assessment studies for the proposed rogun hydropower and regional reservoir project (rogun hpp)...
TRANSCRIPT
Assessment Studies for the Proposed Rogun Hydropower and Regional Reservoir Project (Rogun HPP)
Independent Panels of Experts Independent Panels of Experts
1
Information Sharing and Riparian DiscussionsAlmaty, Kazakhstan
May 17-19, 2011
Two Panels of Experts [PoE]
Purpose: to provide independent, international expertise to the Rogun assessment studies in compliance with World Bank World Bank operational safeguards
Environmental and Social Panel
Engineering and Dam Safety Panel
Salt dome Seismic risk Hydrologic
modeling Sediment
management Engineering
design Economics
Resettlement Biodiversity Hydrologic
modeling Riparian impacts Waste
management
Selected, coordinated and funded by the World Bank 2
3
Objectives of the PoEsKey objective is to ensure international standards of design, risk evaluation and impact assessment, and build confidence in the
quality and integrity of the assessment process and findings
Specifically to:
a)to ensure due diligence and international quality standards in the studies, including integration of international standards for data, methodologies, benchmarks for impacts, and design criteria;
b)to provide high level and professional independent advice and guidance to support objectivity and credibility in the assessment process; and
c)to share technical expertise and knowledge and so contribute to dialogue amongst Consultants, the Government of Tajikistan and riparians
4
Mandatory Qualifications of PoEs
•Internationally recognized
•International experience with large hydropower projects
•Practical application of best practice
•Independent of Central Asian or former Soviet Union
5
Environment and Social PoE: Members
(1) Torkil Jønch Clausen[Denmark] International Water Resources ExpertChairman of ESIA PoE
(2) Eric Helland-Hansen[Norway]
Hydropower and Environment Expert
(3) Richard Fuggle[South Africa]
Environmental Expert
(4) Frederic Giovannetti[France]
Resettlement Expert
previous identified expert had to withdraw
for health reasons
previous identified expert had to withdraw
for health reasons
6
Engineering & Dam Safety PoE: Members
(1) Roger Gill[Australia]
Hydropower Policy Expert Chairman of TEAS PoE
(2) Paul Marinos[Greece]
Engineering Geology/Rock
Mechanics Expert
(3) Ljiljana Spasic-Gril[Great Britain]
Dam Engineering/Dam Safety/Seismic Engineering Expert
(4) To be determinedHydrology /Hydraulic
Expert
7
Panel Process
•Work program is organized around key study milestones and deliverables
•Each meeting will include relevant core members of the Panel and additional experts as deemed necessary by the Bank and Panel Chairs •Meetings of the two Panels will occur at the same time, to the extent possible
8
Panel Process cont’d
•Meetings will generally consist of:a) Review of study documents (in advance) b) Dialogue with the project proponents and the authorized
representatives of the Government of Tajikistanc) Dialogue with riparian stakeholders d) Additional activities as suggested by Panel memberse) Panel deliberations and reporting
•Meetings may be site visits, video- or audio-conferencing
•Meeting agendas will be determined by the Chairs of the Panels, in consultation with the World Bank
9
The Panels and Riparian Stakeholders
•The Panels will work with the World Bank in planning riparian discussions•Panel members will be directly involved in riparian discussions to:
• Share information on study outputs• Provide insight on comparison with international standards• Respond to and discuss technical questions • Incorporate riparian input into guidance to consultants (at the discretion
of the Panel)
•The Panels focus on the technical quality of the studies
10
For more information please see the Information Note on the Panels of Experts published on the website