august 2012 program update opsb & rsd phase i …...program update opsb & rsd phase i...

55
0% 15% 14% 32% 39% 0% 46% 23% 7% 24% August 2012 August 2012 August 2012 Program Update Program Update Program Update OPSB & RSD Phase I Projects OPSB & RSD Phase I Projects OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents the total of full project budgets. The OPSB has $51.2 million in open contracts for the Phase 1 capital program projects after issuing no new contracts, change orders and amendments in August. In addition, the total change orders to date, $493 thousand, accounts for approximately one percent (1.27%) of the total open Phase 1 construction contracts. Finally, OPSB anticipates issuing $27.1 million in new contracts in Phase 1 construction and $167 thousand in professional services contracts/amendments in September. The RSD has $306 million in open contracts for the Phase 1 capital program projects after issuing no new contracts and $526 thousand in change orders and amendments in August. In addition, the total change orders to date, $7.2 million, accounts for approximately three percent (2.63%) of the total open Phase 1 construction contracts. Finally, RSD anticipates issuing no Phase 1 construction contracts and professional services contracts/amendments in September. Program Schedule Status Group 1 Project Mahalia Jackson Edward Hynes School Group 2 Project Audubon School Alice Harte School Eleanor L. McMain School McDonogh 35 HS (Phillips/Waters) New PK-8 at North Kenilworth Park OPSB Phase 1 Projects Design Procurement Construction Complete Occupied (May 2010) Procurement Construction Complete Occupied (January 2012) Design Value of Projects by Phase Design 80,786,843 $ Procurement 41,432,081 $ Construction 12,579,532 $ Complete 41,496,509 $ Future Projects - $ Value of Projects by Phase Design 80,829,261 $ Procurement 76,808,200 $ Construction 175,477,350 $ Complete 210,004,932 $ Future Projects - $ Group 1 Project Guste ES Langston Hughes ES Andrew H. Wilson ES Lake Area HS L.B. Landry HS Joseph A. Craig ES Jean Batiste de Bienville ES Parkview ES Mildred Osborne ES Fannie C. Williams ES William Frantz ES Carter G. Woodson ES Charles J. Colton ES Lawrence D. Crocker ES Group 2 Project Booker T. Washington HS Phillis Wheatley ES Little Woods ES George W. Carver HS Edward Livingston HS RSD Phase 1 Projects Design Occupied (August 2008) Design Occupied (August 2009) Occupied (January 2010) Occupied (January 2010) Occupied (July 2010) Occupied (August 2012) Occupied (August 2012) Complete Procurement Construction Complete Procurement Construction Occupied (January 2010) Occupied (July 2012)

Upload: others

Post on 09-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

0%

15%

14%

32%

39%0%

46%23%

7%24%

August 2012 August 2012 August 2012 Program UpdateProgram UpdateProgram Update

OPSB & RSD Phase I ProjectsOPSB & RSD Phase I ProjectsOPSB & RSD Phase I Projects

Program Financial Status

Status Date: 31 August 2012

Note-The value in each phase represents the total of full project budgets.

The OPSB has $51.2 million in open contracts for the Phase 1 capital program projects after issuing no new contracts, change orders and amendments in August. In addition, the total change orders to date, $493 thousand, accounts for approximately one percent (1.27%) of the total open Phase 1 construction contracts. Finally, OPSB anticipates issuing $27.1 million in new contracts in Phase 1 construction and $167 thousand in professional services contracts/amendments in September.

The RSD has $306 million in open contracts for the Phase 1 capital program projects after issuing no new contracts and $526 thousand in change orders and amendments in August. In addition, the total change orders to date, $7.2 million, accounts for approximately three percent (2.63%) of the total open Phase 1 construction contracts. Finally, RSD anticipates issuing no Phase 1 construction contracts and professional services contracts/amendments in September.

Program Schedule Status

Group 1Project

Mahalia Jackson

Edward Hynes School

Group 2

Project

Audubon School

Alice Harte School

Eleanor L. McMain School

McDonogh 35 HS (Phillips/Waters)

New PK-8 at North Kenilworth Park

OPSB Phase 1 Projects

Design Procurement Construction Complete

Occupied (May 2010)

Procurement Construction Complete

Occupied (January 2012)

Design

Value of Projects by Phase

Design 80,786,843$

Procurement 41,432,081$

Construction 12,579,532$

Complete 41,496,509$

Future Projects -$

Value of Projects by Phase

Design 80,829,261$

Procurement 76,808,200$

Construction 175,477,350$

Complete 210,004,932$

Future Projects -$

Group 1Project

Guste ES

Langston Hughes ES

Andrew H. Wilson ES

Lake Area HS

L.B. Landry HS

Joseph A. Craig ES

Jean Batiste de Bienville ES

Parkview ES

Mildred Osborne ES

Fannie C. Williams ES

William Frantz ES

Carter G. Woodson ES

Charles J. Colton ES

Lawrence D. Crocker ES

Group 2Project

Booker T. Washington HS

Phillis Wheatley ES

Little Woods ES

George W. Carver HS

Edward Livingston HS

RSD Phase 1 Projects

Design

Occupied (August 2008)

Design

Occupied (August 2009)

Occupied (January 2010)

Occupied (January 2010)

Occupied (July 2010)

Occupied (August 2012)

Occupied (August 2012)

Complete

Procurement Construction Complete

Procurement Construction

Occupied (January 2010)

Occupied (July 2012)

Page 2: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

0%

100%

0%

0%

0%0%

100%

0%

0%

0%

August 2012 August 2012 August 2012 Program UpdateProgram UpdateProgram Update

OPSB & RSD Phase 2 ProjectsOPSB & RSD Phase 2 ProjectsOPSB & RSD Phase 2 Projects Program Financial Status

Status Date: 31 August 2012

Note-The value in each phase represents the total of full project budgets.

The OPSB has $4.6 million in open contracts for the Phase 2 capital program projects after issuing $4.3 million in new contracts and $14 thousand in amendments in June. The OPSB anticipates issuing $864 thousand in Phase 2 professional services contracts/amendments in July.

The RSD has $14 million in open contracts for the Phase 2 capital program projects after issuing no new contracts amendments in June. The RSD anticipates issuing $6.4 in Phase 2 professional services contracts/amendments in July.

Program Schedule Status

Note: Projects marked with an asterisk are not included in the financial information shown above.

Full Renovations

Project

Drew ES* Priestley JH

McDonogh 42 ESSophie B Wright ES

* John McDonogh HSDouglass HS

* Clark HS* Live Oak ES* Lafayette ES* Tubman ES

Refurbished/Renovations

Project

* Allen ES* Jackson ES* Crossman ES* Eisenhower HS* Gentilly Terrace ES* Rosenwald ES* O Perry Walker HS* Nelson ES- Refurb* Martin L King ES* Reed HS* Green MS* Sylvanie Williams* Bauduit ES* Laurel ES* McDonogh 28 ES* McDonogh 7 ES* Schwarz HS* Village de L'Est ES* Wicker ES* Marshall ES* Schaumburg ES* Harney ES

Design Procurement Construction Complete

RSD Phase 2 Projects

Design Procurement Construction Complete

New Schools

Project

Lake Forest PK-8 @ GSt StephensNew Karr HS @ JoEllen Smith Site

* Bio District HS

Full Renovations

Project* Franklin ES

Refurbished/Renovations

Project

Warren Easton* Fortier HS * Ben Franklin HS* Lusher ES* Bethune ES

Design Procurement Construction Complete

Design Procurement Construction Complete

OPSB Phase 2 Projects

Design Procurement Construction Complete

New Schools

Project

Dunbar ES* Gaudet ES * Morial * Fischer * New Algiers PreK-8

Alfred LawlessFisk-Howard

* Alexander ES * Abrams HS

New Orleans East (Abramson)Bradley

* Sherwood Forest ES * Behrman ES * Habans ES

Edward Livingston

RSD Phase 2 Projects

Design Procurement Construction Complete

Value of Projects by Phase

Design 58,351,116$

Procurement -$

Construction -$

Complete -$

Future Projects -$

Value of Projects by Phase

Design 254,708,331$

Procurement -$

Construction -$

Complete -$

Future Projects -$

Page 3: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

Superintendents’ Report August 2012

Mr. Stanley C. Smith Orleans Parish School Board

Mr. John White Louisiana Department of Education

Mr. Patrick Dobard Recovery School District

Prepared by:

Page 4: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

1 Status Date: 31 August 2012

Table of Contents TABLE OF CONTENTS ..................................................... 1 OVERVIEW ......................................................................... 3 COMMUNITY MEETINGS .................................................. 4 BID OPENINGS .................................................................. 5 NEW & MAJOR RENOVATION ......................................... 6

Audubon School (OPSB) .............................................. 6 Jean Batiste de Bienville School (RSD) ....................... 6 Stuart R. Bradley School (RSD) .................................. 7 Paul L. Dunbar School (RSD) ...................................... 7 George Washington Carver School (RSD) .................. 7 Charles J. Colton School (RSD) .................................. 8 Lawrence D. Crocker School (RSD) ............................ 8 Drew Elementary School (RSD) ................................. 9 Frederick A. Douglass High School (RSD) ................. 9 Warren Easton School (OPSB) ................................. 10 Fisk-Howard School (RSD) ....................................... 10 William Frantz School (RSD) ..................................... 11 Alice Harte School (OPSB) ........................................ 11 Lake Forest PK-8 at the Greater St. Stephens Site

(OPSB) ....................................................................... 12 New PK-8 School at North Kenilworth Park at Curran Site (OPSB) ................................................................ 12 Alfred Lawless School (RSD) .................................... 13 Edward Livingston High School (RSD) ..................... 13 McDonogh #35 School (Phillip/Waters Site) (OPSB) . 13 McDonogh #42 Elementary School (RSD) ............... 13 Eleanor L. McMain School (OPSB) ........................... 14 Small New Orleans East High School at Abramson (RSD) ....................................................................... 16 Mildred Osborne School (RSD) ................................ 16 Parkview School (RSD) ............................................. 16 New Karr High School at the JoEllen Smith Site (OPSB) ............................................................................... 17 Booker T. Washington School (RSD) ........................ 18 Phillis Wheatley Elementary School (RSD) ............... 18 Fannie C. Williams School (RSD) .............................. 18 Little Woods School (RSD) ........................................ 19 Carter G. Woodson School (RSD) ............................. 20 Sophie B. Wright School (RSD) ................................ 20

OTHER PROJECTS ......................................................... 21

Benjamin Franklin Senior High School (OPSB) .......... 21 Walter L. Cohen High School (RSD) ......................... 21 Warren Easton School (OPSB) ................................. 21 Langston Hughes School (RSD) ............................... 22 Andrew Jackson School (RSD) ................................ 22

Page 5: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

2 Status Date: 31 August 2012

Mahalia Jackson Elementary School Office Renovation (OPSB) .................................................... 23 John McDonogh High School (RSD) ......................... 23 Edna Karr High School - Gymnasium Repair (OPSB) ............................................................................... 23 Dr. Martin Luther King Jr. School (RSD) ................... 24 Lafayette Elementary School (RSD) .......................... 24 Thomy Lafon School (RSD) ....................................... 24 McDonogh #35 High School (OPSB) ......................... 25 Timbers HVAC (OPSB) .............................................. 25 Village de’ Lest Elementary School (RSD) ................ 26 Sylvanie Williams Elementary School (RSD) ............. 26 Dwight D. Eisenhower Elementary School (RSD) ..... 27 Andrew Jackson Elementary School (RSD) ............. 27 Paul B. Habans Elementary School (RSD) ............... 27 Sylvanie F. Williams Elementary School (RSD) ........ 27 Joseph S. Clark Senior High School (RSD) ............... 27 Dr. Martin Luther King School (RSD) ......................... 27 Albert Wicker Elementary School (RSD) .................. 27 A.P. Tureaud Elementary School (RSD) ................... 27 Edgar P. Harney Elementary School (RSD) ............. 27 Harriet R. Tubman Elementary School (RSD) .......... 27 Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) .. 28

MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS ........................................................................ 29

Louis D. Armstrong Elementary School (RSD)) ......... 29 Israel M. Augustine Middle School (RSD) ................. 29 Andrew J. Bell Junior High School (RSD) ................. 30 Oretha C. Haley Elementary School (RSD) .............. 30 Lorraine Hansberry Elementary School (RSD) ......... 31 Morris F. X. Jeff Elementary School (RSD) .............. 31 Valena C. Jones Elementary School (RSD) ............. 32 George Mondy Elementary School (RSD) ................. 32 John A. Shaw Elementary School (RSD)................... 33

DEMOLITION PROJECTS ............................................... 34

Fannie C. Williams Elementary School (RSD) .......... 34 Greater St. Stephens School (OPSB) ........................ 34 L. B. Landry Annex Demolition (RSD) ...................... 35 Mary Church Terrell Elementary School Demolition (RSD) ) ....................................................................... 35 Booker T. Washington High School Partial Demolition (RSD) ..................................................... 36

COMPLETED PROJECTS .............................................. 37

Page 6: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

3 Status Date: 31 August 2012

Overview

The RSD has $383 million in open contracts for the capital program after issuing $5.4 million in new contracts and $989 thousand in change orders and amendments in August. In addition, the total change orders to date, $8.4 million, account for approximately two percent (1.94%) of the total open construction contracts. RSD anticipates issuing approximately $2.7 million in construction contracts and no professional service contracts/amendments in September.

The OPSB has $84 million in open contracts for the capital program after issuing no new contracts, change orders and amendments in August. In addition, the total change orders to date, $1.52 million, account for approximately three percent (2.55 %) of the total open construction contracts. OPSB anticipates issuing approximately $29.9 million in construction contracts and professional service contracts in September.

Page 7: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

4 Status Date: 31 August 2012

Community Meetings

• August 23rd: Fisk-Howard School – 3401 Canal Street, New Orleans, LA 70119

• September 20th: Paul L. Dunbar School – 3613 Cambronne Street, New Orleans, LA 70118

• September 24th: Lake Forest Pk-8– 5600 Read Boulevard, New Orleans, LA 70127

• October 1st: Alfred Lawless School – 1617 Caffin Avenue, New Orleans, LA 70117

• October 3rd: Stuart R. Bradley School – 3939 Gentilly Blvd, New Orleans, LA 70126

• October 4th: Sophie B. Wright School – 1426 Napoleon Avenue, New Orleans, LA 70115

• October 11th: Frederick Douglass High School – 3820 St. Claude Avenue, New Orleans, LA 70117

• October 15th: New Karr High School at the JoEllen Smith Site – 4422 General Meyer, New Orleans, LA 70131

• October 18th: Charles Drew Elementary – 3819 St. Claude Avenue, New Orleans, LA 70117

• October 25th: Small New Orleans East High School at Abramson – 5552 Read Boulevard, New Orleans, LA 70127

Page 8: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

5 Status Date: 31 August 2012

Bid Openings

Bids that were opened in August 2012:

• Phillis Wheatley Elementary School (RSD) – August 9, 2012

• Abatement and Demolition of Annex Building at L. B. Landry High School (RSD) – August 14, 2012

• Mahalia Jackson School Office Space Conversion (OPSB) – August 21, 2012

Over the next sixty days, bids to be opened for the following projects:

• AHU Replacement at Sylvanie Williams Elementary School (RSD) – September 11, 2012

• Thomy Lafon Interpretive Display (RSD) – September 11, 2012

• Test Pile Program at New 3 Section Elementary School at Fisk-Howard (RSD) – September 12, 2012

• Test Pile Program for New 2 Section Elementary School at Paul L. Dunbar School (RSD) – September 12, 2012

• Demolition of Greater St. Stephens (OPSB) – September 13, 2012

• Demolition of Modular Buildings and Associated Services at Fannie C. Williams Elementary School (RSD) – September 18, 2012

• McDonogh #35 High School Stabilization (OPSB) – September 20, 2012

• Mothballing of Closed Schools Safe and Secure at George Mondy Elementary School (RSD) – October 30, 2012

• New Gym Addition at Eleanor McMain Secondary High School (OPSB) – November 6, 2012

Page 9: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

6 Status Date: 31 August 2012

Forecasted dates only include the next project phase

New & Major Renovation – Project Status

Audubon School (OPSB) [428 Broadway Avenue, New Orleans, LA 70118]

Scope of work: Renovation & Addition of Existing Elementary School

• Funding Source – FEMA

• Architect – Blitch/Knevel Architects

• Contractor – FHP Tectonics Corporation

• Construction Phase Selective demolition is complete Cottage demolition is complete Test Pile package is underway Test Pile report is anticipated on September 14th BZA and Safety / Permits are reviewing the Construction

Documents Pile driving is anticipate to start upon release of the permits

• Contractual Substantial Completion – September 2013

• Forecasted Substantial Completion – September 2013

• School Ready for Occupancy – January 2014

Jean Batiste de Bienville School (RSD) [1456 Gardena Drive, New Orleans, LA 70122]

Scope of work: New Pre-K – 8 School

• Funding Source – FEMA

• Architect – Howard Performance Architecture

• Contractor – Walton Construction – a CORE Company, LLC

Final Close-out Phase Project is complete – June 15

The punch list is 90% complete

• School is Occupied – August 2012

Page 10: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

7 Status Date: 31 August 2012

Stuart R. Bradley School (RSD) [ 2401 Humanity Street, New Orleans, LA 70122]

Scope of work: New 3 – section elementary school for 850 students

• Funding Source – FEMA

• Architect – Sizeler Thompson Brown Architects

• Contractor – TBD

• Design Phase – CD

Design Development documents were received on August 17th

100% Construction Documents are due December 16th

• Procurement Phase

Anticipated 1st Advertisement – January 2013 Anticipated Bid Opening – March 2013

Paul L. Dunbar School (RSD) [9330 Forshey Street, New Orleans, LA 70125]

Scope of work: New 2 - section elementary school for 556 students

• Architect - Chenevert Architects LLC

• Contractor – TBD • Design Phase - CD

Design Development documents were received on August 6th Community Meeting #4 – September 20th 100% Construction Documents are due December 10th

• Procurement Phase Anticipated 1st Advertisement – January 2013

Anticipated Bid Opening – April 2013

George Washington Carver School (RSD) [3019 & 3059 Higgins Blvd., New Orleans, LA 70126]

Scope of work: New High School

• Funding Source – FEMA

• Architect – Trapolin Architects & VMDO Architects, A Joint- Venture

• Contractor – TBD

• Procurement Phase Bid Opening – July 27th

Page 11: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

8 Status Date: 31 August 2012

Bids were not accepted Project is on hold pending Owner’s decision

Charles J. Colton School (RSD) [2300 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition

• Funding Source – FEMA

• Architect – Waggonner & Ball Architects

• Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC

• Construction Phase

Roofing material installation is ongoing

Brick work is starting on the east elevation Gypsum board installation on interior walls is ongoing on 2nd

and 3rd floors

Mechanical/Electrical/Plumbing rough-in work is ongoing Pulling of wiring/data lines is in process

Dehumidifying equipment is in use in the building Window installation has started

Damage report from Hurricane Isaac to be provided

• Contractual Substantial Completion – November 2012

• Forecasted Substantial Completion – TBD

• School Ready for Occupancy – TBD

Lawrence D. Crocker School (RSD) [2300 General Taylor Street, New Orleans, LA 70115]

Scope of work: New PK-8 School • Funding Source – FEMA

• Architect – Chenevert Architects LLC

• Contractor – Satterfield and Pontikes Construction Group, LLC

• Construction Phase Glazing is complete and 97% of the exterior wall panels are

complete Kitchen equipment is installed and reviewed by the designer

The interior finishes of the occupied portion of the building are complete

Page 12: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

9 Status Date: 31 August 2012

F.F.E. is complete Temporary Certificate of Occupancy was issued on August 3rd

Certificate of Occupancy from the City of New Orleans was received on August 23rd

Punch list is ongoing on the occupied portion of the building

• Contractual Substantial Completion – March 2012

• Forecasted Substantial Completion – October 2012

• School is Occupied – September 2012

Drew Elementary School (RSD) [3819 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition to meet code requirements

• Funding Source – FEMA

• Architect – Blitch / Knevel Architects, Inc.

• Contractor – TBD

• Design Phase - DD

Community Meeting #2 is anticipated to be held on October 18th

• Design Development documents are due on October 2nd

• Procurement Phase Anticipated 1st Advertisement – June 2013

Anticipated Bid Opening – September 2013

Frederick A. Douglass High School (RSD) [3820 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Renovation of existing high school

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – TBD

• Design Phase - SD

Community Meeting #1 is anticipated to be held on October 11th

Program Completion was received July 30th

• Schematic Design is anticipated on September 27th

Page 13: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

10 Status Date: 31 August 2012

• Procurement Phase

Anticipated 1st Advertisement – May 2013 Anticipated Bid Opening – August 2013

Warren Easton School (OPSB) [3019 Canal Street, New Orleans, LA 70119]

Scope of work: Refurbishment of existing high school

• Funding Source – FEMA

• Architect – Chenevert Architects LLC • Contractor – TBD

• Design Phase - CD 50% Construction Documents were received on June 18th

100% Construction Documents are due on September 15th

• Procurement Phase

Anticipated 1st Advertisement – October 2012 Anticipated Bid Opening – December 2012

Fisk-Howard School (RSD) [211 South Lopez Street, New Orleans, LA 70119]

Scope of work: New 3 - section elementary school for 850 students

• Funding Source - FEMA

• Architect - VergesRome Architects+Fanning Howey

• Contractor – TBD

• Design Phase - CD

Community Meeting #4 - August 23rd

Test pile program bid opening – September 12th 50% Construction Documents are due middle of September 100% Construction Documents are anticipated to be finished

on November 18th

• Procurement Phase

Anticipated 1st Advertisement – December 2012 Anticipated Bid Opening – March 2013

Page 14: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

11 Status Date: 31 August 2012

William Frantz School (RSD) [3811 North Galvez Street, New Orleans, LA 70117]

Scope of work: Renovation of existing elementary school and new addition

• Funding Source – FEMA • Architect – Billes Architecture, LLC

• Contractor – The Lathan Company, Inc.

• Construction Phase

Storefront and curtain wall systems are complete Window installation continues in the new building

Installation of the metal wall is complete Acoustical tile grid installation is ongoing in both buildings

Installation of the refinished trim, casework and interior doors is ongoing in the existing building

Painting of the CMU and sheetrock is ongoing in both buildings Installation of ceramic tile flooring in the new building is

ongoing

Polished concrete and VCT installation has started

• Contractual Substantial Completion – March 2012

• Forecasted Substantial Completion – TBD

• School Ready for Occupancy – TBD Alice Harte School (OPSB) [5300 Berkley Drive, New Orleans, La 70131]

Scope of work: New 3 - section elementary school for 850 students

• Funding Source – CDBG & FEMA

• Architect – WDG Architects Engineers

• Contractor – Woodrow Wilson Construction Company, Inc.

