a.no. 117/20. present : sh. r.d. sharma, ld.counsel for appellant....
TRANSCRIPT
-
A.No. 117/20. 13.03.2020 Present : Sh. R.D. Sharma, Ld.counsel for appellant.
Sh. Pritish Sabharwal, Ld.counsel for respondent no.1.
None for respondent no.2 despite service.
Memo of appearance filed on behalf of respondent.
Ld. counsel for respondent seeks time to file status report
and record.
1. This is an appeal filed against the order of demolition
dated 17.02.2020. Ld. counsel for appellant has pressed
the application for ad-interim stay on the ground that
otherwise the appeal will become infructuous.
2. The submissions made are that the appellant is a Co-
operative Bank and is running its Banking functions since it
was established in the year 1969. It is further stated that in
order to start a branch in Janak Puri, New Delhi, the
appellant approached Reserve Bank of India (RBI) for
necessary permission pursuant to which permission was
granted by RBI to open a branch at Janak Puri, New Delhi.
It is further stated that the appellant approached the
respondent no.2 for allotment of office unit with Leasehold
rights in Local Shopping Complex (LSC) built and
developed by respondent no.2, DDA vide letter dated
22.01.1979, pursuant to which respondent no.2 allotted two
office units / shops no. 6 & 7 to the appellant in Local
Shopping Complex C-4/E, Janak Puri, New Delhi vide
allotment letter bearing No. F-1(262)/78-IMPL dated
03.02.1979 on lease hold basis. It is further stated that
stated that the appellant thereafter approached respondent
no.2 to remove the partition wall in between the office units
6 & 7. The DDA vide letter dated 06.04.1979 acceded to
the said request of the appellant, subject to the condition not
-
to damage the building. It is further stated that the appellant
thereafter vide registered sale deed dated 06.01.2006
purchased office units shop no.5 adjoining units No. 6 & 7.
It is also stated that the appellant has been regularly paying
house-tax of all the units and the temporary structure
construction raised upon the units 5, 6 and 7. It is further
stated that in August, 2019, the appellant received a notice
u/s. 343/344 of DMC and thereafter received another notice
u/s. 345A of DMC Act dated 28.10.2019. The appellant had
filed reply to the said notices. It is also stated that no illegal
construction has been carried out by the appellant in the
said units. The entire office units and temporary structures
above the said units have been assessed to property tax by
respondent no.1 since decades. It is further stated that the
as office / units in question are situated in the LSC
developed by respondent no.2 as such no demolition can be
done by respondent no.1 in the said market without the
consent of respondent no.2. It is also stated that respondent
no.1 has never raised any objection to the temporary unit
prior to09.08.2019. It is also stated that the application for
regularization of the temporary structure is pending before
the appropriate authority.
5. Heard, keeping in view the submissions made and
documents filed by appellant and as time is sought to file
status report and record, in my view appellant has made out
the case for grant of ad-interim interim stay. Respondent is
restrained from taking demolition action in the property in
question bearing no. shop no. 5, 6 and 7,LSC Market,C-4/E,
Janak Puri, New Delhi pursuant to impugned order dated
17.02.2020 till next date of hearing.
6. However, this order is subject to any order passed by
the Hon’ble Supreme Court / Hon’ble High Court / Hon’ble
NGT about sealing and demolition in respect of the property
in question.
-
7. Appellant is directed to file affidavit giving details of
construction with measurements of the existing construction
alongwith existing site plan and photographs of the property
in question within five working days, failing which stay order
granted shall deemed to be vacated.
8. Copy of the affidavit will be provided to concerned
AE(B) by the appellant, who shall verify whether details of
construction mentioned in the affidavit is correct or not.
9. Appellant is also directed not to carry out any
addition, alteration, repair or construction and shall also not
create any third party interest in the property in question.
10. Be listed for filing of status report and record on
11.05.2020.
11. A copy of the order be given Dasti to counsels for
parties, as prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 760/13. 13.03.2020 Present : Sh. Kedisaplung Haikam, Ld. counsel for appellant.
Sh. Mohit Sharma, Ld. counsel for SDMC with Sh. Ravinder
Kumar, AE(B).
