NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT FOR THE WASTE RECOVERY,
TREATMENT AND TEMPORARY STORAGE FACILITIES AT THE BMW PRODUCTION PLANT,
ROSSLYN, CITY OF TSHWANE METROPOLITAN MUNICIPALITY
REF NO: 12/9/11/L435/3
Notice is hereby given in terms of the National Environmental Management: Waste Act (Act No 59 of 2008) that, BMW
South Africa (Pty) Ltd has submitted an application for a waste management license to the Department of Environmental
Affairs.
BMW South Africa operates a Waste Management Centre, effluent treatment plant and a temporary paint sludge storage
area as part of its production activities at their plant in Rosslyn, City of Tshwane Metropolitan Municipality, Gauteng
Province.
According to the NEM: Waste Act, a person who wishes to commence, undertake or conduct an activity listed under
Category B of Government Notice 718, must conduct an Environmental Impact Assessment (EIA) process, as stipulated in
the EIA Regulations (2010) made under section 24(5) of the National Environmental Management Act, 1998 (Act No. 107 of
1998). Consequently, BMW South Africa intends to undertake an Environmental Scoping Study and an Environmental
Impact Assessment and submit a Scoping and EIA report respectively in support of the waste management license
application.
An application for exemption from assessing alternatives in terms of Chapter 5, Section 50 of Government Notice R.543 was
lodged with the Department of Environmental Affairs on 16 September 2010 and the exemption was granted on 01
November 2010.
NOTICE OF AVAILABILITY OF DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR
PUBLIC REVIEW
All Interested and Affected Parties are hereby notified that the draft Environmental Impact Assessment Report (EIAR) will be
available for public comment from 22 February 2011 for a period of 60 days until 04 May 2011. The report will summarise
key environmental issues identified to date and will be available for download on the SSI Environmental website
(http://www.ssi-dhv.com/pages/enviromental/current-projects.php). Hard copies of the draft EIAR will also be available at the
following places:
• BMW Rosslyn Plant (Gate 1, Main Reception, Frans du Toit Street)
• Pretoria North Municipal Library (288 Burger Street)
• Offices of SSI Environmental (78 Kalkoen Street, Monument Park, Pretoria)
WHO SHOULD YOU CONTACT?
SSI Environmental Consultants is the appointed independent Environmental Assessment Practitioner (EAP), undertaking
the required Environmental Impact Assessment and Public Participation Process for the project. To register as an Interested
and Affected Party (I&AP) and to obtain more details about the project, please submit your name, contact information and
interest in the project to:
Phyllis Kalele
SSI Environmental
TEL: 012 367 5800
FAX: 012 367 5878
E-MAIL: [email protected]
WEBSITE: www.ssi-dhv.com
APPENDIX D2
I&AP CORRESPONDENCE
18 February 2011
Dear Interested and Affected Party (I&AP),
NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT FOR THE WASTE RECOVERY,
TREATMENT AND TEMPORARY STORAGE FACILITY AT THE BMW ROSSLYN PRODUCTION
PLANT, ROSSLYN, CITY OF TSHWANE METROPOLITAN MUNICIPALITY
Ref No: 12/9/11/L435/3
Notice is hereby given in terms of the National Environmental Management: Waste Act (Act No 59 of
2008) that, BMW South Africa (Pty) Ltd has submitted an application for a waste management license to
the Department of Environmental Affairs.
BMW South Africa operates a Waste Management Centre, effluent treatment plant and a temporary
paint sludge storage area as part of its production activities at their plant in Rosslyn, City of Tshwane
Metropolitan Municipality, Gauteng Province.
According to the NEM: Waste Act, a person who wishes to commence, undertake or conduct an activity
listed under Category B of Government Notice 718, must conduct an Environmental Impact Assessment
(EIA) process, as stipulated in the EIA Regulations (2010) made under section 24(5) of the National
Environmental Management Act, 1998 (Act No. 107 of 1998). Consequently, BMW South Africa intends
to undertake an Environmental Scoping Study and an Environmental Impact Assessment and submit a
Scoping and EIA report respectively in support of the waste management license application.
An application for exemption from assessing alternatives in terms of Chapter 5, Section 50 of
Government Notice R.543 was lodged with the Department of Environmental Affairs on 16 September
2010 and the exemption was granted on 01 November 2010.
NOTICE OF AVAILABILITY OF DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR
PUBLIC REVIEW
All Interested and Affected Parties are hereby notified that the draft Environmental Impact Assessment
Report (EIAR) will be available for public comment from 22 February 2011 for a period of 60 days until
04 May 2011. The report will summarise key environmental issues identified to date and will be
available for download on the SSI Environmental website (http://www.ssi-
dhv.com/pages/enviromental/current-projects.php). Hard copies of the draft EIAR will also be available
at the following places:
• BMW Rosslyn Plant (Gate 1, Main Reception, Frans du Toit Street)
• Pretoria North Municipal Library (288 Burger Street)
• Offices of SSI Environmental (78 Kalkoen Street, Monument Park, Pretoria)
WHO SHOULD YOU CONTACT?