• Construction Phase Ground Breaking is September 11th

Notice to Proceed – September 12th

• Contractual Substantial Completion – December 2013

• Forecasted Substantial Completion – January 2014

• School Ready for Occupancy – June 2014

Page 15: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

12 Status Date: 31 August 2012

Lake Forest PK-8 at the Greater St. Stephens Site (OPSB) [11110 Lake Forest Boulevard 70128]

Scope of work: New 3 - section elementary school for 850 students

• Funding Source – FEMA

• Architect – Imre Hegedus & Associates Architects

• Contractor – TBD

• Design Phase - SD

Community Meeting #3 – September 24th Schematic Design completion is anticipated for the beginning

of September

• Procurement Phase

Anticipated 1st Advertisement – March 2013 Anticipated Bid Opening – June 2013

New PK-8 School at North Kenilworth Park at Curran Site (OPSB) [8500 Curran Boulevard, New Orleans, LA 70127]

Scope of work: New 3 - section elementary school for 850 students

• Funding Source – FEMA

• Architect – Mathes Brierre Architects

• Contractor – TBD

• Procurement Phase

100% CD Documents were complete on August 13th 100% CD Documents will be revise and returned September

11th with incorporated comments 1st Advertisement – September 25th

2nd Advertisement – October 2nd 3rd Advertisement – October 9th Pre-Bid Conference – 9:00 a.m. on October 10th at

Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Date – October 30th

• Forecasted Substantial Completion – July 2014

• School Ready for Occupancy – August 2014

Page 16: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

13 Status Date: 31 August 2012

Alfred Lawless School (RSD) [5300 Law Street, New Orleans, LA 70117]

Scope of work: New medium high school

• Funding Source – FEMA

• Architect – Sizeler Thompson Brown Architects

• Contractor – TBD

• Design Phase - DD

Community Meeting #1 – July 9th Schematic Design documents were received on August 23rd

Design Development documents are due on November 13th Community Meeting #2 – October

• Procurement Phase Anticipated 1st Advertisement – April 2013

Anticipated Bid Opening – July 2013

Edward Livingston High School (RSD) [7301 Dwyer Road, New Orleans, LA 70126]

Scope of work: New small high school

• Funding Source – FEMA

• Architect – RozasWard / a.i.a. architects, inc.

• Contractor – TBD

• Design Phase - CD 50% Construction Documents were received on August 28th

100% Construction Documents are due on November 9th

• Procurement Phase

Anticipated 1st Advertisement – December 2012

Anticipated Bid Opening – March 2013

Page 17: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

14 Status Date: 31 August 2012

McDonogh #35 School (Phillip/Waters Site) (OPSB) [1200 Senate Street, New Orleans, LA 70122]

Scope of work: New 3-story high school

• Funding Source – FEMA

• Architect – Sizeler, Thompson, Brown Architects

• Contractor - TBD

• Site Remediation Project

A Phase II environmental assessment revealed heavy metals and PAHs exist in the fill

Scope of work is to remediate fly-ash materials found in the soil

Remediation work is anticipated to be completed mid-October

• New Construction Project

Ownership The resubdivision request was submitted to the City Of

New Orleans 100% Construction Documents are due on October 2nd

Bid date was moved to November 15th

• Procurement Phase

1st Advertisement – October 11th 2nd Advertisement – October 18rd

3rd Advertisement – October 25th Pre-Bid Conference – 9:00 a.m. on October 31st at

Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – November 15th

McDonogh #42 ElementarySchool (RSD) [1651 North Tonti Street, New Orleans, LA 70119]

Scope of work: Renovation of existing elementary school and new addition to meet code requirements

• Funding Source – FEMA

• Architect – Eskew+Dumez+Ripple

• Contractor - TBD

• Program Phase Program Documents are anticipated on September 9th

Page 18: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

15 Status Date: 31 August 2012

Community Meeting #1 – Late October

• Procurement Phase

Anticipated 1st Advertisement – May 2013

Anticipated Bid Opening – July 2013 Eleanor L. McMain School (OPSB) [5721 S. Claiborne Avenue, New Orleans, LA 70125]

Scope of work: The exterior of the existing building will be stabilized and a new gym will be added to the site with a connecting breezeway to the main building

• Exterior Stabilization

Funding Source – FEMA Architect – Jahncke & Burns Architects

Contractor – TBD Design management team is reviewing alternates for window

scope

• New Gymnasium and Breezway

• Funding Source – FEMA

• Architect – Jahncke & Burns Architects

• Contractor – TBD

• Design Phase – CD

• 100% Construction Documents are due on September 20th

• Procurement Phase

• 1st Advertisement – October 2nd

• 2nd Advertisement – October 9th

• 3rd Advertisement – October 16th

• Pre-Bid Conference – 9:00 a.m. on October 17th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

• Bid Opening – November 6th

• School Based Health Clinic

• Funding Source – HRSA Grant

• Architect – Jahncke & Burns Architects

• Contractor – TBD

• Procurement Phase

Page 19: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

16 Status Date: 31 August 2012

Bid Opening – June 26th Contract was returned to the Owner, Owner is waiting

on insurance certificates from the contractor

• Contractual Substantial Completion – 120 days after contract award

Small New Orleans East High School at Abramson (RSD) [5552 Read Boulevard, New Orleans, LA 70127]

Scope of work: New small high school

• Funding Source – FEMA

• Architect – RozasWard / a.i.a. architects, inc.

• Contractor – TBD

• Design Phase - SD Design is on hold pending evaluation of scope.

Mildred Osborne School (RSD) [6701 Curran Blvd., New Orleans, LA 70126]

Scope of work: New Pre-K– 8 school

• Funding Source – FEMA • Architect – Fauntleroy & Latham

• Contractor – F.H. Paschen, S.N. Nielsen & Associates, LLC

• Construction Phase Installation of suspended ceiling grid, tiles, lighting, and HVAC

diffusers is complete in the occupied space Finish trades are working in the gymnasium Interior painting is complete Landscaping is nearly complete and the fencing is ongoing Gymnasium flooring is complete

• Contractual Substantial Completion – January 2012 • This school will have a phased delivery schedule

Classrooms, Administration, and Cafeteria – 26 July 2012 Media Center – 12 October 2012 Gymnasium – 12 October 2012

• School was Occupied – 15 August 2012

Page 20: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

17 Status Date: 31 August 2012

Parkview School (RSD) [4617 Mirabeau Avenue, New Orleans, LA 70126]

Scope of work: New Pre-K– 8 school

• Funding Source – FEMA

• Architect – Rozas-Ward

• Contractor – Citadel Builders, LLC

• Construction Phase

The Owner requested sports flooring has been started in the gymnasium

Bleacher installation has started Punch list is anticipated to be complete on the Classrooms,

Administration, Cafeteria, and Media Center in the middle of September

FF&E is complete

• This school will have a phased delivery schedule Gymnasium – September 2012

• School was Occupied – 6 August 2012

New Karr High School at the JoEllen Smith Site (OPSB) [4400 General Meyer Avenue, New Orleans, LA 70131]

Scope of work: New medium high school

• Funding Source – FEMA

• Architect – Lee Ledbetter & Associates / Gould Evans Associates

• Contractor – TBD

• Design Phase - DD

Community Meeting #3 is anticipated to be held on October 15th

Community Meeting #4 is anticipated to be held in November Schematic Design Documents were completed on August 17th

• Procurement Phase

Anticipated 1st Advertisement – April 2013 Anticipated Bid Opening – July 2013

Page 21: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

18 Status Date: 31 August 2012

Booker T. Washington School (RSD) [1201 South Roman Street, New Orleans, LA 70125]

Scope of work: The auditorium and entry will be renovated and the remainder of the facility will be demolished and constructed new

• Funding Source – FEMA

• Architect – Hewitt-Washington & Associates

• Contractor – TBD

• Design Phase - CD

50% Construction Documents were received on July 25th

The design is anticipated to be complete on September 10th

• Procurement Phase

Anticipated 1st Advertisement – January 2013 Anticipated Bid Opening – March 2013

Phillis Wheatley Elementary School (RSD) [2300 Dumaine Street, New Orleans, LA 70119]

Scope of work: New 2 - section elementary school for 556 students

• Funding Source – FEMA

• Architect – Holly & Smith Architects

• Contractor – Gibbs Construction

• Procurement Phase

Bid Date – August 9th Contracts were issued to the contractor

Notice to proceeded is anticipated September 7th

• Notice to Proceed – September 2012

• Forecasted Substantial Completion – March 2014

• School Ready for Occupancy – June 2014

Fannie C. Williams School (RSD) [11755 Dwyer Road, New Orleans, LA 70128]

Scope of work: New Pre-K – 8 school

• Funding Source – FEMA

• Architect – Yeates & Yeates Architects

• Contractor – Brice Building Company, LLC

Page 22: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

19 Status Date: 31 August 2012

Final Close-out Phase Temporary Certificate of Occupancy was issued on August 3rd

Substantial completion - August 24th F.F.E. is ongoing

Owner still installing technology cabling

• Contractual Substantial Completion – April 2012

• This school will have a phased delivery schedule Classrooms, Administration, Cafeteria, and Media Center –

August 2012 Gymnasium – September 2012

• School Ready for Occupancy – 15 October 2012

Little Woods School (RSD) [10200 Curran Blvd., New Orleans, LA 70127]

Scope of work: New Pre-K – 8 school

• Funding Source – FEMA

• Architect – Group Novak, LLC

• Contractor – MAPP Construction

• Construction Phase

Structural steel erection of all phases is complete CMU installation is 98% complete in all areas

Installing brick veneer on interior of 1st floor and exterior of gymnasium

Fireproofing is 98% complete in all areas Installing window frames throughout entire building

Glass installation is 80% complete Sprinkler piping is complete on 3rd floor and ongoing on the

1st and 2nd floors Interior metal stud framing is 90% complete. Pulling and terminating wire into panel boxes throughout

building Roof deck, insulation and roof membrane installed on school,

cafeteria, and gymnasium building

• Contractual Substantial Completion – November 2012

• Forecasted Substantial Completion – TBD

• School Ready for Occupancy – TBD

Page 23: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

20 Status Date: 31 August 2012

Carter G. Woodson School (RSD) [2514 Third Street, New Orleans, LA 70113]

Scope of work: New Pre-K – 8 school

• Funding Source – FEMA

• Architect – Byron J. Stewart & Associates

• Contractor – Brice Building Company, LLC

• Construction Phase F.F.E. is 50% complete Classrooms and Administration will be occupied – September

4th Substantial Completion is anticipated early September

• Contractual Substantial Completion – October 2012

• This school will have a phased delivery schedule Classrooms and Administration – 12 September 2012 Cafeteria, Gymnasium, and Media Center – 12 September

2012 Music / Performance – 24 September 2012

• School Ready for Partial Occupancy – 17 September 2012

Sophie B. Wright Middle School Renovation (RSD) [1426 Napoleon Avenue, New Orleans, LA 70115]

Scope of work: Renovation of existing middle school

• Funding Source – FEMA

• Architect – Waggonner & Ball Architects, APC

• Contractor – TBD

• Design Phase - SD Schematic Design Documents are anticipated on September

18th Community Meeting #1 – October 4th

• Procurement Phase

Anticipated 1st Advertisement – May 2013 Anticipated Bid Opening – August 2013

Page 24: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

21 Status Date: 31 August 2012

OTHER PROJECTS

Benjamin Franklin Senior High School (OPSB) [2001 Leon C. Simon Drive, New Orleans, LA 70122]

Scope of work: Renovation and repairs to the existing courtyard, exterior lighting, metal roof panels, interior lighting, curtain wall, exterior doors (frames), fencing, scoreboard and goal post

• Funding Source – FEMA

• Architect – Perez, APC

• Contractor – Pete Vicari General Contractors Inc.

