annual report 2015/16 - mangaung metropolitan … · 2 table of contents annual report 2015/2016...
TRANSCRIPT
1
ANNUAL REPORT
2015/16
MANGAUNG
METROPOLITAN MUNICIPALITY
2
TABLE OF CONTENTS
ANNUAL REPORT 2015/2016 – MANGAUNG METROPOLITAN MUNICIPALITY
CHAPTER 1 - MAYOR’S FOREWORD AND EXECUTIVE SUMMARY ................................................ 8
COMPONENT A: MAYOR’S FOREWORD ..................................................................................................................... 8
COMPONENT B: EXECUTIVE SUMMARY ................................................................................................................... 10
1.1 MUNICIPAL MANAGER’S OVERVIEW .................................................................................................................. 10
1.2 MUNICIPAL FUNCTIONS, POPULATION AND ENVIRONMENTAL OVERVIEW ...................................................... 11
Figure 1.1 FORMAL AND INFORMAL DWELLINGS IN MANGAUNG ......................................................... 11
1.2.1 SOCIO ECONOMIC STATUS .......................................................................................................................... 11
Table 1.1: SOCIO ECONOMIC STATUS ................................................................................................................. 12
Figure 1.2 Proportion of the population aged 20 years and older by level of education attained ......... 12
Table 1.2: NATURAL RESOURCES ......................................................................................................................... 13
1.2.2 KEY CHALLENGES AND OPPORTUNITIES FOR THE CITY .............................................................................. 13
1.3 SERVICE DELIVERY OVERVIEW ............................................................................................................................ 14
1.4 FINANCIAL HEALTH OVERVIEW ........................................................................................................................... 15
CHAPTER 2 - GOVERNANCE .................................................................................................................... 16
COMPONENT A: POLITICAL AND ADMINISTRATIVE GOVERNANCE ........................................................................... 16
2.1 POLITICAL GOVERNANCE .................................................................................................................................... 16
2.1.1 POLITICAL STRUCTURE OF MMM ............................................................................................................... 16
Table 2.1: MEMBERS OF THE MAYORAL COMMITTEE ........................................................................................ 17
Table 2.2: POLITICAL PARTIES REPRESENTED IN THE COUNCIL ........................................................................... 17
Table 2.3: THE GOVERNANCE STRUCTURE OF MANGAUNG METROPOLITAN MUNICIPALITY ........................... 17
2.2 ADMNISTRATIVE GOVERNANCE ......................................................................................................................... 19
COMPONENT B: INTERGOVERNMENTAL RELATIONS ................................................................................................ 20
2.3 INTERGOVERNMENTAL RELATIONS IN THE CITY ................................................................................................ 20
COMPONENT C: OVERVIEW OF PUBLIC ACCOUNTABILITY AND PARTICIPATION ...................................................... 21
2.4 PUBLIC MEETINGS ............................................................................................................................................... 21
Table 2.4: PUBLIC MEETINGS............................................................................................................................... 22
2.5 IDP PARTICIPATION AND ALIGNMENT ................................................................................................................ 23
Table 2.5: IDP AND ALIGNMENT .......................................................................................................................... 23
COMPONENT D: CORPORATIVE GOVERNANCE ......................................................................................................... 24
2.6. RISK MANAGEMENT ........................................................................................................................................... 24
2.7 ANTI FRAUD AND CORRUPTION ......................................................................................................................... 25
Table 2.6: MEETINGS OF THE AUDIT COMMITTEE .............................................................................................. 26
2.8 MUNICIPAL WEBSITE: CONTENT AND CURRENCY OF MATERIAL ....................................................................... 26
Table 2.7: MUNICIPAL WEBSITE: CONTENT AND CURRENCY OF MATERIAL ....................................................... 26
CHAPTER 3 - SERVICE DELIVERY PERFORMANCE .......................................................................... 30
3
COMPONENT A: BASIC SERVICES .............................................................................................................................. 30
3.1 WATER PROVISION ............................................................................................................................................. 30
Table 3.1: WATER SERVICE DELIVERY LEVEL ....................................................................................................... 30
Table 3.2: HOUSEHOLDS-WATER SERVICE DELIVERY LEVELS BELOW THE MINIMUM ........................................ 31
Table 3.3: WATER AND SANITATION SERVICE POLICY OBJECTIVES TAKEN FROM IDP ........................................ 32
3.3.1 STRATEGIC ................................................................................................................................................... 32
3.3.2 OPERATIONAL ............................................................................................................................................. 33
Table 3.4: EMPLOYEES: WATER AND SANITATION .............................................................................................. 35
Table 3.5: FINANCIAL PERFORMANCE WATER SERVICES .................................................................................... 35
Table 3.6: CAPITAL EXPENDITURE: WATER SERVICES ......................................................................................... 36
Figure 3.1 MANGAUNG CITY TRENDS IN RELATION TO NON-REVENUE WATER ..................................... 36
Figure 3.2 MANGAUNG CITY TRENDSIN RELATION TO SYSTEM/INPUTS VOLUME REDUCTION ............. 37
3.2 WASTE WATER (SANITATION) ............................................................................................................................. 37
Table 3.7: SANITATION DELIVERY LEVELS ............................................................................................................ 38
Table 3.8: HOUSEHOLDS – SANITATION SERVICE LEVELS BELOW THE MINIMUM ............................................. 38
Table 3.9: FINANCIAL PERFORMANCE SANITATION SERVICES ............................................................................ 39
Table 3.10: CAPITAL EXPENDITURE SANITATION SERVICES ................................................................................ 39
3.3 WASTE MANAGEMENT ....................................................................................................................................... 40
Table 3.11: SOLID WASTE SERVICE DELIVERY LEVELS.......................................................................................... 40
Table 3.12: HOUSEHOLDS – SOLID WASTE SERVICES DELIVERY LEVELS.............................................................. 41
Table 3.13: WASTE MANAGEMENT SERVICES POLICY OBJECTIVES TAKEN FROM IDP ........................................ 42
3.13.1 STRATEGIC ................................................................................................................................................... 42
3.13.2 OPERATIONAL ............................................................................................................................................. 42
Table 3.14: EMPLOYEES: SOLID WASTE MANAGEMENT SERVICES ..................................................................... 44
Table 3.15: FINANCIAL PERFOMANCE: SOLID WASTE MANAGEMENT SERVICE ................................................. 44
Table 3.16: CAPITAL EXPENDITURE: WASTE MANAGEMENT SERVICES .............................................................. 44
3.4 ROADS AND STORM WATER ............................................................................................................................... 45
Table 3.17: GRAVEL ROAD INFRASTRUCTURE ..................................................................................................... 45
Table 3.18: TARRED ROADS INFRASTRUCTURE ................................................................................................... 46
Table 3.19: ROADS AND STORM WATER SERVICE POLICY OBJECTIVES ............................................................... 47
3.19.1 STRATEGIC ................................................................................................................................................... 47
Table 3.20: EMPLOYEES: ROAD AND STORM WATER SERVICES.......................................................................... 48
Table 3.21: FINANCIAL PERFORMANCE: ROAD AND STORM WATER SERVICE ................................................... 48
Table 3.22: CAPITAL EXPENDITURE: ROADS AND STORM WATER SERVICE ........................................................ 49
3.5 ELECTRICITY PROVISION...................................................................................................................................... 49
Table 3.23: ELECTRICITY SERVICE DELIVERY LEVELS ............................................................................................ 49
Table 3.24: HOUSEHOLDS – ELECTRICITY SERVICE DELIVERY LEVELS BELOW THE MINIMUM: NON – BELOW
THE MINIMUM ........................................................................................................................................................ 50
Table 3.25: TARIFF GROUPS ................................................................................................................................ 50
Table 3.26: ELETRICITY SERVICE POLICY OBJECTIVES TAKEN FROM IDP ............................................................. 52
3.26.1 STRATEGIC ................................................................................................................................................... 52
3.26.2 OPERATIONAL ............................................................................................................................................. 53
Table 3.27: EMPLOYEES: ELECTRICITY SERVICES ................................................................................................. 54
Table 3.28: CAPITAL EXPENDITURE: ELECTRICITY SERVICES ................................................................................ 54
3.6 HOUSING ............................................................................................................................................................. 54
Table 3.29: HOUSING........................................................................................................................................... 55
Table 3.30: HOUSING SERVICE POLICY OBJECTIVES TAKEN FROM IDP ............................................................... 56
3.30.1 STRATEGIC ................................................................................................................................................... 56
3.30.2 OPERATIONAL ............................................................................................................................................. 57
4
Table 3.31: EMPLOYEES: HOUSING SERVICES ..................................................................................................... 61
Table 3.32: FINANCIAL PERFORMANCE: HOUSING SERVICE ............................................................................... 61
Table 3.33: CAPITAL EXPENDITURE: HOUSING SERVICES .................................................................................... 62
COMPONENT B: PLANNING ..................................................................................................................................... 62
3.7 PLANNING ........................................................................................................................................................... 62
Table 3.34: POLICY OBJECTIVES OF PLANNING TAKEN FROM THE IDP ............................................................... 64
3.34.1 OPERATIONAL ............................................................................................................................................. 64
Table 3.35: EMPLOYEES: ECONOMIC DEVELOPMENT AND PLANNING SERVICES .............................................. 65
Table 3.36: FINANCIAL PERFORMANCE: PLANNING AND FRESH PRODUCE MARKET ......................................... 65
Table 3.37: CAPITAL EXPENDITURE: PLANNING AND LOCAL ECONOMIC DEVELOPMENT .................................. 66
CAPITAL EXPENDITURE: LOCAL ECONOMIC DEVELOPMENT ................................................................................ 67
3.8 LOCAL ECONOMIC DEVELOPMENT (INCLUDING TOURISM AND MARKETING) .................................................. 67
Table 3.38: ECONOMIC GROWTH BY SECTOR ..................................................................................................... 67
Table 3.39: EMPLOYMENT BY ECONOMIC SECTOR ............................................................................................. 67
Table 3.40: JOB CREATION .................................................................................................................................. 68
Table 3.41: LOCAL ECONOMIC DEVELOPMENT POLICY OBJECTIVES TAKEN FROM IDP...................................... 69
3.41.1 STRATEGIC ................................................................................................................................................... 69
3.41.2 OPERATIONAL ............................................................................................................................................. 72
COMPONENT C: COMMUNITY AND SOCIAL DEVELOPMENT ..................................................................................... 74
3.9 LIBRARIES, ARCHIVES, COMMUNITY FACILITIES; OTHER THEATRES, ZOO .......................................................... 74
Table 3.42: LIBRARIES; ARCHIVES; COMMUNITY FACILITIES; OTHER .................................................................. 75
3.42.1 STRATEGIC ................................................................................................................................................... 75
3.42.2 OPERATIONAL ............................................................................................................................................. 76
Table 3.43: EMPLOYEES: LIBRARIES ..................................................................................................................... 77
Table 3.44: FINANCIAL PERFORMANCE: LIBRARIES; ARCHIVES; COMMUNITY FACILITIES; OTHER ..................... 78
3.10 CHILD CARE, CARE OF THE AGED, SOCIAL PROGRAMMES ................................................................................. 79
Table 3.46: SERVICE DELIVERY OBJECTIVES IN THE IDP FOR CHILD CARE ........................................................... 80
3.46.1 OPERATIONAL ............................................................................................................................................. 80
Table 3.47: EMPLOYEES: CHILD CARE; CARE OF THE AGED; SOCIAL PROGRAMMES ......................................... 81
3.11 BIO DIVERSITY AND LANDSCAPE – PARKS ........................................................................................................... 81
Table 3.48: SERVICE DELIVERY OBJECTIVES OF BIO DIVERSITY; LANDSCAPE AND PARKS ................................... 83
3.48.1 STRATEGIC ................................................................................................................................................... 83
COMPONENT E: ENVIRONMENTAL PROTECTION...................................................................................................... 84
3.12 POLLUTION CONTROL ......................................................................................................................................... 84
Table 3.49: SERVICE DELIVERY OBJECTIVES FOR POLLUTION CONTROL ............................................................. 85
3.49.1 OPERATIONAL ............................................................................................................................................. 85
Table 3.50: EMPLOYEES: POLLUTION CONTROL.................................................................................................. 86
COMPONENT F: HEALTH ........................................................................................................................................... 86
3.13 HEALTH INSPECTION, FOOD AND ABBATTOIR .................................................................................................... 86
Table 3.51: SERVICE DELIVERY OBJECTIVES FOR HEALTH INSPECTION, FOOD AND ABBATTOIR ........................ 88
3.51.1 STRATEGIC ................................................................................................................................................... 88
3.51.2 OPERATIONAL ............................................................................................................................................. 88
Table 3.52: EMPLOYEES: HEALTH INSPECTION ................................................................................................... 91
Table 3.53: FINANCIAL PERFORMANCE: HEALTH INSPECTION AND ETC. ........................................................... 91
COMPONENT G: SAFETY AND SECURITY ................................................................................................................... 92
5
3.14 INTRODUCTION TO POLICING ............................................................................................................................. 92
Table 3.54: SERVICE DELIVERY OBJECTIVES FOR SAFETY AND SECURITY ............................................................ 93
3.54.1 STRATEGIC ................................................................................................................................................... 93
3.54.2 OPERATIONAL ............................................................................................................................................. 94
Table 3.55: EMPLOYEES: POLICE OFFICERS/TRAFFIC AND SECURITY OFFICERS .................................................. 95
Table 3.56: FINANCIAL PERFORMANCE: POLICE/TRAFFIC AND SECURITY .......................................................... 96
Table 3.57: CAPITAL EXPENDITURE: POLICE/TRAFFIC AND SECURITY ................................................................. 96
3.15 FIRE ..................................................................................................................................................................... 96
Table 3.58: METROPOLITAN FIRE SERVICE DATA ................................................................................................ 97
Table 3.59: FIRE SERVICE POLICY OBJECTIVES TAKEN FROM THE IDP................................................................. 98
3.59.1 STRATEGIC ................................................................................................................................................... 98
3.59.2 OPERATIONAL ............................................................................................................................................. 99
Table 3.60: EMPLOYEES: FIRE SERVICES ............................................................................................................ 101
Table 3.61: FINANCIAL PERFORMANCE: FIRE SERVICES .................................................................................... 101
Table 3.62: CAPITAL EXPENDITURE: FIRE SERVICES ......................................................................................... 102
3.16 DISASTER MANAGEMENT ................................................................................................................................. 102
Table 3.63: SERVICE DELIVERY OBJECTIVES FOR DISTASTER MANAGEMENT ................................................... 104
3.63.1 OPERATIONAL ........................................................................................................................................... 104
Table 3.64: EMPLOYEES DISASTER MANAGEMENT ........................................................................................... 105
Table 3.65: FINANCIAL PERFORMANCE DISASTER MANAGEMENT ................................................................... 105
COMPONENT H: SPORTS AND RECREATION ........................................................................................................... 106
3.17 INTRODUCTION TO SPORT ................................................................................................................................ 106
Table 3.66: SERVICE DELIVERY OBJECTIVES FOR SPORTS AND RECREATION .................................................... 107
3.66.1 OPERATIONAL ........................................................................................................................................... 107