Sh. A.K. Shrivastav,Ld. counsel for respondents no.2 and 3.
Memo of appearance filed on behalf of appellant.
Ld. counsel for respondent seeks more time to file status
report in terms of order dated 30.11.2017, last opportunity
granted.
In case status report is not filed, concerned Dy.
Commissioner to appear on the next date.
AE(B) to be present on the next date.
To come up for filing of status report on 06.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 747/18. 13.03.2020 Present : Appellant in person.
Sh. Sanjay Gupta, ALO for North DMC with Sh. S.K. Lakra,
LI.
Appellant states that he has moved an application with
respondent for permission to carry out rectification but he
has not received any response from the respondent till date.
Respondent is directed to decide the application within a
week and status report be filed on the next date.
Be listed for filing of status report on 06.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 519/19, 520/19, 521/19, 522/19 and 523/19. 13.03.2020 Present : Sh. Vishesh Issar,Ld. counsel for appellant.
Sh. R.B. Sharma, Ld. counsel for SDMC.
At request of Ld. counsel for respondent, adjourned for filing
of status report qua the affidavit of appellant regarding
details of existing construction and final arguments with the
connected appeals to 15.07.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 06/20, 07/20, 08/20, 09/20 and 10/20. 13.03.2020 Present : Sh. Vishesh Issar,Ld. counsel for appellant.
Sh. Pritish Sabharwal, Ld. counsel for SDMC.
Status report filed, copy supplied.
Ld. counsels for parties seek time to file brief synopsis.
To come up now for final arguments on 15.07.2020.
Interim order, if any, to continue till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 416/19. 13.03.2020 Present : Appellant with Ld. counsel, Sh. Himanshu Singh.
Ms. Nagina Jain, Ld. counsel for North DMC with Sh.
Sanjay Gupta, ALO and Sh. Pradeep Kumar Sharma, LI.
Respondent to intimate the misuse charges payable to the
appellant.
To come up now for filing of status report by the respondent
and arguments on 22.04.2020.
The concerned LI to be present on the date fixed.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 817/19. 13.03.2020 Present : Appellant with Ld. counsel, Sh. Pooran Chand.
Sh. Ashutosh Gupta, Ld. counsel for North DMC with Sh.
Sanjay Gupta, ALO.
Time is sought to file status report and record.
Record be filed within three days.
In case the record is not filed, concerned Dy. Commissioner
to appear on the next date.
To come up for filing of status report on 22.04.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 716/18. 13.03.2020 Present : Sh. Anand Singh, Ld. counsel for appellant.
Sh. Dharamvir Gupta, Ld. counsel for North DMC with Sh.
Sanjay Gupta, ALO and Sh. Pradeep Kumar Sharma, LI.
Ld. counsel for respondent seeks time to file further status
report regarding permissible user of the property in
question.
To come up for filing of status report on 17.04.2020.
LI concerned to be present on the date fixed.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 78/20. 13.03.2020 Present : Sh. Anuj Aggarwal, Ld. counsel for appellant.
Sh. H.R. Aggarwal, Ld. Counsel for North DMC.
Ld. Counsel for appellant states that appellant has applied
for regularization, status report of the same be filed on the
next date.
Documents filed on behalf of appellant, copy supplied.
Appellant is directed to file the house tax receipts with effect
from the year 2004-2005 onwards.
To come up for arguments on the interim application on the
date fixed.(31.03.2020.)
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 702/18. 13.03.2020 Present : Sh. Shoeb Haider, Ld. counsel for appellant.
Sh. V.K. Aggarwal, Ld. proxy counsel for SDMC with Sh.
Faiz Ahmed, AE(B).
Status report filed, copy supplied.
Ld. counsel for appellant seeks time to file objections.
Be listed on 06.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 62/20 and 63/20. 13.03.2020 Present : Sh. Dalip Rastogi, Ld. counsel for appellant.
Sh. Dharamvir Gupta, Ld. counsel for North DMC.
More time is sought to file status report qua the affidavit of
appellant regarding details of existing construction.
AE(B) to be present on the next date.
Be listed for filing of status report and final arguments on
23.07.2020.
