atlas and cern/st 2nd april 2003 marzio nessi. 02/04/2003 today atlas project detector components...

41
ATLAS and CERN/ST 2nd April 2003 Marzio Nessi

Upload: howard-small

Post on 17-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

ATLAS and CERN/ST

2nd April 2003

Marzio Nessi

Page 2: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Today ATLAS project

Detector Components Construction

Detector Integration and Installation

ATLAS

Detector Deliverables

Common Projects

Large Systems Surface Assembly

Underground Assembly

Started in 1996

Well over 50% of all major components constructed

Some sub-detectors (like calorimeters) almost finished

Mid 2004 most of the components will be available

Construction schedule with 4 months installation float

Started in 2002

Calorimeters preassembly on surface well advanced

Toroids integration at CERN advanced but critical

Area infrastructure on surface well advanced

Underground installation (USA15) started

Page 3: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

ATLAS Project Schedule

Detector Components Construction

Large Systems Integration on Surface

Underground Assembly

97 99 01 03 05 07

USA15 UX15

com

mis

sion

ing

Page 4: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Large Systems Preassembly

Today at CERN (bldg 180, 185, 175, 191,…) we are assembling on the surface:

LAr Calorimeters (1 Barrel + 2 Endcaps)

Tile Calorimeters (1 Barrel + 2 Ext. Barrels)

Barrel Toroid individual Coils (8)

Barrel Toroid Endcaps (2)

Mechanical integration

Cryogenics integration

Electrical integration

Functional tests

During 2003 at CERN (bldg BB5, SR1, 157,…) we will start the assembling and integration work for:

Muon Spectrometer (Barrel and Endcaps)

Inner Detectors (3)

Work mostly done with Collaboration Manpower (eng, phys and tecs) + CERN services (ST/HM, EST/SU, LHC/ECR,…)

Page 5: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

First half EM Barrel Calorimeter Cylinder insertion : Bldg 180

LAr EM half barrel in front of the cryostat

LAr EM half barrel after insertion into the cryostat

Page 6: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

LAr hadronic end-cap calorimeters : Bldg. 180

The LAr hadronic end-cap series production is completed, all 134 modules (including 6 spares) have been stacked

3 out of the 4 wheels are now pre-assembled and ready for insertion into the cryostat

Insertion into the cryostat awaits the assembly of the first EM wheel (which has to enter first)

Assembly of the first HEC wheel (horizontal)

Assembled wheel in insertion stand (vertical)

Page 7: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Tile Calorimeter pre-assembly: Bldg. 185

Regular survey measurements are taken to compare actual and expected deformations during assembly of the cylinders

Pre-assembly of the first Extended Barrel, expected to be complete by end of April 2004

Page 8: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Central Solenoid: Bldg. 180

Solenoid field: 2T with a stored energy of 38 MJ

The solenoid is fully tested, and ready at CERN for integration into the common cryostat with the LAr barrel EM calorimeter by the end of 2003

Cryogenics chimney tested in summer 2002

Page 9: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Barrel Toroid Integration 1: Bldg 180

Cold mass #3 to be

impregnated

next coil (#4) in preparation

2 cold masses ready

cold mass #3,4 in preparation

On schedule

Page 10: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Barrel Toroid Integration 2 : Bldg 180

Cooling pipes inst.,Tie- rods, instrumentation : ongoing coil 1&2

Cryostats preparation : just started

Cryostat welding : scheduled

Heat shields, insulation installation : waiting for material

Cooling and B-tests : first time: July 03-Sep03

• Major problems of quality of cooling pipe welding just solved

• 3 months delay in the delivery of first Heat Shields

-> remains very critical, today just in time for installation

Page 11: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Encap Toroids : HMA (NL)

cold mass fabrication :Pancake windings 8 of 16 done

First coil impregnated

Web structures manufacturing 60% done

The first of the two cold masses is expectedto be delivered to CERN in October 2003, ahead of schedule

Page 12: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Endcap Toroids integration: Bldg 191

Heat shields

Installation of the super-insulation

The two vacuum vessels have been completed, delivered toCERN, and vacuum tested

They are being prepared to receive the cold masses

Page 13: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Production Concerns

Technical problems

See WWW top-worries list: http://atlas.web.cern.ch/Atlas/TCOORD/TMB/

Barrel toroid integration and coil tests (Heat shields,..) DMILL chips technology (6 types still in production) TRT on detector electronics boards (Webs, barrel PCBs) Production start-up of forward SCT modules TRT gas system TRT wheel assembly (schedule and resources) RPC chambers production Beam pipe activation Cables need timely procurement