• Construction Phase

Courtyard work is anticipated to be complete in January Exterior roof, frame, lighting work is ongoing

• Forecasted Contractual Substantial Completion – January 2013

Walter L. Cohen High School (RSD) [3520 Dryades Street, New Orleans, LA 70115]

Scope of work: Correct the HVAC return air / ventilation problems and replace eight (8) chilled water pumps

• Funding Source – FEMA

• Architect – Infinity Engineering Consultants, LLC

• Contractor – TBD

• Procurement Phase A / E contract to be approved at the October BESE board

Meeting

• Forecasted Substantial Completion – September 2013

Warren Easton School (OPSB) [3019 Canal Street, New Orleans, LA 70119]

Scope of work: Removal and replacement of existing exterior windows and waterproofing of the courtyard masonry

• Funding Source – Harrah’s

• Architect – VergesRome Architects, apc

• Contractor – Barbara Enterprises, Inc.

• Construction Phase

Additional window trim is on site and being installed

Page 25: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

22 Status Date: 31 August 2012

Miscellaneous window trim, sill painting and punch list work to be completed

Caulking of windows is complete Repair of the sidewalks is anticipated to start in September

• Contractual Substantial Completion – March 2010

• Forecasted Substantial Completion – September 2012

Langston Hughes School (RSD) [3519 Trafalgar Street, New Orleans, LA 70119]

Scope of work: Remove abandoned dumpster pad and grease trap; replace on classroom door/hardware; correct duct system in the IT room; install fencing in place of the dumpster pad; provide and install a fence around the backflow preventer

• Funding Source – FEMA

• Architect – Lachin Oubre & Associates

• Contractor – Tuna Construction, LLC

• Construction Phase

90% of contractual items are complete

• Forecasted Substantial Completion – October 2012

Andrew Jackson School (RSD) [1400 Camp Street, New Orleans, LA 70130]

Scope of work: Installation of solar panels at Andrew Jackson School. This will save energy for the school and serve as a teaching aide for students to learn about solar energy

• Funding Source – Greater New Orleans Foundation/Entergy Grant

• Architect – Perez, APC

• Contractor – TBD

• Procurement Phase

Bid Opening – June 26th

Lead time of solar panels has extended the schedule by a month

Notice to Proceed is anticipated - September 17th

• Forecasted Substantial Completion – January 2013

Page 26: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

23 Status Date: 31 August 2012

Mahalia Jackson Elementary School Office Renovation (OPSB) [2101 Freret Street, New Orleans, LA 70113]

Scope of work: Convert the office space on the second floor of Building C into four classrooms

• Funding Source – New Orleans Parish School Board General Fund

• Architect – VergesRome Architects, APAC

• Contractor – TBD

• Procurement Phase

Bid Opening – August 21st Recommendation letter to be sent September 6th

Permits are in place

• Forecasted Substantial Completion – December 2012

John McDonogh High School (RSD) [2426 Esplanade Avenue, New Orleans, LA 70119]

Scope of work: Replacement of bleachers

• Funding Source – Harrah’s

• Architect – Trapolin Peer Architects, LLC

• Contractor – TBD

• Design Phase - CD

The State Fire Marshal confirmed that with the addition of the new bleachers, a fire sprinkler system will be required in the gymnasium

New bleachers and a new fire sprinkler system will be installed in the gymnasium

Design is expected to be completed on October 15th

• Procurement Phase

Anticipated 1st Advertisement – November 2012

Anticipated Bid Date – January 2013

Edna Karr High School - Gymnasium Repair (OPSB) [3332 Huntlee Drive, New Orleans, LA 70131]

Scope of work: Determine what amount and methods need to be used to stabilize gymnasium for use.

• Funding Source – FEMA

• Architect – Chenevert Architects, LLc

Page 27: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

24 Status Date: 31 August 2012

• Contractor – Crescent Commercial Construction

• Stablization of the Gymnasium Procurement Phase

• Bid Opening date – July 24th

• Contracts were issued to the contractor

• Notice to proceeded is anticipated September 15th

• Forecasted Substantial Completion – January 2013

Dr. Martin Luther King Jr. School (RSD) [1617 Caffin Avenue, New Orleans, LA 70117]

Scope of work: Modular building, deck and canopy system installation

• Funding Source – Harrah’s

• Architect – Perez, APC

• Contractor – T&D Contractors, LLC

• Final Close-out Phase

Project is complete Punch list is complete

Lafayette Elementary School (RSD) [2727 S. Carrollton Avenue, New Orleans, LA 70118]

Scope of work: Roof replacement and masonry repairs • Funding Source – FEMA

• Architect – Montgomery Roth Architecture, LLC

• Contractor – The Lathan Company, Inc.

• Final Close-out Phase Project is complete Punch list is complete

Thomy Lafon School (RSD) [2601 Seventh St, New Orleans, LA 70115]

Scope of work: Stabilization of sculpture and creation of interperative display

• Funding Source – FEMA

• Architect – Mahlum / Scairono Marinez Joint Venture

Page 28: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

25 Status Date: 31 August 2012

• Contractor – TBD

• Procurement Phase 1st Advertisement – August 7th

2nd Advertisement – August 14th 3rd Advertisement – August 21st

Pre-Bid Conference – 9:00 a.m. on August 27th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – September 11th

• Forecasted Substantial Completion – January 2013

McDonogh #35 High School (OPSB) [1331 Kerlerec Street, New Orleans, LA 70116]

Scope of work: Stabilization and replacement of elevator

Funding Source – FEMA Architect – Chenevert Architects LLC

Contractor – TBD

• Procurement Phase

1st Advertisement – August 16th 2nd Advertisement – August 23rd

3rd Advertisement – August 30th Pre-Bid Conference – 9:00 a.m. on September 4th at

Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – September 20th

• Forecasted Substantial Completion – April 2013

Timbers HVAC (OPSB) [3520 General DeGaulle, New Orleans, LA 70114]

Scope of work: Stabilization and replacement of HVAC Funding Source – General Fund Architect – Moses Engineers

Contractor – TBD

• Design Phase - CD

50% Construction Documents are anticipated to be complete on September 6th

Page 29: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

26 Status Date: 31 August 2012

100% Construction Documents are anticipated to be complete on September 25th

• Procurement Phase

Anticipated 1st Advertisement – November 2012 Anticipated Bid Date – December 2012

Village de L’est Elementary School (RSD) [5100 Cannes Street, New Orleans, LA 70129]

Scope of work: Repair of subsidence

• Funding Source – FEMA

• Architect – Richard C. Lambert Consultants, LLC

• Contractor – Owen Construction Co.

• Final Close-out Phase

Project is complete Punch list is complete

Sylvanie Williams Elementary School (RSD) [3127 Martin Luther King Jr. Boulevard, New Orleans, LA 70125]

Scope of work: AHU replacement

• Funding Source – FEMA

• Architect – Integrated Management Services, Inc.

• Contractor – TBD

• Procurement Phase

1st Advertisement – July 24th 2nd Advertisement – July 31st

3rd Advertisement – August 7th Pre-Bid Conference – 9:00 a.m. on August 8th at

Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid opening delayed 13 days due to Hurricane Isaac Bid Opening – September 11th

• Forecasted Substantial Completion – April 2013

Page 30: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

27 Status Date: 31 August 2012

Dwight D. Eisenhower Elementary School (RSD) [3700 Tall Pines Drive, New Orleans, LA 70131]

Andrew Jackson Elementary School (RSD)

[1400 Camp Street, New Orleans, LA 70130]

Paul B. Habans Elementary School (RSD)

[3819 Herschel Street, New Orleans, LA 70114]

Sylvanie F. Williams Elementary School (RSD)

[3127 Martin Luther King Jr. Blvd, New Orleans, LA 70113]

Joseph S. Clark Senior High School (RSD)

[1301 North Derbigny Street, New Orleans, LA 70116]

Scope of work: Roof repairs and replacement

• Funding Source – FEMA

• Architect – HMS Architects, Inc.

• Contractor – Hamp’s Construction, LLC

• Final Close-out Phase Project is complete Punch list will be complete September 2012

Dr. Martin Luther King School (RSD) [3700 Tall Pines Drive, New Orleans, LA 70131]

Albert Wicker Elementary School (RSD)

[2011 Bienville Street, New Orleans, LA 70112]

A. P. Tureaud Elementary School (RSD) [2021 Pauger Street, New Orleans, LA 70116

Edgar P. Harney Elementary School (RSD)

[2503 Willow Street, New Orleans, LA 70113]

Harriet R. Tubman Elementary School (RSD) [2013 General Meyer Avenue, New Orleans, LA 70114]

Scope of work: Roof repairs

• Funding Source – FEMA

• Architect – Richard C. Lambert Consultants, LLC

• Contractor – Hamp’s Construction LLC

• Final Close-out Phase Project is complete

Punch list is complete

Page 31: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

28 Status Date: 31 August 2012

Building Automation System Integration At Recovery School District Central And Remote Offices (RSD) [Various Addresses]

Scope of work: Implementation of a Central Remote Building Automation System that integrates the existing Building Automation Systems of the 4 Quick Start Schools (Andrew H. Wilson ES, Langston Hughes ES, L.B. Landry HS, and Lake Area HS) and Joseph A. Craig ES into a central remote monitoring workstation that will include Fannie C. Williams ES, Lawrence D. Crocker ES, Mildred Osborne ES, William Frantz ES, Bienville ES, Charles J. Colton ES, Carter G. Woodson ES and Parkview ES

• Funding Source – FEMA

• Architect – Moses Engineers

• Contractor – Synergy Building Solutions, Inc.