Table 3.67: EMPLOYEES: SPORT ........................................................................................................................ 108
Table 3.68: FINANCIAL PERFORMANCE SPORTS AND RECREATION .................................................................. 108
COMPONENT I: CORPORATE POLICY OFFICES AND OTHER SERVICES ...................................................................... 109
3.18 EXECUTIVE AND COUNCIL ................................................................................................................................. 109
Table 3.69: SERVICE DELIVERY OBJECTIVES OF EXECUTIVE AND COUNCIL ....................................................... 110
3.69.1 STRATEGIC ................................................................................................................................................. 110
3.69.2 OPERATIONAL ........................................................................................................................................... 111
3.19 FINANCIAL SERVICES ......................................................................................................................................... 112
Table 3.70: DEBT RECOVERY .............................................................................................................................. 112
Table 3.71: SERVICE DELIVERY OBJECTIVES OF FINANCE IN THE IDP ................................................................ 113
3.71.1 STRATEGIC ................................................................................................................................................. 113
3.71.2 OPERATIONAL ........................................................................................................................................... 115
Table 3.72: EMPLOYEES FINANCIAL SERVICES ................................................................................................... 119
Table 3.73: FINANCIAL PERFORMANCE: FINANCIAL SERVICES .......................................................................... 119
Table 3.74: CAPITAL EXPENDITURE FINANCE .................................................................................................... 119
3.20 HUMAN RESOURCES SERVICES ......................................................................................................................... 119
Table 3.75: EMPLOYEES HUMAN RESOURCES SERVICES ................................................................................... 120
Table 3.76: FINANCIAL PERFORMANCE: HUMAN RESOURCE SERVICES ........................................................... 121
Table 3.77: SERVICE DELIVERY OBJEVTIVES FROM THE IDP HUMAN RESOURCES ............................................ 122
3.77.1 OPERATIONAL ........................................................................................................................................... 122
3.21 INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) ........................................................................... 124
Table 3.78: SERVICE DELIVERY OBJECTIVES OF ICT ROM IDP ............................................................................ 125
3.78.1 OPERATIONAL ........................................................................................................................................... 125
Table 3.79: EMPLOYEES: ICT SERVICES .............................................................................................................. 126
6
Table 3.80: FINANCIAL PERFORMANCE: ICT ...................................................................................................... 126
Table 3.81: CAPITAL EXPENDITURE ICT SERVICES ............................................................................................. 127
3.22 LEGAL, RISK MANAGEMENT AND INTERNAL AUDIT SERVICES ......................................................................... 127
Table 3.82: PRINCIPLES, AIMS AND OBJECTIVES ............................................................................................... 128
Table 3.83: SERVICE DELIVERY OBJECTIVES FOR LEGAL, RISK MANAGEMENT AND INTERNAL AUDIT SERVICES
129
3.83.1 STRATEGIC ................................................................................................................................................. 129
3.83.2 OPERATIONAL ........................................................................................................................................... 129
Table 3.84: EMPLOYEES INTERNAL AUDIT ......................................................................................................... 130
3.23 COMPREHENSIVE REPORT ON SDBIP 2015/16 ................................................................................................. 131
3.23.1 PLANNING ................................................................................................................................................. 133
3.23.2 ENGINEERING SERVICES ............................................................................................................................ 138
3.23.3 STRATEGIC PROJECTS AND SERVICE DELIVERY REGULATIONS ................................................................. 143
3.23.4 SOCIAL SERVICES ....................................................................................................................................... 146
3.23.5 FINANCE .................................................................................................................................................... 151
3.23.6 HUMAN SETTLEMENTS ............................................................................................................................. 153
3.23.7 OFFICE OF THE CITY MANAGER ................................................................................................................ 155
3.23.8 CORPORATE SERVICES .............................................................................................................................. 157
CHAPTER 4 - ORGANISATIONAL DEVELOPMENT PERFORMANCE.......................................... 158
COMPONENT A: INTRODUCTION TO MUNICIPAL PERSONELL................................................................................. 158
4.1 EMPLOYEE TOTALS, STAFF TURNOVER AND VACANCIES 2015/16 ................................................................... 158
Table 4.1: EMPLOYEES ....................................................................................................................................... 158
Table 4.2: VACANCY RATE ................................................................................................................................. 159
Table 4.3: STAFF TURN-OVER RATE ................................................................................................................... 159
COMPONENT B: MANAGING WORKFORCE ............................................................................................................. 159
Table 4.4: HR POLICIES AND PLANS ................................................................................................................... 160
Table 4.5: NUMBER AND COST OF INJURIES ON DUTY ..................................................................................... 162
Table 4.6: NUMBER OF DAYS AND COST OF SICK LEAVE ................................................................................... 163
Table 4.7: NUMBER AND PERIOD OF SUSPENSIONS ......................................................................................... 164
Table 4.8: DISCIPLINARY ACTION TAKEN ON CASES OF FINANCIAL MISCONDUCT ........................................... 164
COMPONENT C: CAPACITATING THE WORKFORCE ................................................................................................. 165
Table 4.9: FINANCIAL COMPETENCY DEVELOPMENT ........................................................................................ 165
CHAPTER 5 - FINANCIAL PERFORMANCE ........................................................................................ 167
5.1 STATEMENT OF FINANCIAL PERFORMANCE ................................................................................................... 167
Table 5.1.1: RECONCILIATION OF TABLE A1 BUDGET SUMMARY ..................................................................... 167
COMPONENT A: STATEMENT OF FINANCIAL PERFORMANCE ................................................................................. 170
COMPONENT B: SPENDING AGAINST CAPITAL BUDGET ......................................................................................... 171
COMPONENT C: CASH FLOWS MANAGEMENT AND INVESTMENTS ........................................................................ 171
5.2 GRANTS ............................................................................................................................................................. 172
Table 5.2.1: Operating Grants ........................................................................................................................... 172
7
Table 5.2.2: CONDITIONAL GRANTS RECEIVED: EXCLUDING MIG ..................................................................... 175
5.3 REPAIRS AND MAINTENANCE ........................................................................................................................... 176
Table 5.3.1: REPAIRS AND MAINTENANCE ........................................................................................................ 176
5.4 SPENDING AGAINST CAPITAL BUDGET ............................................................................................................. 176
Table 5.4.1 CAPITAL EXPENDITURE ................................................................................................................... 176
Table 5.4.2: CAPITAL EXPENDITURE FUNDING SOURCES .................................................................................. 177
Table 5.4.3: CAPITAL EXPENDITURE OF 5 LARGEST PROJECTS .......................................................................... 178
5.5 CASHFLOW MANAGEMENT AND INVESTMENTS .............................................................................................. 180
Table 5.5.1: CASH FLOW OUTCOMES ................................................................................................................ 180
5.6 BORROWING AND INVESTMENTS ..................................................................................................................... 182
Table 5.6.1: ACTUAL BORROWINGS – YEAR 2012/2013 TO YEAR 2015/2016 .................................................. 182
Table 5.6.2: MUNICIPAL AND ENTITY INVESTMENTS ........................................................................................ 184
CHAPTER 6 - AUDITOR GENERAL REPORTS 2015/16 ................................................................ 186
COMPONENT A: AUDITOR GENERAL OPINION OF CONSOLIDATED FINANCIAL STATEMENT 2015/16 ..................... 186
COMPONENT B: AUDITOR GENERAL OPINION OF MANGAUNG METROPOLITAN STAND ALONE FINANCIAL
STATEMENT 2015/16 ................................................................................................................................................. 187
COMPONENT C: AUDITOR GENERAL OPINION OF CENTLEC (SOC) LIMITED FINANCIAL STATEMENTS 2015/16 ...... 188
CHAPTER 7 - AUDIT COMMITTEE REPORT ON THE ANNUAL REPORT 2015/16 .............. 189
APPENDICES............................................................................................................................................... 190
APPENDIX A: COUNCILLORS, COMMITTEES ALLOCATED AND COUNCIL ATTENDANCE .................................... 190
APPENDIX B: COMMITEE AND COMMITEE PURPOSE ....................................................................................... 201
APPENDIX C: TWO TIER STRUCTURE ................................................................................................................. 202
APPENDIX D: FUNCTIONS OF THE MUNICIPALITY/ ENTITY ............................................................................... 203
APPENDIX E: WARD REPORTING ....................................................................................................................... 205
APPENDIX F: WARD INFORMATION .................................................................................................................. 222
APPENDIX G: RECOMMENDATIONS OF THE MUNICIPAL AUDIT COMMITTEE .................................................. 224
APPENDIX H: MUNICIPAL ENTITY/SERVICE PROVIDER PERFORMANCE SCHEDULE .......................................... 229
APPENDIX I: DISCLOSURE OF FINANCIAL INTERESTS ......................................................................................... 230
APPENDIX J: REVENUE COLLECTION PERFORMANCE BY VOTE ......................................................................... 249
APPENDIX K: CONDITIONAL GRANTS RECEIVED: EXCLUDING MIG ................................................................... 250
APPENDIX L: CAPITAL EXPENDITURE – NEW & UPGRADE / RENEWAL PROGRAMMES .................................... 251
APPENDIX M: CAPITAL PROGRAMME BY PROJECT (2015/2016) ...................................................................... 260
VOLUME II ................................................................................................................................................................. 297
Mangaung Metropolitan Municipality Consolidated Annual Financial Statements for the year ended 30 June 2015 297
Mangaung Metropolitan Municipality stand- alone Annual Financial Statements for the year ended 30 June 2015 . 297
Centlec (Soc) Limited Annual Financial Statements for the year ended 30 June 2015 ................................................ 297
8
CHAPTER 1 - MAYOR’S FOREWORD AND EXECUTIVE SUMMARY
COMPONENT A: MAYOR’S FOREWORD
During the 2015/16 financial year the city made advances on the implementation of the 8 priority areas which
we set ourselves during the beginning of this electoral term. The City continued in making significant strides in
extending access to water and sanitation services, facilitated access to housing and social housing
opportunities, ensured that indigent households had access to a basket of Free Basic Services (FBS), provided
efficient environmental health and emergency services and rehabilitated social amenities. Effective
maintenance of assets was carried out that included resurfacing roads, rehabilitation of roads, storm-water
canals, catch pits and pedestrian paving, electricity service infrastructure (network and streetlights).
The other highlights of this past year were:
Refurbishment of the Maselspoort Water Treatment Works by installing additional five (5) pumps to ensure
reliable water supply to the City;
98.1% (173 920) of formal households have accesses to water services;
100% completion of Phase 1 to extend the capacity of Thaba Nchu Waste Water Treatment Works;
Upgraded 4065 VIP and Bucket toilets into waterborne sanitation;
Effective implementation of Water Conservation and Demand Management Programme (WCDMP) and
attainment of its set targets;
211 461 households have access to weekly waste removal services;
Upgraded and maintained two land-fill sites;
Thaba Nchu Transfer station 91% complete;
Tarred 5,29 km of gravel road and paved 5,489 km of gravel road;
Five hundred and thirty seven (537) new households were provided with electricity connections;’
2054 smart street lights have been installed to provide reliable public lighting;
132/11kV 20 MVA Groenvlei Distribution Centre is 100% complete;
193 858 formal households have access to basic electricity services;
15 927 households have access to Free Basic Electricity;
34 high mast lights have been erected and 26 have been commissioned;
Seven (7) informal settlements have been upgraded and thus benefitting 3143 households;
3347 title deeds have been transferred to eligible beneficiaries;
5773 sites serviced;
10 informal settlements were upgraded insitu;
Development of Hillside View Phase 1 in partnership with Free State Provincial Government is gaining
traction;
Effective processing of land development application to facilitate development in the City;
35 Hawking stalls were developed at Botshabelo CBD to support Small Medium and Micro Enterprises
(SMMEs);
9
The Upgrading of Maphisa Road is 82% complete and this represent Phase 1 of the Integrated Public
Transport Network (IPTN);
1431 SMMEs were supported and 993 were trained;
Continued provision of an effective library services;
2nd Phase of Upgrading the Selosesha Regional Park by developing an athletic track is 100% complete;;
Continued provision of an effective municipal health services;
24 crime prevention operations targeting crime hot-spots; and
Effective fire, emergency and disaster management services;
In the coming year, the city shall put more effort in the following areas:
The reduction of non-revenue water from 41%;
Accelerating the establishment of electricity distribution centres;
Re-engineering and revitalisation of old power stations;
Facilitate the acceleration of Community Residential Units (CRU);
Facilitate the development of Botshabelo / Thaba Nchu Node and N8 Development Node;
Accelerate the development of Vista Park 2 and 3 mixed development;
Accelerate the upgrading roads at cemeteries;
An establishment of a Metro Police Department;
The City has used community meetings, summits, stakeholder workshops, one-hour engagement with the
Executive Mayor as platforms to engage communities and kept them abreast of the developments in the City.
The City is on course to attaining its set development objectives and will redouble its efforts in the next local
government term to deliver on its mandate in partnership with other spheres of government and social partners.
10
COMPONENT B: EXECUTIVE SUMMARY
1.1 MUNICIPAL MANAGER’S OVERVIEW
The 2015/16 financial year is the last year of the electoral term 2011/16 that will go down in the history of the
Municipality as the term where the City have registered significant successes in relation to service delivery and
improving the lives of its citizen. The said electoral term was concluded on high note with significant
achievements made in relation to the various measurable performance targets informed by the following eight
development priorities:
1) Poverty eradication, rural and economic development and job creation;
2) Financial sustainability e.g. revenue enhancement, clean audit;
3) Spatial development and the built environment;
4) Eradication of bucket system, VIP toilets in Botshabelo, Mangaung and Thaba Nchu, focus on the basics,
building solar farming, power plant feasibility, safety & security;
5) Human Settlement;
6) Public Transport;
7) Environmental Management and Climate change; and
8) Social and community services.
The afore-going Foreword of the Executive attest to the fact that significant progress was made in relation to
the following:
The Development of Bulk Water and Sanitation services and the corresponding reticulation of those
services to households;
Upgrading of roads and stormwater throughout the city to deal with massive road and storm-water backlogs;
Upgrading of informal settlements and thus provide a solid foundation for building of integrated human
settlements;
Upgrading of Maphisa as the phase of Hauweng Public Transport System in the City;
Upgrading of social amenities such as parks, community halls, stadia, swimming pools to create a conducive
environment for social cohesion amongst the residents of the City;
Effective management of the resources of the municipality and improved audit outcome year on year
security of tenure;
All these would not have been possible without the harmonious working relationship between the political
Leadership the administrative arm and the vibrant Community of the Metro. The community have actively
participated in the affairs of the City through the public participation structures .The City is looking forward to
another tem of achievements, taking into account the recently incorporation of the former Naledi Local
Municipality and the town of Soutpan/Ikgomotseng into the jurisdiction of the City.
11
1.2 MUNICIPAL FUNCTIONS, POPULATION AND ENVIRONMENTAL OVERVIEW
According to Community survey by end of June 2016, Mangaung had a population of 759 693, adding Naledi
the total population of Mangaung has increased to 784 490. This shows that Mangaung has the biggest regional
population in the Free State Province followed by Thabo Mofutsanyane (779 600 on average).
Figure 1.1 FORMAL AND INFORMAL DWELLINGS IN MANGAUNG
In 2015/16 there were 223 108 formal dwellings in Mangaung, representing 82% of all dwellings in the city as
reflected in the chart above. In contradiction to this, there were 32 747 informal residential areas in the city
representing only 9% of dwellings in the city. Essentially, the city is highly formalised with the dwellings being
represented by non-traditional type of residential areas.
1.2.1 SOCIO ECONOMIC STATUS
Although there is a significant shift in the unemployment rate in Mangaung it remains very high as the table
below indicates. The biggest gap is with women and youth particularly black females. This in essence means
that as a municipality we must increase our efforts in relation to creation of employment opportunities through
amongst others; the EPWP initiatives and other skill development initiatives.
82%
9%2%2%0%1%0%1%2%1%
%
Formal residential
Informal residential
Traditional residential
Farms
Parks and recreation
Collective living quarters
Industrial
Small holdings
Vacant
Commercial
12
BELOW ARE TABLES RELATED TO SOCIO ECONOMIC STATUS OF THE MMM:
Table 1.1: SOCIO ECONOMIC STATUS
Socio Economic Status
Year Housing
Backlog as
proportion of
current
demand
Unemployment
Rate (Narrow
definition)
Employed /
Population
Ratio
(Absorption)
Labour Force
Participation
Rate
Poverty
Head
Count
Intensity
of
Poverty
2015/16 30,954 28.8% 47,3% 66.3% 5% 41.1%
Source: Community Survey 2016 & Quarterly Labour Force Survey and Stats SA.
