ARCPE JUNE 2018 Architects 4 Hours Name :......................................................................... Date:.............................................. ID (Omang) : ............................................................................ Result:.............................................

Upload: others

Post on 17-May-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

ARCPE

JUNE

2018

Architects 4 Hours Name :......................................................................... Date:..............................................

ID (Omang) : ............................................................................ Result:.............................................

Page 2: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

2 | P a g e Copyright ARC 2018

PART 1: MULTIPLE CHOICE QUESTIONS Instructions for Multiple Choice Questions – (20 marks)

• Please circle the answer in clear indelible ink (blue or black).

• Each correct answer carries a full 2 marks.

_________________________________________________________________________

1. Which statement is correct?

In order to comply with Section 48A of the Architects Registration Act ( as amended),

every drawing submitted to a local authority for planning or building permission,

notwithstanding that it is produced by an architectural draftsperson or technologist,

(2 marks)

a) shall be signed by the City Clerk.

b) shall only be signed by an Engineer.

c) shall be signed by a registered architect with a practicing certificate.

d) Shall be signed by a contractor appointed to carry out the works.

2. Any failure by a registered architect to comply with the provisions of the Code of

Professional Conduct and Ethics of the Profession required under, Section 7 (1) and

Section 51 (2)b of the Architect’s Registration Act 2008,

(2 marks)

a) shall not be cause for any disciplinary proceedings.

b) shall only be considered for disciplinary proceedings for repeat offences.

c) shall be taken into consideration in any disciplinary proceedings before the

Council.

d) shall enable the architect to be duly registered to practice.

3. Which of the following statements is not correct with respect to the Town & Country

Planning Act (2 marks) a) It makes provision for the orderly and progressive development of land b) It seeks to preserve and improve on amenities provided with respect to land c) It seeks to regulate the construction of buildings d) It reviews qualification criteria and regulations of physical planners

Page 3: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

3 | P a g e Copyright ARC 2018

4. Which one of the following is not a point for consideration in the application of a

variation to the building setback requirement? (2 marks)

a) The position of adjacent buildings and their residential character.

b) The effect the setback variation has on sightlines and visibility for pedestrians and vehicles.

c) Building cost and contract duration. d) Size, shape and/orientation of the plot.

5. For a single storey building with a gable roof, ‘the height of storey’ is the height

measured from the base of the wall to; (2 marks) a) Top of the gable roof b) Top of the wall c) Half height of the gable roof d) Underside of the gable roof

6. The correct sectional plans are produced using measurements from:

(2 marks) a) An actual site visit measurements b) G.I.S. network c) The approved building plans d) As built drawings

CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH.

FIDIC 7a. If time to verify the Employer's Requirements and site conditions is not sufficient

within the tender period, what would be a recommended FIDIC Book to be used as a Form of Contract on the project? (2 marks)

a) Red Book b) Yellow Book c) Silver Book d) Green Book

7b. In FIDIC1999 Red Book DAB’s decision is: (2 marks)

a) Binding but not final b) Binding and final c) Binding and may become final d) Neither binding nor final

Page 4: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

4 | P a g e Copyright ARC 2018

JBCC MINOR WORKS AGREEMENT / BIDP STANDARD FORM

8a. Which of the following statements is incorrect with respect to termination clauses: (2 marks)

a) Under the BIDP Standard Form, the Contractor can determine his employment under

contract forthwith after giving the Employer’s 7 Days’ Notice following the employer’s failure to honour certificates within the stipulated period.

b) Under BIDP Standard form, the Contractor can determine his employment under contract forthwith on Employer being declared Bankrupt

c) Under the JBCC Minor Works Agreement, the contractor is obliged to give the employer 5 Working days’ notice of his intention to terminate his employment under the terms of the contract.

d) Under the JBCC’s Minor Works Agreement, the contractor can determine his employment under contract forthwith on Employer being declared Bankrupt.

8b. Which of the following statements is incorrect with respect to Nominated subcontractor and Direct Contractor clauses: (2 marks)

a) Nominated subcontractors under the BIDP Standard Form are appointed by the

architect for the execution of specialised works covered by a sum of money included in a contract and they work under the direct control of the main contractor.

b) Direct contractors under the JBCC Minor works Agreement work under the direct control of the employer. There is no obligation on the contractor to control their work although he is obliged to include them in his programme.

c) Under JBCC Minor Works Agreement the Main contractor cannot claim loss and/or expense for delays caused to the works by a direct contactor as they do not work under his control.

d) Under the BIDP Standard Form, the contractor is entitled to claim extension of time for delays caused by a nominated subcontractor but cannot claim costs.