• Construction Phase

The five Quick Start Schools are 90% complete, with work expected to be complete on in early October

Sylvanie Williams and Sarah T. Reed are 80% complete The remaining integration for schools currently under

construction will occur as each school is complete

• Contractual Substantial Completion – November 2014

• Forecasted Substantial Completion – November 2014

Page 32: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

29 Status Date: 31 August 2012

MOTHBALL OR SAFE & SECURE OF SELECTED SCHOOLS

Louis D. Armstrong Elementary School (RSD)) [5909 St. Claude Avenue, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – CDW Services, LLC

• Mothballing of Closed Schools – Safe & Secure Procurement Phase

• Contract is being reviewed by the contractor

• Notice to Proceed is anticipated September 21st

• Forecasted Substantial Completion – January 2013

Israel M. Augustine Middle School (RSD) [425 S. Broad St., New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – CDW Services, LLC

• Mothballing of Closed Schools – Safe & Secure

Construction Phase

• Project is 15% complete

• Contractual Substantial Completion – November 2012

• Forecasted Substantial Completion – December 2012

Page 33: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

30 Status Date: 31 August 2012

Andrew J. Bell Junior High School (RSD) [1010 N. Galvez St., New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – Cresent Commercial Construction

• Emergency Shoring – 100% complete

Shoring will remain inplace untill roof work is complete

• Mothballing of Closed Schools – Safe & Secure

Design Phase - CD

• 50% Construction Documents are anticipated to be complete on September 15th

• Roof Structure Replacement

Procurement Phase

• Contract is being reviewed by LDOE

• Notice to Proceed is anticipated September 19th

• Forecasted Substantial Completion – May 2013

Oretha C. Haley Elementary School (RSD) [2515 N. Robertson Street, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – CDW Servcies, LLC

• Mothballing of Closed Schools – Safe & Secure Construction Phase

• Roofing work is complete

Page 34: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

31 Status Date: 31 August 2012

• Metal panels over exterior windows are complete

• Punchlist is being compiled

• Contractual Substantial Completion – September 2012

• Forecasted Substantial Completion – September 2012

Lorraine Hansberry Elementary School (RSD) [1339 Clouet Street, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – Tuna Construction LLC

• Mothballing of Closed Schools – Safe & Secure Construction Phase

• Roofing work at terrace is complete

• Metal panels over exterior windows is 40% complete

• Contractual Substantial Completion – November 2012

• Forecasted Substantial Completion – November 2012

Morris F. X. Jeff Elementary School (RSD) [800 N. Rendon Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – CDW Services, LLC

• Mothballing of Closed Schools – Safe & Secure

Procurement Phase

• Contract is being reviewed by LDOE

Page 35: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

32 Status Date: 31 August 2012

• Notice to Proceed is anticipated September 12th

• Contractual Substantial Completion – December 2012

• Forecasted Substantial Completion – December 2012

Valena C. Jones Elementary School (RSD) [1901 N. Galvez Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – CDW Services, LLC

• Mothballing of Closed Schools – Safe & Secure

Procurement Phase

• Contract is being reviewed by LDOE

• Notice to Proceed is anticipated September 17th

• Contractual Substantial Completion – December 2012

• Forecasted Substantial Completion – December 2012

George Mondy Elementary School (RSD) [2327 St. Phillip Street, New Orleans, LA 70119]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – TBD

• Mothballing of Closed Schools – Safe & Secure Procurement Phase

1st Advertisement – September 25th 2nd Advertisement – October 2nd

Page 36: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

33 Status Date: 31 August 2012

3rd Advertisement – October 9th Pre-Bid Conference – 9:00 a.m. on October 10th at

Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – October 30th

• Forecasted Substantial Completion – March 2013

John A. Shaw Elementary School (RSD) [2518 Arts Street, New Orleans, LA 70117]

Scope of work: Design Services to assist in determining the condition of the facilities both interior and exterior, make recommendations to stabilize the facilities and provide drawings required to provide a water barrier, ventilation, and rudimentary fire defection and to secure openings and entryways. Construction Services to stabilize the facility according to the designer’s drawings and specifications.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – Zimmer-Eschette Services II, LLC

• Mothballing of Closed Schools – Safe & Secure

Construction Phase

• Replacement of fire damaged materials is complete

• Metal panels over exterior windows is 50% complete

• Contractual Substantial Completion – August 2012

• Forecasted Substantial Completion – September 2012

Page 37: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

34 Status Date: 31 August 2012

Demolition Projects

Fannie C. Williams Elementary School (RSD) [11755 Dwyer Street, New Orleans, LA 70128]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.

• Funding Source – FEMA

• Architect – VergesRome Architects, APAC

• Contractor – TBD

• Demolition of the Modular Classrooms

Procurement Phase

• 1st Advertisement – August 14th

• 2nd Advertisement – August 21st

• 3rd Advertisement – August 28th

• Pre-Bid Conference – 9:00 a.m. on August 29th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

• Bid Opening – September 18th

• Forecasted Substantial Completion – February 2013

Greater St. Stephens School (OPSB)

[11110 Lake Forest Boulevard 70128]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.

• Funding Source – FEMA

• Architect – Chenevert Architects LLC

• Contractor – TBD

• Procurement Phase

1st Advertisement – August 9th 2nd Advertisement – August 16th

3rd Advertisement – August 23rd

Page 38: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

35 Status Date: 31 August 2012

Pre-Bid Conference – 9:00 a.m. on August 27th at Jacobs/CSRS Program Management, 909 Poydras Street, Suite 1200, New Orleans, LA

Bid Opening – September 13th

• Forecasted Substantial Completion – February 2013

L. B. Landry Annex Demolition (RSD) [1100 Wagner Street, New Orleans, LA 70114]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.

• Funding Source – FEMA

• Architect – Perez Architects

• Contractor – Gulf Services

• Procurement Phase

Bid Opening – August 14th Contract is being reviewed by the contractor

• Forecasted Substantial Completion – Feburary 2013 Mary Church Terrell Elementary School Demolition (RSD) ) [3411 Broadway, New Orleans, LA 70125]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.

• Funding Source – FEMA

• Architect – SCNZ Architects

• Contractor – Hamp’s Construction LLC

• Procurement Phase

Bid Opening – July 31st Contract is being reviewed by the contractor

• Forecasted Substantial Completion – December 2012

Page 39: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

36 Status Date: 31 August 2012

Booker T. Washington High School Partial Demolition (RSD) [1201 S. Roman Street, New Orleans, LA 70125]

Scope of work: Perform a site survey, environmental assessment, demolition design documents and specifications, and perform contract administration of the demolition of designated structures at the facility. Perform the demolition of the designated structures at the site, remove debris, and clear the site for other purposes.

• Funding Source – FEMA

• Architect – Hewitt-Washington & Associates

• Contractor – Gulfcon LLC

• Partial Demolition

Construction Phase

• Demolition of interior of main building is 60% complete

• Leaaf Environmental as given notice to proceed on the environmental plan for DEQ

• Contractual Substantial Completion – Feburary 2013 • Forecasted Substantial Completion – February 2013

Page 40: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

37 Status Date: 31 August 2012

Comprehensive List - Completed Projects

• Abrams | Morial | Abramson | Coghill Demolition (RSD)

• A. D. Cross Elementary School Energy Conservation (RSD)

• Agnes Bauduit Elementary School Boiler (RSD)

• Alfred Lawless Senior High Security Fencing (RSD)

• Alice M. Harte Elementary School Demolition (OPSB)

• Andrew H. Wilson Elementary School Cottage (RSD)

• Arthur Ashe Elementary School (OPSB)

• Arthur Ashe Elementary School Kitchen Renovation (OPSB)

• Augustine Elementary School (RSD)

• Avery-Alexander Elementary School Demolition (RSD)

• Barbara C. Jordan Elementary School Demolition (RSD)

• Bell JH Shoring (RSD)

• Benjamin Banneker Elementary School Energy Conservation (RSD)

• Bienville Elementary School Demolition (RSD)

• Jean Batiste de Bienville School (RSD)

• Carter G. Woodson Middle School Demolition (RSD)

• Central Services Warehouse Demolition (OPSB)

• Charles J. Colton Elementary Selective Demolition (RSD)

• Charles R. Drew Elementary Roof & Installation of Kitchen Hood (RSD)

• Cohen High School Health Clinic (RSD)

• A. D. Crossman Elementary School and Benjamin Banneker Elementary School (RSD)

• Douglass High School Under Floor Utilities (RSD)

• East BankSwing Space for Audubon Charter School (OPSB)

• Edward Livingston Middle School Demolition(RSD)

• Edward Henry Phillips Junior High School Demolition (OPSB)

• Edward Hynes School (OPSB)

• Edwards | Hardin | Lockett | Lawless Demolition (RSD)

• Eleanor L. McMain School Replacement of Existing Chillers (OPSB)

• Ernest N. Morial Elementary Security Fencing (RSD)

• Fannie C. Williams Elementary School Demolition (RSD)

• Fisk-Howard Elementary School Demolition (RSD)

Page 41: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

38 Status Date: 31 August 2012

• Florence J. Chester Elementary School Demolition (RSD)

• Francis W. Gregory Demolition (RSD)

• Frederick A. Douglass High Switchgear (RSD)

• Frederick A. Douglass High Emergency Boiler Roof Repairs (RSD)

• George Washington Carver High School Demolition (RSD)

• Frances Gaudet/Lake Forest Elementary School (RSD)

• William J. Guste Elementary School (RSD)

• Murray G. Henderson Elementary School (RSD)

• Oretha C. Haley Elementary School (RSD)

• Henry Allen Elementary School Roof (RSD)

• Henry C. Schaumburg – Window/Door, Air Condition, Water Fountain/Sink Installation (RSD)

• Holy Cross Modular Relocation (RSD)

• Israel M. Augustine Middle School Roof Replacement (RSD)

• James Derham Demolition (RSD) • James W. Johnson Elementary School Roof (RSD)

• John Dibert Elementary School Roof (RSD)

• Jean Gordon Elementary School Demolition (RSD)

• John W. Hoffman Elementary School Demolition (RSD)

• John F. Kennedy Modular Relocation (Schwarz Campus) (RSD)

• John F. Kennedy Modular Relocation (Coghill Modular Campus) (RSD)

• John F. Kennedy High School Demolition (RSD)

• John McDonogh Senior High School Roof (RSD)

• Joseph A. Craig Elementary Canopies (RSD)

• Joseph A. Craig Elementary Elevator Installation (RSD)

• Joseph A. Hardin Elementary Security Fencing (RSD)

• Lake Area | Landry Demolition (RSD)

• Langston Hughes Elementary School (Phase I) (RSD)

• Langston Hughes Elementary School – New Gymnasium (Phase II) (RSD)

• Lawrence D. Crocker Elementary School Demolition (RSD)

• Little Woods Elementary School Demolition (RSD)

• Live Oak Elementary School (RSD)

• Live Oak Elementary School Exterior Door Replacement (RSD)

Page 42: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

39 Status Date: 31 August 2012

• Mahalia Jackson Elementary School (OPSB)

• Mahalia Jackson Elementary School Dumpster / Other Improvements(OPSB)

• Martin Behrman Elementary School Roof (RSD)

• Martin Luther King Jr. Elementary Canopy System (RSD)

• Martin Luther King Jr. School Modular Building, Deck, Canopy (RSD)

• Mary M. Bethune Elementary 1st Floor Replacement (OPSB)

• Mary M. Bethune Elementary Rear Yard Repair/Resurfacing (OPSB)

• McDonogh #15 Elementary Exterior Masonry to SOI Standards (RSD)

• McDonogh #28 Elementary School Roof (RSD)

• McDonogh #32 Roof Replacement (RSD)

• McDonogh #35 ADA Upgrades to Public Restrooms, Exterior Ramp & Handicap Seating in the Auditorium (OPSB)

• McDonogh #42 Elementary School Roof (RSD)

• McDonogh #42 Elementary School HVAC Replacement (RSD)

• Mildred C. Osborne Elementary School Demolition (RSD)

• Modular Campuses Close Outs (RSD)

• Modular Structures at Langston Hughes Elementary School (RSD)

• Morris F.X. Jeff Elementary School Demolition (RSD)

• New Andrew H. Wilson Elementary School (RSD)

• New Joseph A. Craig Elementary School (RSD)

• New Lake Area High School (RSD) • New L.B. Landry High School (RSD)

• New Equipment & Upgrades at 8 Central & 25 Satellite Kitchens (RSD)

• New Orleans High School Signature Center Study (RSD)

• Oretha C. Haley Demo (RSD)

• Parkview Elementary School Demolition (RSD)

• Paul L. Dunbar Elementary School Demolition (RSD)

• Phillis Wheatley Elementary School Demolition (RSD)

• Robert M. Lusher Elementary Roof Removal & Replacement (OPSB)

• Sarah T. Reed High School Bleachers (RSD)