Interim order to continue till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 817/17. 13.03.2020 Present : None for appellant.
Sh. Pritish Sabharwal, Ld. counsel for respondent.
As none has appeared for appellant, be listed for further
proceedings on 06.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 842/18 and 806/18. 13.03.2020 Present : Ms. Gurmeet Kaur, Ld. counsel for appellant.
Sh. V.K. Aggarwal, Ld. counsel for SDMC with Sh. Atharv
Mustafa, AE(B).
Ld. counsel for respondent states that there are variations in
the existing site plan furnished by the appellant and
sanctioned building plan. It is stated that to resolve the
same, a joint inspection be allowed in the presence of
Architect of appellant.
AE(B) will now inspect the premises in question on
16.03.2020 from 2.00 pm to 5.00 pm. The Architect of
appellant to be present on the said date and time.
Be now listed for filing of status report and final arguments
on 07.04.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 107/20. 13.03.2020 Present : Sh. Shubham Aggarwal, Ld. Proxy counsel for appellant.
Ms. Nagina Jain, Ld. counsel for North DMC with Sh. Rajiv
Garg, ALO.
Status report filed, copy supplied.
Ld. counsel for respondent states that record has been
deposited in the appeal no. 602/19 titled Rajesh Kumar
Chopra Vs. North DMC.
At request of proxy counsel for appellant, adjourned for
arguments on the interim application on 20.04.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 602/19. 13.03.2020 Present : Sh. Shubham Aggarwal, Ld. Proxy counsel for appellant.
Sh. Dharamvir Gupta, Ld. counsel for North DMC with Sh.
Rajiv Garg, ALO.
Sh. Manoj Sharma, Ld. counsel for applicant.
An application has been moved on behalf of applicant M/s.
Hitachi Payments Services Printed Limited u/s. 151 CPC for
temporary de-sealing of the shop of the applicant for
removal of ATM and other equipments.
Ld. counsel for respondent seeks time to file reply.
Ld. counsel for respondent states that for calculation of
misuse charges the premises is required to be de-sealed.
Respondent is directed to de-seal the property of the
applicant where he is operating the ATM machine to
calculate the misuse charges on 23.03.2020 from 12.00 pm
to 3.00 pm. Applicant and appellant are directed to be
present on the said date and time. The property is only
being de-sealed only for calculation of misuse charges and
not for removal of amount from ATM or its equipment.
Respondent to re-seal the property on the same day.
Respondent will intimate to the applicant the misuse
charges which are payable. Applicant to take appropriate
steps in this regard.
To come up for reply and arguments on the application on
20.04.2020.
A copy of order be given dasti to Ld. counsel for parties, as
prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 129/20 13.03.2020 Present : Sh. Dalip Rastogi, Ld. counsel for appellant.
Fresh appeal filed u/s 343 (2) of DMC Act against the order
of demolition dated 17.02.2020 alongwith application for
stay and condonation of delay. Be checked and registered.
Notice of the appeal and application be issued to the
respondent through concerned Chief Law Officer. AE(B) is
directed to appear alongwith entire record of the
proceedings, status report and reply of the appeal on date
fixed. Record be deposited in the Tribunal.
Be listed for arguments on the application for condonation of
delay and stay on 27.03.2020.
Process be given dasti, as prayed for.
The interim protection granted by the Hon’ble High Court is
extended till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 128/20 13.03.2020 Present : Sh. Dalip Rastogi, Ld. counsel for appellant.
Fresh appeal filed u/s 347-B of DMC Act against the order
of rejection dated 10.09.2018 alongwith application for stay
and condonation of delay. Be checked and registered.
Notice of the appeal and application be issued to the
respondent through concerned Chief Law Officer. AE(B) is
directed to appear alongwith entire record of the
proceedings, status report and reply of the appeal on date
fixed. Record be deposited in the Tribunal.
Be listed for arguments on the application for condonation of
delay and stay on 27.03.2020.
Process be given dasti, as prayed for.
The interim protection granted by the Hon’ble High Court is
extended till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 130/20 13.03.2020 Present : Sh. Rajat Aneja with Sh. Sonali Chopra, Ld. counsel for
appellant.
