Asbestos Management
2020 EIC Training
-
2
Asbestos Management
Trainer
Jonathan Bass, Environmental Specialist
Office of Construction
-
3
Standard Specifications Section 210
Removal and Disposal of Asbestos-Containing Materials (Buildings, Bridges & Highways)
✓ Buildings – Thermal Insulations, Siding, Roofing, Caulks, Sealers,
Flooring, Plasters, Ceiling Tile, etc.
✓ Bridges/Culverts – Bond Breakers, Joint Fillers, Caulks, Suspended
& Encased Utilities, Steel Coatings, Masonry Coatings, etc.
✓ Highways – Buried Utilties, Sidewalk Joint Filler, etc.
-
4
Thermal System Insulation
-
5
Thermal System Pipe Insulation
-
6
Transite Siding
-
7
Asbestos Roofing
-
8
Asbestos Floor Tile & Mastic
-
9
Asbestos Ceiling Tile
-
10
BEARING PADS
-
11
Suspended Transite Pipes
-
12
Suspended Coated Utility
-
13
Steel Coating – Up Close
-
14
Steel Coatings – Outside Bays
-
15
Masonry Coating
-
16
Route 30 Mine Kill Masonry Coating Abatement
-
17
Mazur Furniture – I287 Westchester Masonry Coating
-
18
Railbed Curbing
-
19
Railbed Curbing – Close up
-
20
Defunct Residency – Copper Salvage
-
21
Sheetpacking
-
22
Transite Expansion Joint Housing
-
23
Joint Filler
-
24
Culvert Coatings
-
25
NYSDOT Blanket Variance 14
• Statewide Application to Bridges and Highways
• Applies to Non-friable Asbestos-Containing Materials (ACMs) on
Bridges and Highways (no application to buildings).
• Applicable to NYSDOT, Thruway, Canal Corp. and County Highway
Projects (can also be used by private sector or municipal utility
companies working within listed agency, authority or county right-of-
way)
• Cities, Townships and Villages Can Use as Model for Site Specific
Variance Applications
• Requires Renewal by Department Every Three Years
-
26
Project/Air Monitoring
• Provided through Asbestos Term Agreement Consultant Forces
• Three (3) Zonal Agreements (Upstate East, Upstate West & Downstate)
• Managed by Main Office Consultant Management Bureau
• Acts as EIC Inspection Staff for All Asbestos Abatement Work
• Request for Use Made by Regional Construction Environmental
Coordinator or Regional Environmental Unit
-
27
Section 210-3 Construction Details
“The Contractor shall schedule a coordination meeting
between the Asbestos Subcontractor and the
Department Contracted Asbestos Project Monitor to be
held at least two (2) weeks before the start of any
asbestos abatement work.”
-
28
Recordkeeping
• Project Record Documentation is Generated by Both the Asbestos
Abatement Contractor and Project Monitoring Firms
• Following Completion of Asbestos Abatement Work, Copies of All
Asbestos Abatement Documentation is Retained by the Department
for Project Record
• Asbestos Bridge Abatement Project Records are Particularly
Important Because of Future Rehabilitation and Demolition Work
-
29
Waste Disposal
• All Friable Asbestos Waste Must Be Transported Under a Waste
Shipment Record and Disposed of at a Waste Disposal Facility
Permitted to Accept Friable Asbestos Waste (NYSDEC maintains
a current list of permitted NYS facilities)
• Friable Asbestos Waste Transport Also Requires a NYSDEC
Permitted Hauler
• Non-Friable Asbestos Waste May Be Disposed of at Sites
Approved to Accept Construction & Demolition (C&D) Debris
• Non-Friable Asbestos Waste Does Not Require A Waste
Shipment Record or a NYSDEC Permitted Hauler for Transport.
