APS Ten-Year Plans2006-20154th BTA Presentation
Bob Smith
Manager Transmission Planning
June 6, 2006
June 6, 2006 4th BTA 2
APS EHV & OUTER DIVISION 115/230 KVTRANSMISSION PLANS 2006 - 2015
SELIGMAN
ROUNDVALLEY
POWER PLANT
115KV & ABOVE SUBSTATION (EXISTING)
230KV & ABOVE SUBSTATION (FUTURE)
JOINT OWNSHIPJ/O
LEGEND
NORTH
ADAMS
MURAL
SAN MANUELORACLEJUNCTION
SAGUARO
N.GILA
YUMA
PALO VERDE-HASSAYAMPA
YUCCA
GILA BEND
500KVJ/O
TO CALIF.500KV
REDHAWK
JOJOBA
GILA RIVER/PANDA
RUDDLIBERTY
KYRENE
SANTAROSA
DESERTBASIN
WESTWING
500KV J/O
BAGDAD
YAVAPAI VERDE
FLAGSTAFF
PRESCOTT
PINNACLEPEAK
PREACHERCANYON
CHOLLA
230KV
345KVTO CALIF.
500KV J/O
500KV J/O
TOCRYSTAL
TO MEAD /MARKETPLACE
MOENKOPI
NAVAJO
PAGE
FOURCORNERS
500KV
TUCSON
PHOENIXLIBERTY
12/1/05Transmission Planning
2012MAZATZAL
COCONINO
Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.
CASAGRANDE
TAT MOMOLI
KNOX
GAVILANPEAK
(WAPA)
FLAGSTAFF(WAPA)
To GLENCANYON (WAPA)
(WAP
A)
EXISTING 500 KV LINESEXISTING 345 KV LINESEXISTING 230 KV LINESEXISTING 115 KV LINES
PLANNED 500KV LINES NUCLEAR POWER PLANT
2 circuits
WILLOWLAKE
PLANNED 345KV LINES
PLANNED 230KV LINES
PLANNED 115KV LINES
CORONADO(SRP)
FLAGSTAFF(APS)2009
SECONDKNOLL2009
2012J/O
2012
2009 TS52009
TBD
TBD
VV12009
RACEWAY2010
2010
June 6, 2006 4th BTA 3
BELL RD.
I - 10 FWY.
BASELINE RD..
I-17
FWY.
I-17
FWY.
I - 10 FWY.
I-10
FWY.
SUPERSTITION FWY.
BASELINE RD..
MCDONALD RD.
PINNACLEPEAK
CACTUS
OCOTILLO
KYRENE
500kV
TO JOJOBA
KNOX(SRP)
TO BROWNING500kV
TO SANTA ROSA
REACH
LONE PEAK
SUNNYSLOPE
MEADOWBROOK
LINCOLN ST.
COUNTRY CLUB
ALEXANDER
J/O APS/SRP
To Prescott
GAVILAN PEAK
WAPA
2 - Circuits 2 - Circuits
345KV
TOGLEN
CANYON(WAPA)
TOCHOLLA
PHOENIX METROPOLITAN AREATRANSMISSION PLANS
2006-2015
Transmission Planning
GLENDALE
APS EXISTING 500KV LINESAPS EXISTING 345KV LINESAPS EXISTING 230KV LINES
UNDERGROUND
APS PLANNED LINES230KV
500KV
230KV SUBSTATION (EXISTING)230KV SUBSTATION (FUTURE)
GENERATING SITE &230KV SUBSTATIONJOINT OWNSHIPOTHER COMPANY LINES
J/O
CAREFREE HWY.
TB
D(S
RP
)
BETHANY HOME RD.
Substations locations and line routings are approximate345KV
TBD
SURPRISE
AGUAFRIA
EL SOL
DEERVALLEY
RUDD
TO PALO VERDE
WESTPHOENIX
WESTWING
LIBERTY/TS4
BUCKEYE
TOGILA BEND
To Navajo
WAPA
TOPALO VERDE
500KV
500KV
To NewWaddell
WA
PA
WHITE TANKS(APS)
TOPALO
VERDE
500kvJ/O
LIT
CH
FIE
LD R
D.
2010
2010Raceway
PIM
A R
D.
