asce oc ewri - gobernadora basin facility planning design

102

Upload: american-society-of-civil-engineers-orange-county-branch

Post on 15-Aug-2015

378 views

Category:

Engineering


0 download

TRANSCRIPT

Page 1: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 2: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Presentation Topics Outline

SMWD Alternative Water Supplies

Background /Objectives / Funding

Watershed Planning / Constraints

Design and Hydraulic Operation

Basin Design Features

Basin Construction

Page 3: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

SMWD Water Supplies / Alternative Sources

Page 4: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Santa Margarita Water District

SMWD Service

Area

• 50th Anniversary• Provides Water and Wastewater Service to over

155,000 residents• Over Next 20-30 years ~40,000 More Residents

Page 5: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Indoor Use13,400 AF

(February low flows)

27,000 AF Potable Water

MWD

Outdoor Use13,600 AF

WastewaterChiquita, 6.4 MGD, 7,200 AFOso Creek, 2.0 MGD, 2,200 AFSOCWA, 2.2 MGD, 2,500 AF

Ocean Outfall6,300 AFRecycled Water

5,600 AFChiquita, 3,800 AFOso Creek, 1,800 AF

Runoff

Urban Return Flows1,800 AF

Oso Barrier, 1,120 AFHorno Basin, 180 AFTrabuco, 300 AFDove Canyon, 200 AFFuture: Gobernadora

SMWD 2014 Water Supply

Page 6: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

District’s Existing RW System

• ~ 2,740 Dedicated Irrigation Meters

• ~ 1,260 Non-Domestic• Future ~ 3,000 Non-Dom

Page 7: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Coto de Caza Non-Domestic System

Currently • Usage ~ 1,370 afy• Purchase 1,210 afy

MWD water• 160 afy well water

Page 8: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

SMWD Proactively Seeks Multiple Types of Non-Potable Sources

8

• Reclaimed Water– Oso Creek WRP (2.0

MGD)– Chiquita WRP (5 MGD)– SOCWA, IRWD, TCWD

• Urban Runoff Capture– Oso Creek Barrier Project– Dove Canyon Basin– Horno Basin

• Imported Water (Portola Reservoir)

Non-Domestic Irrigation

Water Sources

Imported Water

Urban Runoff

Capture

Recycled Water

Page 9: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

SMWD Leader in Sourcing Dry Weather Nuisance Flow for Recycled Water

9

Oso Creek Barrier ProjectConstructed 1970’s – Modified 2008

Page 10: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Oso Creek Barrier Diversion Operated Successfully for > 35 Years

10

– 2 Million Gallons Per Day– Mixes w/ Oso Creek WRP Effluent– Pumped to Upper Oso Reservoir

Page 11: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Facility Planning Background and Objectives

Page 12: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Gobernadora Detention Basin Location

Page 13: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Basin Location – Aerial Image (2006)

Coastal Sage

Gobernadora Environmental Restoration Area

Coto de Caza

Design Constraints• Groundwater• Biological Habitat• Available R/W• Floodplain• Topography• Natural alluvial

Creek

Page 15: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Project Background and Objectives

• District’s Goals– Capture Urban Runoff– Protect Downstream Facilities

• 10” and 16” sewer force main• 36” Regional Water Transmission Main

• RMV/OC Public Works– Storm water management– Protect downstream GERA

• OC Parks– Connect two Regional Wilderness Parks

Page 16: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

• Multiple Benefits for Multiple Partners• Improved/Leverage Funding Opportunities

• Reuse Urban Runoff up to 800 afy• Possible Forebay for additional xfer of RW

for add’l 400 afy• Reduce Impacts of Storm Events• Stream Stabilization• Improved OC Parks Trail System

Gobernadora Multi-Purpose BasinNon-Domestic Water Supply

Page 17: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Cost and Funding Sources

17

Total Project Cost

$23.4 M

RMVLand Transfer Value

($2.0M)

RMV Cash Contributions

($9.8 M)

SMWD General Fund Contributions

($0.2 M)SMWD

CFD ($3.2 M)

OC ParksCash Contribution

($0.7 M)

Prop. 50 Funds($2.5 M)

Prop 1E Funds($5.0 M)

Page 18: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Regional Watershed Planning

Page 19: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 20: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Regional Watershed Analyses

• San Juan Creek = 176 sq. miles• RMV SJC Watershed = 20.85 sq. mi.