However, recent Part 360 revision does now require registration
and tracking for C&D
• C&D Disposal Receipts are Required
-
30
EB 16-048 – Section 210 CIM
II. Procedure (Project Monitor Responsibilities)
1. Reviewing & Approving Asbestos Contractor Pre-Abatement Submittals
2. Maintaining Daily Asbestos Abatement Project Documentation for the EIC
3. Ensuring Regulatory and Contractual Compliance by the Asbestos Contractor
4. Conducting Any Necessary Compliance Air Monitoring & Lab Analysis
5. Conducting Any Necessary Additional Bulk Sampling & Lab Analysis
6. Performing All Final Clearance Inspections (authorizing 75% item payment)
7. Verifying and Documenting All Removal Quantities for the EIC
8. Reviewing & Approving Asbestos Contractor Post-Abatement Submittals
9. Compiling All Asbestos Project Documentation for EIC Into Electronic File
(includes waste disposal documentation and authorizing final 25% item
payment)
-
31
EB 16-048 – Section 210 CIM
III. Documentation Retention
• Retain All Interim Daily Asbestos Abatement Project Documentation as
Attachments to Corresponding DWRs. Together With Approved Pre-
Abatement Submittals, This Represents the Project Record.
• Final Electronic Asbestos Abatement Close-Out File(s) Received From
the Project Monitor Shall be Retained for Long-Term Storage on
Corresponding Project-Wise Folders. Construction Environmental
Coordinator (CEC) Responsibility.
-
32
-
33
-
34
-
35
I81 State Street Demo
-
36
I81 State Street Demo
-
37
Region 7 Masonry Coating Abatement
-
38
Region 7 Masonry Coating Abatement
-
39
Region 9 Route 17 Steel Coating Abatement
-
40
Masonry Coating Shrouded Tool Abatement
-
41
Steel Coating Shrouded Tool Abatement
-
42
More Steel Coating Shrouded Tool Abatement
-
43
Cross Westchester Transite Pipe Abatement
-
44
Cross Westchester Transite Pipe Abatement
-
45
Cross Westchester Transite Pipe Abatement
-
46
North-South Arterial
Controlled Demolition
-
47
North South Arterial Controlled Demolition
-
48
North South Arterial Controlled Demolition
-
49
Questions???
-
50
Poll Question #1
NYSDOT Blanket Variance 14 is not applicable to
Asbestos Abatement for which Government Entity(s)?
1. NYSDOT
2. NYS Thruway
3. NYS Canal Corp.
4. County Highways
5. City, Town & Villages
-
51
#1 Answer
5. City, Town & Villages
* Mention NYC Asbestos Regulations & NYSDOT Applicability (Region 11 and NYC Watershed)
-
52
Poll Question #2
According to Standard Specification 210, the Contractor
is responsible for coordinating an asbestos abatement
start-up meeting between the Asbestos sub-contractor
and the Department Project Monitor a minimum of how
many weeks prior to the start of abatement work?
1. One
2. Two
3. Three
4. Four
-
53
#2 Answer
2. Two Weeks
-
54
Poll Question #3
Non-Friable Asbestos Waste Transport and Disposal
Requires NYSDEC Permitted Haulers and Waste
Shipment Records.
TRUE OR FALSE?
-
55
#3 Answer
FALSE
-
56
Poll Question #4
The Department-Contracted Asbestos Project Monitor
Acts as Separate Inspection Staff for the EIC and is
Responsible for the Following:
1. Pre-abatement Submittal Review & Approval
2. Regulatory and Contractual Compliance by the
Asbestos Abatement Sub-contractor
3. Verification/Documentation of All Removed Asbestos
Material Quantities
4. Final Asbestos Close-out Reporting
5. All of the Above
-
57
#4 Answer
5. All of the Above
-
58
Poll Question #5
Long Term Retention of Asbestos Abatement
Documentation in Project Wise is the Responsibility of
Who?
1. EIC
2. Project Monitor
3. Asbestos Abatement Sub-contractor
4. Construction Environmental Coordinator (CEC)
5. None of the Above
-
59
#5 Answer
4. Construction Environmental Coordinator