There are more employed people in Mangaung than those who are unemployed from the economically active
groups, the challenge is that most people are employed in low skilled jobs because of amongst other things,
their levels of education as the table below will demonstrate that about 38.0% of the labour force of Mangaung
has completed some secondary and 28.2% have completed matric and only 12.7% has post matric qualification
Figure 1.2 Proportion of the population aged 20 years and older by level of education attained
According to figure 1.2 above, the number of persons with just a primary education and below constituted just
above 46% in 1996 in the Free State. The same persons with completed primary and below in the Mangaung
Metro constituted 37% plus, which indicates that Mangaung Metro was better off than the Province in terms of
this group or level of education. The numbers of the same cohort of completed primary and below for both Free
State and Mangaung have drastically improved in 2011, with 28.7% and 22.4% respectively. The percentage
of persons with some secondary schooling, but who have not passed matric has remained in mid-thirties for
both Free State and Mangaung Metro over the entire review period (33.5% and 35.5% in 1996 and 34.7% and
13
33.2% in 2011 respectively), indicating mixed results for that section of schooling. The general indication is that
people are able to proceed to secondary school, but are unable to complete their studies. The congestion in
secondary school in terms of the level of education achieved is a prelude to problems in education system
indicated by large dropouts at that level. However, the number of those completing secondary schooling for
Free State and Mangaung Metro has increased from 13.5% and 18.7% in 2004 to 26.8% and 30.3% in 2014
respectively; which is an increase of 13.3 percentage points and 11.6 percentage points respectively. In terms
of those with some skills, Mangaung Metro had a better advantage over Free State in terms of the number and
the percentage of growth (5.9% to 9.8% and 8.2% to 14.2% respectively), is reflective of the economic
advantage that Mangaung Metro has over the entire province.
Table 1.2: NATURAL RESOURCES
MAJOR NATURAL RESOURCE RELEVANCE TO COMMUNITY
Water Provision of water is very essential to any community
Vast Agricultural land Given the high unemployment rate, communities still have
access to land for agricultural activities
Sunshine Solar power
Naval Hill Being developed as a tourist attraction
1.2.2 KEY CHALLENGES AND OPPORTUNITIES FOR THE CITY
1.2.2.1 FINANCE
The City has committed itself to ensuring prudent financial management and fiscal discipline through developing
and reviewing internal controls; establishing various oversight committees and improving capacity within
financial management. The fiscal discipline shown by the City has assisted in ensuring improved audit results.
The Municipality received a Qualified Audit Opinion for the 2014/15 Financial Year, which, in the light of the
Clean Audit Drive will have to be addressed in a systematic and effective manner. The Mangaung Metropolitan
Municipality was awarded the following credit rating by Moody’s Investors Service in May 2016.
Short Term Issuer Rating (South African national scale local currency) - P-2
Long Term Issuer Rating (South African national scale local currency) – Ba1
Long term issuer rating was revised from A3 in April 2015 to Ba1 in May 2016 due to South Africa's national
rating scale.
The rating of the municipality represents the following:
Improving liquidity
Strong operating balance
14
Low debt levels relative to rated metros in SA (A1 to baa3)
Improvement from historic disclaimers to unqualified audit reports
1.2.2.2 HUMAN SETTLEMENTS
Like most South African municipalities, Mangaung Metro has the characteristic of a segregated and fragmented
city. Bloemfontein is the economic bellwether upon which Botshabelo and Thaba-Nchu regions depend. The
city has developed in a binary manner with much investment in the northern areas, growing speedily towards
the western part of the City, whereas the south-eastern part has been characterised by low-income and low
density government subsidised settlements. These characteristic evinces apartheid spatial planning. In an
endeavour to overcome this and foster integration, the Metro has determined that a development corridor be
initiated along the N8 connecting the three regions.
The community Survey 2016 indicate that the housing backlog in the City stood at 30 954. The demand was
mainly found in the affordable (GAP) and rental market. The attendant pressures of urbanisation, migration,
population increase and declining economic performance of all factors of production collectively places
strenuous demands on the services government provides.
Among instruments to address its housing backlog, has been the acquisition by the Mangaung Metro of Eight
(8) strategic land parcels for the implementation of mixed use development to create integrated human
settlements. Such an instrument upon which the Metro has predicated its approach is the strategy consisting of
a combination of retail, recreational, residential, and industrial and community facilities. Collectively, these
developments will entail various housing typologies and provide wide tenure options to beneficiaries, such as
ownership, rent, and rent-to-buy as well as mortgage loan options within the same geographic space.
1.2.2.3 SOCIAL SERVICES
The City continues to provide effective social services such as fire, emergency and library services, HIV/ AIDS
awareness. However, the Department should deal with the following challenges:
Accelerate the upgrading of cemeteries with the installation of perimeter fences and roads and storm-
water services;
Establishing the metro police and obtaining assignment in relation to ambulance services are still
persistent challenges facing the City.
1.3 SERVICE DELIVERY OVERVIEW
The city has been able to deliver 3347 title deeds to its citizens in the financial year 2015/16 and upgraded
seven (7) informal settlements. The following encouraging strides were registered in 2015/2016 FY:
15
Refurbishment of the Maselspoort Water Treatment Works by installing additional five (5) pumps to ensure
reliable water supply to the City;
98.1% (173 920) of formal households have accesses to water services;
100% completion of Phase 1 to extend the capacity of Thaba Nchu Waste Water Treatment Works;
Upgraded 4065 VIP and Bucket toilets into waterborne sanitation;
Effective implementation of Water Conservation and Demand Management Programme (WCDMP) and
attainment of its set targets;
211 461 households have access to weekly waste removal services;
Upgraded and maintained two land-fill sites;
Thaba Nchu Transfer station 91% complete;
Tarred 5,29 km of gravel road and paved 5,489 km of gravel road;
Five hundred and thirty seven (537) households have access to electricity services;
2054 smart street lights have been installed to provide reliable public lighting;
132/11kV 20 MVA Groenvlei Distribution Centre is 100% complete;
193 858 formal households have access to basic electricity services;
15 927 households have access to Free Basic Electricity;
34 high mast lights have been erected and 26 have been commissioned;
5773 sites serviced;
10 informal settlements were upgraded insitu;
Development of Hillside View Phase 1 in partnership with Free State Provincial Government is gaining
traction;
Effective processing of land development application to facilitate development in the City;
35 Hawking stalls were developed at Botshabelo CBD to support Small Medium and Micro Enterprises
(SMMEs);
The Upgrading of Maphisa Road is 82% complete and this represent Phase 1 of the Integrated Public
Transport Network (IPTN);
1431 SMMEs were supported and 993 were trained;
Continued provision of an effective library services;
2nd Phase of Upgrading the Selosesha Regional Park by developing an athletic track is 100% complete;;
Continued provision of an effective municipal health services;
24 crime prevention operations targeting crime hot-spots; and
Effective fire, emergency and disaster management services;
1.4 FINANCIAL HEALTH OVERVIEW
The Municipality received an Unqualified Audit Opinion for the 2014/15 Financial Year, which, in the light of the
Clean Audit Drive will have to be addressed in a systematic and effective manner. As at 30 June 2016,
Mangaung Metropolitan Municipality had accumulated surplus of R 11.5 billion and that the entity's total assets
exceed its liabilities by R13.5 billion.
16
CHAPTER 2 - GOVERNANCE
INTRODUCTION
Municipalities in South Africa are governed by Municipal Councils. Mangaung Council is therefore the governing
body of the Mangaung Metropolitan Municipality and the custodian of its powers, duties and functions, both
legislative and administrative. Essentially, the Council performs a legislative and executive role. The
Constitution of the Republic of South Africa, 1996, Chapter 7, Section 160 (1) defines the role of the Council as
being:
(making) decisions concerning the exercise of all the powers and the performance of all the functions of the
municipality;
(electing) its chairperson;
(electing) an executive committee and other committees, subject to national legislation;
(Employing) personnel that are necessary for the effective performance of its functions.
Municipal Council comprises the governing and decision making body of the Municipality whilst municipal
officials and staff focus on implementation. Council determines the direction for the municipality by setting the
course and allocating the necessary resources. Council establishes the policies, and municipal staff ensures
that those policies are implemented. Decisions made at Council or committee level are often the result of a lot
of research, consultation and advice from staff, residents, business people, and interested parties. Often there
are competing interests and financial constraints that must be considered.
COMPONENT A: POLITICAL AND ADMINISTRATIVE GOVERNANCE
2.1 POLITICAL GOVERNANCE
The Mangaung Metropolitan Municipality is governed by a council led by an Executive Mayor. All major policy
and administrative decisions are presented, resolved and implemented after the approval of Council. The
political system in the municipality is functioning well in that all major committees and participatory organs in the
Metro are fully functional. The Municipality has a functional oversight committee that meets regularly to consider
policy direction and track performance of the municipality, There is a functional audit committee that periodically
provide advice to Council. There is a Municipal Public Accounts Committee (MPAC) that continues to interrogate
municipal performance and thus assist the municipality to act in the manner that assist service delivery. The
annual report is publicized for scrutiny and comment of the public as well.
2.1.1 POLITICAL STRUCTURE OF MMM
17
1) Executive Mayor: Councillor Thabo Manyoni
2) Deputy Executive Mayor: Councillor Constance Rampai
3) Speaker: Councillor Mxolisi Siyonzana
4) Chief Whip: Councillor Zolile Mangcotywa
Table 2.1: MEMBERS OF THE MAYORAL COMMITTEE
Members of the Mayoral Committee Responsible Councillor
Finance Councillor Nthabiseng Modisaesi
IDP and Strategic Projects Councillor Constance Rampai
Agriculture and Rural Development Councillor Sabelo Monnakgori
Local Economic Development and Tourism Councillor Mmaneheng Tsomela
Economic Development and Spatial Planning Councillor Papiki Moeng
Health and Social Development Councillor Maditaba Matsoetlane
Community Safety, Emergency, Transport and Fleet
Services
Councillor Gladys Thipenyane
Environment and Waste Management Councillor Joanne Petersen
Infrastructure Service and Energy Services Councillor Lebohang Masoetsa
MPAC Councillor Lulama Titi-Odili
The Mangaung Council is constituted by 97 elected public representatives of which 49 are ward representatives
and 48 represent their political parties on a proportional basis. The parties in Council are illustrated in the table
below.
Table 2.2: POLITICAL PARTIES REPRESENTED IN THE COUNCIL
Political Parties in Council Total Seats Ward Seats PR Seats
African National Congress 65 38 27
Democratic Alliance 26 11 15
Freedom Front 2 - 2
African People’s Convention 1 - 1
Congress of the People 3 - 3
Table 2.3: THE GOVERNANCE STRUCTURE OF MANGAUNG METROPOLITAN MUNICIPALITY
18
Structure Responsible for Oversight Over Accountable to
Council Approve policies and budget Executive Mayor, Mayoral
Committee and Audit Committee
Community
Executive
Mayor
Policies, budget, outcomes,
management and oversight over
City Manager
City Manager Council
City
Manager
Outputs and implementation The administration Executive
Mayor
CFO & EMT Outputs and implementation Financial management and
operational functions
City Manager
POLITICAL DECISION MAKING
A routing system of matters reserved referred to the Council is followed, namely:
Reports are initiated by the Heads of Departments and submitted to the Corporate Secretariat Sub-Directorate.
The reports are covered with a yellow cover page, numbered, headed and registered in the Council Item
Register Book to indicate that the reports have been entered as an item into the system. The items are sent to
the City Manager for scrutiny. The City Manager engages with the reports, indicates under comments whether
the reports are recommended for consideration to the Executive Mayor, signs it and the items are then
forwarded to the Executive Mayor for political engagement. The Executive Mayor then under comments on the
yellow cover page indicates whether he approves the items, whether the items should be served on an agenda
of the relevant Section 80 Committee meeting or whether the items should go to Council, signs the yellow form
and sent it back to the Corporate Secretariat Sub-Directorate. The items with the yellow cover page, now fully
completed with all the necessary comments and signatures, are then included in the agenda of the next
ordinary/special agenda of the Mayoral Committee where all the approved items be placed on the agenda of
the Council to serve before the Council for final approval.
Items on the agenda of the ordinary meetings of the Mayoral Committee and the Council are categorized as
follows, namely:
Section A - Items for Consideration
Section B - Items in terms of Delegated Power
Section C - Items for Information
Once the Council has decided on a report, it is then a resolution of the Council. The City Manager executes
the decision/resolution taken by the Council by issuing execution letters to the relevant Departments.
19
Decisions/Resolutions taken by the Mangaung Metropolitan Municipal Council: -
MEETING HELD NUMBER OF RESOLUTIONS
03 July 15 12
06 August 15 2
20 August 18
22 Sept 15 3
22 Oct 15 12
01 Nov 2
02 Dec 2
14 Dec 12
14 Dec 2
12 Jan 2016 1
28 Jan 5
28 Jan 1
25 Feb 1
25 Feb 18
02 March 2
31 March 6
05 May 22
31 May 3
31 May 4
09 June 2
09 June 3
30 June 20
2.2 ADMNISTRATIVE GOVERNANCE
The administration is headed by the City Manager as the Chief Accounting Officer. The day-to-day management
of the Municipality is done by staff under the direction of the City Manager and Heads of Departments. The City
Manager and Heads of Departments have broad and general management responsibilities, such as making
sure staff is kept abreast on Council’s direction, and identifying gaps in service delivery. Together with Council
they must monitor progress on set goals and priorities.
20
TOP ADMINISTRATIVE STRUCTURE
The administration is made up of the following Departments headed by members of the Executive Management
Team:
City Manager
Head: Corporate Services
Head: Finance
Head: Engineering service
Head: Fleet and Solid Waste Head: Strategic Services and Projects
Head: Social Services
Head: Planning
Head: Economic Development
CEO: Centlec (entity)
Deputy Executive Director: Organisational Planning and Performance Management
COMPONENT B: INTERGOVERNMENTAL RELATIONS
2.3 INTERGOVERNMENTAL RELATIONS IN THE CITY
The City participates in Intergovernmental Forum at national and provincial level. The municipality participates
actively in the Premier Co-ordinating Forum (PCF) and the MECLOGA to raise challenges facing the
municipality with other municipalities, provincial government departments and South African Local Government
Association (SALGA) Free State Provincial Chapter. Further the city is a member of the Forum of Heads of
Departments in the province (FOHOD).
At national level, the municipality participates in Human Settlements and Cooperative Governance and
Traditional Affairs MINMECs which are platforms to provide progress in implementing the Urban Settlement
Development Grant (USDG) as well as Back to Basics programme and tease out the impact and outcomes
thereof.
The benefit of participating in these structures is highlighted in opportunities to be harnessed by the municipality
in fostering strategic partnerships with government departments.
RELATIONSHIP WITH MUNICIPAL ENTITIES
The municipality has established a municipal entity Centlec to provide electricity services to its citizen and
manage and maintain public lightning on the behalf of the City. The decisions of Centlec, are taken by a duly
21
constituted Board of Directors and through the business plan and Sale of Business agreement the entity account
to the City through the Executive Mayor.
COMPONENT C: OVERVIEW OF PUBLIC ACCOUNTABILITY AND
PARTICIPATION
As provided for in Legislation the municipality convened a series of meetings using a ward clustering system to
involve communities to participate actively in the unfolding planning, monitoring and budgeting processes.
The Municipal Systems Act (MSA) states that the IDP must include a vision for the long-term development of
the municipality and development priorities, which must be aligned with national and/or provincial sectoral plans
and planning requirements. In terms of the MSA and Municipal Finance Management Act (MFMA), the
Municipality has been reviewing its Integrated Development Plan and the organizational scorecard on an annual
basis whilst on the other hand compiling the Service Delivery and Budget Implementation Plans for each year.