• Sarah T. Reed High School Auditorium Wall (RSD)

• Seabrook Computer Training Center Demolition (OPSB)

• Schaumburg Chillers (RSD)

Page 43: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

40 Status Date: 31 August 2012

• Schwarz Alternative (RSD)

• Schwarz Alternative Modulars Demolition (RSD)

• Sherwood Forest Elementary School Demolition (RSD)

• Sophie B. Wright Various Repairs/Restroom Renovations (OPSB)

• Stuart R. Bradley Elementary School Demolition (RSD)

• Sylvanie Williams Elementary School Play Yard (RSD)

• Sylvanie Williams Elementary School HVAC/Chiller Replacement (RSD)

• Temporary Campus for McDonogh #11 Expropriation (OPSB)

• Thomas A. Edison Elementary School Demolition (RSD)

• Thomy Lafon Elementary School Demolition (RSD)

• Timbers Park Office Building #1 & #2 Demolition (OPSB)

• Vorice J. Waters Elementary School Demolition (RSD)

• West Bank Swing Space for Alice Harte Elementary School (OPSB)

• William J. Guste Elementary School (RSD)

• William J. Guste Elementary School Science Lab (RSD)

• William Frantz Elementary School Environmental Remediation & Selective Demolition (RSD)

• William Frantz Elementary School Roof (RSD)

Page 44: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

DEMOLITIONSWoodson MS Demolition FEMA Hamp's Enterprises, Inc 456,000.00$ 20,790.93$ 476,790.93$

Woodson MS Demolition Sum 476,790.93$ Gregory Junior High School Demolition FEMA Bayou Sheet Metal & Roofing, Inc. 342,000.00$ -$ 342,000.00$

M3A Architecture, PLLC 98,793.50$ (28,390.00)$ 70,403.50$ Gregory Junior High School Demolition Sum 412,403.50$

Jordan ES Demolition FEMA Louisiana Demolition, Inc. 180,299.65$ 7,931.00$ 188,230.65$ M3A Architecture, PLLC 62,795.00$ (15,203.90)$ 47,591.10$

Jordan ES Demolition Sum 235,821.75$ Fisk-Howard ES Demolition FEMA M3A Architecture, PLLC 55,426.00$ 9,800.00$ 65,226.00$

Fisk-Howard ES Demolition Sum 65,226.00$ Kennedy HS Demolition FEMA Contaminant Control 549,500.00$ 3,500.00$ 553,000.00$

Shaw Environmental & Infrastructure 186,028.68$ 45,960.17$ 231,988.85$ Kennedy HS Demolition Sum 784,988.85$

James Derham JHS Demolition (NOHSSC) FEMA Concrete Busters of LA 538,000.00$ 287,157.53$ 825,157.53$ SRF Group Consulting, LLC 94,759.50$ 1,872.00$ 96,631.50$

James Derham JHS Demolition (NOHSSC) Sum 921,789.03$ Lafon ES Demolition FEMA Shaw Environmental & Infrastructure 101,450.00$ (66,281.20)$ 35,168.80$

Lafon ES Demolition Sum 35,168.80$ Wheatley ES Demolition FEMA Zimmer-Eschette Service II, LLC 199,500.00$ 37,210.68$ 236,710.68$

Wheatley ES Demolition Sum 236,710.68$ Terrell ES Abatement & Demolition FEMA SCNZ Architects, LLC 27,777.00$ 23,166.00$ 50,943.00$

Terrell ES Abatement & Demolition Sum 50,943.00$ Andrew Bell JH Demolition FEMA VergesRome Architects, APAC -$ 10,147.00$ 10,147.00$

Andrew Bell JH Demolition Sum 10,147.00$ Oretha Haley ES Demolition FEMA RAMJ Construction, LLC 79,000.00$ -$ 79,000.00$

VergesRome Architects, APAC -$ 9,172.00$ 9,172.00$ Oretha Haley ES Demolition Sum 88,172.00$

George Mondy Demolition FEMA VergesRome Architects, APAC -$ 2,633.00$ 2,633.00$ George Mondy Demolition Sum 2,633.00$

Booker T Washington HS Demolition - Annex & Accessory Bldgs FEMA Gulfcon, LLC 778,870.00$ 171,326.14$ 950,196.14$ Hewitt-Washington & Associates Architects and Planne 80,385.00$ 5,796.60$ 86,181.60$

Booker T Washington HS Demolition - Annex & Accessory Bldgs Sum 1,036,377.74$ L.B. Landry Annex Building Demolition FEMA Perez, APC 26,533.50$ -$ 26,533.50$

L.B. Landry Annex Building Demolition Sum 26,533.50$ Fannie C Williams - Modular Bldgs Demolition FEMA VergesRome Architects, APAC 30,575.00$ -$ 30,575.00$

Fannie C Williams - Modular Bldgs Demolition Sum 30,575.00$

QUICKSTARTSLake Area HS Construction FEMA Farnsworth Group, Inc - Building Commissioning Quic 190,956.00$ -$ 190,956.00$

Lake Area HS Construction Sum 190,956.00$ Langston Hughes ES Construction FEMA Farnsworth Group, Inc - Building Commissioning Quic 137,296.00$ 45,358.28$ 182,654.28$

Roy Anderson Corp Contractors 26,430,000.00$ 1,219,581.15$ 27,649,581.15$ Langston Hughes ES Construction Sum 27,832,235.43$

L B Landry HS Construction FEMA Farnsworth Group, Inc - Building Commissioning Quic 213,985.00$ -$ 213,985.00$ Satterfield & Pontikes Construction Group LLC 52,723,000.00$ 3,072,801.10$ 55,795,801.10$

L B Landry HS Construction Sum 56,009,786.10$

Page 1

Page 45: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

PHASE 1 SCHOOLSFC Williams ES Construction FEMA Brice Building Company 21,997,000.00$ 186,979.74$ 22,183,979.74$

Farnsworth Group, Inc - Building Commissioning Quic 154,382.00$ 68,862.00$ 223,244.00$ Yeates & Yeates Architects, LLC -$ 2,039,343.37$ 2,039,343.37$

FC Williams ES Construction Sum 24,446,567.11$ Crocker ES Construction FEMA Chenevert Architects, LLC -$ 1,457,030.74$ 1,457,030.74$

Farnsworth Group, Inc - Building Commissioning 7 Ne 157,600.00$ 48,039.00$ 205,639.00$ Satterfield & Pontikes Construction Group LLC 18,598,500.00$ 850,406.66$ 19,448,906.66$

Crocker ES Construction Sum 21,111,576.40$ Frantz ES Renovation/Addition FEMA The Lathan Company 19,537,000.00$ 745,431.46$ 20,282,431.46$

Farnsworth Group, Inc - Building Commissioning Quic -$ 184,255.48$ 184,255.48$ Billes Architecture, LLC 855,945.00$ 1,157,217.45$ 2,013,162.45$

Frantz ES Renovation/Addition Sum 22,479,849.39$ Bienville ES Construction FEMA Howard Performance Architecture, LLC 1,336,822.00$ 296,197.29$ 1,633,019.29$

Walton Construction Company, a CORE Company, LLC 18,880,000.00$ 161,234.31$ 19,041,234.31$ Farnsworth Group, Inc - Building Commissioning 7 Ne 157,600.00$ 48,039.00$ 205,639.00$

Bienville ES Construction Sum 20,879,892.60$ Colton ES Renovation FEMA F.H. Paschen, S.N. Nielsen & Associates, LLC 26,173,000.00$ 150,335.34$ 26,323,335.34$

Waggonner & Ball Architects, APC 1,208,475.00$ 1,477,134.85$ 2,685,609.85$ Farnsworth Group, Inc - Building Commissioning 7 Ne 164,900.00$ 51,213.00$ 216,113.00$

Colton ES Renovation Sum 29,225,058.19$ Osborne ES Construction FEMA F.H. Paschen, S.N. Nielsen & Associates, LLC 21,375,000.00$ 52,250.33$ 21,427,250.33$

Fauntleroy Latham Weldon Barre Architects, APC 1,336,822.00$ 322,222.28$ 1,659,044.28$ Farnsworth Group, Inc - Building Commissioning 7 Ne 157,600.00$ 48,039.00$ 205,639.00$

Osborne ES Construction Sum 23,291,933.61$ Woodson ES Construction FEMA Brice Building Company 19,500,000.00$ 387,264.82$ 19,887,264.82$

Byron J. Stewart & Associates 1,336,822.00$ 283,630.93$ 1,620,452.93$ Farnsworth Group, Inc - Building Commissioning 7 Ne 157,600.00$ 58,932.63$ 216,532.63$

Woodson ES Construction Sum 21,724,250.38$ Parkview ES Construction FEMA Citadel Builders, LLC 21,137,000.00$ 332,477.00$ 21,469,477.00$

Rozas-Ward/a.i.a. architects, inc. 1,336,822.00$ 311,974.06$ 1,648,796.06$ Farnsworth Group, Inc - Building Commissioning 7 Ne 157,600.00$ 53,472.50$ 211,072.50$

Parkview ES Construction Sum 23,329,345.56$ Little Woods ES Construction FEMA Group Novak, LLC 1,498,299.00$ 166,099.84$ 1,664,398.84$

MAPP Construction, LLC 21,980,000.00$ -$ 21,980,000.00$ Farnsworth Group, Inc - Building Commissioning 5 plu 222,742.00$ -$ 222,742.00$

Little Woods ES Construction Sum 23,867,140.84$ Wheatley ES New Construction FEMA Holly & Smith Architects, APAC 1,749,900.00$ 199,622.06$ 1,949,522.06$

Farnsworth Group, Inc - Building Commissioning 5 plu 222,742.00$ -$ 222,742.00$ Wheatley ES New Construction Sum 2,172,264.06$

Wheatley ES Test Pile FEMA Holly & Smith Architects, APAC (blank) (blank) -$ Sealevel Construction, Inc. 52,990.00$ -$ 52,990.00$

Wheatley ES Test Pile Sum 52,990.00$ George W. Carver HS Construction FEMA Trapolin Architects & VMDO Architects, A Joint Ventur 3,238,172.00$ (2,232,525.80)$ 1,005,646.20$

Trapolin-Peer Architects, APC - VMDO Architects, PC-A 2,267,824.80$ 855,190.50$ 3,123,015.30$ Farnsworth Group, Inc - Building Commissioning 5 plu 321,880.00$ 17,500.00$ 339,380.00$

George W. Carver HS Construction Sum 4,468,041.50$ New Booker T Washington HS & Auditorium Rehabilitation FEMA Hewitt-Washington & Associates Architects 3,854,210.00$ 408,395.50$ 4,262,605.50$

Farnsworth Group, Inc - Building Commissioning 7 Ne 239,900.00$ 107,489.04$ 347,389.04$ New Booker T Washington HS & Auditorium Rehabilitation Sum 4,609,994.54$

Page 2

Page 46: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

PHASE 2 SCHOOLSNew HS @ Alfred Lawless - HS Construction FEMA Sizeler Thompson Brown Architects Project Design Gro 1,981,345.00$ 39,809.00$ 2,021,154.00$

New HS @ Alfred Lawless - HS Construction Sum 2,021,154.00$ Bradley ES Renovation/Construction FEMA Sizeler Thompson Brown Architects Project Design Gro 1,582,878.00$ 35,425.50$ 1,618,303.50$

Bradley ES Renovation/Construction Sum 1,618,303.50$ Drew ES Renovation FEMA Blitch Knevel Architects, Inc. 1,456,546.00$ -$ 1,456,546.00$