2010
2011TS2
2010TBD
TBD
TS12009
TS52009 2009
TBD
2010
2010
TS62010
2010J/O
SRPSRP
2007PALM VALLEY
2007
TB
D
AVERY2009
2009
June 6, 2006 4th BTA 4
Changes from 2004 to 2006Project Status
2005 Gavilan Peak 230kV Completed
TS3 230/69kV substation Named Palm Valley
2006 Rudd-Palm Valley-TS4 230kV Changed to I/S date of 2007
2006 Flagstaff 345/69kV interconnection
Changed to I/S date of 2009
2006 Jojoba cut-in of TS4-Panda 230kV Changed to I/S date of 2011
South East Valley 500kV project - Hassayampa-Pinal West & Pinal West-Santa Rosa-Browning
Removed from APS plan - APS no longer participating
2007 PV Hub-TS5 500kV Changed to I/S date of 2009 and added interconnection options (AVGS & HQJNT)
June 6, 2006 4th BTA 5
Changes from 2004 to 2006Project Status
2007 TS5-TS1 230kV Changed to I/S date of 2009
2008 TS1-TS2-Palm Valley 230kV
w/TS2 I/S of 2012
Changed to I/S date of 2010
w/TS2 I/S date of 2011
2008 RY-AV 230kV Changed to I/S date of 2009
2009 PP-TS6-AV 230kV Changed to I/S date of 2010
2009 Second Knoll 500/69kV Interconnect moved from CO-SK line to CO-CH line
2010 TS5-RY 500kV Changed to I/S date of 2012
2010 WW-RY 230kV Changed to I/S date of TBD
2012 Gila Bend-TS8 230kV Replaced with PV Hub-N.G. 500kV
June 6, 2006 4th BTA 6
Changes from 2004 to 2006Project Status
2013 WW-ES 230kV Changed to I/S date of TBD
TBD Mazatzal 345/69kV Changed to I/S date of 2011
2009 VV1 500/69kV New Project
2010 TS9-PP 500kV New Project
2012 N.G.-TS8 230kV New Project
TBD Yucca-TS8 230kV New Project
TBD SR-Pinal South 230kV New Project
June 6, 2006 4th BTA 7
Conceptual Projects
TransWest Express Transmission from Wyoming to Arizona and/or
southern Nevada Access coal and wind resources in Wyoming Three AC alternatives
Looking at 500kV and 765kV options One DC alternative Developing through open stakeholder process Compliments other planned projects Cost range $2B-$5B
June 6, 2006 4th BTA 8
Conceptual Projects:TransWest Express Project
June 6, 2006 4th BTA 9
Conceptual Projects
230kV west of White Tank Mountains Large developments planned for the area
immediately to the west of the White Tank Mountains
230kV line(s) between TS5 substation and Buckeye substation
Working with developers, gov’t agencies, and any identified stakeholders to stay ahead of the growth.
June 6, 2006 4th BTA 10
BELL RD.
I - 10 FWY.
BASELINE RD..
I-17
FWY.
I-17
FWY.
I - 10 FWY.
I-10
FWY.
SUPERSTITION FWY.
BASELINE RD..
MCDONALD RD.
PINNACLEPEAK
CACTUS
OCOTILLO
KYRENE
500kV
TO JOJOBA
KNOX(SRP)
TO BROWNING500kV
TO SANTA ROSA
REACH
LONE PEAK
SUNNYSLOPE
MEADOWBROOK
LINCOLN ST.
COUNTRY CLUB
ALEXANDER
J/O APS/SRP
2010
AVERY2009
To Prescott
GAVILAN PEAK
WAPA
2 - Circuits 2 - Circuits
345KV
TOGLEN
CANYON(WAPA)
TOCHOLLA
PHOENIX METROPOLITAN AREATRANSMISSION PLANS
2006-2015
TS62010
Transmission Planning
GLENDALE
APS EXISTING 500KV LINESAPS EXISTING 345KV LINESAPS EXISTING 230KV LINES
UNDERGROUND
APS PLANNED LINES230KV
500KV
230KV SUBSTATION (EXISTING)230KV SUBSTATION (FUTURE)
GENERATING SITE &230KV SUBSTATIONJOINT OWNSHIPOTHER COMPANY LINES
J/O
CAREFREE HWY.
TBD
( SR
P)
BETHANY HOME RD.
Substations locations and line routings are approximate345KV
2010
TBD
SURPRISE
AGUAFRIA
EL SOL
DEERVALLEY
RUDD
TO PALO VERDE
WESTPHOENIX
2007PALM VALLEY
2007
2010
2012TS2
TS12009
WESTWING
LIBERTY/TS4
BUCKEYE
TOGILA BEND
To Navajo
WAPA
TOPALO
VERDE
TS52009
500KV
500KV
To NewWaddell
WA
PA
WHITE TANKS(APS)
2009
2010
TOPALO
VERDE
500kvJ/O
LIT
CH
FIE
LD R
D.
2010
2010Raceway
2009
PIM
A R
D.
TBD
TBD
TBD
2010J/O
SRPSRP
SUN
VAL
LE
Y P
KW
Y.
TBD