Annual reports address the performance of the Municipality against its performance measures as outlined in
the SDBIP. The SDBIP primarily captures annual delivery agenda of the municipality as spelt out in the
Integrated Development Plan and the budget. In sync with the deeply entrenched culture of public participation,
the setting of the delivery for the period under review was highly participatory. The participation in the IDP as
well as the budget encompassed involvement in the planning for the development and budget allocation
including implementation of programmes and projects that require community involvement for them to be
sustainable and have the lasting impact.
2.4 PUBLIC MEETINGS
The Mangaung Metropolitan Municipality consult with the public throughout the financial year on IDP and tariffs
including annual reports and by laws, The Municipality has 49 wards, and 49 ward committees that are
functional. Because of the vast nature of our Municipality we cluster wards to be able to reach a wider audience
as possible and consult with our public from November to April on the revised tariffs and IDP priorities. The
Municipality publishes its public meetings in local newspapers and radio stations and also on municipal website.
The following is a list of documents published and made available to the public yearly:
The annual and adjustments budgets and all budget-related documents;
All budget related policies
The Annual Report
All Performance Agreements required in terms of section 56 of the Municipal Systems Act
All Service Delivery Agreements
All Municipal Tenders
All Weekly Quotations of the Municipality
22
All quarterly reports tabled in the council in terms of section 52 (d)
All Vacancies of the Municipality
Information about Tourism and Places of interest in Mangaung
Contact Information for all Directorates and Sub-Directorates
The Integrated Development Plan (IDP)
The Service Delivery and Budget Implementation Plan (SDBIP)
Spatial Development Framework (SDF)
Council Resolutions
WARD COMMITTEES
Ward committees in the Metro serve as an interface between the community and the municipality. They pick up
day to day service delivery issues in wards and through the ward councillor they advance those issues for
council attention. Ward committees are a single most important institutional arrangement to ensure efficient and
result based participatory system
Table 2.4: PUBLIC MEETINGS
Public meetings
Nature and
purpose of the
meeting
Dates of
event
No of
participating
councillors
No of
participating
Municipal
councillors
Number of
community
members
attending
Dates and
manner of
feedback given
to community
IDP and budget
consultative
meetings
Nov to April All ward
councillors of
the clusters
involved
All ward
councillors of the
clusters involved,
the deputy mayor
and the Speaker
Numbers vary
from cluster to
cluster
Feedback is
provided
during the
second round
of the
consultations
normally in
March
Annual report Feb to
March
All
councillors
All councillors Numbers vary
from cluster to
cluster
Feedback is
provided
during the
second round
of the
consultations
normally in
March
23
Public meetings
Nature and
purpose of the
meeting
Dates of
event
No of
participating
councillors
No of
participating
Municipal
councillors
Number of
community
members
attending
Dates and
manner of
feedback given
to community
By laws As and when
they are up
for public
consumption
Councillors
affected
Councillors
affected and the
relevant MMC
Numbers vary
from cluster to
cluster
Feedback
provided after
consultations
have been
finalised and
council has
resolved
Tariffs Nov to April All ward
councillors of
the clusters
involved
Councillors
affected and the
relevant MMC
Numbers vary
from cluster to
cluster
Feedback is
provided
during the
second round
of the
consultations
normally in
March
SDF and other
sector plans
Nov to April All ward
councillors of
the clusters
involved
Councillors
affected and the
relevant MMC
Numbers vary
from cluster to
cluster
Feedback is
provided
during the
second round
of the
consultations
normally in
March
Public engagements in the city provide opportunities for the public to contribute, interrogate and engage
municipal priorities. Furthermore, the municipality organise feedback sessions to report back on what
communities have been reflecting and how the municipality is responding. The IDP of the municipality also has
a section that addresses issues raised by communities and municipal responses.
2.5 IDP PARTICIPATION AND ALIGNMENT
Table 2.5: IDP AND ALIGNMENT
IDP Participation and alignment criteria Yes/no
Does the municipality have impact, outcome, input, output indicators Yes
24
IDP Participation and alignment criteria Yes/no
Does the IDP have priorities, objectives, KPI’s development strategies? Yes
Does the IDP have multiyear targets? Yes
Are the above aligned and can they calculate to a score Yes
Does the budget align directly to the KPI in the strategic plan? Yes
Does the IDP KPI align to section 56 managers? Yes
Do the IDP KPI lead to functional area KPI as per SDBIP Yes
Were the indicators communicated to the public Yes
Were the four quarter aligned reports submitted within stipulated time frames? Yes
COMPONENT D: CORPORATIVE GOVERNANCE
OVERVIEW OF CORPORATE GOVERNANCE
2.6. RISK MANAGEMENT
The Municipal Finance Management Act (MFMA), Act 56 of 2003 stipulates that the municpality must maintain
an effective, efficient, transparent and accountble system of Risk Management.
The Risk Management Framework, March 2015 as developed by the South African Local Government
Association instructs response to the requirements of the Public Finance Management Act (PFMA), Act 1 of
1999 and Municipal Finance Management Act, Act 56 of 2003 for the municipalities to implement and maitain
effective, efficient and apparent systems of risk management and control.
However, it is the Municipal policy to assure that informed decision making is made with regards to service
delivery activities by correctly identifying and considering both risk and opportunities within the municipality.
Mangaung Metropolitan Municipality’s Risk Management Committee has been established to performs its
functions and responsibilities in accordance with its approved Terms of Reference Charter and Advise
Management and the Audit Committee on matters which relates to the Risk Management within the City of
Mangaung.
We dare not to allow the situation to arise whereby corruption is seen as an inevitable fact of life in South Africa.
We believe that South Africa has not yet reached this point of no return. Whilst corruption poses a major
governance challengess, there are concrete, practical steps that can be taken to halt and reverse the tide of
25
corruption. We must seize the moment and turn the tide. Currently all departments work together in a consistent
and integrated manner with the overall objective of reducing risks to acceptable and manageable levels.
The municpality resolved after review that the risks that were identified during the 2014/15 financial year
remained the same and relevant for the 2015/2016 financial year, the acknowledged twelve strategic risks were
related to the strategic objectives. Hence, the risks were all rated and an action plan was developed to mitigate
these risks. However, the strategic risk development progress was then compiled for 2015/16.
1) High level of poverty and unemployment in the City;
2) Threatened sustainability and financial viability of the City;
3) Lack of Spatial integration and built environment;
4) Inadequate service delivery;
5) Housing baacklogs;
6) Ineffective public transport system;
7) Climate change and environmental degradation;
8) Threatened sustainability of social and community services;
9) Protest unrest
10) Fraud and corruption;
11) Inadequate Information Technology and Communication
12) Lack of good governance
The following are challenges in implementing Risk Management:
1. Budget constraints
2. Aligning risk management with overall business strategy
3. Defining risk
4. Skills shortage (Moratorium)
5. Lack of innovation
6. Strategic Risk Register
2.7 ANTI FRAUD AND CORRUPTION
The municipality has Fraud Prevention Plan that outlines the municipality’s approach to curtailing the likelihood
of fraud occurring, its prevention as well as the early detection thereof.
The numerous awareness sessions on fraud related matters were held.Apart from fraud prevention awareness
sessions, the city also had information session on code of conduct and ethics.
26
Anti-Fraud and Corruption Unit investigate 33 reported allegations of fraud and has issued 6 reports for the year
under review. Depending on the outcome of the investigation other cases are further referred to South African
Police Services,HAWKS and the South African Revenue Services (SARS),etc
The municpality has established an Audit Committee that is periodically reviewing and advising on internal
controls of the municipality. The Audit Committee is administratively supported by the Internal Audit Unit.
Table 2.6: MEETINGS OF THE AUDIT COMMITTEE
Meeting Number Date
01/2015-16/38 27 August 2015
03/2015-16/40 9 October 2015
04/2015-16/41 6 November 2015
05/2015-16/42 3 December 2015
06-2015/16-43 27 January 2016
07-2015/16-44 29 March 2016
The municipality also has a functional Internal Audit Unit. This Unit is working in collaboration with both the Risk
and Anti-Fraud Units to strengthen municipality’s efforts to manage risks and combat fraud and corruption.
2.8 MUNICIPAL WEBSITE: CONTENT AND CURRENCY OF MATERIAL
Table 2.7: MUNICIPAL WEBSITE: CONTENT AND CURRENCY OF MATERIAL
Please see the Live Website with all the Details & History available @ www.mangaung.co.za
Municipal Website: Content and Currency of Material
Documents published on the
Municipality's / Entity's Website Yes / No Publishing Date
Current annual and adjustments
budgets and all budget-related
documents
Yes 8 May 2016
All current budget-related policies Yes 15 June 2016
The previous annual report
(2013/2014)
Yes 5 February 2015
27
Municipal Website: Content and Currency of Material
Documents published on the
Municipality's / Entity's Website Yes / No Publishing Date
The annual report (Year 2014/2015)
published
Yes 3 February 2016
All current performance agreements
required in terms of section 57(1)(b)
of the Municipal Systems Act (Year
2013/2014) and resulting scorecards
No
All service delivery agreements (Year
2013/2014)
No
All long-term borrowing contracts
(Year 2013/2014)
No
All supply chain management
contracts above a prescribed value
(give value) for Year 2014/2015
Yes Awarded Formal Quotations (R 30 001.00 – R 200
000.00) & Awarded Formal BIDS (above R 200 000) for
the Period during July 2014 till June 2015
An information statement containing
a list of assets over a prescribed
value that have been disposed of in
terms of section 14 (2) or (4) during
2012/2013
No
Contracts agreed in 2013/2014 to
which subsection (1) of section 33
apply, subject to subsection (3) of
that section
No
Public-private partnership
agreements referred to in section 120
made in 2013/2014
No
All monthly reports tabled in the
council in terms of section 71 during
2014/2015
Yes MFMA Mangaung In Year Reports:
July 2015 - Published on 18/08/2015
August 2015 - Published on 17/09/2015
September 2015 - Published on 13/10/2015
October 2015 - Published on 19/11/2015
November 2015 - Published on 17/12/2015
December 2015 - Published on 15/01/2016
28
Municipal Website: Content and Currency of Material
Documents published on the
Municipality's / Entity's Website Yes / No Publishing Date
January 2016 - Published on 11/02/2016
February 2016 - Published on 11/03/2016
March 2016 - Published on 20/04/2016
April 2016 - Published on 17/05/2016
May 2016 - Published on 20/06/2016
June 2016 - Published on 21/07/2016
WEBSITE VISITOR TRAFFIC AND USAGE STATISTICS - WWW.MANGAUNG.CO.ZA
RANDOM EXTRACT REPORT DURING PERIOD 1 MAY 2016 TO 30 JUNE 2016 (2 Month Report)
It may be noted that approximately 118 GIGABYTES of data has been transferred in a 60 day period.
Hits
Total Hits 1543328
Average Hits per Day 25300.459
Average Hits per Visitor 11.672
Total Reloads 411005
Average Reloads per Day 6737.787
Average Reloads per Visitor 3.108
Cached Requests 221386
Visitors
Total Visitors 132222
Average Visitors per Day 2167.574
Average Time Spent (min:sec) 7:07
Total Unique IPs 41225
Resource Accessed
Total Page Views 704409
Average Page Views per Day 11547.689
Average Page Views per Visitor 5.327
Total File Downloads 142162
29
Average File Downloads per Day 2330.525
Average File Downloads per Visitor 1.075
Total Images 174887
Average Images per Day 2867.000
Average Images per Visitor 1.323
Total Other Resources 782079
Average Other Resources per Day 12820.967
Average Other Resources per Visitor 5.915
Bandwidth
Total Data Transferred 118.571 GB
Average Data Transferred per Day 1.944 GB
Average Data Transferred per Hit 80.560 KB
Average Data Transferred per Visitor 940.319 KB
30
CHAPTER 3 - SERVICE DELIVERY PERFORMANCE
INTRODUCTION
For the year under review the City continues to make significant strides in extending access to water and
sanitation services, facilitated access to housing and social housing opportunities, implemented a number of
projects to support Small Medium and Micro Enterprises (SMME).ensured that indigent households had access
to Free Basic Water, Electricity, Sanitation and Refuse removal services and promoted development through
prompt processing of development applications, provided efficient environmental health and emergency
services and rehabilitated social amenities. Effective maintenance of assets was carried out that included
resurfacing roads, rehabilitation of roads, storm-water canals, catch pits and pedestrian paving, electricity
service infrastructure (network and streetlights)
The City has through its municipal entity; CENTLEC has ensured that all formal households have access to
electricity services.
COMPONENT A: BASIC SERVICES
3.1 WATER PROVISION
Table 3.1: WATER SERVICE DELIVERY LEVEL
Households Percentages
Water: (above min level)
Piped (tap) water inside dwelling/institution
Piped (tap) water inside yard
Piped (tap) water on community stand: distance less than 200m from
dwelling/institution
Minimum Service Level And Above sub-total 243 885 95.2%
Water: (below min level)
Piped (tap) water on community stand: distance between 200m and 500m
from dwelling/institution
0 0%
Piped (tap) water on community stand: distance between 500m and
1000m (1km) from dwelling /institution
0 0%
Piped (tap) water on community stand: distance greater than 1000m
(1km) from dwelling/institution
0 0%
No access to piped (tap) water
31
Households Percentages
Below Minimum Service Level And Above sub-total 12 054 4.8%
Total 255 938 100%
Table 3.2: HOUSEHOLDS-WATER SERVICE DELIVERY LEVELS BELOW THE MINIMUM
Households-Water Service Delivery Levels below the minimum
2014/15 2015/16
Formal and informal residential 169 678 243 885
Total households 169 678 243 885
Proportion of households below minimum service level 1.5% 4.8%
32
Table 3.3: WATER AND SANITATION SERVICE POLICY OBJECTIVES TAKEN FROM IDP
3.3.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Eradicate water
backlog
Ensure that
there is reliable
water supply
from source
Completed
bankable feasibility
study on Gariep
Dam to
Bloemfontein
pipeline
Bankable
Feasibility
Study Reports
Pre-feasibility study in
accordance with the
National Treasury
Guidelines completed.
Bankable feasibility
study 100% completed
100% approved
designs for the pipeline
Not Achieved
To be
accelerated in
the new FY
-95% of Bankable
feasibility study
completed
Number of water
service points
installed for informal
settlement dwellers
within a 200m radius
Completion
certificates
113 communal
standpipes
10 communal standpipes
providing a basic level of
potable water above RDP
standard
2 communal
standpipes providing
a basic level of
potable water above
RDP standard
Standpipes are
installed as per
ward
councillors'
request
-8 communal
standpipes providing
a basic level of
potable water above
RDP standard
100% refurbishment
of Maselspoort Water
Treatment Works
Completion
certificates
N/A 8 pumps installed at
Maselspoort Water
Treatment Works
5 pumps installed at
Maselspoort Water
Treatment Works
To be
accelerated in
next FY
3 pumps installed at
Maselspoort Water
Treatment Works
Kilo metres of water
supply systems
refurbished
Completion
certificates
N/A 4 km of water supply
system refurbished
(Zastron street pipeline
4 km of water supply
system refurbished
none none
Eradicate
sanitation
backlogs
Expand bulk
sanitation
infrastructure
Percentage
expansion of North
Eastern Waste
Water Treatment
Work capacity
Completion
certificates
Phase One
Commissioned
1.1 km outfall sewer
constructed
1.1 km outfall
sewer constructed
none none
Percentage
extension of
Botshabelo of Waste
Water Treatment
Work capacity
Completion
certificates
N/A 100% completion of
Phase 1 to extend the
capacity of Botshabelo of
Waste Water Treatment
Work
Not achieved Review the
implementation
approach irt
Botshabelo
Waste Water
Treatment
Works
-100% completion of
Phase 1 to extend the
capacity of
Botshabelo of Waste
Water
Percentage
extension of Thaba
Nchu Waste Water
Treatment Work
capacity
Completion
certificates
N/A 100% completion of
Phase 1 to extend the
capacity of Thaba Nchu
Waste Water Treatment
Works
100% completion of
Phase 1
None none
33
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
100% Upgrading of
Bloemspruit Waste
Water Treatment
Works
Completion
certificates
Construction of 6
digesters
21.50% %
construction of 6
digesters
Works to be
completed in
first quarter of
2016-17
-78.50% construction
of 6 digesters
Provide formal
stands with
waterborne
sanitation to
eradicate VIP
and Pit toilets
Provide formal
stands with
waterborne
sanitation to
eradicate VIP
and pit toilets
Number of formal
stands with
waterborne
sanitation and to
eradicate VIP and
pit toilets
Completion
certificates
8281 Erven provided
with waterborne
sanitation
6410 VIP toilets
eradicated
4065 VIP toilets
eradicated
Funding
constraints
problematic.
