Assumptions in FIV:
1. Analysis shall be performed on design condition- Loadcase 2 where all 4 meter runs, Prover loop, headers will be in design condition
a. Temperature : 75°Cb. Pressure : 18.1 Barg
2. Crude Oil Bulk Modulus : 1551300 N/m23. Young's Modulus of main line material : 204000000000 N/m2
(API 5L Gr.B)
ENERGY INSTITUTE GUIDELINES FOR AVOIDANCE OF VIBRATION INDUCED FATIGUE FAILURE IN PROCESS PIPEWORK
Clarification required from Client:
A. What is the Flow rate for this package?B.
ENERGY INSTITUTE GUIDELINES FOR AVOIDANCE OF VIBRATION INDUCED FATIGUE FAILURE IN PROCESS PIPEWORK