SSI Environmental Consultants is the appointed independent Environmental Assessment Practitioner
(EAP), undertaking the required environmental impact assessment and public participation process for
the project. To register as an Interested and Affected Party (I&AP) and to obtain more details about the
project, please submit your name, contact information and interest in the project to:
Phyllis Kalele
SSI Environmental
PO Box 25302
Monument Park 0105
Pretoria.
TEL: 012 367 5800
FAX: 012 367 5878
E-MAIL: [email protected]
Website: www.ssi-dhv.com
APPENDIX E 1
I&AP DATABASE
Name Company / Organization
Terry Starkey Metalco
Jaco Verster NN Metals
Wiets Botes Wasteman
Natasha Buitendagh UCG Recyclers
Christo Human Le Risto Houtwerke
Charles Swart Equility Enterprises
Nolean du Plessis Nampak
Ashley Shub Polyethylene recoveries
Ismeal Enviroserve
Fawie Enviroserve
Andre Ungerer Enviroserve
Dereck Strauss Top line steel
Frans Alberts B Martin Trading
Brett Lewis Oil Separation Solutions
NEIGHBOURING INDUSTRIES
Galebalwe Ramorola South African Breweries
Alrie Nissan SA
Louis Hellberg August Lapple SA
Johnny Cowley Strandfoam
Jannes Strydom Bevcan / Nampak
Jaco Wessels Trident Steel
Veronica Pule Feltex Automotive (Pty) Ltd
OTHERS
J.F. Rynners Land Owner
P. Rynners Land Owner
Dries Prinsloo SGE Boiler & Maintenance
Gert van Veeren
Ron Veljoen Thlomamo Construction
J. Saunders EKA Safety
E Maher Lance Engineering
O Gasewentia Zan-nik
L Du Toit Autocarrier Transport
J Swart Pallet Makers
G Janse Van Vuuren Bachmann Garage
H Buitenbag WFM Wholesome Foods
Stoffel Henrico Getec
WASTE COLLECTION CONTRACTORS
FEBRUARY 2011
Wessel van Biljon Getec
Ross Matkovich
Peter De Haas Peter De Haas Town Planning
Mendel Sass Autocarrier Transport
Hendrik Engen Garage
Ehan Lategan E & S Engineering
Linda Stonder Fellex Automotive
G Du Toit GCA
Desiree Jordan G4S
Y van Heerden CPM
John Barendrecht Ward councillor
Frederik van Weele Tshwane metropolitan municipality
Marlah Hammond
Tshwane Metropolitan Municipality-
Environmental Management
Johan Human
Tshwane Municipality-Chief Director
Environmental Department
Wanda Byrne
Tshwane Municipality - Open Space
Management Section
Justice Maluleke DWA
Masego Khambule DWA
Concilience Sambo DWA-Working for Water
Dineo Masemola DWA
Joanne Yawitch
DEA-Environmental Quality and Protection
Department
Sibusisiwe Hlela DEA-Environmental Impact Management
Zingisa Smale GDA&RD-Director: Waste Management
Mafu Nkosi
GDA&RD-Director: Environmental Planning
and Impact Assessment
Disebo Mashitisho
GDA&RD-Chief Director: Compliance and
Enforcement Branch
Lucy Ramatapa
Gauteng Department of Health:
Environmental Health
GOVERNMENT AUTHORITIES
FEBRUARY 2011
APPENDIX E 2
ISSUES TRAIL
`
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS
ISSUES TRAIL
WASTE MANAGEMENT LICENSE APPLICATION FOR THE WASTE RECOVERY, TREATMENT AND TEMPORARY STORAGE FACILITIES AT THE BMW PRODUCTION PLANT, ROSSLYN, GAUTENGPROVINCE
SUMMARY OF ISSUES / CONCERNS AND SUGGESTIONS RAISED BY INTERESTED AND AFFECTED PARTIES (I&AP’s)
FEBRUARY 2011
WASTE MANAGEMENT LICENSE APPLICATION FOR THE WASTE RECOVERY, TREATMENT AND TEMPORARY STORAGE FACILITY AT THE BMW PRODUCTION PLANT, ROSSLYN
SSI ENVIRONMENTAL 1 January 2011
ISSUE/COMMENT RAISED BY RESPONSE
1. Bevcan neighbours BMW with the road to Brits running between
them. They have no points of concern about the project.