Poor
performing
contractors to
be assisted.
-2345 VIP toilets
eradicated
3.3.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Eradicate
water backlog
Formal domestic
customers
receiving water
services
% of formal erven
with access to
functioning basic
water supply
% of 177 288 total
stands with
access to a
functioning basic
water supply
98% of 176 088 stands
received a functioning
basic water supply
99% of formal ervens
with access to functioning
basic water supply
98.1 of formal
ervens with
access to
functioning basic
water supply
Proceed with VIP
eradication project
and Informal
Settlement
Upgrading
-0.9
compliance with
drinking water
quality standards
A)Regular Monitoring
of drinking water
Blue Drop
System
Compliance.
SANS 241
Compliance
Water Safety
Plan target
85%
100%
100%
Regular monitoring and
samples taken at
strategic points of the
City
100% of SANS
241 compliance.
none none
34
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Reduce level of
Non-Revenue
water and
improve water
security
Replace water
meters and Fire
Hydrants
Number of water
meters &fire hydrants
(replaced &installed)
Number of water
meters &fire
hydrants
(replaced
&installed)
3346 water meters &fire
hydrants (replaced
&installed)
20 000 water meters &fire
hydrants (replaced
&installed)
9 676 water
meters &fire
hydrants
(replaced
&installed)
Continue in
implementing the
water meters and
fire hydrants
replacement
programme
A. Replace meters
older than 12 years.
B. Replace
dysfunctional water
meters.
C. Metering of
unmetered sites in
areas of Mangaung
-10 324 water
meters &fire
hydrants (replaced
&installed)
Pressure
management
Ml/day 7.6 Ml/day Combined 3.5Ml/day
1.38 Ml/day Commission more
PRV in areas of
Mangaung.
-2.12 Ml/day
Active leak control
and leak repairs
Completion
certificate
N/A 1.3Ml/day 1.48 Ml/day None +0.18 Ml/day
Refurbishment of
water supply
systems:
Telemetry and
Scada
Number of new
Pump Station
Monitoring
equipment installed
Number of new
Pump Station
Monitoring
equipment
installed
6 Pump Station
Monitoring equipment
installed
6 Pump Station
Monitoring equipment
installed
11 Pump Station
Monitoring
equipment
installed
None +5 Pump Station
Monitoring
equipment
installed
Number of new Flow
meter Monitoring
equipment installed
Number of new
Flow meter
Monitoring
equipment
installed
6 Flow meter Monitoring
equipment installed
6 Flow meter Monitoring
equipment installed
27 Flow meter
Monitoring
equipment
installed
None +21 Flow meter
Monitoring
equipment
installed
Number of new
applications (MIS)
Number of new
applications
(MIS)
0 0 5 new
applications (MIS)
None +5 new
applications (MIS)
Replacement/Ref
urbishment of
valves in BFN,
Botshabelo and
Thaba Nchu.
Number of valves
replaced/refurbished
Number of valves
replaced/refurbis
hed
271 valves
replaced/refurbished
924 valves
replaced/refurbished
2 334 valves
replaced/refurbish
ed
None +1410 valves
replaced/refurbish
ed
35
Table 3.4: EMPLOYEES: WATER AND SANITATION
Employees: Water &Sanitation
Job Level
Year -1 Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies
(as a % of
total posts)
No. No. No. No. %
0 – 3 5 4 1 20.0%
4 – 6 90 17 73 81.1%
7 – 9 121 31 90 74.4%
10 – 12 294 117 177 60.2%
13 – 15 67 38 29 43.3%
16 – 18 702 475 227 32.3%
Total 1 279 682 597 46.7%
Table 3.5: FINANCIAL PERFORMANCE WATER SERVICES
Financial Performance: Water Services
R'000
Details
30/06/2015 30/06/2016
Actual
Original
Budget
Adjustment
Budget
Actual Variance to
Adjustment
Budget
Total
Operational
Revenue -740,333,009 -975,462,824 -762,953,572 -724,220,325 -38,733,247
Expenditure:
Employees 71,602,601 77,440,253 91,751,454 93,515,672 -1,764,218
Repairs and
Maintenance 44,399,494 63,674,127 77,521,042 149,401,315 -71,880,273
Other 668,421,453 717,589,831 691,806,556 679,295,875 12,510,681
Total
Operational
Expenditure 784,423,548 858,704,211 861,079,052 922,212,862 -61,133,810
Net
Operational
Expenditure 44,090,539 -116,758,613 98,125,480 197,992,537 -99,867,057
36
Table 3.6: CAPITAL EXPENDITURE: WATER SERVICES
Capital Projects
Year 2015/2016
Budget Adjustment
Budget
Actual
Expenditure
Variance
from
adjustment
budget
Total All 255,062,870 311,033,478 266,813,910 44,219,568
Project A- Water Networks to stands 0 4,154,981 3,657,036. 497,945
Project B- Botshabelo and Thaba Nchu
Internal Bulk 17,062,870 22,031,891 16,473,141 5,558,750
Project C- New 45 ML Longridge Supply Line
8.3 km 1,000,000 5,058,976 4,887,567 171,409
Project D –Replace pumps Masselspoort 2,000,000 10,120,692 10,389,313 -268,621
Project E- Refurbishment of water systems 50,000,000 58,006,223 58,259,211 -252,988
Figure 3.1 below shows the City trends in relation to Non-Revenue (NRW) for the past four financial years. The
NRW for the financial year 2014-2015 has increased from 31% to 40%. This situation is abnormal. The cause
of this is that the monthly water sales report which was drawn from financial records showed that the municipality
has been selling more water than it has purchased. This prompted Engineering Services Directorate to review
water balance calculation which reflected less percentage in the two financial years (2012-2013 and 2013-
2014). In the 2014-2015 financial year, the annual water sales records which were drawn with high level
confidence indicate that the City’s NRW is at 40%. The NRW for financial year 2015-2016 has increased by 1%
(i.e. from 40% to 41%).
Figure 3.1 MANGAUNG CITY TRENDS IN RELATION TO NON-REVENUE WATER
43 %
35 %31 %
[]% 41 %
- 5
10 15 20 25 30 35 40 45 50
2011-2012 2012-2013 2013-2014 2014-2015 2015-2016
% o
f N
RW
Financial Year
Non-Revenue Water by %
% NRW
37
The net effect indicates that the city continues to register encouraging progress in extending water services to
its citizens. Attendant bulk water infrastructure such as main water supply lines have been extended to informal
settlements through installing 2 communal water stand pipes. In pursuit of reducing non-revenue water:
- A water demand management project was implemented and its set milestones were achieved.
- The city has refurbished 2 km of water supply system in Zastron Street
- The city has constructed and completed 100% civil works the outfall sewer which is an North Eastern
Waste Water Treatment Work capacity that will benefit + 26 500 households at the Eastern part of
Bloemfontein, Vista Park and Hillside View
- 4065 VIP and Bucket Toilets were upgraded into Water Borne Sanitation
Below shows that the water purchased from BloemWater for the financial year 2014-2015 has decreased from
86.6 to 72.31 million m3/annum. In financial terms, the municipality saved a total of R13 million rand. The system
input volume (SIV) reduction was caused by the following activities;
Active leak detection and repairs programme
Implementation of pressure management programme
Consumer education and awareness campaign
Figure 3.2 MANGAUNG CITY TRENDSIN RELATION TO SYSTEM/INPUTS VOLUME REDUCTION
3.2 WASTE WATER (SANITATION)
The municipality has ensured that additional 4065 additional have access to sanitation services for the period
under review. According to Community Survey 2016 the city has 185 311 households with improved
sanitation. There is still however 70 627 households with below minimum service level.
80,32 84,67 86,57 82,7772,31
102030405060708090
100
2011-2012 2012-2013 2013-2014 2014-2015 2015-2016
SIV
(m
illio
n m
3/a
nn
um
)
Financial Year
System Input Volume
SIV
38
Table 3.7: SANITATION DELIVERY LEVELS
SANITATION SERVICE DELIVERY LEVELS 2015/16
Households Percentages
Sanitation/sewerage: (above min level)
Flush toilet (connected to sewerage system)
Flush toilet (with septic tank) 0 0
Chemical toilet 0 0
Minimum Service Level And Above sub-total 185 311 72.4%
Sanitation/sewerage: (below min level)
Pit toilet with ventilation (VIP) 70 627 27.6%
Pit toilet without ventilation
Bucket toilet
None
Other
Below Minimum Service Level And Above sub-total 70 627 27.6%
Total 255 938 100%
Table 3.8: HOUSEHOLDS – SANITATION SERVICE LEVELS BELOW THE MINIMUM
2015/16
Formal and informal residential 185 311
Total households 185 311
Households below minimum service levels 70 627
Proportion of households below minimum service level 255 938
39
Table 3.9: FINANCIAL PERFORMANCE SANITATION SERVICES
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget
Actual Variance to
Adjustment
Budget
Total Operational
Revenue -363,835,777 -355,690,253 -317,531,647 -346,064,495 28,532,848
Expenditure:
Employees 82,731,756 84,514,732 83,845,950 81,084,084 2,761,866
Repairs and
Maintenance 13,163,134 22,742,027 23,377,711 71,722,269 -48,344,558
Other 198,125,474 159,618,424 156,484,599 122,087,171 34,397,428
Total Operational
Expenditure 294,020,364 266,875,183 263,708,260 274,893,524 -11,185,264
Net Operational
Expenditure -69,815,413 -88,815,070 -538,23,387 -71,170,971 17,347,584
Table 3.10: CAPITAL EXPENDITURE SANITATION SERVICES
Capital Projects Year 2015/2016
Budget Adjustment
Budget
Actual
Expenditure
Variance from
adjustment
budget
Total All 456,136,576 492,123,035 485,964,839 6,158,196
Project A-North Eastern WWTW
(15ML/Day) and 1 8Km 52,783,461 29,599,410 28,274,822 324,598
Project B-Addition of 10ML to SterkWater
WWTW 30,000,000 10,470,892 10,558,825 -87,933
Project C- Refurbishment of Bloemspruit 35,000,000 64,873,000 69,843,602 -4,970,602
40
3.3 WASTE MANAGEMENT
211 461 households access to weekly waste removal services, whilst rural areas, farms, small holdings and
some informal areas do not have access to the service due to, amongst other, accessibility and distance. Some
informal settlements already receive a weekly door to door refuse collection service. Weekly backlogs are
experienced due to low availability of fleet and equipment and that the SMMEs that have been appointed to
assist as and when necessary do not all have the necessary capacity. Illegal dumping is rampant as a result
of the aforementioned. A programme called ‘Woza Friday’ for the removal of illegal dumps was drawn to ensure
that priority dumping areas are attended from ward to ward specifically on Fridays and this has assisted in
reducing the illegal dumps backlog. Although the programme was hampered by often breakdown of equipment
about 51 clean -ups were conducted. 30 Education and awareness sessions on waste management were also
undertaken in the year under review. Another challenge is the shortage of supervisory and skilled personnel.
The revision of the 2011 Integrated Waste Management Plan (IWMP) was also completed in the year under
review. Currently solid waste disposal at landfill is the most common form of solid waste management in
Mangaung and two external audits and one internal audit were performed as part of the permit conditions for
these landfills. The municipality has been selected and participating in a ‘Waste Management Flagship
Programme’ which is an initiative of the National Department of Environmental Affairs (DEA) in conjunction with
the German Federal Enterprise for International Cooperation (GIZ). This project will assist the municipality to
put the IWMP into practice as it is aimed at the development of a strategy and project preparation for the
diversion of solid waste away from landfills and GHG emission mitigation. Three buy-back centres (one in each
region) have been donated to the municipality by the Department of Environmental Affairs during the report
period. The Waste Transfer Station was about 91% complete by the end of financial year. About 208 294
households had access to a weekly door to door refuse removal in the report period although due to vehicle
challenges these households often experienced a service backlog which would be cleared within 7 days from
the scheduled collection day. 37 953 of these households were serviced by the SMMEs. More than 80%of
informal settlements also had access to refuse removal and some of these had access to the weekly service.
