NORTH SEA REGION Richard Stark Paul Williams Apache Subsea Projects

Upload: hoangthuy

Post on 15-Feb-2018

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NORTH SEA REGION Richard Stark Paul Williams

Apache Subsea Projects

Page 2: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Presenters Richard Stark, Project Services Manager, Apache North Sea Paul Williams, Subsea Projects Manager, Apache North Sea

Itinerary

Apache and Apache North Sea 2011 Subsea Campaigns

Lunch

In progress projects Upcoming projects Apache North Sea – The Future Procurement Questions

INTRODUCTION TO APACHE

2

20 mins

20 mins

Page 3: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

APACHE – A GLOBAL COMPANY

3

North Sea

Egypt

Australia

Central

Canada

Argentina

Gulf of Mexico Shelf

Julimar – tie back to platform Wheatstone - LNG plant Balnaves – FPSO Conniston – Tie back to FPSO Macedon - Onshore

Kittimat pipeline

Deepwater

FASP

Page 4: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

1Q 2012 Results 769 MBOE/D net Up 7% YOY (50% liquids) $1.2 BN adjusted earnings up 4% YOY $2.6 BN cash flow up 18% YOY 3 BN boe in 2011 YE reserves at all‐time high (46% liquids)

2011 Financial Results 748 MBOE/D net +14 % YOY

(50% liquids) $10.2 BN* cash flow +39 % YOY $4.5 BN earnings +50 % YOY

APACHE – A GROWTH COMPANY

Page 5: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

APACHE – GROWTH THROUGH EXPLORATION

Page 7: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Richard Stark

APACHE IN THE NORTH SEA

7

Page 8: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Acquired Mobil North Sea Limited (Beryl) and a non‐operated interest in the Nelson field

Q1 2012 production up 67% YoY, 41% sequentially with plans for continued ramp up

Bacchus well 1 online April 2012 @ ~6,000 Bbls/d gross

Zero to 40 subsea wells 15 to 80+ pipelines 0% to 20% production from subsea

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

110,000

Oct‐11 Dec‐11 Feb‐12 Apr‐12 Jun‐12 Aug‐12 Oct‐12 Dec‐12

Net

Rat

e (b

oe/d

) Nelson IMSBacchus IMSBeryl IMSForties + Maule IMSTelford BPFScott BPFNelson BPFBeryl BPFForties + Maule BPF

APACHE – LOCAL GROWTH AND ASSETS

Page 9: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NNS – BERYL PLATFORMS

9

Beryl Alpha • Condeep structure • RAT and flare tower • 2 x drilling rigs • Tanker export (oil) • SAGE export pipeline (gas) • Buckland / Skene / Nevis / Ness / Lewis • Gryphon

Beryl Bravo • Steel jacket • Oil and gas export to Beryl Alpha • 1 x drilling rig • Nevis / Ness / Linnhe

Page 10: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NNS – SUBSEA BERYL AREA

Page 11: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

SAGE GAS PLANT

Page 12: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

CNS – FORTIES PLATFORMS

• 5 x platforms + FASP • Oil export through Forties Charlie via FPS • Limited gas (power)

Page 13: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

CNS – SUBSEA FORTIES AREA

• 14 x infield pipelines • 1 (+) x subsea well (Bacchus) • Impressed Current Cathodic Protection (ICCP)

Page 14: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

APACHE NORTH SEA – NEW LOCATION

Page 15: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Paul Williams

IN PROGRESS PROJECTS

15

Page 16: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

2011 CAMPAIGNS

16

Page 17: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

2011 VESSEL CAMPAIGNS ‐ FORTIES

17

Survey and ROV Inspection – 21 Days Subsea Construction (Non Diving) – 22 Days Diving Support Vessel Works (DSV) – 110 Days Pipelay & Trenching – 30 Days

Page 18: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

2011 VESSEL CAMPAIGNS ‐ BERYLS

18

Survey and ROV Inspection – 20 Days Subsea Construction (Non Diving) – 0 Days Diving Support Vessel Works (DSV) – 34 Days Pipelay & Trenching – 0 Days

Seven Atlantic Hydrotest of Riser D1. Switch Skene Power B to C. Riser base spool UT 12th Feb to 22nd Feb 10Ernest Shackleton Beryl Survey (UK portion) 1st July to 14th Aug 20

Bibby Topaz N11 riser re-route and leaking N12 grease nipple repair. N12 AMV visual inspection 8th Aug to 20th Aug 12Bibby Topaz Skene IR investigation and S48 greasing 27th Sept to 1st Oct 4Bibby Topaz N13 (N1y) SCM changeout. Nevis IR investigation and repairs. Attempt at skene caisson 15th Oct to 23rd Oct 8

Page 19: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

19

19

FORTIES ALPHA SATELITTE MANHOURS ENGINEERING 331,532hrs CONSTRUCTION 1,453,303hrs WEIGHT STRUCTURAL WEIGHT (tons) 16,647 EQUIPMENT WEIGHT 1,550 PIPING LENGTH (Miles) 10.5 No. OF VALVES 2107 ELECTRICAL , INSTRUMENT & TELECOMMS ELEC. CABLE (Miles) 31.9 ELEC. BULKS (Lights etc.) No. 18435 INST. CABLE (Miles) 86.9 INST. BULKS (Gland/Term etc.) No. 21388

This image cannot currently be displayed.

