assignment 2 project breakdown

4
CONSTRUCTION OF AN ADMINISTRATIVE BLOCK AND A HOSTEL BLOCK OF Starting Date: 1st Feb 2012 Completion Date: 30th June 2013 No Tasks Sub Tasks Main Tasks 1 Site possession 0.00 2 Preliminaries and General Conditions 340,000.00 Initial 143,000.00 Recurring 197,000.00 3 Site Clearing and Earthwork 929,000.00 Site Clearing 33,000.00 Survey work 5,000.00 Temporary earth drain & sediment control work 5,000.00 Excavation and embankment 886,000.00 4 Piling Work 1,440,000.00 Setting out 10,000.00 Mobilization & Setting up Piling Equipment 40,000.00 Initial Pile 15,000.00 Load Test 40,000.00 Piling Work 1,300,000.00 PDA Test 20,000.00 Cut Off Pile 15,000.00 5 Substructure Work Pile Cap 210,000.00 Excavation 7,000.00 Form Work 15,000.00 Lean Concrete 5,000.00 Reinforcement 82,000.00 Concrete Works 88,000.00 Dismantling Formwork - Anti Termite 7,000.00 Backfill 6,000.00 Stump 62,000.00 Form Work 8,000.00 Concrete Works 54,000.00 Dismantling Formwork - Ground beam 197,000.00 Excavation 2,000.00 Form Work 51,000.00 Lean Concrete 4,000.00 Reinforcement 91,000.00 Concrete Works 49,000.00 Dismantling Formwork - Ground Slab 122,000.00 Backfill 4,000.00 Hardcore 10,000.00 Form Work 5,000.00 FOR MEDICAL FACULTY TRAINING CENTRE IN BANGI Cost TWO STOREY BUILDING AND EXTERNAL WORKS

Upload: armada7000

Post on 24-Jan-2015

389 views

Category:

Documents


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Assignment 2 Project Breakdown

CONSTRUCTION OF AN ADMINISTRATIVE BLOCK AND A HOSTEL BLOCK OF

Starting Date: 1st Feb 2012

Completion Date: 30th June 2013

No Tasks

Sub Tasks Main Tasks

1 Site possession 0.00

2 Preliminaries and General Conditions 340,000.00

Initial 143,000.00

Recurring 197,000.00

3 Site Clearing and Earthwork 929,000.00

Site Clearing 33,000.00

Survey work 5,000.00

Temporary earth drain & sediment control work 5,000.00

Excavation and embankment 886,000.00

4 Piling Work 1,440,000.00

Setting out 10,000.00

Mobilization & Setting up Piling Equipment 40,000.00

Initial Pile 15,000.00

Load Test 40,000.00

Piling Work 1,300,000.00

PDA Test 20,000.00

Cut Off Pile 15,000.00

5 Substructure Work

Pile Cap 210,000.00

Excavation 7,000.00

Form Work 15,000.00

Lean Concrete 5,000.00

Reinforcement 82,000.00

Concrete Works 88,000.00

Dismantling Formwork -

Anti Termite 7,000.00

Backfill 6,000.00

Stump 62,000.00

Form Work 8,000.00

Concrete Works 54,000.00

Dismantling Formwork -

Ground beam 197,000.00

Excavation 2,000.00

Form Work 51,000.00

Lean Concrete 4,000.00

Reinforcement 91,000.00

Concrete Works 49,000.00

Dismantling Formwork -

Ground Slab 122,000.00

Backfill 4,000.00

Hardcore 10,000.00

Form Work 5,000.00

FOR MEDICAL FACULTY TRAINING CENTRE IN BANGI

Cost

TWO STOREY BUILDING AND EXTERNAL WORKS

Page 2: Assignment 2 Project Breakdown

Lean Concrete 10,000.00

Damp proof Layer 3,000.00

Reinforcement 53,000.00

Concrete Works 37,000.00

Dismantling Formwork -

6 Superstructure Work for two storey blocks

Ground Column 56,000.00

Reinforcement 33,000.00

Form Work 5,000.00

Concrete Works 18,000.00

Dismantling Formwork -

Ist Floor Beam and Slab 235,000.00

Reinforcement 74,000.00

Form Work 91,000.00

Concrete Works 70,000.00

Dismantling Formwork -

1st Floor Column 56,000.00

Reinforcement 34,000.00

Form Work 5,000.00

Concrete Works 17,000.00

Dismantling Formwork -

2nd Floor Beam and Slab 235,000.00

Reinforcement 74,000.00

Form Work 91,000.00

Concrete Works 70,000.00

Dismantling Formwork -

Roof beams 69,000.00

Reinforcement 25,000.00

Form Work 23,000.00

Concrete Works 21,000.00

Dismantling Formwork -

Trusses Design and submission - 0.00

7 Roofing 303,000.00

Trusses Installation 135,000.00

Fascia Board 8,000.00

Covering & Finishes 90,000.00

Gutters and Rain water downpipes 70,000.00

8 Covered Walkway 36,000.00

Structue Work 19,000.00

Finishes Work 17,000.00

9 Architectural Finishes

Brickworks 303,000.00

Ground Floor 101,000.00

1st Floor 101,000.00

2nd Floor 101,000.00

10 Windows and External Door Frame 250,000.00

11 Internal Wall Finishes 247,000.00

12 Internal Floor Finishes 260,000.00

13 Steps and Railing 20,000.00

14 Ceiling Finishes 128,000.00

Page 3: Assignment 2 Project Breakdown

15 External Wall Finishes 90,000.00

16 External Floor Finishes 18,000.00

17 Internal Painting 64,000.00

18 External Painting 36,000.00

19 Door & Window Panel 127,000.00

20 Sanitary Fittings & Finishes 37,000.00

21 Apron & perimeter drains 82,000.00

22 Electrical and Mechanical Services 1,134,000.00

a) Cold water services 170,000.00

b) Sanitary services 90,000.00

c) Fire protection system 92,000.00

d) Air conditioning and ventilation system 160,000.00

e) Internal electrical services 322,000.00

f) Internal telephone services 40,000.00

g) External electrical services 190,000.00

h) External telephone services 70,000.00

23 External Works 1,000,000.00

a) Road and car parks 450,000.00

b) Surface water drainage 390,000.00

c) Water reticulation 60,000.00

d) Sewerage system and treatment plant 100,000.00

24 Final inspection

25 Testing & commissioning

26 Handing over

Total Project Cost 8,086,000.00