Table 3.11: SOLID WASTE SERVICE DELIVERY LEVELS
Solid Waste Service Delivery Levels 2015/16
Households Percentages
Solid Waste Removal: (minimum level)
Removed by local authority/private company at least once a week
Minimum Service Level And Above sub-total 211 465 82.6%
Solid Waste Removal: (below minimum level)
Removed by local authority/private company less often
41
Solid Waste Service Delivery Levels 2015/16
Households Percentages
Communal refuse dump
Own refuse dump
No rubbish disposal
Other
Below Minimum Service Level And Above sub-total 44 473 17.4%
Total 255 938 100%
Table 3.12: HOUSEHOLDS – SOLID WASTE SERVICES DELIVERY LEVELS
Households-Solid Waste Services Delivery Levels below the minimum 2015/16
Formal residential 211 465
Total households 255 938
Households below minimum service levels 44 473
Proportion of households below minimum service level 17.4%
Informal residential
Total households 255 938
Households below minimum service levels 44 473
Proportion of households below minimum service level 17.4%
42
Table 3.13: WASTE MANAGEMENT SERVICES POLICY OBJECTIVES TAKEN FROM IDP
3.13.1 STRATEGIC
IDP
Objective
Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/2016
Corrective
Action
Variance
Accelerate
waste
removal
Provide households
with weekly kerb-side
waste removal services
in formal areas
Number of households
with weekly kerb-side
waste removal services in
formal areas
Collection schedule 165 464
households with
weekly kerbside
waste removal
service
178 367
households
with weekly
kerbside
waste
removal
service
211 465
households with
weekly kerbside
waste removal
service
N/A +33 098
3.13.2 OPERATIONAL IDP
Objective
Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/2016
Corrective
Action
Variance
Accelerate
waste
removal
Informal settlement
dwellings with access to
refuse removal
% of informal settlements
with access to refuse
removal
% of informal
settlements
26688 households
had access to refuse
removal
80% of informal
settlements have
access to refuse
removal
80% informal
settlements have
access to refuse
removal
N/A N/A
Reduction of weekly kerb
side refuse removal
backlog to consumer
units within 14 days
% reduction of weekly
backlog within 07 days after
scheduled collection day
% waste removal
backlog eradicated
100% waste removal
backlog eradicated
in consumer units
within 07 days after
scheduled collection
day
100% waste
removal backlog
eradicated in
consumer units
within 07 days
after scheduled
collection day
100% waste
removal backlog
eradicated in
consumer units
within 07 days
after scheduled
collection day
N/A N/A
Provide Education and
awareness on Waste
Management issues
Number of education and
awareness sessions
undertaken
Number of education
and awareness
sessions undertaken
36 Education and
awareness sessions
undertaken
36 Education
and awareness
sessions
undertaken
30 Education and
awareness
sessions
undertaken
-6
43
IDP
Objective
Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/2016
Corrective
Action
Variance
Organise clean- up
campaigns
Number of clean-up
campaigns conducted
Number of clean-up
campaigns conducted
21 clean up
campaigns
conducted
4 major clean-up
campaigns
conducted
4 major clean-ups
and 47 normal
clean -ups
N/A N/A
Permitted Landfill sites
comply with legislation
Audits are performed at
landfill sites(internal and
external)
Audit reports 1 internal audit
performed
2 internal and 1
external audit
performed
2 Internal and 1
External Audit was
done
N/A N/A
No of permitted landfill sites
maintained and upgraded
monthly progress
reports
3 permitted landfill
sites upgraded and
maintained
3 permitted
landfill sites
upgraded and
maintained
2 landfill sites
upgraded and
maintained
Re-advertise for
the Refurbishment
and Upgrading of
Botshabelo
Landfill Site and
appoint a
Contractor
-1
Establishment of a new
regional landfill site
Quarterly progress
reports
Process of
acquisition of land
started
Establishment of
a regional landfill
site process
continuing
none Human
Settlements
Directorate will be
requested to
assist in speeding
up the process
Establishment
of a regional
landfill site
process
continuing
Transfer station developed
in Thaba Nchu
Monthly progress
reports
60% of the first
phase finished
Transfer station
completed
Transfer station is
±91% complete
To complete the
transfer station by
30 July 2016
9% transfer
station
complete
Development of waste drop-
off areas in Mangaung
Quarterly progress
reports
N/A Designs for the
drop-off areas
completed
Request was made
to Planning for
sites to develop
waste drop-off
areas
To make another
request to
Planning
directorate to
make land
available for the
drop off areas
Designs for
the drop-off
areas
completed
44
Table 3.16: CAPITAL EXPENDITURE: WASTE MANAGEMENT SERVICES
Table 3.14: EMPLOYEES: SOLID WASTE MANAGEMENT SERVICES
Employees: Solid Waste Management Services
Year -1
(2014/15)
Employees: Solid Waste Management Services
Job Level
Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies
(as a % of
total posts)
No. No. No. No. %
0 - 3 3 2 1 33.3%
4 - 6 37 13 24 64.9%
7 - 9 45 15 30 66.7%
10 - 12 292 84 208 71.2%
13 - 15 214 72 142 66.4%
16 - 18 1 088 920 168 15.4%
Total 1 679 1 106 573 34.1%
Table 3.15: FINANCIAL PERFOMANCE: SOLID WASTE MANAGEMENT SERVICE
Financial Performance: Solid Waste Management Services
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue -230,159,643 -265,979,913 -262,327,671 -236,035,760 -26,291,911
Expenditure:
Employees 81,549,064 122,706,584 120,020,760 128,243,822 -8,223,062
Repairs and
Maintenance 619,627 11,091,087 2,484,717 1,841,884 642,833
Other 113,474,148 97,926,143 110,935,332 66,251,318 44,684,014
Total Operational
Expenditure 195,642,839 231,723,814 233,440,809 196,337,024 37,103,785
Net Operational
Expenditure -34,516,805 -34,256,099 -28,886,862 -39,698,736 10,811,874
45
Capital projects Year 2015/2016
Budget Adjustment
budget
Actual
Expenditure
Variance
from
adjustment
budget
Total all 12,800,000 12,800,000 9,595,589 3,204,411
Upgrading and construction of Northern
Land 1500,000 1,512,987 - 12,987
Upgrading and construction of Southern
Land 4,200,000 3,784,8080 415,192
Upgrading and rehabilitations of
Botshabelo *800,000 347,220 452,780
Development of transfer station in Thaba
Nchu 5,000,000 3,784,808 1,036,437
3.4 ROADS AND STORM WATER
Roads and Storm water infrastructure constitutes an integral part of the country’s economy. Chapter 7 of the
Constitution of the Republic of South Africa provides a directive to municipalities to provide services to the
communities in a sustainable manner. It is also imperative that those services are kept in satisfactory condition
at all times. To this end, the Mangaung Metropolitan Municipality has heeded this call by ensuring that:
Table 3.17: GRAVEL ROAD INFRASTRUCTURE
Gravel Road Infrastructure
Kilometres
Total gravel
roads
New gravel
roads
constructed
Gravel roads
upgraded to tar
Gravel roads
graded /maintained
Year - 2012/2013 1206 25 14 20
Year - 2013/2014 1231 20 4.67 20
Year - 2014/2015 1251 20 3.9 20
Year - 2015/2016 1271 5,489km 5,29 km
46
Table 3.18: TARRED ROADS INFRASTRUCTURE
Tarred Road Infrastructure
Kilometres
Total tarred
roads
New tar
roads
Existing tar
roads heavy
rehabilitated
Existing tar
roads re-
sealed
Tar roads
maintaine
d
Year - 2012/2013 1435 0
Not reported at
that stage 20 20
Year - 2013/2014 1435 4.67
Not reported at
that stage 55 20
Year - 2014/2015 1439.67 4.53
Not reported at
that stage 36 20
Year - 2015/2016 1444.2 5,29 6.2 14.428 20
Storm water Infrastructure
Kilometres
Total storm water
measures
New storm-water
measures
Storm-water measures
upgraded
Year - 2012/2013 166 25 14
Year - 2013/2014 191 4.67 4.67
Year - 2014/2015 195.67 1.27 1.27
Year - 2015/2016 196.94 6.114 6.114
47
Table 3.19: ROADS AND STORM WATER SERVICE POLICY OBJECTIVES
3.19.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target 2015/16 Actual Performance
2015/16
Corrective
Action
Variance
Address roads
conditions
Tar gravel
roads
Paving of
gravel roads
Km of 7m wide
gravel roads
tarred
Completion
certificates for
gravel roads
tarred
5.8km 8 km of Gravel Road
tarred
5,29 km of Gravel
Road tarred
N/A -2.71 km of Gravel
Road tarred
Km 7m wide gravel
roads paved
Completion
certificates for
gravel roads paved
3.719 km derived from
2nd and 3rd Q
3 km of gravel road
paved
5,489 km of gravel
road paved
N/A +2.489
Tarred + Paved
=10.7
Heavy
rehabilitation of
existing main tar
roads
Km of 7m wide
roads rehabilitated
Completion
certificates for
roads rehabilitated
36.16 km obtained from
all Quarters of the last FY
4 km of roads resurfaced 6,2 km of roads
resurfaced
N/A +2.2 km of roads
resurfaced
Resurfaced
(resealed) roads
Km of 7m wide
roads resurfaced
Completion
certificates for
roads resurfaced
(resealed)
36.16 km obtained from
all Quarters of the last FY
14km Resurfaced
(resealed) roads
14,428 km
Resurfaced
(resealed) roads
N/A +0.428km
Resurfaced
(resealed) roads
Install storm-
water drainage
Length (Km) of
Storm-water
drainage
installed
Completion
certificates for
storm-water
drainage
installed
1.27 km obtained from
all Quarters of the last
FY
7km of storm water
drainage installed
6,114 km of storm
water drainage
installed
N/A -0.886 km of storm
water drainage
installed
48
Table 3.20: EMPLOYEES: ROAD AND STORM WATER SERVICES
Employees: Roads & Storm-water
Job Level
Year -1 Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancie
s (as a %
of total
posts)
No. No. No. No. %
0 – 3 4 4 0 0.0%
4 – 6 47 14 33 70.2%
7 – 9 71 31 40 56.3%
10 - 12 125 50 75 60.0%
13 - 15 87 9 78 89.7%
16 – 18 348 194 154 44.3%
Total 682 302 380 55.7%
Table 3.21: FINANCIAL PERFORMANCE: ROAD AND STORM WATER SERVICE
Details 30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue 0 -664,586 -664,586 - -664,586
Expenditure:
Employees 61,380,300 97,598,632 63,124,542 61,899,266 1,225,276
Repairs and
Maintenance 74,208,687 83,642,721 122,047,991 107,477,575 14,570,416
Other -419,068,505 197,144,093 188,596,028 586,386,339 -397,790,311
Total Operational
Expenditure -283,479,519 378,385,446 373,768,561 755,763,180 381,994,619
Net Operational
Expenditure -283,479,519 377,720,860 373,103,975 755,763,180 -382,659,205
49
Table 3.22: CAPITAL EXPENDITURE: ROADS AND STORM WATER SERVICE
Capital Projects
Year 2015/2016
Budget Adjustment
Budget
Actual
Expenditure
Variance from
adjustment
Budget
Total All 281,050,107 333,623,525 308,199,393 25,424,132
Upgrading of streets and Storm-
Water: Batho Learnership 2,500,000 20,142,568 20,142,409 159
Resealing of Streets 14,412,979 45,089,323 36,977,619 8,111,704
Heavy Rehabilitation of Kenneth
Kaunda 10,000,000 17,383,686 17,383,685 1
Maphisa Upgrading - 26,128,000 17,680,926 8,447,074
3.5 ELECTRICITY PROVISION
Mangaung is committed to achieving its mandate of providing access to electricity to the residents of the
Municipality and the Southern Free State Municipalities at large.
The City is providing electricity services to 193 8589 formal households;
Five hundred and thirty seven (537) households were provided with electricity connections;
15 927 households provided with Free Basic Electricity;
2054 smart street lights have been installed to provide reliable public lighting;
132/11kV 20 MVA Groenvlei Distribution Centre is 100% complete;
36 high mast lights have been erected and 26 of which have been commissioned;
Table 3.23: ELECTRICITY SERVICE DELIVERY LEVELS
ELECTRICITY SERVICE DELIVERY LEVELS 2015/16
Households Percentages
Energy: (above minimum level)
Electricity – Non FBE
Minimum Service Level And Above sub-total 245,339 95.8%
Energy: (below minimum level)
Other - FBE
Below Minimum Service Level And Above sub-total 10,599 4.2%
Total 255,938 100%
50
Table 3.24: HOUSEHOLDS – ELECTRICITY SERVICE DELIVERY LEVELS BELOW THE MINIMUM:
NON – BELOW THE MINIMUM
2015/16
Formal residential
Total households 255,938
Households below minimum service levels 10,599
Proportion of households below minimum service level
Informal residential
Total households 255,938
Households below minimum service levels 10,599
Proportion of households below minimum service level 4.2%
Table 3.25: TARIFF GROUPS
Tariff Group: 2015-2016
(Baseline)
Number of Consumers
MMM Kopanong Naledi Mohokare Mantsopa Total
INCLINING BLOCK 188 626 10 816 5 442 5 229 2 208 212 321
FLAT RATE BUSINESS 4 154 664 262 218 9 5 307
BULK RESELL 2 31 31
BULK RESELL 3 179 179
BULK RESIDENTIAL 2
SFS 1 1
BULK RESIDENTIAL 3
SFS 2 5 7
CENTLEC
DEPARTMENTAL TOU 2 2
COMFLEX - SINGLE
PHASE 7 7
COMFLEX - THREE
PHASE 103 103
COMFLEX SFS –
SINGLE PHASE
COMFLEX SFS –
THREE PHASE 9 1 10
51
Tariff Group: 2015-2016
(Baseline)
Number of Consumers
MMM Kopanong Naledi Mohokare Mantsopa Total
ELECFLEX 1 4 4
ELECFLEX 2 162 162
ELECFLEX 2 SFS 4 4
ELECFLEX 3 496 496
ELECFLEX 3 SFS 17 3 9 29
HOMEFLEX - SINGLE
PHASE 3 3
HOMEFLEX - THREE
PHASE 84 84
HOMEFLEX - THREE
PHASE SFS 8 8
SPORT STADIUMS 7 7
SPORT STADIUMS SFS 2 2
TOTAL
193 858 11 522 5 714 5 456 2 217
218 767
52
Table 3.26: ELETRICITY SERVICE POLICY OBJECTIVES TAKEN FROM IDP
3.26.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Address
electricity
backlog
Formal
households
with access
to basic
electricity
Number of formal
households with
access to basic
electricity
Completion
Certificate
1264 Households + 200 000 formal
household access
basic electricity
193 858 formal
household access
basic electricity
Accelerate basic
electricity services
-6142 formal
household
access basic
electricity
Provide new
households
with
electricity
connections
Number of new
households
provided with
electricity
connections
Completion
Certificate
545 households provided
with electricity
connections
1866 new
households provided
with electricity
connections
537 New
households
connections
Upon the
confirmation by the
applicant that the
houses are
completed,
CENTLEC will
facilitate the
connections.
-1329 New
households
connections
Provide
households
with access
to free basic
electricity
Number of
households
provided with
access to free
basic electricity
Completion
Certificate
+ 18 000 households
provided with access to
free basic electricity
35 000 households
provided with access
to free basic
electricity
15 927 households
provided with
access to free
basic electricity
Engage with
Eskom where
there are dual
electricity supply
arrangements in
Thaba Nchu
-19073
households
provided with
access to free
basic electricity
Provide a
reliable
supply of
electricity
100% Completed
132/11kV 20MVA
Fichardtpark
Distribution Centre
Completion
Certificates
N/A 100% completed
distribution Centre
commissioned.
. Not achieved Speed up the
internal processes
such that the
consultant can be
appointed.
The tender has
been advertised
and has served in
the evaluation
committee
100%
Completed
132/11kV
20MVA
Fichardtpark
Distribution
Centre
100% Completed
132/11kV 30MVA
Cecilia Distribution
Centre
Completion
Certificates
N/A 100% completed
distribution Centre
commissioned.
Not achieved
.
Accelerate
implementation in
the next Financial
Year
- 50%
compl
ete
53
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
132 KV Northern
Ring from Noordstad
to Harvard DC
Completion
Certificates
N/A 100% completed 132
KV Northern Ring from
Noordstad to Harvard
DC distribution Centre
commissioned.
Not Achieved
Accelerate
implementation in
new FY
-100%
completed 132
KV Northern
Ring from
Noordstad to
Harvard DC
distribution
Centre
commissioned
Elite Substation
(Airport
Development Node)
Completion
Certificates
N/A 100% completed
distribution Centre
commissioned. Not achieved
Accelerate
implementation in
the new FY after
obtaining approval
on the location of
the sub-station
and having acquird
land
- 100%
completed Elite
Sub-station
distribution
Centre
commissioned.
3.26.2 OPERATIONAL IDP Objective Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target 2015/16 Actual
Performance
2015/16
Corrective Action Variance
Address
electricity
backlog
Install high
mast lights in
informal
settlements
High mast lights
installed in informal
settlements
Completed high mast
light by 30 June 2016
28 erected and
commissioned high mast
lights within Mangaung
by 30 June 2016
34 High Masts
have been erected
and 26 have been
commissioned.
Follow up with Eskom
on electricity
connection to
outstanding high
masts.
-2 high mast
lights to be
commissioned
Ensure
reliability of
electricity
supply
Ensure 100%
management of
customers’ essential
loads on a
continuous basis
throughout 2015/16
% of customers’
essential loads
managed on a
continuous basis
throughout 2015/16
2014/15 reports Ensure 100%
management of
customers’ essential
loads on a continuous
basis throughout 2015/16
Target is 100%
achieved.
100% achieved. None
Provide access
to electricity
Provide 100%
access to
electricity
Convert and / or
replace 5 000
electricity meters in
Botshabelo by June
2016.
Number of conversions
and / or replacement
electricity meters made
in Botshabelo by 30
June 2016
500 meters
converted and / or
replaced by 2014/15
financial year.
Convert and / or replace
5 000 electricity meters in
Botshabelo by June
2016.