SJC U/S RMV = 79 sq. mi.SJC D/S RMV = 106 sq. mi.

Page 21: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

RMV Ranch Plan Development

Page 22: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Highlights of Stormwater Facilities• 32 miles storm drain pipe• 21 storm drain outfalls to creeks (27

total reserved 6 future use)• 22 detention basins – 8 regional• Local Detention Basin areas = 87.8 acres• Regional Detention Basin = 87.8 acres• WQ Basin areas = 46.8 acres• HM Basin areas = 88.2 acres

Page 23: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 24: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Facility Planning – Existing Conditions & Constraints

Page 25: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Hydrology – Tributary Watershed Characteristics

Gobernadora Watershed = 3,797 acres

Wagon Wheel Watershed = 1,128 acres

Page 26: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Site Field Characteristics

Page 27: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Site Field Characteristics

Page 28: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Existing Creek 100-Year Floodplain

Page 29: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Gobernadora Creek Experienced Significant Erosion and Sedimentation Issues• Constant amount of urban dry weather flows• Erosion of the proposed basin area with 3 acres loss

of land• Sedimentation downstream

March 2005

“prevent this from happening”

Source: Balance Hydrologics, Inc., 2006

Page 30: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Creek Erosion Between Preliminary to Final Design

• Preliminary design performed in 2008.

• Large storm event December 2010

• Erosion between Preliminary Design reduced available footprint of basin by over 3 acres

• Increased environmental regulatory areas

Page 31: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 32: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

High Groundwater Near Surface

Page 33: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 34: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Overview of Proposed Facility

Page 35: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Existing Site Condition – Pre-project

Page 36: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Milestone No.1 Construction

Page 37: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Milestone No.2 – Completed Basin

Page 38: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Division of Basins

Page 39: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 40: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Peak Flood Attenuation FromUpper (35 AF) and Lower (100 AF) Basins

Page 41: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Basin Embankment SectionLength DSOD

JurisdictionStorage Volume

Embankment Height

Variation

Embankment Height from

SpillwayUpper Basin 1,400 feet No 34 AF 10-15 feet 7.4 feet (wall)

Intermediate / Separation Berm

900 feet No N/A 12 feet 4.3 feet

Lower Basin 1,440 feet No 2(49 AF) 15-16 feet 12 feet

Page 42: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Primary Spillway Hydraulics / Dissipator

• Trapezoidal broad crest weir• Tumbling flow element dissipator• Designed for intercepted Q1500-year = 3,400 cfs

– Maximum flow depth y1500-year = 3.2 feet

Page 43: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Facility Operation – Dry Weather / Flood Flows

Page 44: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Milestone No.2 – Completed Basin

Page 45: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Inflatable Dams – Upper Basin

Inflatable Dams – Flood Flow Conditions

Inflatable Dams – Dry Weather Diversion

Page 46: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Lateral Channel Side-Weir Hydraulic Performance

• Weir Length = 200 feet• Sharp Crest Weir• Height above channel = 7.4 feet• Crest to top channel = 6.3 feet • Downstream Rubber Dam = 6 feet

Page 47: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Side Weir Hydraulics – Spatially Varied Flow Analysis

Storm Event Hydraulic method Lag (hr) Runoff (ac-ft) Peak Flow

(cfs)Bypass (cfs)

Channel To Basin (cfs)

2-yr EV 1.279 118.0 387 387 0

5-yr EV BAS 1.067 217.9 803 803 0

10-yr EV BAS 0.938 432.2 1848 1575 273

25-yr EV BAS 0.856 732.6 2695 2043 652

50-yr EV BAS 0.821 873.2 3159 2269 890

100-yr EV BAS 0.795 991.6 3630 2500 1130

100-yr HC (AMCIII) BAS 0.73 1796.3 5329 3320 2009

100-yr HC (AMCIII) with Sediment HEC-RAS 0.73 1796.3 5329 2807 2522

1000-yr HC (AMCIII) BAS 0.73 2637.5 7665 4405 3260

1500-yr HC (AMCIII) BAS 0.73 2784.6 8057 4585 3472

Page 48: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Normal Dry Weather Conditions – Water Reuse Functions