Page 14: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Schedule Concerns (components production)

Production Schedule difficulties (with respect to ready for installation milestones = 4 months installation float)

Following system are using part of the 4-month float

- ID Barrel: 1.5 months (SCT 1.5 m, TRT 1m)

- ID Endcap C: 2.0 months (SCT)

- ID Endcap A: 4.0 months (SCT&TRT)

- LAr Barrel: 2.0 months - LAr Endcap C: 1.5 months

- LAr Endcap A: 1.0 month

- Barrel Toroid: 4.0 months (last 2 coils)Corrective actions to restore some of the installation time contingency will be investigated

during summer 2003, when the entire production chain is fully understood!

Page 15: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

ATLAS

Page 16: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation Constraints

Starting mid April 2003, ST/CE will deliver an empty cavern for the ATLAS Detector: UX15.

For cost reasons in 1995 it was decided to have 2 access shafts instead of a very large one: PX14 (diameter 18m) and PX16 (diameter 12.6m).

ATLAS will be lowered piece-by-piece and assembled 92 m underground during 3.5 years. The maximal weight allowed by the single surface crane is 280 tons. Underground we will have two 65-ton cranes.

For cost reasons the surface building SX1 has been kept minimal, with just sufficient space to receive and lower down material. All necessary components will have to be delivered to POINT 1 in a “just-in-time” fashion. Space will always be a critical issue.

Page 17: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation in Phases

6 phases: - Infrastructure- Barrel Toroid + Barrel

Calorimeters- Barrel Muon Chambers + Endcap

Calorimeters- Inner Detectors + Muon Big

Wheels- Endcap Toroids + Muon Small

Wheels- Vacuum pipe, shieldings, closing

For each phase: Clear mandate and goals Work organized in Work Packages (WP) Functional tests as early as possible

Schedule strategy : vacuum pipe and detector closed by …..… Dec 2006Apr 03

Aug 06

Installation in 6 phases Global commissioni

ng

PIT delivery

Page 18: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation Schedule v. 6.0.5

