is complete.

• Expect to start GMP#5‐ front expansions in Fall 2017. Front construction fencing is complete, and side entry will be ready for school.  All parking will be in back lot during construction, to prepare for first school day.  We are preparing for the lengthened entry turn lanes to the school, in coordination with the County.

3

Page 4: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Bond 2014 (Which is Phase 1) comprises 5 GMP’s.

3

Page 5: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Exterior landscaping and hydromulching is 95% complete.• Interior finishing and trim work is complete.• Interior first final clean is complete.• Interior VCT floor clean and waxing is complete.• Interior punch list by the design team is complete.• Final city inspections for a Certificate of Occupation are tentatively scheduled for 

the week of August 14th.• Classroom furniture has been placed in the classrooms.• The project is approximately 98% complete, substantial completion of 

construction is anticipated for mid to late August 2017.

4

Page 6: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Irrigation system installation is complete, landscape planting has begun.• Stage rigging installation continues.• Installation of the stage flooring continues.• Installation of the LOBBY ceiling continues. • Installation of remaining metal panels on the sunscreen continues.• Site clean‐up and restoration continues.• Anticipated completion date is August 22.

5

Page 7: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Work has begun on the excavation of the building pad.• Installation of the new building pad will start this week.• Utility work has begun inside the existing building. Both POWER and GAS will be 

brought over from the existing building.• Two of the three mobile restroom units have arrived on campus for temporary 

restroom facilities.

6

Page 8: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• All construction work is substantially complete.

• Final building inspections and punch list will be complete by 8/21.

• Punch list repair work is underway.

• Delivery of furniture and equipment began July 10th and should be substantially complete by 8/11.

• Building systems operations and maintenance training of District staff is underway.

• The project is approximately 99% complete.

7

Page 9: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Installation of underground utilities continues.• Building pad installation is complete. Pier drilling to begin this week.• Installation of remaining metal panels on the sunscreen continues.• Anticipated completion date is August 2018.

8

Page 10: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Window installation in all classrooms and assembly areas complete.

• Remainder of window installation in progress.

• Metal roof panel installation in progress.

• The project is approximately 75% complete.

9

Page 11: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Construction punch scheduled for Monday, August 14.

• Furniture deliveries ongoing.

• The project is approximately 95% complete.

10

Page 12: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Construction punch scheduled for Monday, August 14.

• Furniture deliveries ongoing.

• The project is approximately 95% complete.

11

Page 13: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Flooring install in progress.

• Goals and padding on site and ready to be installed.

• The project is approximately 80% complete.

12

Page 14: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Construction punch scheduled for Monday, August 14.

• Furniture deliveries ongoing.

• The project is approximately 95% complete.

13

Page 15: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Roofing except for flashing on parapet is complete‐95%.

• Cooling units are running and computer controls are 100% connected to energy management.

• The 2 large additional outside air units will be installed on a weekend and running by September 1st, however, all other new units are running currently and these 2 will not affect temperature.

• Substantial Completion for roofing and ac less 2 outside air units is August 11th.  Hallways and classrooms are cleaned and floors are waxed in most areas.

14

Page 16: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Roofing except for flashing on parapet is complete‐95%.

• Nurses Station is complete except for locks‐98%.

• Cooling units are running and computer controls being installed with energy management.

• The 2 large additional outside air units will be installed on a weekend and running by September 1st, however, all other new units are running currently and these 2 will not affect temperature.

• Substantial Completion for roofing and ac less outside air units is August 11th weekend.  Hallways and classrooms are cleaned and floors are waxed in most areas.

15

Page 17: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Demolition is complete.

• Foundation excavation is complete.

• Foundation piers are complete.

• The project is approximately 10% complete.

16

Page 18: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

• Chaney Cox Construction has mobilized to the site.

• Job trailer installation is complete.

• Construction site fencing will be completed on August 21st.

17

Page 19: August 2017 BOT construction update.ppt...Microsoft PowerPoint - August 2017 BOT construction update.ppt [Compatibility Mode] Author e114961 Created Date 8/16/2017 1:01:45 PM

18