Johannes Strydom
Risk Control Superintendent
Bevcan Rosslyn
Tel: 012-521 9043
Fax: 012-541 2847
Email: [email protected]
PO Box: 911095, Rosslyn 0200
Email received on 4 October 2010
Comment is noted.
2. Recycling is their main area of interest with regards to the
proposed waste management license application by BMW.
Nastassia Buytendag
UCG Recycling (Pty) Ltd
Tel: 011-762 4336
Fax: 011-762 6490
Email: [email protected]
PO Box: 3201, Krugersdorp 1745
Email received on 19 October 2010
Comment noted.
3. MA Automotive is situated next to BMW and so the company
would like to know in what way they could be affected.
Louis Hellberg
QS, Environmental and Safety Manager
MA Automotive Rosslyn (Pty) Ltd
Email, 19 October 2010
Tel: 082-447 8564
Fax: 012-521 2547
Email: [email protected]
PO Box : 91168, Rosslyn 0200
Email received on 19 October 2010
BMW South Africa operates a Waste Management Centre (WMC) for the recovery of solid
waste; an effluent treatment plant and a temporary paint sludge storage area as part of its
production activities at their plant in Rosslyn, City of Tshwane Metropolitan Municipality,
Gauteng Province.
All these waste management activities are located within the BMW plant premises and have
been in operation for over 15 years. Additionally, the facilities are designed such that they
have a dedicated storage area for the various waste streams to prevent environmental
contamination and to treat waste water prior to the release into the municipal sewerage
system. The waste management license application is a pro-active action by BMW SA to
comply with the requirements of the Waste Act (Act No. 59 of 2008) and thus, the
neighbouring premises will not be affected in any way.
All comments raised by I&APs will be captured in an issues trail which will form part of the
final Environmental Scoping and Environmental Impact Reports.
WASTE MANAGEMENT LICENSE APPLICATION FOR THE WASTE RECOVERY, TREATMENT AND TEMPORARY STORAGE FACILITY AT THE BMW PRODUCTION PLANT, ROSSLYN
SSI ENVIRONMENTAL 2 January 2011
ISSUE/COMMENT RAISED BY RESPONSE
4. Palletmakers (Pty) Ltd. would like some more briefing on the
waste management license application.
E Wynand Swart
Director
Palletmakers (Pty) Ltd
Tel: 012-541 3598/9
Fax: 012-541 2513
Email: [email protected]
PO Box: 911729, Rosslyn 0200
Fax received on 21 October 2010
BMW South Africa operates a Waste Management Centre (WMC) for the recovery of solid
waste; an effluent treatment plant and a temporary paint sludge storage area as part of its
production activities at their plant in Rosslyn, City of Tshwane Metropolitan Municipality,
Gauteng Province.
All these waste management activities are located within the BMW plant premises and have
been in operation for over 15 years. Additionally, the facilities are designed such that they
have a dedicated storage area for the various waste streams to prevent environmental
contamination and to treat waste water prior to the release into the municipal sewerage
system. The waste management license application is a pro-active action by BMW SA to
comply with the requirements of the Waste Act (Act No. 59 of 2008). Please see the
enclosed draft scoping report for more information on the project.
All comments raised by I&APs will be captured in an issues trail which will form part of the
final Environmental Scoping and Environmental Impact Reports.
5. The Open Space Management Section of the City of Tshwane
Metropolitan Municipality requires four copies of the final reports
so that they can provide comments on the project.
In preparing such reports you are advised to consult all relevant
policy documents of the City of Tshwane Metropolitan
Municipality with particular reference to the Tshwane Open
Space Framework.
Wanda Byrne
Open Space Management Section
Agriculture and Environmental Management
Department
City of Tshwane Metropolitan Municipality
Tel: 012 358-8731
Fax: 012-358 8934
Email: [email protected]
PO Box: 1454, Pretoria 0001
Email, 6 October 2010
SSI Environmental will send four copies of the final copies of the Environmental Scoping
Report and Environmental Impact Report to the City of Tshwane the once they are ready.
Please note that hard copies of the draft scoping report were available for public review for a
period of 60 days from 21 October to 21 December 2010 at the following places: BMW
Rosslyn Plant (Gate 1, Main Reception, Frans du Toit Street); Pretoria North Municipal
Library (288 Burger Street); and Offices of SSI Environmental (Monument Park, Pretoria).
Section 6.10 of the Environmental Scoping Report makes reference to the City of Tshwane’s
Integrated Development Plan for 2010/2011. The City of Tshwane’s Open Space Framework
was also used as a reference in the compilation of the above-mentioned section, however, it
should be noted that the waste operations/facility at the BMW Rosslyn Plant have been
ongoing for the past 15 years.