applapplying g overance ying g overance on projects web in ar
DESCRIPTION
Applying g OveranceTRANSCRIPT
1 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Applying Governance on Projects
Tom Mochal, PMP, PgMP, PMI-ACP, TSPM, ITBMC
2 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
What is Governance?
• Describes how management hierarchy establishes and enforces rules and policies
• You have to have processes, policies, standards – If not you can't expect people to follow them.
• You have to enforce the processes – Don’t create mandatory processes if no enforcement – Unenforced processes should be guidelines
3 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
P roject Governance
• Need project management and lifecycle processes • Determine what parts are required • Apply governance to required portions
4 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Portfolios and Projects
Portfolio
Project
Governance Points
5 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Scale Project Governance
• Don’t use one-size-fits-all approach - apply scalably • Small projects
– Few requirements, little (but not no) governance
• Large projects – Need more rigor and structure – More required elements
• Medium projects – Less than large projects and more than small projects
6 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
P lan the Project
• Need planning process • Need document to define work
– Project Charter, scope statement, SOW, etc.
• Governance Point – The planning document
should be formally approved
7 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Build and Manage Schedule
• Projects need a schedule • The schedule needs to be updated • The schedule is too tedious to validate • Governance Point
– Milestones are used to validate overall schedule – Managers monitor milestones to validate overall progress
8 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Build and Manage Budget
• Costs are estimated in planning • Budgets are allocated • Costs needs to be managed • Governance Point
– Project reports expected spending and actual spending – Managers monitor spending through status reporting and
especially at phase gate reviews
9 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Gather Requirements
• Gain agreement on characteristics of deliverables • Governance Point
– Formal approval of requirements – Signifies requirements are
complete and correct
10 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Manage Change Control
• Establish and agree on standard change control • Generally means scope change, but some projects
manage all changes • Governance Point
– Ensure all changes go through a formal process – All changes to scope, schedule, budget should be approved
11 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Manage Risks and Issues
Risks • Potential problems
Issues • Current (large) problems
Governance Point
• Validate risks and issues are identified • Validate they are being managed and closed
12 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Manage Project Status
• Manage expectations • Report current status
– Schedule / budget – Risks / issues / changes – Anything else of interest
• Governance Point – All projects should report status – Validate governance against many of the other criteria – Makes it easier to monitor and provide governance
13 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Phase Gate Reviews
• Formal reviews between start and end of project – End of each phase / milestones
• Validate all prior work is completed
• Ensure project is ready to proceed • Governance Point
– Gate reviews are critical governance points – Sponsor and key stakeholders focus on project status – Ensure project is in control before proceeding
14 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Other Governance Points
• Governance Points – Set up and enforce as needed – Don’t go overboard
Lifecycle processes and
documents
Project Management
Plans Safety plans
Disaster recovery
Government reports / filings
15 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
P roject Closure
• Formal approval that project objectives are fulfilled • Governance Point
– Last governance point before team disbands
16 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Governance and Culture
• Some organizations are good at it – See a problem, fix it and ensure everyone follows the
revised process
• Some organizations are very weak – See problems and how to fix – Can’t actually make the
required changes – Problems are known for years
but resolution is outside of their cultural ability
17 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
Summary
• Governance is process of making and enforcing rules • Projects need required processes based on size • Project governance ensures processes are followed • Typical governance points explained in this session • Some organizations are good at it, some not
18 Copyright © 2012 TenStep, Inc Applying Governance on Projects - Webinar
More Information
• TenStep, Inc. • Tom Mochal, President • 877-536-8434