Drew ES Renovation Sum 1,456,546.00$ McDonogh 42 ES Renovation FEMA Eskew+Dumez+Ripple, APC 1,371,659.00$ -$ 1,371,659.00$

McDonogh 42 ES Renovation Sum 1,371,659.00$ Ernest 'Dutch' Morial School (New - PK-8) FEMA Waggonner & Ball Architects, APC 1,151,421.08$ -$ 1,151,421.08$

Ernest 'Dutch' Morial School (New - PK-8) Sum 1,151,421.08$ New Algiers School (New - PK-8) FEMA Waggonner & Ball Architects, APC 1,151,421.08$ -$ 1,151,421.08$

New Algiers School (New - PK-8) Sum 1,151,421.08$ Edward Livingston HS Construction FEMA Rozas-Ward/a.i.a. architects, inc. 1,058,410.78$ -$ 1,058,410.78$

Edward Livingston HS Construction Sum 1,058,410.78$ Avery Alexander School (New - PK-8) FEMA Waggonner & Ball Architects, APC 1,588,167.00$ -$ 1,588,167.00$

Avery Alexander School (New - PK-8) Sum 1,588,167.00$ Sherwood Forest School (New - PK-8) FEMA Waggonner & Ball Architects, APC 1,151,421.08$ -$ 1,151,421.08$

Sherwood Forest School (New - PK-8) Sum 1,151,421.08$ Sophie B Wright MS Renovation FEMA Waggonner & Ball Architects, APC 1,847,676.00$ -$ 1,847,676.00$

Sophie B Wright MS Renovation Sum 1,847,676.00$ Frederick A Douglass HS Renovation FEMA VergesRome Architects, APAC 2,618,653.00$ -$ 2,618,653.00$

Frederick A Douglass HS Renovation Sum 2,618,653.00$ New Orleans East HS (Abramson Site) FEMA Farnsworth Group, Inc 236,206.39$ -$ 236,206.39$

Rozas-Ward/a.i.a. architects, inc. 1,056,051.52$ -$ 1,056,051.52$ New Orleans East HS (Abramson Site) Sum 1,292,257.91$

REFERBISHEMENTSSCHOOL FUNDING SOURCE CONTRACTOR/ARCHITECT CONTRACT AMOUNT Change Orders/Amend Sum of Total Contract

Village de L'est ES Refurb FEMA BlitchKnevel Architects 6,145.00$ 14,786.00$ 20,931.00$ Village de L'est ES Refurb Sum 20,931.00$

Albert Wicker ES Refurb FEMA BlitchKnevel Architects 5,815.00$ 13,886.00$ 19,701.00$ Albert Wicker ES Refurb Sum 19,701.00$

Thurgood Marshall ES Refurb FEMA BlitchKnevel Architects 6,765.00$ 14,786.00$ 21,551.00$ Thurgood Marshall ES Refurb Sum 21,551.00$

Henry C. Schaumburg ES Refurb FEMA BlitchKnevel Architects 7,885.00$ 14,631.00$ 22,516.00$ Henry C. Schaumburg ES Refurb Sum 22,516.00$

Edgar P. Harney ES Refurb FEMA BlitchKnevel Architects 6,115.00$ 15,091.00$ 21,206.00$ Edgar P. Harney ES Refurb Sum 21,206.00$

Julius Rosenwald ES Refurb FEMA BlitchKnevel Architects 9,260.00$ 13,781.00$ 23,041.00$ Julius Rosenwald ES Refurb Sum 23,041.00$

Sylvanie Williams ES Refurb FEMA Chenevert Architects, LLC 4,218.35$ 15,330.75$ 19,549.10$ Sylvanie Williams ES Refurb Sum 19,549.10$

Agnes L. Bauduit ES Refurb FEMA Chenevert Architects, LLC 4,218.35$ 25,970.05$ 30,188.40$ Agnes L. Bauduit ES Refurb Sum 30,188.40$

Laurel ES Refurb FEMA Chenevert Architects, LLC 4,218.35$ 15,330.75$ 19,549.10$ Laurel ES Refurb Sum 19,549.10$

McDonogh 28 ES Refurb FEMA Chenevert Architects, LLC 4,218.35$ 15,330.75$ 19,549.10$ McDonogh 28 ES Refurb Sum 19,549.10$

McDonogh 7 ES Refurb FEMA Chenevert Architects, LLC 4,218.35$ 15,330.75$ 19,549.10$ McDonogh 7 ES Refurb Sum 19,549.10$

Schwarz Alternative HS Refurb FEMA Chenevert Architects, LLC 4,218.35$ 15,330.75$ 19,549.10$ Schwarz Alternative HS Refurb Sum 19,549.10$

Martin Luther King Jr. ES Refurb FEMA Chenevert Architects, LLC 4,218.35$ 15,330.75$ 19,549.10$ Martin Luther King Jr. ES Refurb Sum 19,549.10$

Henry Allen ES Refurb FEMA Perez, APC 6,241.00$ 9,760.00$ 16,001.00$ Henry Allen ES Refurb Sum 16,001.00$

Page 3

Page 47: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

STABILIZATIONS - Roofs Live Oak ES Repair of Auditorium Floor/Roof CDBG CMR Construction & Roofing LLC 759,625.00$ 224,763.62$ 984,388.62$

FEMA HMS Architects 65,736.00$ 13,883.43$ 79,619.43$ Live Oak ES Repair of Auditorium Floor/Roof Sum 1,064,008.05$

Dibert ES Roof FEMA Hamp's Construction 41,900.00$ -$ 41,900.00$ Dibert ES Roof Sum 41,900.00$

Gentilly Terrace ES Roof FEMA Hamp's Construction 67,900.00$ -$ 67,900.00$ Gentilly Terrace ES Roof Sum 67,900.00$

Roof Repairs Various Sites - Martin Luther King Charter Roof FEMA Hamp's Construction, LLC 57,192.00$ (blank) 57,192.00$ Richard C. Lambert Consultants, LLC 6,412.00$ 993.00$ 7,405.00$

Roof Repairs Various Sites - Martin Luther King Charter Roof Sum 64,597.00$ Roof Repairs Various Sites - Wicker ES Roof FEMA Hamp's Construction, LLC 11,452.00$ (blank) 11,452.00$

Richard C. Lambert Consultants, LLC 2,502.00$ (856.75)$ 1,645.25$ Roof Repairs Various Sites - Wicker ES Roof Sum 13,097.25$

Roof Repairs Various Sites - Tureaud ES Roof FEMA Hamp's Construction, LLC 14,602.00$ (blank) 14,602.00$ Richard C. Lambert Consultants, LLC 1,870.00$ (640.34)$ 1,229.66$

Roof Repairs Various Sites - Tureaud ES Roof Sum 15,831.66$ Roof Repairs Various Sites - Harney ES Roof FEMA Hamp's Construction, LLC 8,352.00$ (blank) 8,352.00$

Richard C. Lambert Consultants, LLC 584.00$ (199.98)$ 384.02$ Roof Repairs Various Sites - Harney ES Roof Sum 8,736.02$

Roof Repairs Various Sites - Tubman ES Roof FEMA Hamp's Construction, LLC 14,102.00$ (blank) 14,102.00$ Richard C. Lambert Consultants, LLC 325.00$ (111.29)$ 213.71$

Roof Repairs Various Sites - Tubman ES Roof Sum 14,315.71$ McDonogh 42 ES Roof & Stabilization FEMA Richard C. Lambert Consultants, LLC 36,334.00$ 11,549.80$ 47,883.80$

Roofing Solutions, LLC 370,200.00$ -$ 370,200.00$ McDonogh 42 ES Roof & Stabilization Sum 418,083.80$

Roof Repairs Various Sites - Eisenhower ES Roof Repairs FEMA Hamp's Construction, LLC 36,412.46$ (blank) 36,412.46$ HMS Architects, Inc. 6,586.00$ 1,614.00$ 8,200.00$

Roof Repairs Various Sites - Eisenhower ES Roof Repairs Sum 44,612.46$ Roof Repairs Various Sites - Jackson ES Roof Repairs FEMA Hamp's Construction, LLC 8,854.09$ (blank) 8,854.09$

HMS Architects, Inc. 3,731.00$ 534.00$ 4,265.00$ Roof Repairs Various Sites - Jackson ES Roof Repairs Sum 13,119.09$

Roof Repairs Various Sites - Paul Habans ES Roof Repairs FEMA Hamp's Construction, LLC 6,640.56$ (blank) 6,640.56$ HMS Architects, Inc. 2,182.00$ 534.00$ 2,716.00$

Roof Repairs Various Sites - Paul Habans ES Roof Repairs Sum 9,356.56$ Roof Repairs Various Sites - Sylvanie Williams Roof Repairs FEMA Hamp's Construction, LLC 4,980.43$ (blank) 4,980.43$

HMS Architects, Inc. 682.00$ 167.00$ 849.00$ Roof Repairs Various Sites - Sylvanie Williams Roof Repairs Sum 5,829.43$

Roof Repairs Various Sites - Clark Roof Repairs FEMA Hamp's Construction, LLC 5,312.46$ (blank) 5,312.46$ HMS Architects, Inc. 474.00$ 116.00$ 590.00$

Roof Repairs Various Sites - Clark Roof Repairs Sum 5,902.46$ Gaudet/Lake Forest Charter Roof FEMA Chatmon Construction, LLC 281,370.00$ -$ 281,370.00$

HMS Architects, Inc. 37,967.00$ -$ 37,967.00$ Gaudet/Lake Forest Charter Roof Sum 319,337.00$

Murray Henderson ES Roof FEMA Crown Architectural Metal Co, LLC 55,834.00$ -$ 55,834.00$ HMS Architects, Inc. 666.00$ 39,574.40$ 40,240.40$

Murray Henderson ES Roof Sum 96,074.40$ McDonogh 28 ES Roof FEMA Richard C. Lambert Consultants, LLC 325.00$ 7,932.60$ 8,257.60$

Roofing Solutions, LLC 46,000.00$ 1,312.51$ 47,312.51$ McDonogh 28 ES Roof Sum 55,570.11$

McDonogh 32 ES Roof FEMA Richard C. Lambert Consultants, LLC 905.00$ 40,650.00$ 41,555.00$ The Ellis Company, LLC 417,600.00$ -$ 417,600.00$

McDonogh 32 ES Roof Sum 459,155.00$ Marquis de Lafayette - Roof & Masonry Repairs FEMA Montgomery Roth Architecture & Interior Design, LLC 99,152.00$ (10,797.00)$ 88,355.00$

The Lathan Company 857,020.00$ -$ 857,020.00$ Marquis de Lafayette - Roof & Masonry Repairs Sum 945,375.00$

Village de L'est Roof Repairs (Einstein Charter) FEMA Richard C. Lambert Consultants, LLC 9,269.00$ 13,928.01$ 23,197.01$ Village de L'est Roof Repairs (Einstein Charter) Sum 23,197.01$

Andrew J Bell Roof Replacement FEMA VergesRome Architects, APAC -$ 70,290.00$ 70,290.00$ Andrew J Bell Roof Replacement Sum 70,290.00$

Page 4

Page 48: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

STABILIZATIONS - Various Reed High School Wall Repair FEMA Precision Construction & Maintenance, LLC 10,850.00$ -$ 10,850.00$

Reed High School Wall Repair Sum 10,850.00$ Live Oak ES (Door Replacement) CDBG M. Slayton Construction, Inc. 319,500.00$ -$ 319,500.00$