Fresh appeal filed u/s 347 (1) (k) of DMC Act against the
demolition alongwith application for stay. Be checked and
registered.
Notice of the appeal and application be issued to the
respondent through concerned Chief Law Officer. AE(B) is
directed to appear alongwith entire record of the
proceedings, status report and reply of the appeal on date
fixed. Record be deposited in the Tribunal.
Be listed for arguments on the application for stay on
19.03.2020.
Process be given dasti, as prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 120/20 13.03.2020 Present : Sh. Y.P. Singh, Ld. counsel for appellant.
Fresh appeal filed u/s 254 of New Delhi Municipal Council
Act against the order of sealing dated 20.09.2019 alongwith
application for stay and condonation of delay. Be checked
and registered.
Notice of the appeal and application be issued to the
respondent through concerned Chief Law Officer. AE(B) is
directed to appear alongwith entire record of the
proceedings, status report and reply of the appeal on date
fixed. Record be deposited in the Tribunal.
Be listed for arguments on the application for condonation of
delay and stay on 19.03.2020.
Process be given dasti, as prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 121/20 13.03.2020 Present : Sh. Y.P. Singh, Ld. counsel for appellant.
Fresh appeal filed u/s 247 (2) of New Delhi Municipal
Council Act against the order of demolition dated
29.03.2019 alongwith application for stay and condonation
of delay. Be checked and registered.
Notice of the appeal and application be issued to the
respondent through concerned Chief Law Officer. AE(B) is
directed to appear alongwith entire record of the
proceedings, status report and reply of the appeal on date
fixed. Record be deposited in the Tribunal.
Be listed for arguments on the application for condonation of
delay and stay on 19.03.2020.
Process be given dasti, as prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 614/19 and 615/19 13.03.2020 Present : Sh. Dalip Rastogi, Ld. counsel for appellant.
Sh. Ajay Arora with Sh. Dharamvir Gupta, Ld. counsel for
MCD and Ms. Manjusha Jha, with A Neduchazian Dy.
Commissioner, Sh. S.D. Tomar, EE(B), and Ms. Rajni
Sehdev, ALO, EDMC.
Vakalatnama filed on behalf of respondent.
Ld. counsel for appellant states that appellant had moved an
application under section 151 of CPC for rectification/correction
in the order dated 23.102019. It is alleged that vide order dated
23.10.2019 interim protection was granted to the appellant in
Appeal No. 614/19 filed against the order or sealing dated
24.07.2018. Respondent was restrained from taking coercive
action in the property in question. It is further stated that due to
typographical error, the date of impugned sealing order
mentioned in the order dated 23.10.2019 was 26.06.2018
instead of 24.07.2019. The respondent has therefore, sealed the
property of the appellant on 17.01.2020. It is also stated that
necessary corrections were made in the order dated 23.10.2019
in appeal No. 614/19 regarding the date of impugned order on
20.01.2020 but till date the property has not been desealed.
I have heard the Ld. counsel for parties.
It is submitted on behalf of respondent that property would
be desealed till further orders in compliance of orders dated
23.10.2019 and 20.01.2020.
To come up for compliance report and final arguments on
31.07.2020.
-
Interim order, if any, to continue till next date.
A copy of the order be given dasti, to Ld. counsel for parties,
as prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 77/20 13.03.2020 Present : Sh. Ankur Manar, Ld. counsel for appellant.
S. Adil Hussain Ld. counsel for respondent with Sh. Rajeev
Garg, ALO and Sh. Ashwani Rana, AE(B).
Status report filed, copy supplied.
At request of Ld. counsel for appellant adjourned for
arguments on the interim application to 06.05.2020.
AE(B) to be present on next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 855/18 and 107/19 13.03.2020 Present : Sh. K.N. Singh, Ld. counsel for appellant.
Sh. H.R. Aggarwal / Sh. Dharamvir Gupta, Ld. counsel for
MCD.
Ld. counsel for parties seeks time to file brief synopsis.
Be listed for final arguments on 17.04.2020.
