ASME Boiler and Pressure Vessel Code SECTION V INTERPRETATIONS Volume 46 The Interpretations to the Code will be issued twice a year (July and December) up to the publication of the 2001 Edition of the Code. The Interpretations for each individual Section are published separately and are part of the update service to that Section; Interpretations of Section III, Divisions 1 and 2, are part of the update service to Section III, Subsection NCA. Interpretations Volumes 36 through 41 were included with the update service to the 1995 Edition of the Code; Volume 42 is the first Interpretations volume to be included with the update service to the 1998 Edition. Section Vol. 42 Vol. 43 Vol. 44 Vol. 45 Vol. 46 Vol. 47 I 7/98 12/98 7/99 12/99 I-A 7/98 7/99 12/99 7/00 II-B 7/00 II-C II-D III-NCA 7/98 12/98 7/99 12/99 7/00 III-3 IV 7/98 12/98 7/99 12/99 7/00 V 7/98 12/98 7/99 7/00 VI VII VIII-1 7/98 12/98 7/99 12/99 7/00 VIII-2 7/98 12/98 7/99 12/99 7/00 VIII-3 12/98 IX 7/98 12/98 7/99 12/99 7/00 X XI 7/98 12/98 7/99 12/99 7/00 Copyright © 2000 THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS All Rights Reserved

Upload: harrinson-ferrebus

Post on 29-Sep-2015

99 views

Category:

Documents


1 download

DESCRIPTION

norma

TRANSCRIPT

  • ASME Boiler and Pressure Vessel CodeSECTION V

    INTERPRETATIONSVolume 46

    The Interpretations to the Code will be issued twice a year (July and December) up to thepublication of the 2001 Edition of the Code. The Interpretations for each individual Section arepublished separately and are part of the update service to that Section; Interpretations of SectionIII, Divisions 1 and 2, are part of the update service to Section III, Subsection NCA.

    Interpretations Volumes 36 through 41 were included with the update service to the 1995 Editionof the Code; Volume 42 is the first Interpretations volume to be included with the update serviceto the 1998 Edition.

    Section Vol. 42 Vol. 43 Vol. 44 Vol. 45 Vol. 46 Vol. 47

    I 7/98 12/98 7/99 12/99 I-A 7/98 7/99 12/99 7/00II-B 7/00II-C II-D III-NCA 7/98 12/98 7/99 12/99 7/00III-3 IV 7/98 12/98 7/99 12/99 7/00V 7/98 12/98 7/99 7/00VI VII VIII-1 7/98 12/98 7/99 12/99 7/00VIII-2 7/98 12/98 7/99 12/99 7/00VIII-3 12/98 IX 7/98 12/98 7/99 12/99 7/00X XI 7/98 12/98 7/99 12/99 7/00

    Copyright 2000THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS

    All Rights Reserved

  • 173

    INTERPRETATIONS

    NO. 46 SECTION V

    Replies to Technical InquiriesJuly 1, 1999 through December 31, 1999

    FOREWORD

    General Information

    This publication includes all written interpretations issued between the indicated dates by the ASMEStaff on behalf of the ASME Boiler and Pressure Vessel Committee in response to inquiries concerninginterpretations of the ASME Boiler and Pressure Vessel Code. A contents is also included which listssubjects specific to the interpretations covered in the individual volume.

    These interpretations are taken verbatim from the original letters, except for a few typographicaland editorial corrections made for the purpose of improved clarity. In some instances, a review of theinterpretation revealed a need for corrections of a technical nature. In these cases, a revised interpretationis presented bearing the original Interpretation Number with the suffix R and the original file numberwith an asterisk. Following these revised interpretations, new interpretations and revisions to themissued during the indicated dates are assigned Interpretation Numbers in chronological order. Interpretationsapplying to more than one Code Section appear with the interpretations for each affected Section.

    ASME procedures provide for reconsideration of these interpretations when or if additional informationis available which the inquirer believes might affect the interpretation. Further, persons aggrieved byan interpretation may appeal to the cognizant ASME committee or subcommittee As stated in theStatement of Policy in the Code documents, ASME does not "approve," "certify," "rate," or "endorse"any item, construction, proprietary device, or activity.

    An interpretation applies either to the Edition and Addenda in effect on the date of issuance of theinterpretation or the Edition and Addenda stated in the interpretation. Subsequent revisions to the Codemay supersede the interpretation.

    For detailed instructions on preparation of technical inquiries to the ASME Boiler and PressureVessel Committee, refer to Appendix B.

  • 175

    SECTION V

    Subject Interpretation File No.Article 2, Radiographic Examination and T-150, Procedure ....... V-98-08 BC98-495Article 2, Radiographic Examination and T-262, Step Wedge Film and Densitometer V-98-10 BC98-516Figure T-542.2.1, Basic Calibration Block .... V-98-11 BC99-234T-542.6, Welds in Wrought and Cast Ferritic Product Forms, Excluding Pipe .... V-98-09 BC99-055

  • Interpretation: V-98-08

    Subject: Article 2, Radiographic Examination and T-150, Procedure (1998 Edition)

    Date Issued: April 7, 1999

    File: BC98-495

    Question: Do the provisions of Article 1, paragraph T-150(a) for special configurations permitdeviation from mandatory radiographic density requirements of Article 2?

    Reply: No.

    Note: This Interpretation was inadvertently omitted from Volume 45.

    Interpretation: V-98-09

    Subject: T-542.6, Welds in Wrought and Cast Ferritic Product Forms, Excluding Pipe (1998Edition)

    Date Issued: April 7, 1999

    File: BC99-055

    Question (1): Does the basic calibration block described in T-542.6.1.1 require both side-drilledholes and notches for angle-beam calibration as described in Article 4, Appendix B?

    Reply (1): Yes.

    Question (2): Does T-542.6 prohibit angle-beam calibration for sound paths greater than v-path?

    Reply (2): No.

    Note: This Interpretation was inadvertently omitted from Volume 45.

    177

    Section V Interpretations No. 46 V-98-08, V-98-09

  • Interpretation: V-98-10

    Subject: Article 2, Radiographic Examination and T-262, Step Wedge Film and Densitometer(1995 Edition)

    Date Issued: June 29, 1999

    File: BC98-516

    Question (1): Does Article 2 address the validity period of calibrated step wedge film?

    Reply (1): No.

    Question (2): Does Article 2 address periodic verification of calibrated densitorneters?

    Reply (2): No.

    Question (3): Does Article 2, T-262 permit the use of a step wedge comparison film for verificationof densitometer calibration?

    Reply (3): No.

    Question (4): Does Article 2, T-262 address validity duration requirement for a calibrated stepwedge film or a step wedge comparison film?

    Reply (4): No.

    Question (5): Does Article 2, T-262 address the requirement that a calibrated step wedge film bereadily available if a valid step wedge comparison film is used to measure the density of productionradiographs?

    Reply (5): No.

    Note: This Interpretation was inadvertently omitted from Volume 45.

    Section V - Interpretations No. 46

    Interpretation: V-98-11

    Subject: Figure T-542.2.1, Basic Calibration Block (1995 Edition)

    Date Issued: June 29, 1999

    File: BC99-234

    Question: Does Fig. T-542.2.1 require calibration blocks to be a minimum of 6 in. wide?

    Reply: Yes.

    Note: This Interpretation was inadvertently omitted from Volume 45.

    178

    V-98-10, V-98-11 Section V Interpretations No. 46