assignment on project scope management
TRANSCRIPT
-
8/3/2019 Assignment on Project Scope Management
1/7
INSTITUTE OFBUSINESS
MANAGEMENT
Submitted To : Mr. Sheikh Addul Qadir
Submitted By : Majid Khan
Roll No : 10293
Date
:20/11/2011
Project Management
-
8/3/2019 Assignment on Project Scope Management
2/7
Assignment on
Project Time
Management
Time Management & Scheduling in Project
Management
-
8/3/2019 Assignment on Project Scope Management
3/7
The management projects require analytical tools for time management & scheduling activities
and allocating resources. This assignment describes a set of tools that has proven to be
consistently valuable to project managers. The tools are collectively known as the Project
Evaluation and Review Technique (PERT) and the Critical Path Method (CPM).
These include the construction of network diagrams, the calculation of feasible project schedules,
determining the effect of uncertainty on project schedules, and adjusting schedules to conform to
time and resource constraints. The tools are important for planning a project and for keeping it
on track once it has begun.
Throughout this assignment we will refer to a particular project: the installation of an
Maximo 6.2.2 at Engro Polymer Cheimical Ltd. Once in place, the system will collect
information about the inventory. The Engros present system is with Maximo 6.3.1, and once the
new system is up and running it will upgrade the system and would remove the errors from the
inventory management.
Table 1 below describes the projects activities and expected durations. The system will bedeveloped and installed by computer programmers, systems analysts, and personnel from the
accounting function. Currently, only three systems analysts are available to the firm, and the
number of analysts needed for each activity is listed in the table. The table also specifies
immediate predecessors, the smallest possible list of tasks which must be completed before
starting each activity.
S.No Descriptions Predecessor Duration System Analyst
A Specify functional and user interface features - 4 2
B Design and code functional component A 4 2
C Test and debug functional component B 4 2
D Internal audit of functional test C 2 1
E Design and code graphical user interface A 6 1
F Integrate functional component and interface C,E 6 2
G Train Inventory personnel on interface E 6 1
H Train personnel on test bed using integrated system F, G 4 2
Table 1: Description of Engro Polymer & Cheimical Ltd
Network Diagrams and Critical Paths
-
8/3/2019 Assignment on Project Scope Management
4/7
The information in the table may also be represented by a network diagram in which
rectangles, or nodes, signify activities. The relationships between activities are
represented by arrows between the nodes.
All arrows to a node begin at the nodes immediate predecessors, indicating that theactivity cannot be started until all activities prior to that node in the network are
completed. Figure 2 displays the complete project network for InterTrust. Activity A
must be completed before activities B and E are started. Activity F cannot be started
until both activities C and E are completed.
Key
Figure 2: Project Network for Maximo 6.2.2 Engro Polymer Cheimical Ltd Project
Once the project network is drawn, the answer is also simple: the duration of the project is
equal to the longest path from the beginning to the end of the network. Since all activities along
this path must be completed, the duration of the project must be at least the length of the longest
path. Since all other paths are shorter, the duration of the project must be the length of the longest
path. For InterTrust, the longest path from Ato END may be found easily by trying all paths
(how many are there?) and choosing the longest. This path is A-B-C-F-H-END and its duration is
4+4+4+6+4 = 22 weeks.
Earliest and Latest Start and Finish Times
A, 4
C, 4
G, 6
D, 2
END, 0H, 4
B, 4
E, 6 F, 6
Activit , Duration
-
8/3/2019 Assignment on Project Scope Management
5/7
For each activity we will calculate the following:
Quantity Abbreviation Description
Earliest Start Time ES Earliest time the activity may begin after allowing
preceding activities to finish
Earliest Finish Time EF Earliest time the activity may finish after allowing
preceding activities to finish
Latest Start Time LS Latest time the activity may begin without delaying
project completion
Latest Finish Time LF Latest time the activity may finish without delaying
project completion
Activity Slack SLACK Extra time an activity is allowed before it delays
the project (assuming that it begins at ES). Under
this definition, slack is sometimes also calledtotal slack or total float.
ES = max[EF of immediate predecessors]
EF = ES + activity duration
For Maximo 6.2.2 project, begin with activity A at week zero. The earliest finish time
for A is fourweeks later, and this is the earliest start times for activities B and E. The earliest
finish time for B is 4 + 4 = 8 weeks, and the earliest start time for its successor, C, is 8 weeks.
Figure 3 displays the results of these calculations. One must be careful with activity F since it has
two predecessors. The earliest start time for F is the later of the earliest finish times of its
predecessors:
ES for activity F = max(EF for activity C, EF for activity E)
= max(12, 10)
= 12 weeks
Similar calculations are completed for remaining activities until we reach END. We find that the
project will take 22 weeks.
Latest Finish time = LF = min [LS of immediate successors]
Latest Start time = LS = LF - activity duration
For END, latest start and finish times are set equal to the earliest start and finish times
since any delay to END will delay project completion. The latest finish time for activity
-
8/3/2019 Assignment on Project Scope Management
6/7
H is the latest start time for END, 22 weeks, and the latest start time for activity H is 22 -
4 = 18 weeks. The latest finish time for D is also 22 weeks, while the LF for F is the LS
for H, 18 weeks. Activity C has two immediate successors, so:
LF for activity C = min (LS for activity D, LS for activity F)
= min (20, 12)= 12 weeks
These calculations are repeated until latest times for activity A are found. See Figure 3 for the
results.
Resource Constraints
0 4
A
0 4 4
4 8
B
4 4 8
12 14
C
12 2 14
8 12
C
8 4 12
6 10
E 2
6 6 12
12 18
F
12 6 18
18 22
H
18 4 22
22 22
END
22 0 22
10 16G 2
12 6 18
-
8/3/2019 Assignment on Project Scope Management
7/7
An invaluable method for shortening the duration of a project is the ability to run multiple
activities in parallel. For example, the Maximo 6.2.2 project allows both activities B and E to run
in tandem from week four to week eight. If all its activities were to occur in series, the project
would last 36 weeks rather than 22. A Gantt chart, such as the one shown in Figure 4, displays
the degree of parallelism in the project. The chart displays the activities beginning at their
earliest start times, as well as the number of analysts needed for each activity.
(Time in Weeks from Project Start)
Figure 4: Gantt chart for Maximo with All Activities at Their Earliest Start Times
However, sufficient resources must be available for activities to be completed in parallel.If all activities in the Maximo 6.2.2 project were to begin on their earliest start dates, then the
number of systems analysts needed varies from two to four, which is derived from the resource
listing in the Gantt chart. Note that the period from the end of week 12 to the end of week 14
requires four programmers: one for activity D, two for F and one for G.