ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) Richard Apsimon (@CERN) Martin Gibson Stephen Haywood Jeff Bizzell Peter Phillips (@CERN/commuting) Richard Holt Steve McMahon (@CERN) & Lewis Batchelor (@CERN) Adlene Hicheur Bill Murray report Giulio Villani in Feb 06 Marc Weber Norman McCubbin John Hart Steve Dallison

Upload: adelia-dixon

Post on 30-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1

ATLAS SCT Builders Inc.2005 Annual Report

• Mike Tyndel (Group leader & SCT Project Leader)

– Richard Apsimon (@CERN)

– Martin Gibson– Stephen Haywood– Jeff Bizzell– Peter Phillips (@CERN/commuting)

– Richard Holt– Steve McMahon (@CERN)

&– Lewis Batchelor (@CERN)

– Adlene Hicheur– Bill Murray

report– Giulio Villani in Feb 06– Marc Weber– Norman McCubbin– John Hart– Steve Dallison

Page 2: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 2

CV M. Tyndel ( ….. 1972 – 2005 ….) “the Rutherford trail”

• First degree in NZ (birthplace of Ernest Rutherford)– “Search for quarks in cosmic rays”

• PhD in Rutherford building, Cambridge (1894-1898; 1919-1937)– “Properties of the K0 meson using 2m bubble chamber”

• Post-doc at Rutherford Laboratory– “Neutrino physics using bubble chambers”

• Technical adventures at RAL and CERN– Upgrade external Muon system for BEBC– Small diversion into solar neutrinos– Calorimetry for DELPHI– b-tagging studies & design & development of first collider vertex detector– ATLAS SCT– Electronics (DSM) and pixel development (MAPs)

• …. & then the ‘leader’ phase– Project leader DELPHI Micro-vertex CERN– Group leader RAL tracking– Project leader ATLAS SCT tracker

Page 3: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 3

Point 1 activities and perspectives

Marzio Nessi

ATLAS plenary 2nd October 2004

SCT

ATLAS

LHC @ CERN

Page 4: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 4

Activities of the ATLAS tracking group

• Past (1992 - )– Design of the ATLAS SCT

– Established the CCLRC clean room facility in R12

– Assembled & tested >700 silicon modules & >900 hybrids

– Designed & built support structures & cooling

– Assembled & tested Optical links & power tapes

– Engineering (~30 EID people involved)

• Present (2005)– Integrating SCT into ATLAS

– Installing services & getting SCT ready for physics

– Preparing Readout & DAQ

• Future (2006 – )– Commissioning & data-taking

– Physics

– Preparing an Upgraded tracker for 2015

• 10x more channels 2015

2007 Up to 1000 tracks

1 billion collisions/sec

10 billion collisions/sec

Page 5: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 5

Pictures of ATLAS

Page 6: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 6

Tracking in ATLAS

• Barrel = 4 Carbon cylinders tiled with silicon detector modules

B6 • 2 Endcaps = 9 Carbon discs tiled with

silicon detector modules

D5

• SCT = Silicon tracker; a device to measure tracks precisely (~20m)

Page 7: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 7

Gluing sensors

Hybrid MountingSensor Alignment

Module in Test Box

A silicon module is:4 silicon detectors

1536 particle detecting strips & readout amplifiers

Page 8: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 8

Assembly steps at RAL

Engineering Structures & cooling

Optolinks and power Assembly

Page 9: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 9

Assembly steps at CERNthe first barrel

Page 10: ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 1 ATLAS SCT Builders Inc. 2005 Annual Report Mike Tyndel (Group leader & SCT Project Leader) –Richard Apsimon

ATLAS Tracker Group PPD Staff Talk 28/Nov/2005 10

Assembly steps at CERNthe 3rd barrel