Name Start Finish

PHASE 1: Infrastructure 10 Jun '02 8 Sep '06

Service Cavern USA15 10 Jun '02 8 Sep '06

Access Building SDX1 10 Jul '02 8 Apr '04

Pit PX15 2 Sep '02 28 Jan '04

UX 15 Hand-over 14 Apr '03 14 Apr '03

Experimental Cavern UX15 5 Apr '03 24 Sep '04

Experiment Surface building SX1 14 Apr '03 21 Jan '04

Pit PX14 23 Jun '03 31 Oct '03

UX available for ATLAS 21 Nov '03 21 Nov '03

PHASE 2: Barrel Toroid & Barrel Calorimeter 14 Nov '03 26 Aug '05

Phase 2a: Bedplates & Feet 14 Nov '03 19 Dec '03

Phase 2b: Barrel Toroid 12 Dec '03 28 Feb '05

Phase 2c: Barrel Calorimeter 9 Jan '04 26 Aug '05

Phase 2d: Racks, Pipes & Cables 24 Nov '03 20 Dec '04

PHASE 3: End-cap Calorimeters & Muon Barrel 7 Sep '04 5 Apr '06

Phase 3a: Pipes & Cables 7 Sep '04 9 Aug '05

Phase 3b: Endcap Calorimeter C 20 Oct '04 25 Aug '05

Phase 3c: Muon Barrel 14 Dec '04 9 Dec '05

Phase 3d: Endcap Calorimeter A 10 May '05 5 Apr '06

PHASE 4: Big Wheels & Inner Detector 6 Jul '05 31 Aug '06

Phase 4a: Big Wheels 6 Jul '05 31 Aug '06

Phase 4b: Inner Detector 5 Sep '05 30 May '06

PHASE 5: End-Cap Toroid & Small Wheels 17 Nov '05 10 Jul '06

Phase 5a: Endcap Toroid 17 Nov '05 10 Jul '06

Phase 5b: Small Wheels 7 Apr '06 28 Jun '06

PHASE 6: Beam Vacuum, End wall Chambers, Shielding24 May '06 7 Aug '06

Phase 6a: Completion of the Beam Vacuum 24 May '06 3 Jul '06

Phase 6b: End wall Chambers (EO) 21 Jun '06 20 Jul '06

Phase 6c: Shielding & full Magnet test 16 Jun '06 7 Aug '06

Global Commissioning 8 Aug '06 30 Oct '06

Cosmic tests 31 Oct '06 27 Dec '06

ATLAS Ready For Beam 27 Dec '06 27 Dec '06

PHASE 1

1090 days Service Cavern USA15

444 days Access Building SDX1

355 days Pit PX15

14 Apr UX 15 Hand-over

382 days Experimental Cavern UX15

200 days Experiment Surface building SX1

95 days Pit PX14

21 Nov UX available for ATLAS

PHASE 2

26 days Phase 2a: Bedplates & Feet

308 days Phase 2b: Barrel Toroid

420 days Phase 2c: Barrel Calorimeter

278 days Phase 2d: Racks, Pipes & Cables

PHASE 3

235 days Phase 3a: Pipes & Cables

216 days Phase 3b: Endcap Calorimeter C

253 days Phase 3c: Muon Barrel

236 days Phase 3d: Endcap Calorimeter A

PHASE 4

301 days Phase 4a: Big Wheels

191 days Phase 4b: Inner Detector

PHASE 5

167 days Phase 5a: Endcap Toroid

59 days Phase 5b: Small Wheels

PHASE 6

29 days Phase 6a: Completion of the Beam Vacuum

22 days Phase 6b: End wall Chambers (EO)

37 days Phase 6c: Shielding & full Magnet test

60 days Global Commissioning

40 days Cosmic tests

27 Dec

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

Aug ‘06

Page 19: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation Considerations

Complex installation sequence and assembly of many sub-components underground logistical, safety, conflicts … issues.

The Air-Core Toroid concept implies a major interference of components, access and services in a very large volume and inside the detector.

Our strategy:

Correct configuration control: we created in 2001 a central office; with it many problems have been solved while a few items remain to be worked out.

A work coordination organization at POINT 1: ATLAS EXPERIMENTAL AREA MANAGEMENT (EAM)

A complete planning of all tasks, with high granularity: This is done through a central TCn office. Today we have ~ 2000 individual tasks.

Page 20: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

POINT 1

SX1

PX14PX16

PX15

UX15USA1

5

Page 21: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation Organization ATLAS TCn (in consultation with ST, EST and EP leadership) takes

responsible for the proper coordination of the installation and commissioning of the detector and its services underground.

The installation work is organized in Work Packages (WP’s).

The technical responsibility for each WP is with the experts for the system which is being installed (for the detector and for the infrastructure).

The resources associated to a given WP are defined case-by-case and are a mixture between subcontractors work, technical sector experts, central TCn resources and specific Institute resources. The exact sharing has been agreed upon with the various groups.

The interplay between WPs and basic services is managed by a dedicated organization which takes care of the overall work organization at POINT 1:

Experimental AREA Management (EAM)

Active since October ’02….working well

Page 22: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

EAM Organization at Point 1

WPi

Contractors manpower

ST/EST experts

WPi+1

ATLAS common

resources

Institute

resources

EAM logistic

s

surv

ey team

safety

planning & control

cranes and riggers

WPi+3WPi+2

WPi+n

Page 23: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

ATLAS EAM Installation Organization

Work site installation consists in organizing a succession and cohabitation of more than 1900 Tasks, spread over 3.5 years

The organization on site of WP’s is coordinated by EAM (Experimental Area Management), a team of 11 persons ( from ST/EST/ EP) since Oct 2002

Weekly EAM meeting with EAM team and work conductors (minutes on http://atlas.web.cern.ch/Atlas/TCOORD/Activities/Logistics/G1/EAM_minutes/eam_minutes_index.html)

About 50 WP’s have already been processed, a WP becomes active 2 months before it starts.

