Asset Management – Finding the Value Business Requirements Life Cycle Costs System Requirements Reliability & Safety

Upload: vuongduong

Post on 29-Mar-2018

221 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Asset Management – Finding the Value

Business Requirements

Life Cycle Costs

System Requirements

Reliability &

Safety

Page 2: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

•  Low Rates •  Reliable Power

Customers

•  Safe System •  Reliable System

Employees

•  Rate of Return •  Low Financial Risk

Shareholders

Best Value

Assets

AM Mission – Get Maximum Value out of our Assets

Page 3: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Integrated Model

System Data Structure, Corrective & Planned

Work, Inspections, Failure Model,

Equipment & Contracts, Labor, Spares, Risk

AM Plans Maintenance & Replacement

Strategies AM Budgets

Equipment Needs Spares Inventory

Labor Needs

System Performance

Data Industry Data

KPI’s OMT Data

METS AFM/GIS Financial

Team Crafts

Managers Engineers

Subject Matter Experts

AM Cycle

Page 4: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 •  Integrated System

Maintenance •  Electric Asset

Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 5: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 •  AM committee

makes recommendation for AM organization

•  Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 6: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 •  AM group with

two engineers •  14 programs •  Rate Case

Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 7: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 •  ARMS

introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 8: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 •  Wood Pole

Management Plan •  Chance Cutout

Program •  URD Cable

Replacement •  Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 9: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 •  Wood Pole

Management Implemented

•  Chance Cutout Value Demonstrated

•  Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 10: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 •  Integrated

Distribution Feeder Analysis

•  Little Falls HED AM paper

•  Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 11: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs

• Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 •  Third Member

of AM Hired •  Rate Case

Success •  Decision to

take AM company wide

Page 12: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

How we win

•  Demonstration of value •  Quantified Comparison

of Alternatives •  Continuous Feedback •  Team Approach •  Information Integration

12

Page 13: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Early Successes

•  WPM •  Vegetation

Management •  Chance Cutouts •  URD Cable

Replacement •  Wildlife Guards •  Gas Meters

13

Page 14: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Overall OMT Trend – Jan - Jun

0

1000

2000

3000

4000

5000

6000

7000

2004 2005 2006 2007 2008 2009 2010 2011

Num

ber o

f OM

T Ev

ents

Year

Page 15: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Asset Management Related Events – Jan - Jun

0 200 400 600 800

1000 1200 1400 1600 1800 2000

2004 2005 2006 2007 2008 2009 2010 2011

Num

ber o

f OM

T Ev

ents

Year

Page 16: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Wildlife Guard Program Results – Jan - Jun

0

50

100

150

200

250

300

350

400

2004 2005 2006 2007 2008 2009 2010 2011

Num

ber o

f OM

T Ev

ents

Year

Bird Squirrel

Page 17: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Chance Cutout Replacement Program

0

100

200

300

400

500

600

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Numbe

r  of  O

MT  Even

ts

Year

Projected  OMT  Events  w/o  Action Projected  OMT  Events  w/  Action

Actual  Number  of  OMT  Events

Cutout  Failures  if  all  Chance  Cutouts  had  been  removed

Trend  based  on  current  OMT  Data

Page 18: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Current AM

•  Optimize Value of Programs

•  Demonstrate the Value •  Support Function •  By Program or Project

Basis •  Recommendation

Mode •  Niche Role within

Company

18

Page 19: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Role of ARMS

•  Systematic Process •  Integrated Approach •  Deals with Bad Data •  Provides the Answers

19

Page 20: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Future AM

•  Company wide •  Decision Authority •  Department Level •  Expanded Role •  Releasing Value from

all Assets

20

7.0

8.0

6.0

5.0

Opportunity Prioritization

Hard EasyEase of ImplementationPo

tent

ial I

mpa

ct(V

alue

/Ben

efit)

Low

High Highest Priority (Tier 1)

LowestPriority(Tier 3)

(Tier 2)

7.1

7.2

7.3

7.4

7.5

3.1

3.2

3.3

3.4

3.5

3.63.7

3.8

3.9 3.10

3.11

3.12

8.1

8.2

8.3

8.4

8.5

8.6

8.7

8.8

4.1

4.2

4.34.4

4.5

1.11.2

1.3

1.4

1.5

2.1

2.2

2.32.4

2.5

6.1

6.2

6.3

6.4

6.5

5.1

5.2

5.3

1.6

1.7

1.8

1.101.9

4.6

1.0 Asset Management2.0 Capital Prioritization/

O&M Budgeting3.0 Planning/Scheduling

Project Management4.0

Standards and Estimates AssessmentPerformance Management

Technology and Enablement Support

Page 21: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Questions?