FEMA HMS Architects, APC 37,529.00$ 6,717.00$ 44,246.00$ Live Oak ES (Door Replacement) Sum 363,746.00$

Sarah T Reed - Bleachers FEMA Hamp's Construction, LLC 67,700.00$ -$ 67,700.00$ Trapolin-Peer Architects, APC 11,822.50$ (3,838.50)$ 7,984.00$

Sarah T Reed - Bleachers Sum 75,684.00$ John McDonogh HS - Bleachers Harrah's Trapolin-Peer Architects, APC 11,822.50$ -$ 11,822.50$

John McDonogh HS - Bleachers Sum 11,822.50$ Fredrick Douglass HS Room #214 Remodel Insurance Proceedes Montgomery Roth Architecture & Interior Design, LLC 10,942.00$ -$ 10,942.00$

Fredrick Douglass HS Room #214 Remodel Sum 10,942.00$ Guste ES Roof Replacement & Elevator Installation FEMA Crown Architectural Metal Co 1,105,000.00$ -$ 1,105,000.00$

N-Y Associates, Inc. 70,624.00$ 24,854.00$ 95,478.00$ Guste ES Roof Replacement & Elevator Installation Sum 1,200,478.00$

Carbon Credit - AD Crossman (aka Esperanza Charter) Harrah's Integrated Management Services, P.A., Inc. 16,329.19$ 22,528.19$ 38,857.38$ W.L. Wyman Construction Company, Inc 199,850.00$ -$ 199,850.00$

Carbon Credit - AD Crossman (aka Esperanza Charter) Sum 238,707.38$ Carbon Credit - Banneker ES Harrah's Integrated Management Services, P.A., Inc. 5,749.00$ 15,143.81$ 20,892.81$

W.L. Wyman Construction Company, Inc 143,350.00$ -$ 143,350.00$ Carbon Credit - Banneker ES Sum 164,242.81$

Sylvanie Williams HVAC & Chiller Replacement FEMA Integrated Management Services, P.A., Inc. -$ 49,802.00$ 49,802.00$ Towers Construction LLC 398,000.00$ -$ 398,000.00$

Sylvanie Williams HVAC & Chiller Replacement Sum 447,802.00$ Douglass HS - Replace under floor utilities & Selective HVAC FEMA Infinity Engineering Consultants, LLC 32,529.00$ (3,909.10)$ 28,619.90$

Douglass HS - Replace under floor utilities & Selective HVAC Sum 28,619.90$ Langston Hughes ES - Dumpster Pad FEMA Lachin Oubre & Associates, APC 6,000.00$ -$ 6,000.00$

Tuna Construction, LLC 42,500.00$ -$ 42,500.00$ Langston Hughes ES - Dumpster Pad Sum 48,500.00$

McDonogh 15 ES - Exterior Masonry Repair FEMA Hamp's Construction, LLC 176,900.00$ -$ 176,900.00$ VergesRome Architects, APAC -$ 21,975.50$ 21,975.50$

McDonogh 15 ES - Exterior Masonry Repair Sum 198,875.50$ Andrew Jackson ES Solar Panels GNOF - Entergy Perez, APC 22,578.00$ -$ 22,578.00$

South Coast Solar, LLC 145,180.00$ -$ 145,180.00$ Andrew Jackson ES Solar Panels Sum 167,758.00$

Martin Luther King - Modular Buildings Harrah's Perez, APC -$ 15,433.00$ 15,433.00$ T & D Contractors 142,100.00$ -$ 142,100.00$

Martin Luther King - Modular Buildings Sum 157,533.00$ Sylvanie Williams ES AHU FEMA Integrated Management Services, P.A., Inc. -$ 39,757.00$ 39,757.00$

Sylvanie Williams ES AHU Sum 39,757.00$ Village de L'est ES Subsidence FEMA Owen Construction Company LLC 98,900.00$ -$ 98,900.00$

Richard C. Lambert Consultants, LLC -$ 18,198.00$ 18,198.00$ Village de L'est ES Subsidence Sum 117,098.00$

Page 5

Page 49: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

MOTHBALLINGIsrael Augustine Roof FEMA Crown Architectural Metal Co 301,000.00$ 55,338.75$ 356,338.75$

VergesRome Architects, APAC -$ 38,523.00$ 38,523.00$ Israel Augustine Roof Sum 394,861.75$

Andrew J Bell Shoring Main Classroom Building FEMA Abry Brothers, Inc. 910,000.00$ 273,425.00$ 1,183,425.00$ VergesRome Architects, APAC -$ 106,095.00$ 106,095.00$

Andrew J Bell Shoring Main Classroom Building Sum 1,289,520.00$ Israel Augustine Safe & Secure FEMA C.D.W. Services, LLC 729,000.00$ -$ 729,000.00$

VergesRome Architects, APAC 71,059.00$ (2,905.00)$ 68,154.00$ Israel Augustine Safe & Secure Sum 797,154.00$

Louis Armstrong Mothballing FEMA C.D.W. Services, LLC (blank) (blank)VergesRome Architects, APAC 26,023.00$ 11,880.00$ 37,903.00$

Louis Armstrong Mothballing Sum 37,903.00$ Andrew J Bell Safe & Secure - Mothballing FEMA VergesRome Architects, APAC 92,568.00$ 3,131.00$ 95,699.00$

Andrew J Bell Safe & Secure - Mothballing Sum 95,699.00$ Oretha Haley ES Mothballing FEMA C.D.W. Services, LLC 440,000.00$ -$ 440,000.00$

VergesRome Architects, APAC 26,023.00$ 29,665.00$ 55,688.00$ Oretha Haley ES Mothballing Sum 495,688.00$

Lorraine Hansberry Mothballing FEMA Tuna Construction, LLC 495,000.00$ -$ 495,000.00$ VergesRome Architects, APAC 26,023.00$ 35,725.00$ 61,748.00$

Lorraine Hansberry Mothballing Sum 556,748.00$ Morris Jeff Mothballing FEMA C.D.W. Services, LLC (blank) (blank)

VergesRome Architects, APAC 26,023.00$ 11,220.00$ 37,243.00$ Morris Jeff Mothballing Sum 37,243.00$

Valena Jones Mothballing FEMA C.D.W. Services, LLC (blank) (blank)VergesRome Architects, APAC 26,023.00$ 12,430.00$ 38,453.00$

Valena Jones Mothballing Sum 38,453.00$ George Mondy ES Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 11,220.00$ 37,243.00$

George Mondy ES Mothballing Sum 37,243.00$ John Shaw Mothballing FEMA VergesRome Architects, APAC 26,023.00$ 33,837.00$ 59,860.00$

Zimmer-Eschette Service II, LLC 489,900.00$ -$ 489,900.00$ John Shaw Mothballing Sum 549,760.00$

Page 6

Page 50: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents

 

BESE MONTHLY REPORT

OPEN CONTRACTS as of 09/05/12

PROJECT FUNDING SOURCE CONTRACTOR/ARCHITECT

ORIGINAL CONTRACT AMOUNTS

CHANGE ORDERS/

AMENDMENTS CONTRACT AMOUNTS

BUILDING AUTOMATION SYSTEMBuilding Automation System - Bienville FEMA Moses Engineers, Inc. -$ 2,275.16$ 2,275.16$

Synergy Building Solutions 18,238.90$ -$ 18,238.90$ Building Automation System - Bienville Sum 20,514.06$

Building Automation System - Colton FEMA Moses Engineers, Inc. -$ 3,633.41$ 3,633.41$ Synergy Building Solutions 29,127.41$ -$ 29,127.41$

Building Automation System - Colton Sum 32,760.82$ Building Automation System - Craig ES FEMA Moses Engineers, Inc. 10,873.76$ 2,370.11$ 13,243.87$

Synergy Building Solutions 56,716.33$ -$ 56,716.33$ Building Automation System - Craig ES Sum 69,960.20$

Building Automation System - Crocker FEMA Moses Engineers, Inc. -$ 2,060.12$ 2,060.12$ Synergy Building Solutions 16,515.03$ -$ 16,515.03$

Building Automation System - Crocker Sum 18,575.15$ Building Automation System - FC Williams FEMA Moses Engineers, Inc. -$ 2,185.10$ 2,185.10$

Synergy Building Solutions 17,516.91$ -$ 17,516.91$ Building Automation System - FC Williams Sum 19,702.01$

Building Automation System - Frantz FEMA Moses Engineers, Inc. -$ 2,181.43$ 2,181.43$ Synergy Building Solutions 17,487.49$ -$ 17,487.49$

Building Automation System - Frantz Sum 19,668.92$ Building Automation System - L.B. Landry HS FEMA Moses Engineers, Inc. 10,873.76$ 1,555.96$ 12,429.72$

Synergy Building Solutions 50,189.62$ -$ 50,189.62$ Building Automation System - L.B. Landry HS Sum 62,619.34$

Building Automation System - Lake Area HS FEMA Moses Engineers, Inc. 10,873.76$ 1,397.88$ 12,271.64$ Synergy Building Solutions 48,450.83$ -$ 48,450.83$

Building Automation System - Lake Area HS Sum 60,722.47$ Building Automation System - Langston Hughes ES FEMA Moses Engineers, Inc. 10,873.76$ 2,370.11$ 13,243.87$

Synergy Building Solutions 44,855.18$ -$ 44,855.18$ Building Automation System - Langston Hughes ES Sum 58,099.05$

Building Automation System - Osborne FEMA Moses Engineers, Inc. -$ 2,232.89$ 2,232.89$ Synergy Building Solutions 17,900.05$ -$ 17,900.05$

Building Automation System - Osborne Sum 20,132.94$ Building Automation System - Parkview FEMA Moses Engineers, Inc. -$ 2,378.08$ 2,378.08$

Synergy Building Solutions 19,063.99$ -$ 19,063.99$ Building Automation System - Parkview Sum 21,442.07$

Building Automation System - Sarah T Reed FEMA Moses Engineers, Inc. (blank) (blank) -$ Synergy Building Solutions (blank) 12,027.80$ 12,027.80$

Building Automation System - Sarah T Reed Sum 12,027.80$ Building Automation System - Sylvanie Williams FEMA Moses Engineers, Inc. (blank) (blank) -$

Synergy Building Solutions (blank) 11,075.21$ 11,075.21$ Building Automation System - Sylvanie Williams Sum 11,075.21$

Building Automation System - Wilson ES FEMA Moses Engineers, Inc. 10,873.76$ 903.44$ 11,777.20$ Synergy Building Solutions 44,958.72$ -$ 44,958.72$

Building Automation System - Wilson ES Sum 56,735.92$ Building Automation System - Woodson FEMA Moses Engineers, Inc. -$ 2,164.90$ 2,164.90$

Synergy Building Solutions 17,355.04$ -$ 17,355.04$ Building Automation System - Woodson Sum 19,519.94$

OTHER PROFESSIONAL SERVICESPM/CM FEMA Jacobs Project Management/CSRS Consortium 26,994,177.00$ 9,102,290.45$ 36,096,467.45$

PM/CM Sum 36,096,467.45$

GRAND TOTAL 376,872,425.22$

Page 7

Page 51: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents
Page 52: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents
Page 53: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents
Page 54: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents
Page 55: August 2012 Program Update OPSB & RSD Phase I …...Program Update OPSB & RSD Phase I Projects Program Financial Status Status Date: 31 August 2012 Note-The value in each phase represents