Interim order, if any, to continue till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
M.No. 27/19 13.03.2020 Present : Sh. K.N. Singh, Ld. counsel for appellant.
Sh. Dharamvir Gupta, Ld. counsel for MCD.
Sh. A.K. Jain, AE(B) Respondent No.1 in person.
An application moved for exemption from personal
appearance on behalf of R-2. Heard, in view of
submissions made he is exempted for today.
Ld. counsel for MCD seeks time to file reply to the show
cause notice.
Be listed on 17.04.2020.
Both respondents are directed to be present on next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 303/17 13.03.2020 Present : Sh. K.N. Singh, Ld. counsel for appellant.
Sh. Gian Chand, Ld. counsel for MCD.
More time sought on behalf of MCD to file status report
regarding the regularization application. Last opportunity
granted.
Be listed on 06.05.2020.
AE(B) concerned to be present on next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 655/16 13.03.2020 Present : None for the appellant.
Sh. Pritish Sabharwal, Ld. counsel for SDMC with Sh.
Naeem, AE(B).
As none has appeared for appellant, be listed for further
proceedings / final arguments on 08.05.2020.
Parties are directed to file written submissions.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 808/17 13.03.2020 Present : Sh. Manan M. Sisodia, Ld. proxy counsel for appellant.
Sh. Mohit Sharma, Ld. counsel for EDMC.
Sh. Charanjeet Singh, Ld. counsel for Monitoring
Committee.
At request of Ld. proxy counsel for appellant adjourned for
arguments on 06.05.2020, as main counsel is not available
today.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 833/14 13.03.2020 Present : Sh. Ajay Kumar, Ld. proxy counsel for appellant.
Sh. Ashok Kumar, Nodal Officer, NDMC with JE Sh.
Yashpal.
At request of Ld. proxy counsel for appellant adjourned for
arguments on date already fixed i.e. 23.03.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 245/17 13.03.2020 Present : Ms. Zarina Begum of the appellant with Ld. counsel Ms.
N.Sehar.
Sh. V.K. Aggarwal, Ld. counsel for MCD.
Sh. Vikas Aggarwal, Ld. counsel for R-6 and R-7.
Respondent No.2 to 5 unserved.
An application moved on behalf of appellant under order 22
Rule 3 CPC to bring on record the LRs of deceased Mohd.
Jameel, , copy supplied.
To come up for reply and arguments on the application
14.05.2020.
Appellants are directed to deposit the cost before next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 691/19 13.03.2020 Present : Sh. Sanjay Rathi with Sh. Divyansh Rathi, Ld. counsel for
appellant.
Sh. Mohit Sharma, Ld. counsel for SDMC.
Sh. Charanjeet Singh, Ld. counsel for Monitoring
Committee.
Reply filed on behalf of the appellant to the application
moved by respondent for vacation of interim stay, copy
supplied.
Ld. counsel for Monitoring Committee seeks time to file
status report.
To come up on 13.04.2020 for arguments.
Interim order, if any, to continue till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
M.No. 9/20 and 10/20 13.03.2020 Present : Sh. Satish Kumar, Ld. counsel for appellant.
Sh. Mohit Sharma, Ld. counsel for with AE(B) Sh. Naeem.
Ld. counsel for respondent seeks time to file reply to the
application under Contempt of court Act.
To come up for arguments on the application on
23.04.2020.
The concerned officials to be present on next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 818/16 and 104/2017 13.03.2020 Present : Appellant in person.
Ms. Nagina Jain, Ld. counsel for respondent .
Request is made for adjournment by appellant as his
counsel is in personal difficulty, request is opposed.
Ld. counsel for respondent has pointed out that the
appellant has not deposited the cost imposed vide orders
dated 17.08.2017. The appellant is directed to deposit the
same within three days. Ld. Counsel for respondent has
also pointed out that on the date of hearting of 30.05.2018
last opportunity was granted to appellant to address
arguments, but again today request is made for
adjournment.
In the interest of justice, one final opportunity granted for
final arguments to appellant, as his counsel is in some
personal difficulty today.
Be listed for final arguments on 04.06.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 988/16 13.03.2020 Present : Shri Sandeep Verma, Ld. counsel for appellant .