ASSET MANAGEMENT

Business Requirements

Life Cycle Costs

System Requirements

Reliability &

Safety

Page 22: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Chance Cutout Replacement Related OMT Events

0

20

40

60

80

100

120

140

160

2004 2005 2006 2007 2008 2009 2010 2011

Num

ber o

f OM

T Ev

ents

Year

Cutout/Fuse

Page 23: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Phases of AM Analysis

Strategic Analysis

Maintenance Planning

Tactical Optimization

Noxon Plant – GSU Analysis

Gen Circuit Breaker Maintenance

Future – Plant Model?

Page 24: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Click to edit Master title style

AM Related OMT Trends

Events are increasing at a rate of 312 events/yr

0

1000

2000

3000

4000

5000

Num

ber o

f Eve

nts

Year &Quarter

Top 10 AM Upward Trends

No. Sub-Reason Change per Year

1 Tree Growth 59

2 Connector - Sec 54

3 Conductor - Sec 31

4 URD Cable - Sec 19

5 Connector - Pri 16

6 Squirrel 6

7 Tree Fell 6

8 Transformer UG 6

9 Pole-rotten 5

10 Transformer OH 2

Page 25: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Click to edit Master title style

Squirrel Event Trend

500

600

700

800

900

1000

2005 2006 2007 2008 2009

Num

ber o

f Squ

irrel

Eve

nts

Year

Page 26: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Contributions to SAIFI Outage Causes - 2009

Dig In1%

Forced3%

Bird3% Car Hit Pole

4% Other4% Pole Fire

4%

Lightning6%

Weather7%

Wind7%

Maint/Upgrade9%Snow/Ice

11%

Undetermined20%

Asset Management

Related21%

Page 27: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Contributions to SAIFI AM Related Outage Causes - 2009

Transformer - OH3% URD Cable - Pri

3% Arrester3% Switch/Disconnect

4%Cutout/Fuse

6%

Conductor - Pri8%

Other10%

Lowside OCB/Recloser

10%Insulator11%

Connector - Pri12%

Squirrel15%

Tree Fell15%

Page 28: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan

1. Wood Pole Management

2. Capital

Follow-Up Work

3. Feeder Design Improvements

4. Vegetation Management

5. Wildlife Guards

6. URD and Padmount Inspection

7. PCB Transformers

8. Street Lights

Page 29: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan - Crossarm - Insulator - Lightning Arrester - Cut-Out - Guy - Pole - Ground - Stub

Wood Pole Management & Capital Follow-Up Work

Page 30: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan - Primary Conductor - Capacitor Bank

Feeder Design Improvements

Page 31: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan

Vegetation Management

Page 32: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan

Wildlife Guards

Page 33: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan

URD and Padmount Inspection

Page 34: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan

PCB Transformers

Page 35: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Distribution Feeder Management Plan

Street Lights

Page 36: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

PCB Risks

Page 37: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

PCB Elimination Strategy

! Next 6 Yrs to ND

– Spokane River Watershed

– Pend Oreille Watershed

– Remaining System Area

! Next 20 Yrs Pre-’81

– OH thru WPM

– Pad & Sub

Page 38: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Transformer Update

0

1000

2000

3000

4000

5000

2005 2006 2007 2008 2009

# of

Tra

nsfo

rmer

s

Year

0

1000

2000

3000

4000

5000

2005 2006 2007 2008 2009

# of

Tra

nsfo

rmer

s

Year

Purchased Retired

Page 39: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Click to edit Master title style

Ninth and Central 12F4 Feeder Rebuild Results

0

10

20

30

40

50

60

70

80

2002 2003 2004 2005 2006 2007 2008 2009 2010

All  OMT  Sub-­‐Reasons  except  Maint/Upgrade

2010  is  projected  based  on  data  through  August  2010

Page 40: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Click to edit Master title style

Ninth and Central 12F4 Feeder Rebuild Results

0

5

10

15

20

25

2005 2006 2007 2008 2009 2010

Cutout/Fuse

Weather

URD  Cable  -­‐ Sec

Tree  Growth

Tree  Fell

Squirrel

Snow/Ice

Service

Pole-­‐rotten

Lightning

Crossarm-­‐rotten

Connector  -­‐ Sec

Page 41: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Click to edit Master title style

