ATLAS SCT Status Report. Overview of major production issues Silicon sensors & FE ASIC procurement Power & Readout Power supplies Readout DAQ & DCS Barrel Barrel modules Barrel Harnesses Barrel Engineering Endcap Endcap modules Endcap Engineering Testbeam - PowerPoint PPT Presentation

TRANSCRIPT

  • ATLAS SCT Status ReportOverview of major production issues Silicon sensors & FE ASIC procurementPower & Readout Power supplies Readout DAQ & DCS

    Barrel Barrel modules Barrel Harnesses Barrel Engineering

    Endcap Endcap modules Endcap Engineering

    Testbeam

    Schedule & critical issues

    AOW 2003 Prague - SCT Report

  • SCT silicon sensors procurementProduction & acceptance testing of the silicon sensors is ~ completeQuality of the detectors is excellentAll quantities within specificationHamamatsu barrel detector summaryVery low leakage currentsTypically 99.9% good readout strips

    CIS detectors: some IV problems

    0.2 mA# defects

    AOW 2003 Prague - SCT Report

  • SCT ASIC procurement Post irradiation studies indicate 10years lifetime @ LHCProduction stopped by ATMELUse ASICs with 1 ch. out of specs wherever reasonable (possible): qualification, rework, etc.

    Wafers delivered1053Wafers accepted (Yield >10%)798Yield of the accepted wafers is26%Fraction of wafers rejected24%Number of die accepted53K% of total requirement (61.5K)~86%Die with 1 channel out of spec~24%

    AOW 2003 Prague - SCT Report

  • SCT Readout & Power systemSystem specification 4088 modules x 1536 channels6 x 106 readout channels40 kW power100 m detector control room

    Readout =RODs48Channels/VME cardPre-series of 7 cards being evaluated+BOCOptoelectronic Back of crate cards First 10% batch in productionCustom Opto-packages in production in Taiwan+ TIMAvailable for assembly+Crates, backplanes &SBC+Optical fibresSystem statusAll elements prototyped and ATLAS PRR completed Readout & power needed for testing during assembly

    Power & Cables =LV0 cards (Prague)4 channels/card10% production delivered and burned in +HV0 cards8 channels/card10% production launched+Backplane, 48V &5V power supplies+Crate controller, crates+Patch-panelsPP3 with filters & limiters on ATLAS+Cables 4 typesTender started in August

    AOW 2003 Prague - SCT Report

  • SCT Power system schematic

    AOW 2003 Prague - SCT Report

  • SCT Readout & Power systemReadout (ROD/BOC/TIM) system is under user evaluationFirst unit has readout 4 modules in different configurationsPerformance meets specification trying to reduce calibration timeSystems are being prepared for macro-assembly sites

    Power systemFirst crate has been tested with dummy loads & modules, 10% LV cards deliveredPerformance meets specificationSystems are being produced for macro-assembly sites

    DateNo. of 48Ch cardsTotalCommentAugust 20037Pre-seriesSeptember 200366First series deliveriesOctober 2003410November 2003818January 20042240April 20041252Total for assemblyJanuary 200540+spares92+sparesTotal available for installation

    AOW 2003 Prague - SCT Report

  • SCT DAQ & DCSMajor effort now underway to develop DAQ & DCS within ATLAS frameworkAssembly & integration sites

    AOW 2003 Prague - SCT Report

  • SCT DAQ & DCS

    AOW 2003 Prague - SCT Report

  • SCT Module Design (Endcap)4 wedge shape silicon sensors

    768 p-in-n strips, single sided

    supplied by Hamamatsu and CiS

    sensor alignment < 5m

    40mrad stereo angleSPINETPG bar for heat removal (1700 W/m/K)

    AlN wings for mechanical stability hybrid connected to sensors only by fanins thermal split12 ABCD3TA binary read-out chips

    hybrid: flex circuit on carbon-carbon

    AOW 2003 Prague - SCT Report

  • SCT Barrel modulesBarrel modules are in production

    Barrel module PRRMay 01Silicon sensor production completeMay 03 Barrel module PARMay 03

    Hybrids complete (target)Aug 031214/2500 (49%)Baseboards complete (target)Oct 031481/2530 (59%)

    Modules-Japan 445/ 786 (57%)Modules-UK 144/ 549 (26%)Modules-US 104/ 483 (21%)Modules-Scand (qualification soon)31/ 404 ( 8%)Total (2112+5%)734/ 2218 (33%)

    Modules complete (target)Apr 04

    Production goal is to complete by Apr 04 with a yield > 90%

    AOW 2003 Prague - SCT Report

  • SCT Barrel baseboard & hybrid productionProduction rate is under control (recently stalled, but recovered)

    AOW 2003 Prague - SCT Report

  • SCT Barrel module assembly

    Note : Backup slide on s-curvesCritical issues:Get all clusters into productionProduction yield > 90%

    AOW 2003 Prague - SCT Report

  • SCT Barrel OptoharnessesOpto-harnesses are in productionBarrel LM tape production completeFirst 2 batches of 8 harnesses each for Barrel-3 evaluatedStart-up delay was caused by ESD damage to DORIC ASIC & other production issuesStart of production recommended

    Schedule can be recovered (complete production by the end of 2003)