Ms.Ayman Naaz, Ld. proxy counsel for respondent .
At request of Ld. counsel for respondent, adjourned for final
arguments to 08.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 844/18 13.03.2020 Statement of Sh. Sagar Sharma, Ld. counsel for appellant Enrol No.D-
4095/2016 Chamber No.B-39 and 40 BGS Block, Tis Hazari Courts, Delhi
Without oath.
I have instructions to withdraw the present appeal, the same may be
dismissed as withdrawn.
RO & AC
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 25/16 and 26/16 13.03.2020 Present : Sh. Anuj Garg, Ld. Counsel for the appellant.
Sh. Madan Sagar, Ld. counsel for MCD.
Sh. R.N. Oberoi, Ld. counsel for intervener.
Ld. Counsel for parties seeks time to file brief synopsis.
To come up for final arguments on 03.06.2020.
AE(B) concerned who booked the property in question to
appear on next date with explanation in terms of the order
dated 30.01.2019.
A copy of this order be given dasti to Ld. counsel for
respondent, as prayed for.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 998/16 13.03.2020 Present : None for appellant.
Sh. K.K. Arora, Ld. counsel for North DMC.
Sh. Mohit Sharma, Ld. counsel for SDMC.
Sh. Vijay Kumar, Ld. proxy counsel for applicant.
As none has appeared for appellant, be listed for further
proceedings / final arguments on 09.07.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 901/16 and 391/18 13.03.2020 Present : Sh. Sanjay Kumar, Ld. Counsel for the appellant.
Sh. Dharamvir Gupta / Sh. Sanjay Sethi, Ld. Counsel for
respondent with Sh. Amar Singh, AE(B).
Status report filed stating that regularization file of the
property in question is not traceable.
Time is sought on behalf of respondent to file the status
report regarding regularization.
Be listed on 06.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 622/19 13.03.2020 Present : Appellant with Ld. counsel Sh. Ajay Singh.
Sh. Dharamvir Gupta, Ld. Counsel for respondent with
Sh. Basant, L.I.
Status report filed, copy supplied.
The appellant is directed to file the receipt of the misuse
charges and supply a copy of the same to the respondent.
Be listed on 06.05.2020 for arguments.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 270/14 13.03.2020 Present : None for the appellant.
Sh. Shashikant Sharma, proxy counsel for MCD.
As none has appeared for appellant, be listed for further
proceedings / final arguments on 02.06.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 844/18 13.03.2020 Present : Shri Sagar Sharma, Ld. Counsel for the appellant .
Sh. Dharamvir Gupta, Ld. Counsel for respondent.
Shri Suresh Kumar, PHI.
Ld. Counsel for the appellant states that he has instruction
to withdraw the appeal. The statement of Ld. Counsel for
the appellant recorded. In view of the statement of Ld.
Counsel for the appellant, the appeal stands dismissed as
withdrawn with liberty to approach the appropriate form.
Resultantly the impugned order dated 16.06.2016 is
confirmed. Respondent is at liberty to take action in the
property in question in accordance with law.
The file of the department, if any, be returned to the
respondent alongwith copy of this order.
File be consigned to record room.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 913/17 13.03.2020 Present : Ms. Seema Mishra, Ld. Counsel for the appellant .
Shri Sanjiv Kumar, Ld. Counsel for the respondent
Shri Mohit Sharma, Ld. Counsel for applicant.
Ld. Counsel for the appellant seeks time to file title
documents.
At request of Ld. Counsel for the appellant, adjourned for
final arguments to 04.08.2020.
Interim orders, if any, to continue till next date of hearing .
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 898/18 13.03.2020 Present : Shri Sanjay Gupta, appellant in person.
Shri Ashutosh Gupta, Ld. Counsel for the respondent.
Appellant seeks adjournment as his counsel is not available
today.
To come up for final arguments on 31.07.2020.
Interim orders, if any, to continue till next date of hearing
(POONAM CHAUDHRY)
AD&SJ-cum-P.O. Appellate Tribunal:MCD
13.03.2020
-
M. in A.No. 232/15 13.03.2020 Present : None for appellant.
Sh. Dharamvir Gupta, Ld. Counsel for respondent.