In the Future for Asset Management

1.1 Define AM scope, organizational structure and decision rights 1.2 Focus more on balancing cost and service by prioritizing maintenance and

inspection programs based on a mix of early-stage failure, reliability or cost experience and manufacturers

1.3 Create new focus on life-cycle costs while incorporating “affordable utility”

concepts 1.5 Develop overarching asset mgmt. system to support information sharing across all

phases of project life-cycle 7.0

8.0

6.0

5.0

Opportunity Prioritization

Hard EasyEase of Implementation

Pote

ntia

l Im

pact

(Val

ue/B

enef

it)

Low

High Highest Priority (Tier 1)

LowestPriority(Tier 3)

(Tier 2)

7.1

7.2

7.3

7.4

7.5

3.1

3.2

3.3

3.4

3.5

3.63.7

3.8

3.9 3.10

3.11

3.12

8.1

8.2

8.3

8.4

8.5

8.6

8.7

8.8

4.1

4.2

4.34.4

4.5

1.11.2

1.3

1.4

1.5

2.1

2.2

2.32.4

2.5

6.1

6.2

6.3

6.4

6.5

5.1

5.2

5.3

1.6

1.7

1.8

1.101.9

4.6

1.0 Asset Management2.0 Capital Prioritization/

O&M Budgeting3.0 Planning/Scheduling

Project Management4.0

Standards and Estimates AssessmentPerformance Management

Technology and Enablement Support

Asset Management Tier 1 Opportunities

Strategic and Operational Planning

Page 42: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Starting Point

•  No CMMS

•  No comprehensive WMS

•  Accounting System - FERC

!  No Activity Based Accounting

!  No tracking of actual time per task

!  Estimating guides based on work done in 1969-1970

•  Technology

!  Leader in use of GIS software

!  Legacy WMS for Distribution Construction work

!  Legacy Customer Service Solution

!  Custom Build Component Tracking system for Substations

!  Advanced Outage Management Tool for Distribution outages just implemented in 2005

!  Excel and Access reign!

42

Page 43: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Challenges Remaining

•  Labor Resource Constraints

•  Budget Constraints •  Proven Projects,

Budgeted but not performed

43

Page 44: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Avista’s Asset Management Timeline

2003 • Integrated System Maintenance

• Electric Asset Optimization Status Report

2004 • AM committee makes recommendation for AM organization

• Vegetation Management in Rate Case

2005 • AM group with two engineers

• 14 programs • Rate Case Attempt

2006 • ARMS introduced RCMCost and AVSim+

2007 • Wood Pole Management Plan

• Chance Cutout Program

• Gas Meter Project

• Rate Case Success

2008 • Wood Pole Management Implemented

• Chance Cutout Value Demonstrated

• Rate Case Success

2009 • Integrated Distribution Feeder Analysis

• Little Falls HED AM paper

• Partial Rate Case Success

2010 • Third Member of AM Hired

• Decision to take AM company wide

• Rate Case Success

Page 45: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

History

•  Knew RCM was the way to go and develop AM strategic plans

•  2003 started work on Integrated System Maintenance

!  Question: Why should we do maintenance?

•  2003 Electric Asset Optimization Status Report

•  2004 AM committee makes recommendation for AM organization

•  2005 AM organization not adopted but created AM group with two engineers

•  2005 - 14 programs Identified

•  2005 Rate Case Attempt - Failed to provide justification for program

45

Page 46: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

History (2)

•  2006 ARMS introduced RCMCost and AVSim+ into Avista

•  2006 Begin to use interns to help with the data

•  2007 Wood Pole Management Plan - First Success

•  2007 Chance Cutout Program

•  2007 Individual AM Plan Development

•  2007 Gas Meter Project

•  2007 Succeeded in Rate Case

•  2008 WPM Implemented along with other programs

•  2008 Chance Cutout Value Demonstrated

•  2009 Integrated Distribution Feeder Analysis Demonstration

46

Page 47: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

History (3)

•  2009 Little Falls HED AM paper

•  2009 Gas Meter Practices changed

•  2010 Third member hired

•  2010 Company Initiative to expand AM principles to all areas of the company

47

Page 48: Asset Management – Finding the Value Safety System ... · PDF fileAsset Management – Finding the Value Business Requirements Life Cycle ... OMT Data METS AFM/GIS Financial Team

Business Requirements

Life Cycle Costs

System Requirements

Reliability &

Safety