9. In a planned area, if your client has a plot of 1000m² designated as a single family residential plot, and builds a house which is 500m², she can later accommodate two separate families without contravening the building regulations if: (2 marks)

a) She provides two separate entrances to the building. b) She does not make separate entrances to the building. c) She applies for a change of land use. d) She provides two separate accesses to the plot.

10. Which of the following entities is/are deemed to have the capacity to contract:

(2 Marks)

a) Mentally disturbed or intoxicated individuals. b) Individuals below the age of 18. c) Unincorporated association. d) Legal Persons.

Page 5: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

5 | P a g e Copyright ARC 2018

PART 2: Instructions for Part Two Questions; – (80 marks)

• Write your answers precisely using clear hand writing.

• Use clear indelible ink (blue or black).

• Write your answers in the spaces provided. Please use additional paper available at the end of the document.

_________________________________________________________________________

1. In your own words, briefly describe the three categories of Continual Professional Development programs from which points can be claimed towards acquiring a Practicing Certificate. (3 marks)

a) State any 2 requirements for eligibility to apply for a Practicing Certificate under the Architects’ Registration Regulations (2 marks)

Page 6: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

6 | P a g e Copyright ARC 2018

2. Maranyane University has issued an Invitation to Tender (ITT) for registered

architects to tender for the provision of Architectural Services for the design and supervision of a research facility building consisting of amphitheatres, teaching spaces, research laboratories and staff offices. As part of the submission for the ITT, they have requested drawings to demonstrate the design concept commensurate with Workstage (2) of the Framework for the Delivery of Architectural Services and Use of the Tariff of Fees. Tendering architects will have to bear all costs arising from the tender preparation and submission.

a) As a registered architect, will you submit design concept drawings as part of your tender submission? Briefly explain why. (2 marks)

b) As a registered architect intending to comply with the provisions of the Code of Professional Conduct and Ethics of the Profession, what would your advice be to Maranyane University about the best way to procure Architectural Services at this stage of the project? (3 marks)

Page 7: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

7 | P a g e Copyright ARC 2018

c) List any 2 (two) circumstances under which the Architects’ Registration Council can order the removal from the register of the name of an architectural professional. State the procedure followed for the reinstatement of the removed name to the register. (5 marks)

Page 8: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

8 | P a g e Copyright ARC 2018

3. a) What is the importance/function of the Development Control Code (DCC)? (4 marks)

b) When can one apply variation to the building setback requirements? State two (2) relevant matters that must be addressed in a request for a setback variation.

(4 marks)

Page 9: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

9 | P a g e Copyright ARC 2018

c) Can a private residential house include a consulting room for an Architect? If yes, what requirements should the dwelling and the consulting rooms meet?

(2 marks) 4. Government buildings in Botswana and some other countries are mostly erected by

the Ministry responsible for Works (DBES or otherwise), and are exempted from Building Regulations. In your view, why does this exemption exist?

(3 marks)

Page 10: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

10 | P a g e Copyright ARC 2018

5. Botswana Institute for Technology Research and Innovation (BITRI) in collaboration with the Faculty of Engineering and Technology of University of Botswana want to investigate the performance of new building materials including Compressed Earth Bricks (CEB) and Straw Clay Roof Tile (SCRT). They have designed 5 different buildings they want to erect using these materials. They have approached you as a registered professional with ARC to assist them with the submission to Gaborone City Council to obtain the necessary compliances with the Building Regulations. How will you assist them? (5 marks)

Page 11: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

11 | P a g e Copyright ARC 2018

6. You have been approached by a Client to design a multi-family development of 15 Townhouses on a 3000m2 plot in Tlokweng. In close proximity to the plot are a Shopping Centre, a Daycare Centre and a Public Park.

a) Is it mandatory for you to provide for Open Space on your design? Explain

your answer. (2 marks)

b) What is the minimum number of parking bays required for your development? (3 marks)

c) Your Client would like the development to be one large building. What is your advice to her? (2 marks)