145 New
Connections and
1968 Conversions
, Target has not been
reached
-3032 electricity
meters
converted
54
Table 3.27: EMPLOYEES: ELECTRICITY SERVICES
Employees: Centlec (Seconded Only)
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a
% of total
posts)
No. No. No. No. %
0 – 3 0 23 2 18 22%
4 – 6 22 179 14 113 37%
7 – 9 98 502 73 309 34.4%
10 - 12 35 217 59 156 28.1%
13 - 15 79 287 30 173 40%
16 - 18 103 736 79 670 9%
Total 337 1944 257 1439
Table 3.28: CAPITAL EXPENDITURE: ELECTRICITY SERVICES
Capital projects
2015/16
Budget Adjustment
budget
Actual
Expenditure
Variance from
adjustment
budget
Total all 60,204,119 70,697,563 70,697,330 0
ELECTRIFICATION CONNECTIONS
DME 26,315,789 26,315,789 26,315,789 0
Fichardpark DC: 132Kv/11/Kv 20MA
DC 13,000,000 0 0 0
Groenvlei DC: 132kv/11kv 30MVA 7,888,330 6,098,514 6,098,514 0
Cecelia DC: 132Kv/11kv 30MVA DC 13,000,000 38,283,260 38,283,027 0
3.6 HOUSING
For the year under review, the City has succeeded in facilitating housing opportunities in partnership with the
provincial department of Human Settlement. Importantly, the City has ensured that seven (7) informal
55
settlements were upgraded and benefitting 3143 households.. The City is also progressing toward the following
targets:
375 residential sites disputes resolved
2982 Title deeds were transferred
3347 Title deeds issued
Rental schemes were upgraded using the Youth Enterprise Development Programme
Table 3.29: HOUSING
Formal
dwelling
Informal
dwelling
Traditional
dwelling
Other Grand Total
Formal residential 223,108 29,990 1867 964 255,929
Source Community Survey 2016, STATSSA
56
Table 3.30: HOUSING SERVICE POLICY OBJECTIVES TAKEN FROM IDP
3.30.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Address
housing
backlog
Number of
informal
settlements
upgraded
Completion
certificates
Happy letters
N/A 2 informal
settlements
upgraded
(Magashule
Square and
Botshabelo
Section R)
7 (seven) Informal
Settlements upgraded
with installation of
services (MK Square-
482); Sonderwater 1-
92; Sonderwater 2 -
130 Kgotsong-1448;
Bloemside 4 - 581;
Bloemside 2- 271;
Bloemside 3- 139;
Three (3) Informal
Settlements upgraded
only leve1 (designs)-
Magashule-48; Section
R-2530; Namibia
27921 and 2777-52
None none
Number of Title
Deeds transferred
to eligible
beneficiaries
Number of Title
Deeds
transferred
1230 Title Deeds
transferred
2 000 Title Deeds
transferred
2965 Title Deeds
transferred
+965 Title
Deeds
transferred
Acquisition of
land for Human
Settlements
Construction of
new affordable
rental/social
housing units
Number of new
affordable
rental/social
housing units
constructed
Rental/Social
housing units
constructed
N/A 40 units – White
City
1 000 Social &
CRU
0
0
There was a delay in the
finalisation of the contract between
the contractor and the municipality
and this has led to a project not
being completed on the set time.
The contract has now been
finalised and the contractor is
granted two months to recover
time lost.
Contractors moved out of sites due
to lack of funding. The department
will engage the DHS to unlock the
challenges facing the Social and
CRU projects
-40
-1000
57
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Promotion of
mixed use
development in
Estoire
Redesign of
Estoire layout plan
New layout plan
promoting
mixed-use in
Estoire
N/A 1 layout plan 0 Bid withdrawn subject to Council
resolution
-1 layout plan
Refurbishment of
rental stock
Refurbishing of
rental schemes
Completion
certificates
N/A 100%
refurbishment of
scheme
100% Complete
refurbishment
None none
Acquisition of
land for burial
space
Hectares of land
acquired
Number of
hectares
acquired
N/A 203 hectares 203,3136 hectares
acquired
none +0.3136
3.30.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Address
housing
backlog
Provide housing
opportunities
Number of housing
opportunities
provided
-Permission to
occupy Issued
-Title deeds issued
2502 Title deeds issued 4000 668 Permission to
occupy Issued
3347 Title deeds
issued
None +3332 Permission
to occupy Issued
+3347 Title deeds
issued
Completion of
housing Subsidy
forms for low
cost houses and
inspection of
houses of
approved
beneficiaries
Number of subsidy
application forms
submitted to DHS
and number of
houses inspected
and approved
-Forms submitted
-Units built
N/A 3000 1664 subsidy
application forms
submitted to DHS
109 Units built
Fast –track the
subsidy application
forms
-1336 subsidy
application forms
submitted to DHS
+109 Units built
Consumer
education
provided to
Households in
Informal
Settlements and
Beneficiary
Management
Consumer education
provided to
Households in
Informal Settlements
and Beneficiary
Management s
-Number of
workshop held
- no. of people
educated
2283 48 workshop held
4000 people
educated
55 workshop held
5135 people
educated
None
none
+7 workshop held
+1135 people
educated
58
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Incremental
Upgrade
informal
settlements
Number of informal
settlements with
upgrading plans
Land development
process(including
security of tenure)
Infrastructure
Top Structure
Socio Economic
Amenities
Services plans
developed and
approved
N/A 5 Services plans
developed and
approved
10 Services plans
developed and
approved
None +5 Services plans
developed and
approved
Number of sites
serviced
Services provided N/A 2000 sites serviced 5773 sites
serviced
None +3773 sites
serviced
Number of informal
settlements upgraded
(services provided):
In Situ
Informal settlement
upgraded in Situ
N/A 3 Informal
settlement
upgraded in Situ
10 Informal
settlement
upgraded in Situ
None +7 Informal
settlement
upgraded in Situ
Households
relocated from
floodplains and
other servitudes
Number of
households relocated
from floodplains and
other servitudes
All households
affected
48 households relocated
from floodplains and
other servitudes
100 households
relocated from
floodplains and
other servitudes
0 households
relocated from
floodplains and
other servitudes
Awaiting Planning
to identify suitable
land for relocation.
-100 households
relocated from
floodplains and
other servitudes
Households
allocated
affordable
rental/social
housing units
Households allocated
affordable
rental/social housing
units
Rental Social
Housing Tenants
Registered
245 500 Households
allocated affordable
rental/social
housing units
46 Households
allocated
affordable
rental/social
housing units
111 Households
allocated
affordable
rental/social
housing units at
Hillside View
Current rental
stock fully rented
Engage with the
PDoHS to unlock
all the Hillside
View project which
is currently at a
standstill due to
funding constraints
-454 Households
allocated affordable
rental/social
housing units
+111 Households
allocated affordable
rental/social
housing units at
Hillside View
Households
allocated
affordable GAP
housing
Number of
households allocated
affordable GAP
housing
households
allocated affordable
GAP housing
N/A 30 households
allocated affordable
GAP housing
0 households
allocated
affordable GAP
housing
The bid did not
receive response
at closing of the
advertisement.
Request for re
advertisement was
submitted
-30 households
allocated affordable
GAP housing
59
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Consumer
education
provided to
Households in
Rental housing
Consumer education
provided to
Households in
Rental housing
households provided
consumer education
in Rental housing
2524 1000 households
provided consumer
education in Rental
housing
1235 households
provided
consumer
education in
Rental housing
None +235 households
provided consumer
education in Rental
housing
Consumer
education
provided to
Households in
GAP housing
Number of
households provided
consumer education
in GAP housing
households provided
with consumer
education in GAP
housing
2283 500 households
provided with
consumer
education in GAP
housing
1235 households
provided with
consumer
education in GAP
housing
None +735 households
provided with
consumer
education in GAP
housing
Consumer
education
provided to
Households in
Social housing
Number of
households provided
consumer education
in Social housing
households provided
consumer education
in Social housing
339 800 households
provided consumer
education in Social
housing
90 households
provided
consumer
education in
Social housing
Develop a new
strategy in
conducting
consumer
education in the
social housing
market.
-710 households
provided consumer
education in Social
housing
Stakeholder
management
and engagement
in the City rental
housing market
to improve rent
collection
Number of meetings
and engagement held
with different
stakeholders in the
City rental housing
market
meetings and
engagement with
different
stakeholders in the
City rental housing
market
3 5 meetings and
engagement with
different
stakeholders in the
City rental housing
market
4 meetings and
engagement with
different
stakeholders in
the City rental
housing market
Proper scheduling
of engaging
stakeholders
-1 meeting and
engagement with
different
stakeholders in the
City rental housing
market
Promote Inner
City High Density
mixed use
development
Number of Inner City
High Density mixed
use developments
promoted
Inner City High
Density mixed use
developments
promoted
N/A 1 Inner City High
Density mixed use
developments
promoted
Bid send for
adjudication but
not yet finalised
Follow up with
Adjudication
Committee
-1 Inner City High
Density mixed use
developments
promoted
Promote hostel
redevelopment
initiatives
Number of hostel
redevelopment
initiatives promoted
Hostel
redevelopment
initiatives promoted
3 1 Hostel
redevelopment
initiatives promoted
0 Unlock challenges
facing the
completion of the
project
-1 Hostel
redevelopment
initiatives promoted
Review Strategic
Human
Settlements
Policy
documents
Number of Strategic
Human Settlements
Policy documents
reviewed
Reviewed Strategic
Human Settlements
Policy documents
N/A 1 Strategic Human
Settlements Policy
documents
reviewed
1 Final draft None none
60
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Implementatio
n of Seven
Land Parcels
Mixed use land
development
100% implementation
designs of Cecelia
Park
Formalization of
Cecelia Park
17.50% 100% completion
of town planning
and approved SG
plans
100% compilation
of information for
township
establishment
Public
participation
processes 100%
complete
Urban designs
and layout
designs
outstanding
Accelerate the
completion of
Urban designs
and layout
designs
Completion and
submission of
Urban designs and
layout designs
100% implementation
designs of Brandkop
702
Formalization of
Brandkop 702
16.25 100% completion
of town planning
and approved SG
Plans
Lodged township
establishment
application
Township
establishment to
be completed
General plan
outstanding
80% development of
Hillside View phase1
Development of
Hillside View
18% 100% 55% completion
of Hillside View
phase1
Engage with the
PDoHS to unlock
the challenges
facing the project
-25% completion of
Hillside View
phase1
Revenue
Enhancement
Review of
revenue
agreements
Percentage review of
sundry and
commercial property
lease agreements
Lease agreements
reviewed
Number of lease
agreements reviewed
80 contracts 44 contracts Engage legal unit
to speed-up
finalisation of
contracts
-36% contracts
Percentage Increase
rental housing
revenue collection
collection of rental
housing revenue
33.75% 50% Increase in
rental housing
revenue collection
39% Increase in
rental housing
revenue collection
Intense collection
measures will be
taken including
evictions of
defaulters with
assistance from
legal division
-11% Increase in
rental housing
revenue collection
Sale of Land Quarterly
Advertisement of land
for sale
Erven /Land parcels
advertised
N/A 50Erven /Land
parcels advertised
0 Erven /Land
parcels
advertised
Engaged supply
chain on
disagreements
relating to
specifications
-50 Erven /Land
parcels advertised
61
Table 3.31: EMPLOYEES: HOUSING SERVICES
Job Level Year 2015/16
posts
Employees Vacancies
(fulltime
equivalents
VACANCIES ?% OF
TOTAL
0-3 8 4 4 50%
4-6 68 40 28 41%
7-9 50 28 22 44%
10-12 78 41 37 47%
13-15 11 4 7 64%
16-18 61 32 29 48%
Total 276 149 127 46%
Table 3.32: FINANCIAL PERFORMANCE: HOUSING SERVICE
Financial Performance: Housing Services
R'000
Details
30/06/2015 30/06/2016
Actual Original Budget Adjustment
Budget
Actual Variance to
Adjustment
Budget
Total Operational
Revenue -26,290,876 -364,266,750 -364,266,750 -36,753,881 -327,512,869
Expenditure:
Employees 60,595,563 78,303,330 71,877,202 66,880,595 4,996,607
Repairs and
Maintenance 1,379,047 11,397,972 22,415,957 20,804,538 1,611,419
Other 37,866,116 29,484,960 38,191,571 47,782,931 -9,591,360
Total Operational
Expenditure 99,840,726 119,186,262 132,484,730 135,468,064 -2,983,334
Net Operational
Expenditure 73,549,850 -245,080,488 -231,782,020 98,714,183 -330,496,203
62
Table 3.33: CAPITAL EXPENDITURE: HOUSING SERVICES
Capital Projects
Year 2015/16
Budget Adjustment
Budget
Actual
Expenditure
Variance from
adjustment
budget
Total All 60,200,000 60,200,000 49,420,514 10,779,486
Informal Settlements (Priority Projects) 46,200,000 46,200,000 42,186,268 4,013,732
COMPONENT B: PLANNING
The municipality has a fully-fledged planning unit that provides SMME support to small and medium and
established business in the city. Key to the objectives of the City is Promotion of Economic opportunities in
strategic locations for sustainable development, Establish Accountable and pro-active management of change
in land use and to development patterns, To Enhance Regional Transport Efficiency, Grow Economy and Create
Job Opportunities and Rural Development
INTRODUCTION TO PLANNING
As part of its strategies for economic development, the Planning Directorate of the City aims to formalise
townships along the N8 and other strategic investment nodes in the metro.)
The City embarked on an extensive programme to improve public transportation system through the Integrated
Public Transport Network (IPTN) process. Fundamental to the planning process is the Implementation of the
Spatial Planning Land Use Management Act (Act 16 of 2013). Through this process the metro has established
a development tribunal to fast track land use applications.
3.7 PLANNING
The current city fabric is characterised by disjointed apartheid city spaces. It is also characterised by inefficient
city structure that leads to expensive service levels. In order to overcome these challenges strategic decisions
should be made. Key priorities should address the following:
• Densification of the city through infill planning and group housing schemes;
• Elimination of informal settlements and access to proper community services;
• Creation of liveable urban spaces;
• Integration of the city through the creation of economically viable urban transport corridors; and
• Creating economic and social opportunities for all the residents of the city to benefit (e.g. Economic
nodes of Botshabelo and Thaba Nchu, Airport Node, etc.).
63
For the year under review, the City has made strides in the following areas:
Effective processing of land use applications to ignite development in the City;
Facilitated planning and township establishment processes irt the three land parcels viz, Cecilia Park,
Brandkop 702 and the Airport Development Node
64
Table 3.34: POLICY OBJECTIVES OF PLANNING TAKEN FROM THE IDP
3.34.1 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target 2015/16 Actual
Performance
2015/16
Corrective
Action
Variance
Establishment of
accountable and
Pro Active
management of
change in Land Use
and development
patterns
Rural Development
Establishment of
Corporate
Geographic
Information
Services
To develop regional
tourism
infrastructure
Effective
Management
of Planning and the
Build Environment
Municipal Pound
Incubation Centre
Effective corporate
Geographic
Information system
Redeveloped Naval
Hill
A vibrant and viable
regional recreational
facility
Completion of detail
designs and bid
documentation for
Funicular
0 100% completion of Detail
Designs and bid
documentation for funicular
100% completion of
Detail Designs for
funicular
None
Percentage
improvement in
turnaround times for
processing of
building plans
No of Buildings
Plans < 500m²
approved within
30 days and no of
Building Plans
approved > 500m²
within 60 days
<500m² =1872 applications
received and processed
>500m² =78 applications
received & processed
<500m² = 1500
>500m² = 50
<500m² = 2080
>500m² = 77
None
None
+580
+27
No of days taken to
effect action from
date of identification
No of notices issued
and cases to court
Notices issued =161
Cases to court =25
Notices to be issued= 200
Cases to court =50
Notices issued=148
Cases to court=7
Appointment
of personnel.