    AOW 2003 Prague - SCT Report

  • SCT Barrel LM tapes & patchpanels

    AOW 2003 Prague - SCT Report

  • SCT Barrel Optoharnesses

    AOW 2003 Prague - SCT Report

  • SCT Barrel Engineering Support StructureAll 4 CF cylinders deliveredbut there are ~40000 small parts!B3 delivered to RALB4,5,6 assembly test starting

    AOW 2003 Prague - SCT Report

  • SCT Barrel Engineering - CoolingDesign is finalised48 module unitsCuNi with soldered joints

    Concept tested on sector

    Cooling design is evolving; which causes delays

    Production is ready to start

    AOW 2003 Prague - SCT Report

  • SCT Barrel Engineering - AssemblyAssembly phasesSpindle & service cagesUnderwayFSICompletedOpto-harnessesDeliveredCoolingWaiting coolingModulesModules available

    Oxford Assembly site almost ready4 months lateB3 harness assembly at RAL

    AOW 2003 Prague - SCT Report

  • SCT Endcap ModulesModulesEndcap module FDR & PRRAug 02 & Dec 02Module design was validated as suitable for productionThermal & electrical performance validated

    ProductionHybridsHybrid production & assembly transferred to industryPre-series of 200 in production 44(+48) delivered, remaining show delamination problemsFull order for 2300 placed (2500 in total)Spines229 produced by Protvino/MPI, but with low quality Contract for 2500 issuedModule assembly3 out of 7 production sites qualified for production1rst modules within specificationAim is to have all sites qualified in 2 monthsTarget is to complete module production in Dec 04

    AOW 2003 Prague - SCT Report

  • SCT Endcap hybrid & module production

    AOW 2003 Prague - SCT Report

  • SCT Endcap Modules

    Hybrid production is starting need industry to sort out quality problems and achieve required rateSpine production is criticalOther components are ~ OK (with additional collaboration effort)Rapid cluster qualification is critical Aggressive production plan being developed (see backup)

    AOW 2003 Prague - SCT Report

  • SCT Endcap Endcap Engineering - Structure Support structuresCF support cylinders & disks orderedFirst support cylinder shown Scheduled delivery Aug 03Problems with wings which will cause 3-4months delayFirst 4 discs deliveredScheduled completion Dec 03Again many small parts

    AOW 2003 Prague - SCT Report

  • SCT Endcap Endcap Engineering - Cooling CoolingDesign is finalised & prototypedProduction of cooling circuits ready to startServicesHarnesses expected nowLM tapes & PPF0 prototyped

    AOW 2003 Prague - SCT Report

  • SCT Testbeam 2002/3 & 2004Understanding of intrinsic performance of an increasing number of real modules with final components

    June 2002, 2 weeksJuly 2002, 2 weeksAugust 2002, 2 weeksMay 2003, 2 weeks including 25ns measurementsSeptember 2003, ~2 weeks; irradiated modules; common DAQ run2004 Plans for tracking; common DAQ

    AOW 2003 Prague - SCT Report

  • SCT Testbeam 2002/3(preliminary)

    AOW 2003 Prague - SCT Report

  • SCT Testbeam track finding studies(preliminary)Example of a second track due to hard interaction with silicon.Example of a track reconstructed in telescope & 4 planes

    AOW 2003 Prague - SCT Report

  • SCT schedule & Critical issuesBarrel SCT (ready for integration 15/12/04; ID ready 22/05/05)Modules~33% complete~3 months delayFull production all clustersYield is criticalHarnesses~1% complete~4 months delayBarrel-3 complete~3 months lateB3 services ~4 months late

    B3 assembly start~5 months late

    Endcap SCT (ready for integration 01/03(05)/05; ID ready 16/08(10)/05)Current schedule delivers the Endcaps 2 & 4 months late wrt baselineModulesStarting productionSpines criticalHarnessesStartedDisc-9To be delivered now~4 months lateCriticalD9 services Most orders placed~6 months lateCritical

    D9 assembly start~5 months late

    Power, Readout & cables are OK for the experiment but critical for use during assembly

    AOW 2003 Prague - SCT Report

  • Invitation For The Lab ToursAStrip Detector Lab - Institute of Physics ASStrip detectors for ATLASLVPSSCT Lab - Charles UniversityEnd Cap Module ProductionBSemiconductor Lab - CTU, IEAPEnd Cap Module Production

    AOW 2003 Prague - SCT Report

  • Backup - SCT ABCD Yield

    AOW 2003 Prague - SCT Report

    Copy to Monthly Report

    Lot ##WafersRec.#Tested#RejectedYieldYield Accepted# of ChipsLot #Yield% RejectedMin Yield

    Z396931919221.6%23.7%1,031Z3969323.69%10.53%26.00%0

    Z399921515313.9%16.3%500Z3999216.28%20.00%26.00%0

    Z399932020129.2%30.3%1,474Z3999330.30%5.00%26.00%0

    Z406031212037.6%37.6%1,156Z4060337.63%0.00%26.00%0

    Z406152222227.2%29.4%1,506Z4061529.41%9.09%26.00%0

    Z406162222910.0%13.1%437Z4061613.13%40.91%26.00%0

    Z406172323122.1%22.9%1,289Z4061722.89%4.35%26.00%0

    Z408002323121.7%22.6%1,273Z4080022.60%4.35%26.00%0

    Z408011919234.5