Application of Simulation in Construction Processes
By: Khalid Al-Gahtani
King Saud University
CE417CE417CONSTRUCTION EQUIPMENT AND METHODSCONSTRUCTION EQUIPMENT AND METHODS
Project Content
Simulation software.Simulation models in construction.Case study of earthmoving by
using simulation.
Simulation SoftwareCycloneSTOPSCOPESimulation using javaSimEarth simulation systemBelief networks for construction
STOPSCOPE
SimEarth simulation system
Simulation Models for Some Construction ProcessesBridge damp earthmovingSteel erection modelBridge process simulation model
Bridge Dam Earthmoving Model
Bridge Dam Model
Steel Erection Model
Bridge Process Simulation Model
Case Study Of Earthmoving by Using Um-cyclone
Loaders Used in Simulation
Model CAT 936 CAT 950E
Machines available 2 1
Bucket Size (m3) 2 2.4
Soil loaded in loader’s bucket, S (m3)
Bucket Size*
N[1,0.05]
Bucket Size *
N[1,0.04]
Time to load a scoop of soil in truck (min)
0.40+0.05S 0.43+0.035S
Cost ($/hr) 45 62
Truck Equipment That Used.Model CAT 769C CAT 773B
Machines available 8 3
Capacity (m3) 23.6 34.1
Max. speed (km/hr) 75 62
Actual speed (km/hr)Calc. Speed*N[1,0.03]
Calc. Speed*N[1,0.02]
Dumping time (min) 1 1.12
Maneuvering time at loading area (min)
0.6 0.72
Cost ($/hr) 117 175
Result of CycloneThe total time that required moving
200,000 m3 based on 3 loader and 11 trucks is 19128.7 minute = 318.8 hours = 45.5* working days.*Assuming 7 hours/day.
Cyclone software.