Assembly Line Balancing
The process of equalizing the amount of work at each work station on an assembly line.
![Page 2: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/2.jpg)
How to Balance a Line Specify the task relationships and their order
of precedence. Draw and label a precedence diagram. Calculate the desired cycle time (Cd). Calculate the theoretical minimum number of
workstations (N). Group elements into workstations recognizing
cycle time & precedence. Evaluate the efficiency of the line (E). Repeat until desired line efficiency is reached.
![Page 3: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/3.jpg)
Order of Precedence
Joe’s Sub ShopTask Work Element Precedence Time (min)
A Receive Order — 2
B Cut Bread A 1
C Prepare Toppings A 2
D Assemble Sandwich B,C 3
E Wrap Sandwich D 1
F Deliver Sandwich E 3
Specify the task relationships and their order of precedence.
![Page 4: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/4.jpg)
The Precedence Diagram
Draw and label a precedence diagram.
A2 min
B1 min
![Page 5: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/5.jpg)
The Precedence Diagram
Draw and label a precedence diagram.
A2 min
B1 min
C2 min
D3 min
E1 min
F3 min
![Page 6: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/6.jpg)
Cycle Time
Calculate the desired cycle time (Cd). If Joe’s Sub Shop has a demand of 100
sandwiches per day. The day shift lasts 8 hours.
Cd =production time available
desired units of output
Cd =8 hours x 60 minutes/hour
100 sandwiches
Cd = 4.8 minutes
![Page 7: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/7.jpg)
Minimum Work Stations
Calculate the theoretical minimum number of workstations (N). If Cd = 4.8 minutes
N = ti
Cd
j
i =1
ti = completion time for
task i
j = number of tasks
Cd = desired cycle time
![Page 8: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/8.jpg)
Minimum Work Stations
Calculate the theoretical minimum number of workstations (N). If Cd = 4.8 minutes
N = ti
Cd
j
i =1 N =2 + 1 + 2 + 3 + 1 + 3
4.8
N = 2.5 workstations 3 workstations
![Page 9: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/9.jpg)
Order Work Stations Group elements into workstations
recognizing cycle time & precedence.
Joe’s Sub Shop
Workstation TaskElement
Time (min)Workstation Time (min)
1 A 2 3
B 1
2 C 2 2
3 D 3 4
E 1
4 F 3 3
![Page 10: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/10.jpg)
Line Efficiency
Evaluate the efficiency of the line (E). If Ca = 4 minutes and n = 4 work stations.
E = ti
nCa
j
i =1
ti = completion time for
task i
j = number of tasks
Ca = actual cycle time
n = actual number of workstations
![Page 11: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/11.jpg)
Line Efficiency
Evaluate the efficiency of the line (E). If Ca = 4 minutes and n = 4 work stations.
E = ti
nCa
j
i =1 E =2 + 1 + 2 + 3 + 1 + 3
4 * 4
E = 75.0% effective
![Page 12: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/12.jpg)
Trial and Error Repeat until desired line efficiency is reached.
Joe’s Sub Shop
Workstation TaskElement Time
(min)Workstation Time (min)
1 A 2 4
C 2
2 B 1 4
D 3
3 E 1 4
F 3
E = 100.0% effective
![Page 13: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/13.jpg)
Class Exercise
Task Precedence Time (min)
A — 3
B A 5
C — 2
D B,C 4
E D 2
A sample precedence chart
![Page 14: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/14.jpg)
Class Exercise
Draw and label a precedence diagram.
A3 min
B5 min
![Page 15: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/15.jpg)
Class Exercise
Draw and label a precedence diagram.
A3 min
B5 min
C2 min
D4 min
E2 min
![Page 16: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/16.jpg)
Calculate the desired cycle time (Cd). If, there is a demand for 100 units to be
produced every 12 hours.
Class Exercise
Cd =production time available
desired units of output
Cd =12 hours x 60 minutes/hour
100 units
Cd = 7.2 minutes
![Page 17: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/17.jpg)
Class Exercise
Calculate the theoretical minimum number of workstations (N). If Cd = 7.2 minutes
N = ti
Cd
j
i =1
ti = completion time for
task i
j = number of tasks
Cd = desired cycle time
![Page 18: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/18.jpg)
Class Exercise
Calculate the theoretical minimum number of workstations (N). If Cd = 7.2 minutes
N = ti
Cd
j
i =1N =
2 + 5 + 2 + 4 + 2
7.2
N = 2.08 workstations 3 workstations
![Page 19: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/19.jpg)
Class Exercise Group elements into workstations
recognizing cycle time & precedence.
Workstation TaskElement
Time (min)Workstation Time (min)
? A 3 ?
? B 5 ?
? C 2 ?
? D 4 ?
? E 2 ?
![Page 20: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/20.jpg)
Class Exercise
Evaluate the efficiency of the line (E).
E = ti
nCa
j
i =1
ti = completion time for
task i
j = number of tasks
Ca = actual cycle time
n = actual number of workstations
![Page 21: Assembly Line Balancing The process of equalizing the amount of work at each work station on an assembly line](https://reader035.vdocuments.mx/reader035/viewer/2022081506/56649f395503460f94c55c9b/html5/thumbnails/21.jpg)
Class Exercise The most efficient set up of the line
Workstation TaskElement
Time (min)Workstation Time (min)
1 A 3 5
C 2
2 B 5 5
3 D 4 6
E 2
E = 83.3% effective