Page 12: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

12 | P a g e Copyright ARC 2018

7. You are a registered and Practicing Principal/ Architect at D4000 (Pty) Ltd. The tenders have just been retuned and the lowest bidder’s price of P12, 600,000 (twelve million six hundred thousand pula only) inclusive of 12% VAT has been accepted by your client. The accepted tender amount includes contingencies of P800, 000 (Eight hundred thousand Pula only). The VAT included in the contract sum is P1, 350,000 (One million three hundred and fifty thousand pula). Just prior to tender you had claimed Stage 4a Fees based on the Quantity Surveyors pre-tender estimate of P10,000,000 (Ten million Pula only) which did not include VAT but still included a contingency of P800,000 (Eight hundred thousand Pula only). a) In the space provided below, calculate the fees now due for stage 4b

(11 marks)

Page 13: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

13 | P a g e Copyright ARC 2018

b) The contract amount is eventually exceeded due to client initiated variations and the Final Account is agreed and signed off at a figure of P14,301,250 (Fourteen million, three hundred and one thousand two hundred and fifty Pula only) inclusive of VAT. In the space below calculate the full fee that would be payable for stages 5 and 6 based on the final account sum. (5 marks)

c) After completion of the project, the client dispenses with your services but

informs you of his intention to re-use your designs with another architect on another site. How would you respond to the client’s decision and how much would you charge for re-use of your drawings if at all. (4 marks)

Page 14: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

14 | P a g e Copyright ARC 2018

8. Briefly explain, is the spaces provided below, your understanding of the following Extension of Time terms:

a) Act of Prevention (2 marks)

b) Time becoming at large (2 marks)

c) Time being of the essence (2 marks)

Page 15: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

15 | P a g e Copyright ARC 2018

9. Name at least four actions that follow the release of the Practical Completion Certificate in most building contracts (4 marks)

Page 16: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

16 | P a g e Copyright ARC 2018

CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 10a, 10b, 10c and 10d OR QUESTION 11a, 11b, 11c and 11d BUT NOT BOTH.

FIDIC 10.

a) Create a timeline for the submission of a Contractor’s claims under FIDIC 1999 Red Book if the event or circumstance giving rise to the claim has a continuing effect. (2.5 marks)

b) Explain the role of the Engineer under FIDIC 1999 Red Book by comparing the Engineer’s authority to issue instructions under Sub-Clause 3.3 and the Engineer’s duty to make determinations in accordance with sub-Clause 3.5

(2.5 marks)

Page 17: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

17 | P a g e Copyright ARC 2018

c) Explain the role of a standing DAB under FIDIC 1999 Red Book (2.5 marks)

d) Explain the steps to be taken by the Engineer in accordance with Sub-Clause 3.5 (Determinations) of FIDIC 1999 Red Book and illustrate the requirements by providing the sequence of events under the Sub-Clause

(2.5 marks)

Page 18: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

18 | P a g e Copyright ARC 2018

BIDP STANDARD FORM & JBCC MINOR WORKS AGREEMENT 11.

a) Describe below the main difference between how the BIDP Standard form of Contracts and the JBCC Minor Works (or JBCC Principal Building Agreements) are administered in relation to both the Architect’s registration act and the Framework for the use of Tariff of Fees . (2.5 marks)

b) What is the Prescription Period for written contracts under Botswana Law and what effect does this have on the latent defects liability period?

(2.5 marks)

Page 19: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

19 | P a g e Copyright ARC 2018

c) The BIDP Standard Form has the option of being executed “under hand” or “under seal”. Explain your understanding of the 2 terminologies in the space below. (2.5 marks)

d) Explain below the major differences in Insurance provisions between the BIDP Standard form of Building Contract and the JBCC Minor Works Agreement. (2.5 marks)

Page 20: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

20 | P a g e Copyright ARC 2018

Page 21: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

21 | P a g e Copyright ARC 2018

Page 22: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

22 | P a g e Copyright ARC 2018

Page 23: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

23 | P a g e Copyright ARC 2018

Page 24: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

24 | P a g e Copyright ARC 2018

Page 25: ARCPE JUNE 2018 - arc.org.b · CANDIDATES HAVE THE OPTION OF ANSWERING EITHER QUESTION 7a and 7b OR QUESTION 8a and 8b BUT NOT BOTH. FIDIC 7a. If time to verify the Employer's Requirements

Architects Registration Council Professional Exam - June 2018

25 | P a g e Copyright ARC 2018