Physical address: 3501 Carmichael Rd Ext. Augusta GA. 30906 Office: 706-504-4033 Fax: 706-504-4259 BJ Duncan 706-833-5641 [email protected] Chris Duncan 706-829-2487 [email protected] Lucy Swilling - [email protected] ARK will gladly work with and submit quotes to pre-fabricate, test, deliver and install pipe for your facility. ARK will fabricate stainless and carbon steel ...piping in a professional and diligent manner. ARK will work along with your company and its employees to ensure that the work you provide us will be fabricated and installed in a timely SAFE manner and with outstanding quality. Just a few of our Recent Performances: ARK Recently performed a project at Potash Corp. Fabricating and Installing approximately 8500 ft of 24" river water piping throughout the entire plant. Contact: Larry Walker 706-469-1252 ARK provides industrial piping for many projects & maintenance at International Paper in Augusta GA. Contact: Glen Hughes 706-796-5545 ARK recently completed a large stainless piping job on the main fermenter at the Eli Lilly (Elanco) site in Augusta GA. The work consisted of the pre- fabrication of piping at our shop offsite, delivery, installation and testing of 316 schedule 40, piping sizes from ¾” up to 12”. Contact: Frank Ondrea 706-303-6204 ARK fabricated and installed piping on the recent PCS Outage. Contact: Dale Bobo 706-469-1292 ARK performs piping projects twice a month during scheduled outages at Resolute Forest Products. Contacts: Anthony Wallis 706-421-3776 Burt Barber: 803-480-5283

Upload: lucy-swilling

Post on 14-Apr-2017

77 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ark_Information Sheet (1) rev 2

Physical address: 3501 Carmichael Rd Ext. Augusta GA. 30906

Office: 706-504-4033 Fax: 706-504-4259

BJ Duncan 706-833-5641 [email protected]

Chris Duncan 706-829-2487 [email protected]

Lucy Swilling - [email protected]

ARK will gladly work with and submit quotes to pre-fabricate, test, deliver and install pipe for your facility. ARK will fabricate stainless and carbon steel ...piping in a professional and diligent manner. ARK will work along with your company and its employees to ensure that the work you provide us will be fabricated and installed in a timely SAFE manner and with outstanding quality.

Just a few of our Recent Performances:

• ARK Recently performed a project at Potash Corp. Fabricating and Installing approximately 8500 ft of 24" river water piping throughout the entire plant.

Contact: Larry Walker 706-469-1252

• ARK provides industrial piping for many projects & maintenance at International Paper in Augusta GA.

Contact: Glen Hughes 706-796-5545

• ARK recently completed a large stainless piping job on the main fermenter at the Eli Lilly (Elanco) site in Augusta GA. The work consisted of the pre-fabrication of piping at our shop offsite, delivery, installation and testing of 316 schedule 40, piping sizes from ¾” up to 12”.

Contact: Frank Ondrea 706-303-6204

• ARK fabricated and installed piping on the recent PCS Outage.

Contact: Dale Bobo 706-469-1292

• ARK performs piping projects twice a month during scheduled outages at Resolute Forest Products.

Contacts: Anthony Wallis 706-421-3776 Burt Barber: 803-480-5283

Page 2: Ark_Information Sheet (1) rev 2

Safety: ARK is a growing family owned business. We take pride in doing SAFE professional work. ARK has an impeccable safety record and holds safety as our highest priority. We have had a .79 MOD Rate for the past three years. We also have never had a Lost Time Accident.

Thank you for your consideration of ARK for your projects. We guarantee that you will not be disappointed with our safety standards, quality of work, and dedication to your project.

Page 3: Ark_Information Sheet (1) rev 2