The appeal was dismissed as withdrawn on 13.07.2016,
status report filed in terms of order dated 13.07.2016. The
miscellaneous file be accordingly consigned to record.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 698/18 13.03.2020 Present : Shri Jaspreet Singh, Ld. Counsel for the appellant .
Ayman Naaz, Ld. proxy counsel for the respondent.
Shri J.C. Mehendru, Ld. counsel for applicant.
Written submissions filed on behalf of appellant and
applicant. Copies exchanged.
Ld. Counsel for the respondent seeks time to file brief
synopsis.
To come up for final arguments on 09.07.2020.
Interim orders, if any, to continue till next date of hearing
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 32/17 13.03.2020 Present : Shri Arun Kumar, Ld. Counsel for the appellant .
Ms. Sudesh Sharma, Ld. counsel for the respondent.
Final arguments heard.
Be listed for orders on 09.04.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 273/18 and 97/16 13.03.2020 Present : Sh. B.S. Mathur, Ld. counsel for appellant.
Sh. Shashikant Sharma, Ld. counsel for MCD.
Ld. counsel for appellant has placed on record copy of new
rules for grant of electricity connection to building of height
of 17.5 mtrs.
Ld. counsel for respondent seeks time to verify the same.
To come up on 30.04.2020 for status report.
AE(B) to be present on next date.
Interim order to continue till next date.
(POONAM CHAUDHRY)
AD&SJ-cum-P.O. Appellate Tribunal:MCD
13.03.2020
-
A.No. 558/19 13.03.2020 Present : Sh. Manish Srivastava, Ld. counsel for appellant.
Sh. Shashikant Sharma, Ld. counsel for MCD.
Final arguments heard.
Be listed for orders on 08.04.2020.
Interim order, if any, to continue till next date.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 379/19 13.03.2020 Present : Sh. Sandeep Chauhan, Ld. proxy counsel for appellant.
Sh. Dharamvir Gupta, Ld. counsel for MCD.
At request of Ld. counsel for appellant adjourned for final
arguments to 07.07.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 599/18 13.03.2020 Present : Ms. Pushpa, Ld. proxy counsel for appellant.
Sh. Shashikant Sharma, Ld. counsel for MCD.
Ld. counsel for respondent states that appellant has till date
not deposited the misuse charges.
Ld. proxy counsel for appellant seeks adjournment as main
counsel is unwell.
At request, last opportunity granted for final arguments.
To come up on 15.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 512/19 13.03.2020 Present : Sh. Vinod Gupta, husband of the appellant.
Ms. Osita Kirti Ranjan, Ld. proxy counsel for MCD with Sh.
Raj Bhushan, Nodal Officer.
Appellant seeks adjournment as his counsel is not available
today due to death in his family.
At request adjourned for arguments to 26.05.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 696/19 13.03.2020 Present : Sh. Ashwini Kumar, Ld. counsel for appellant
File taken up on application moved for early hearing. Notice be issued to respondent for 29.03.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 396/11 13.03.2020 Present : Sh. K. B. Gupta, Ld. counsel for appellant
None for respondent.
One regular steno is on leave. No time left.
To come up for further arguments/orders on 30.03.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 60/SCM/13 13.03.2020 Present : Sh. Amit Sethi, Ld. counsel for appellant
Sh. Nilesh Sahani, Ld. counsel for respondent
One regular steno is on leave. No time left.
Be listed for orders on 27.03.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 393/19 13.03.2020 Present : Appellant in person.
Sh. S. A. Hussain, Ld. counsel for North DMC
One regular steno is on leave. No time left.
Be listed for orders on 13.04.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020
-
A.No. 979/15 & 976/15 13.03.2020 Present : Sh. K. B. Gupta, Ld. counsel for appellant
Sh. Sh. H.R. Aggarwal, counsel for MCD.
One regular steno is on leave. No time left.
To come up for clarification/orders on 23.03.2020.
(POONAM CHAUDHRY) AD&SJ-cum-P.O.
Appellate Tribunal:MCD 13.03.2020