Page 1: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)
Page 2: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Transforming lives

RAMAGUNDAM

“Economizer Modification–A focused perspective(A Case Study on Project Management)

A Team effort by

Balaram Reddy TSatish Chandra VNaresh Raju PPavan M

Page 3: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Presentation Outline …

Page 4: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Present scenario at NTPC

Page 5: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

PLF trend over the years…

Source: NTPC Annual Report 2015

Page 6: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Ramagundam PLF

Page 7: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

“My flight should fly”

- Sh. Aditya Ghosh, CEO, Indigo

Page 8: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Boiler

Page 9: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Boiler Efficiency Losses

Page 10: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

First time in India by handling 1200MT in a running plant

Economiser modification at U#6

Page 11: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Reduction in Flue gas Exit temperature

Improvement in Boiler EfficiencyReduction in Flue gas velocity thereby erosion

reduction in economizer

SH spray reduction

Environmental benefits

Improvement in ESP collection efficiency.Emission reduction (CO/CO2 / SOx / Nox)

Targeted Benefits

Page 12: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Project Approvals

Corporate Centre OEM Statutory Bodies Budget

Page 13: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Project PlanningContract Awarding

Preparatory works

Interim Change of plans

Safety plans

Page 14: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Logistics PlanningMaterial Procurement In house designAlternate vendor

development Awarding of Service contract Split contracts Additional resources

Page 15: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

In House Design of Hanger Bends

Designed with the help of NETRA, Exactly suitable at site

Page 16: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Contract Awarding

Works divided among two agencies on 50-50% basis

Page 17: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Preparation

Best Man power chosen, to avoid re-work

Page 18: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Eco coil shifting

Shifted from stores 1 week before OH

Page 19: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Eco coil shortening

Shortening works started 15 days before OH

Page 20: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Interim Change of Plans

Page 21: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Coil Removal

Per day coil removal raised to 43 against 24

Page 22: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Coil Placement

Removed 20 sets and inserted 15 sets.

Page 23: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Safety Plans

Page 24: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Safety PlansWorkers safety training T&P Testing Safety monitoring Safe material handling

Page 25: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Time

Actual coil placement completed in 15 days against 25 days planned

RAMAGUNDAM

SYNCHRONISATION

BOILER SAFETY VALVE FLOATING

BOILER LIGHT UP

BOILER HYDRO TEST

RESTORATION

RADIOGRAPHY

WELDING WORKS

COIL INSERTION

COIL REMOVAL

PREPARATORY WORKS FOR COIL REMOVAL

ACTIVITY Vs. DAY WISE PLAN

MILE STONE CHART NTPC

9

TARGET

STARTED ON 22.07.2016

3 12 3315 18 216

END DATE 22.08.2016

24 27 30

ACTUAL

ECONOMISER MODIFICATION WORKS IN U#6 OH

34 & 35 DAYS

Page 26: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Performance Achievement

Page 27: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Benefits achieved Flue Gas exit temperature reduction: 15 deg.C Heat Rate Improved by 15 K.cal/Kw.Hr Boiler efficiency improved by 0.75% Annual coal consumption reduced by 16000MTPAT benefits SH attemperation reduction APC reduction Variable Cost Reduction

Page 28: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

APC REDUCTION

Page 29: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Benefits in Physical parameters

Description

Before modif. HT Surface

( 12833sq.M) in economiser

After modif. HT Surface

( 16426sq.M) in economiser

Feed water Eco. i/l Temp

254 254

Feed water Eco. o/l Temp

317 321

FGT at Eco i/l 438/477 442/484FGT at Eco o/l 375 333

Page 30: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Monetary Benefits Cost of the project:

Material cost: Rs 8.5 Cr ( 2existing +1 new bank)Services cost: Rs 1.5 CrTotal cost incurred Rs10Cr

Monetary Benefits achieved:

Benefit due to coal saving: Rs 4.8 Cr.Energy Certificates earning in PAT cycle-II(PAY BACK PERIOD: 10 Months)

Page 31: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Performance 1 Reduction in Flue Gas Exit

temperature 15 deg C

2 Corresponding Heatrate reduction 15 kCal/kWhr

3 Per annum Energy savings 59130 Million Kcal

4 Energy equivalent of coal 15561 MT of coal

5 Saving in Rs Cr / year 4.67 Rs Cr

6 Pay back in years (incl two existing banks) 2.4 Years

7 Pay back in years (additional bank) 10.0 Months

Page 32: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Towards Environment Gains Emission reduction of CO2 by 19650MT Reduction in CO, SOx, Nox Enhanced ESP efficiency thereby reduction in SPM Future FGD investment cost reduction Reduction in ash handling

Page 33: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Replication of the project

R&M Budget Proposal i/p for Implementation at other units-4 & 5 of NTPC-Ramagundam

A detailed study report beingsent to CC for the projectimplementation at similar units of NTPC

Page 34: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

Installing VFD Motors in ID, FD, PA Fans

R&M of Air Pre Heaters

LP Coil Pre Heating

Energy efficient equipments – IE coded motors for CT

Installation of FGD

Our other smart ideas

Page 35: “Economizer Modification–A focused perspective PC_B… · Transforming lives RAMAGUNDAM “Economizer Modification–A focused perspective (A Case Study on Project Management)

The difference between what we do and what we are capable of doing would suffice to solve most of the problems.