Page 20: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

BACCHUS SUBSEA TIE‐BACK

Page 21: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

FORTIES CHARLIE SSIV

Page 22: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

FORTIES CHARLIE SSIV

22

Completion Status Design 100% complete Valves 100% complete

Structures 50% complete Umbilical 100% complete Flange manufacture 80% complete Pipe manufacture 80% complete Conduit 40% complete

3D Visualisation of SSIV Layout (Brae Import) Valve and Actuator Post Testing

Man

Page 23: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

FORTIES CHARLIE SSIV

23

3D Model of SSIV & Structure

Base Frame (shows scale)

36” Pipe Weld Qualification Tests

36” Concrete Coated Pipes

Schedule to Completion All manufacturing complete, Sept 2012 Final items into storage, Oct 2012 Site integration tests, Feb 2013

Phase 1 installation, June 2013 Phase 2 installation, Aug 2013

Page 24: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

FORTIES D TO C PIPELINE REPLACEMENT

24

Completion Status Design 100% complete Pipelay 100% complete

Trenching 100% complete Riser manufacture 90% complete Clamp manufacture 90% complete

Page 25: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

GAS RINGMAIN REPAIR

Page 26: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

1ST BERYL CAMPAIGN – NEVIS SOUTH REPAIR

26

Well N13 leaking hydraulic fluid

165 Litres per day being discharged Decision taken to mobilise DSV Original schedule was 3 days for Nevis works SCM changed out in 10 hours All Nevis works completed in 1.5 days Well now back online, no leaks reported

Leak at N13 (greenish fluid)

Airbag change out of SCM

Page 27: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Around 500 unsupported pipeline lengths, freespans, have been identified on the SAGE pipeline (lengths 10m‐57m/ gaps 0.1‐2.0m)

5 of these were addressed in detail as the spans fail the pre‐determined criteria

1 freespan was rectified in March 2012 at the Beryl Alpha SSIV (44m) to prevent any potential for further growth and requirement for annual monitoring

4 remaining critical spans will be re‐inspected in 2012

1ST BERYL CAMPAIGN – SAGE FREESPAN

27

2012 Freespan Repair

Freespan Prior to Repair

Page 28: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

UPCOMING PROJECTS

28

Page 29: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NNS – SUBSEA BERYL AREA

Page 30: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

LORISTON SOUTH WEST

30

Page 31: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

LORISTON SOUTH WEST

31

Currently based on using an existing and available tree

Use of PL893 2.5km flexible flowline extension required

Flexible flowline is available and under Apache control

Controls & chemicals, new umbilical required

Umbilical chemical hoses to directly tie into the new tree

FEED engineering starting

Page 32: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NESS SOUTH

32

Page 33: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NESS SOUTH

33

Currently based on using an existing and available tree

Flexible jumper from N7 flowbase to tree

Injection gas also from N7 or other local flowbase

Controls & chemicals, new umbilical required

Jumpers (6” and 8”) are available in the market

New umbilical required Umbilical chemical hoses to

directly tie into the new tree FEED engineering starting

Page 34: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NEVIS CENTRAL LEWIS 4

34

Page 35: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NEVIS CENTRAL LEWIS 4

35

Currently based on using an existing and available tree

New flowline required, longest lead item currently 12 months

Controls & chemicals, new umbilical required, or alternately put enough cores in Loriston South umbilical

Umbilical chemical hoses to directly tie into the new tree

FEED engineering will start in the next quarter

Page 36: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Aviat (WI 100%)

power demand

diesel

Forties gas

2006

2020

Aviat‐1 was drilled in 3Q 2010 and successfully tested A fuel gas resource for Forties Field 26kM from Forties Alpha Two well tie back A final appraisal well currently being planned Project delivery planned for 2014 Engineering works will commence Q3 2012

AVIAT

FORTIES

NELSON

Page 37: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Richard Stark

APACHE NORTH SEA – THE FUTURE

37

Page 38: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

NORTH SEA REGION – EXPLORATION, DRILLING AND APPRAISAL

38

Forties & Nelson

Beryl

◤ FASP ◤ Forties Echo ◤ Isabella 3D Wide

Azimuth Seismic ◤ Tryfan well ◤ Seagull North Well ◤ Seagull Well ◤ 27th License Round

Tryfan

Seagull & Seagull North Isabella

UK Norway

Page 39: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Richard Stark

PROCUREMENT

39

Page 40: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Qualification for work FPAL

Offshore Construction ‐ Currently Petrofac Onshore Engineering / Offshore Construction – Award Pending

Subsea Project Management Flexlife

Subsea Engineering Detailed Design Award Pending

Subsea Construction ITT being prepared

PROCUREMENT

40

Page 41: Apache Subsea Projects NORTH SEA REGION sut projects.pdf · Apache Subsea Projects ... Aviat‐1 was drilled in 3Q 2010 and successfully tested

Apache have been in the North Sea for almost a decade

Forties has been a great success for Apache The plan is that the Beryls will be too Questions

SUMMARY

41