The status of active WP’s can be monitored on EDMS doc 359483 on https://edms.cern.ch/document/359483/1

Page 24: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

USA15 instrumentation

• Metallic structures well advanced• Service pipes installed• Installation of cable trays waiting for installation• Electronic racks ordered

Page 25: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

UX15 Cavern

• final delivery April ’03

• first step TAS shielding + washers

• …. then infrastructure

• November ’03 start with detector installation

Page 26: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

UX15 Infrastructure installation

Version 29

May 5thCV

EL

May 1st USA

CryoLifts

ELGasEL

CryoAr

trench

*

End of rental of CCC's crane (and crane driver)

NB. Overhead crane used by CV full time during the installation workNB. Overhead crane used by ECR full time during the 3 weeks installation work under PX14 and A side of the UXNB. UX dewars delivered before start of HS USA15 side. Maybe necessary to do overnight handling as CV block crane

Color codesMetallic structures Ducts and air systems Electrical systems Cryogenics HM Lifts

TX1S Cranes Hydraulics systems Gas Detection Piping

ATLAS FEET

SX1

Side C (16)

Side A (14)

PX16

UX15

PX14

Cavern

Side US

Side USA15

11/27/2003

EL

CV

LiftsCV

CV

Jun. 04May-04Apr. 04Jan. 04 Feb. 04May 03 Jun. 03 Jul.03

Ventilation

Aug. 03 Sept. 03 Oct. 03 Dec. 03 Mar. 04

HS

HS

Nov. 03

EL

CV

BedplatesCranes

280t

20 t.

HM

HO

HO

Page 27: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Infrastructure Installation

• Very critical, starting now…detector installation needs most of the infrastructure in place

• Most of the work is done within CERN contracts, under the supervision of ST, EST and LHC/ECR

• In these weeks we are reviewing with our technical sector colleagues the installation

methods and the readiness in order to avoid surprises

• It will be very difficult to absorb delays, the only possible solution will be extra shifts and

more parallel work

Page 28: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Infrastructure Installation

ST/CE - TAS shielding washers installation

ST/HM - all transports (normal and special), all crane manipulations.

- all cranes/lifts installation

EST/IC - most metallic structures

ST/CV - HVAC systems- primary cooling systems and piping- detector cooling units- compress air system- detector piping work?

EST/SU - all survey work

LHC/ECR - magnets and LAr cryogenics (with EP/TA3)

Page 29: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

ST/CV HVAC work in UX15

Page 30: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Infrastructure Installation

ST/MA - safety detection systems- access structures- detector sniffer system

EST/ISS - equipment database

LHC/VAC - beam vacuum system

EP/TA1 - gas distribution systems

EP/TA3 - magnets control system

ST/EL - electric power distribution (incl UPSs) - detector cabling ?

All this work is (will be) covered by internal agreements between ATLAS and the various groups/divisions

Page 31: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Detector Cabling

One of the biggest challenges in front of us

Little or no expertise left at CERN for detector cabling

~ 2200 km of copper and fibers cables

We are interested in the ST/EL methods

We will be limited by resources (few CHF/m available)

Surface bundling as one possible strategy

Complex routing inside the detector

We are currently finalizing the cable trays layout and the racks layout (inside and outside the detector)

We have developed interactive tools for routing optimization

Page 32: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Detector Cable Trays

Page 33: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

AVI test

Page 34: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence (Barrel Toroid + Barrel Calorimeter)

August ‘04

Page 35: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence

December ‘04

Side C : End Cap calorimeter installation

Side A : Barrel muon chambers installation

Page 36: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence

September ‘05

Side C : Barrel Inner Detector installation

Side A : Forward muon chambers installation (Big Wheels)

Page 37: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence (End Cap Toroid C)

December ‘05

Page 38: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence (Pixel detector + Be pipe)

April ‘06

Page 39: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence (Small Wheel C)

May ‘06

Page 40: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Installation sequence (Forward Shielding C)

July ‘06

Page 41: ATLAS and CERN/ST 2nd April 2003 Marzio Nessi. 02/04/2003 Today ATLAS project Detector Components Construction Detector Integration and Installation ATLAS

02/04/2003

Summary

ATLAS detector construction is well advanced and tuned to the installation schedule

As much as possible all components will be assembled and tested on the surface. This work is well visible at CERN today

Underground installation is starting. It is complex & time critical

The management structures for it are in place and working

CERN/ST is strongly committed to the infrastructure installation. Next 8 months will be very demanding.

ATLAS has many intersection points with CERN/ST. Few more projects could still be finalized (piping, cabling,..)