Upper Basin Water Quality Treatment & Recharge

12

3

4

Dry weather diversion gated culvert

Return Water Flow for habitat

SMWD Pump Station

UPPER BASIN

LOWER BASIN

Force Main

Page 49: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Dry Weather Flow Diversion Operation

Page 50: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Two 80’ Deep Recovery Wells that Lift to Distribution Pumps’ Suction

50

Groundwater Wells

Page 51: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pumping Facility Embedded into Side of Upper Basin to Draw Flows

51

Upstairs Electrical Control Room

Isolation Valves from Basin (storm flows and maintenance

Access Hatches to Wet and Dry Wells

Inflow from BasinHabitat Return flow to creek

Force main to upper reservoir

Page 52: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Water Reclamation Pump Station Designed w/ Four Different Sections

12

34

Basin Inflow

Creek Habitat Return FlowQmin= 0.3 cfs

Force main to Reservoir

Page 53: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pumping Facility has Desilting, Straining, and Return Flow to Creek

53

Pump Station Features:

• 2 Blowers Rubber Dams• 2- 100 hsp pumps (500

gpm each 550 ft head)• VFD

• Hydroneumatic tank for force main

• PLC and Manual Controls• SCADA radio control

Page 54: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Flood Flow Operations

Channel Side Weir

Upper to Lower Basin Spillways

Outlet Spillways to Channel

Gravity Outlet

LOWER BASIN = Flood Control

Lower Dam Inflated

Upper Dam Deflated

Gravity Outlet

Page 55: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Flood Flow Operations – Specialty Features

Lower Dam Inflated

Upper Dam Deflated

Portable Generator Connection

Manual Dam Control

Stream Gauge Sensor 1

Stream Gauge Sensor 2

Page 56: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Flood Control Operation

Page 57: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Flood Control Operation – Lower Dam Inflated• Intercept Q=2,000 cfs out of the Q100 = 5,330 cfs• D/S Flood Control Rubber Dam height = 6 ft

• Hydraulic control for side weir operation• Stilling well at rubber dam with water level transducer

• Height of Side Weir = 7.4 ft• Total Project Flood Storage = 99 (D/S) + 34 (U/S) = 133 AF

Page 58: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Project Design Features Construction – Pump Station

Page 59: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station Structure Foundation

Page 60: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station Structure Initial Construction Item

Page 61: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station & Creek Return Pipe

Page 62: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station – Constructed

Page 63: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station – Dry Well

Page 64: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station – Dry Well

Page 65: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Pump Station Construction

65

Page 66: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Project Design Features Construction – Rubber Dams

Page 67: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 68: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

North Dam Foundation

Page 69: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 70: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 71: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 72: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 73: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Inflatable Dam Installation Process

73

Page 74: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 75: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 76: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Inflatable Dams – Installed

Page 77: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 78: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 79: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 80: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Project Design Features Construction – Side Weir

Page 81: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 82: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 83: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Channel Side Weir - Installed

Page 84: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 85: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Project Design Features Construction – Basin / Embankment

Page 86: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Perimeter Embankment Section

Page 87: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Embankment Stability Analysis

Page 88: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Primary Outlet Spillway to Channel

Page 89: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Two Separate Gated Low Level Outlet

Page 90: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 91: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Low-Level Outlet Lower Basin

Page 92: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Temporary Creek Relocation – Water Control

Page 93: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Extensive Groundwater Dewatering Operation

Page 94: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Revetment Installation

Page 95: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 96: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 97: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 98: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 99: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Project Design Features Construction – Primary Spillway

Page 100: ASCE OC EWRI - Gobernadora Basin Facility Planning Design
Page 101: ASCE OC EWRI - Gobernadora Basin Facility Planning Design

Summary - Unique Multipurpose Water Resources Facility

• Automated operation for dry / flow floods• Multiple benefits beyond flood and water

recycling leverage public grant funding• Successful public/private partnership• Dual agency operation and maintenance• Innovative hydraulic operation through

flexibility provided by inflatable dams

Page 102: ASCE OC EWRI - Gobernadora Basin Facility Planning Design