Purchase of
sufficient
dockets
-52
-43
65
Table 3.35: EMPLOYEES: ECONOMIC DEVELOPMENT AND PLANNING SERVICES
Table 3.36: FINANCIAL PERFORMANCE: PLANNING AND FRESH PRODUCE MARKET
Financial Performance: Planning Services
R'000
Details
30/06/2015 30/06/2016
Actual
Original
Budget
Adjustment
Budget Actual
Variance to
Budget
Total
Operational
Revenue
-6,616,747 -6,551,181 -6,551,181 -5,511,617 -1,039,564
Expenditure:
Employees 39,651,752 67,772,816 63,547,424 35,131,743 28,415,681
Repairs and
Maintenance 20,238,265 81,256 52,676 2,196,833 -2,144,157
Other 22,660,185 45,081,540 49,890,764 68,957,051 -19,066,287
Total
Operational
Expenditure
82,550,203 112,935,612 113,490,864 106,285,627 7,205,237
Net
Operational
Expenditure
75,933,455 106,384,431 106,939,683 100,774,010 6,165,673
Employees: Economic Development & Planning
Job Level
Year -1 Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a %
of total posts)
No. No. No. No. %
0 – 3 19 12 7 36%
4 – 6 163 32 131 80%
7 – 9 74 24 50 67%
10 – 12 24 12 12 50%
13 – 15 9 3 6 66%
16 – 18 6 1 5 83%
Total 295 84 211 71%
66
FINANCIAL PERFORMANCE: FRESH PRODUCE MARKET
Financial Performance: Planning Services
R'000
Details
30/06/2015 30/06/2016
Actual
Original
Budget
Adjustment
Budget Actual
Variance to
Budget
Total Operational
Revenue -20,654,288 -21,588,440 -21,588,440 -22,446,058 -3,97%
Expenditure:
Employees 7,196,014 10,017,606 10,017,606 8,710,171 13,05%
Repairs and
Maintenance 405,228 861,110 1,491,110 691,942 19,65%
Other 5,439,675 11,509,203 10,879,203 6,625,198 42,44%
Total Operational
Expenditure 13,040,917 22,387,919 22,387,919 16,027,311 28,41%
Net Operational
Expenditure -7,613,371 799,479 799,479 -6,418,747 902,87%
Table 3.37: CAPITAL EXPENDITURE: PLANNING AND LOCAL ECONOMIC DEVELOPMENT
Capital Projects Year 2015/2016
Budget Adjustment
Budget
Actual
Expenditure
Variance
From
Adjustment
Budget
Township Establishment Cecilia
Park 20,000,000 17,078,540 9,535,958 7,543,000
Township Establishment
Brandkop 702 16,000,000 16,002,474 2,727,500 13,274,974
Township Establishment
Botshabelo 0 600,000 383,318 216,682
Township Establishment Bfn
South 0 4,000,000 2,497,904 1,502,096
Airport Development Node 46,000,000 59,753,987 32,545,028 27,208,000
GIS System Implementation 6,000,000 10,275,055 0 10,,275,055
67
CAPITAL EXPENDITURE: LOCAL ECONOMIC DEVELOPMENT
Capital Projects Year 2015/2016
Budget Adjustment
Budget
Actual
Expenditure
Variance From
Adjustment
Budget
Naval Hill Funicular 4,501,933 5,966,183 5,842,754 2%
Hawking Stalls Botshabelo
Phase 1 7,157,000 9,507,000 9,410,766 1%
3.8 LOCAL ECONOMIC DEVELOPMENT (INCLUDING TOURISM AND MARKETING)
Table 3.38: ECONOMIC GROWTH BY SECTOR
Economic Growth by Sector
Sector Year 2012 Year 2013 Year 2014 Year 2015
Agriculture 1.4% 1.4% 1.5% -8.0
Mining 0.4% 0.4% 0.5% 25.9
Manufacturing 4.3% 4.1% 4.1% -12.9
Electricity 2.5% 2.3% 2.3% 1.0
Construction 2.9% 3.0% 3.0% 16.3
Trade 19.6% 18.5% 18.3% 10.1
Transport 14.1% 14.1% 14.1% 10.6
Finance 21.0% 21.1% 21.5% 25.8
Community services 33.3% 34.8% 34.7% 8.9
Table 3.39: EMPLOYMENT BY ECONOMIC SECTOR
Economic Employment by Sector
Jobs
Sector Year 2012/13 Year 2013/14 Year 2014/15 Year 2015/16
No. No. No. No.
Agriculture, forestry and fishing 1.6 2.6 3.9 6,560
Mining and quarrying 0.1 0.1 0.1 459
Manufacturing 7.9 6.9 6.1 9,600
Wholesale and retail trade 22.6 22.3 0.7 23,900
Finance, property, etc. 10.6 10.3 3.8 17,100
Government, community and
social services 44.6 46.6 12.4 50,929
Infrastructure services 6.7 5.7 5.9 28,780
68
Table 3.40: JOB CREATION
Job creation through EPWP projects
Details
EPWP Projects Jobs created through EPWP
projects
No. No.
Year - 2011/2012 45 2452
Year - 2012/2013 36 1247
Year - 2013/2014 40 1687
Year - 2014/2015 16 1074
Year 2015/2016 70 2958
69
Table 3.41: LOCAL ECONOMIC DEVELOPMENT POLICY OBJECTIVES TAKEN FROM IDP
3.41.1 STRATEGIC
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Economic
Development
Rejuvenation of
the CBDs within
the municipality
Number of Hawking
Stalls developed at
Botshabelo
Completion
certificates
100% detailed
designs
completed
44 of Hawking Stalls
developed at
Botshabelo
79, 55% or 35 Hawking
Stalls developed at
Botshabelo
Extension of time was
granted. The contractor will
endeavour to increase their
number of resources.
-21.45% or -9
Hawking Stalls
developed at
Botshabelo
Number of Hawking
Stalls developed at
Thaba Nchu
Completion
certificate
100% detailed
designs
completed
20 of Hawking Stalls
developed at Thaba
Nchu
Preliminary designs
completed. Service
Provider Paid.
Project halted. Project to
continue after completion
of the Thaba Nchu CBD
Master plan.
-20 of Hawking
Stalls
developed at
Thaba Nchu
Rural
Development
Formulating Rural
Development
through Agri–Park
Facilitating rural
development and
supporting rural
enterprises
100%
implementation of
Phase 1 of Thaba –
Nchu Agri-Park
Project Completion
Certificates
New Indicator 100%
implementation of
Phase 1 of Thaba –
Nchu Agri-Park
Competition of the
business plan
Accelerate the
implementation of the
Business Plan
-100%
implementatio
n of Phase 1 of
Thaba –Nchu
Agri-Park
Spatial
Integrations
Unlock N8 Nodal
development
Percentage
implementation of
the
Botshabelo/Thaba
Nchu economic
node
Detailed town
planning designs
80% Concept
designs of the
two nodes
100% completion
of town planning
designs and
surveying of
nodes
Not Achieved Accelerate procurement
processes and clarity
institutional arrangement
for co-ordination
-100%
completion of
town planning
designs and
surveying of
nodes
Implementation of
the N8
Development
Node
Approved SG
plans
95%
completion of
the designs,
100% Completion
of surveying and
approved SG
plans
Not Achieved Accelerate procurement
processes and clarity
institutional
arrangement for co-
ordination
-100%
Completion of
surveying and
approved SG
plans
Project Completion
Certificates
95% completion
of the design
95% completion of
civil services
Not Achieved Accelerate procurement
processes and clarity
institutional arrangement for
co-ordination
--95%
completion of
civil services
Project
Completion
Certificates
95% completion
of the design
100% completion of
bulk services
Not Achieved Accelerate procurement
processes and clarity
institutional arrangement
for co-ordination
-100%
completion of
bulk services
70
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Implementation
of 7 land parcels
Promotion of
mixed land use
development
Vista Park
extension 2
Detailed engineering
designs
Completion
certificates
Urban design,
lay out plan,
signed lad
availability
grant and
service level
agreement
100% completed
engineering designs
(Urban design layout
plan)
20% implementation
of phase 1
Urban Designs finalised
and GP calculations and
pegging still in process.
The designs for the
following services have
been finalised:
Roads and storm water,
waste management plan
and broadband
Electricity: The
Preliminary Designs
Report (PDR) for the
MV, LV and House
connections has been
completed in terms of
the Centlec guidelines
and regulations.
The PDR has been
submitted for evaluation
and approval
Accelerate implementation
according to the revised
programme indicates the
estimated project duration
and phases
Vista Park
extension 3
Detailed designs 95% planning
completed –
SLA signed,
township
application
lodged
100% completion of
town planning and
approved SG Plans
The land surveyor
appointed by Calgro M3
has pegged Extensions
256, 257 and 261.
The General Plans for Ext
256, 257 & 261 together
with the approved
Conditions of
Establishment were
submitted with the SG for
approval.
The approved General
Plan for Vista Park Ext 256
was issued on 29 June
2016.
Accelerate implementation
according to the revised
programme indicates the
estimated project duration
and phases
71
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Implementation
of 7 land parcels
Promotion of
mixed land use
development
Vista Park
extension 3
Completion
certificates
95% planning
completed – SLA
signed, township
application
lodged
100% installation of
civil services
Once the traffic impact
study has been finalised
and approved, and formal
confirmation of bulk
services availability has
been obtained, installation
of services for
the Vista Park Ext 256, 257
and 261 townships can
commence
Accelerate implementation
according to the revised
programme indicates the
estimated project duration
and phases
-100%
installation of
civil services
Completion
certificates
95% planning
completed – SLA
signed, township
application
lodged
100% installation of
electricity services
Once the traffic impact
study has been finalised
and approved, and formal
confirmation of bulk
services availability has
been obtained, installation
of services for
the Vista Park Ext 256, 257
and 261 townships can
commence
Accelerate implementation
according to the revised
programme indicates the
estimated project duration
and phases
-100%
installation of
electricity
services
Formalisation of
Brandkop 702
Lodged
application for
township
establishment
95% planning
completed for
Brandkop 702;
100% completion of
town planning and
approved SG Plans
Lodged township
establishment application
Township establishment to
be completed
General plan
outstanding
100% completion of
Hillside View Phase
one
Number of social
Rental houses
completed
Construction of
Phase 1.1. has
commenced
Application for
Township Re-
layout lodged
Design of
services
completed
940 social rental
housing units
completed
100% completion of
Phase 1
Construction for 405 units
which is phase 1 has
commenced and is at wall
plate level with no final
completions done due to
funding challenges
Contractors moved out of
sites due to lack of
funding. The Human
Settlements Directorate
continue to engage the
DHS to unlock the
challenges facing the
Social and CRU projects
-940 social
rental housing
units
completed
Formalisation of
Cecilia Park
Lodged
application for
township
establishment
Cecilia Park 95%
planning
completed
100% completion of
town planning and
approved SG plans
Topographical survey is
complete
Township establishment
to be completed
General plan
outstanding
72
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Improve Public
Transport Network
Implementation of
Integrated Public
Transport Network
(IPTN) with Non-
Motorised
Transport
Initiatives
100% completion of
Phase 1 of IPTN
Percentage of
completion of
Operations-and
Business Plan and
infrastructure
designs of phase 1
of IPTN
Procurement
of professional
consultants
100% completion of
IPTN Operations
Plan and Business
Plan
100 % upgrading of
Maphisa Road that
constitute phase 1 of
IPTN
The Upgrading of Maphisa
Project is 82% complete.
The contractual project
completion date is
November 2016 and
according to the
programme, the
construction is ahead of
the projected progress
and will be completed
before the actual
completion date.
In accordance
to the set
targets, the
variance is -
18%.
3.41.2 OPERATIONAL IDP Objective Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Economic
development
Support SMME
development
Number of viable and
sustainable SMMEs
supported
No of SMME
supported
12 922 SMME
supported
500 SMMEs
supported
1431 SMMEs
supported
none +931 SMMEs
supported
Skills upgrading,
training provided
Training programme
for SMME
No SMME ‘s trained 562 300 SMMEs trained 993 SMMEs trained
none +693 SMMEs
trained
Pedestrianisation of
Ella Street
% of project
completed
Payment certificates
Concept Designs
completed
100%
Pedestrianisation of
Ella Street
Project halted to
bring in line with the
IPTN
Awaiting design of the
IPTN routes
-100%
Pedestrianisation
of Ella Street
Marketing the
municipality as
premier
destination for
investment and
tourism
Marketing events
and programmes
No of marketing
events
5 marketing events 6 marketing
events
1 marketing event Adequate budgetary
provision for marketing
events
-5 marketing
events
Capacity Building
Programme for
Tourism &
Hospitality
2 Exhibition Training
Sessions
2 Sign Language
Training Sessions
1 Tourism
Awareness Training
1 Session 5 Training Sessions 2 Training Sessions 0 Organise training
sessions
-2 Training
Sessions
73
IDP Objective Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective Action Variance
Economic
development
To enhance local
and international
tourism
Number of Tourism
Routes Developed
2 Tourism Routes
Concept Designs
and Phase 1
completed
0 2 Tourism Routes
Concept Designs and
Amenities Packaging
100% completed
1. Heritage route
2. Tolkien trail route
3. Ghost route
4. Batho route
5. N6 route
None +3
To develop a
Municipal Pound in
Botshabelo
Completion of
Application
processes and
design phase
0 100% Application
process
0% Appointment of a
service provider to
commence with the
conceptual concepts
and implementation.
-100% Application
process for a
municipal pound
To Develop an
Agricultural
Incubation Center
Completion of
Project
0 100% Design
Completed
0% The project is linked
to the Agri-Park and
will commence in the
new financial year
2016-2017.
-100% Design
Completed
% implementation of
Corporate GIS
% implementation of
GIS applications to
User Functions.
1. Service Provider
appointed.
2. Confirmation of
User Needs
Requirements
completed in all MMM
Directorates.
3. Corporate GIS
System Designs
and System
Architecture
Requirements
completed.
100%
implementation of
Corporate GIS
Generic Viewer
Application.
100%
Implementation of
Corporate GIS
Generic Viewer
Application.
None none
100%
implementation of
functional Tribunal
GIS Application.
100%
Implementation of
Functional Tribunal
Application.
None none
74
COMPONENT C: COMMUNITY AND SOCIAL DEVELOPMENT
3.9 LIBRARIES, ARCHIVES, COMMUNITY FACILITIES; OTHER THEATRES, ZOO
The City is doing very well in meeting all its set targets in relation to the promotion of literacy in communities
through ensuring access to new library materials, marketing of the library services and implementing library
outreach programmes to communities.
The City has succeeded in initiating and supporting arts and cultural programmes by providing platform for them
to showcase their talent. We initiated and supported various arts and cultural groups, activities and events in
the effort to unearth raw talent in MMM. Local arts and cultural groups are afforded opportunity during the
celebrations of the following events. Women's day, Heritage day, Youth day, Moshoeshoe day, International
Mother Tongue day, Botshabelo School Art Festival, Mangaung Theatre Production Festival, Youth day, Africa
day, Indoni Cultural Carnival. Arts and cultural groups are assisted with free use of facilities for rehearsals,
performances and fund raising initiatives.
The City has approved the Relocation of the Zoo, and during the 2014 / 2015 financial year the security fence
was erected, as well as a temporary game fence on the Kwaggafontein Game Farm. Furthermore, detailed
plans and designs for the bulk services were also compiled during the financial year, as well as commencement
of the detailed designs and plans for the facility. 2015 /2016 financial year Environmental Impact assessment
underway, no construction work can be commenced until an EIA certificate has been received.
75
Table 3.42: LIBRARIES; ARCHIVES; COMMUNITY FACILITIES; OTHER
3.42.1 STRATEGIC
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance 2015/16 Corrective Action Variance
Improve service
delivery by
providing
recreation
facilities and
public amenities
to all residents of
Mangaung
Provision of
recreational
facilities to all
residents of
Mangaung
Create a clean and
green environment
Relocation of
the Zoo to
Kwaggafontein
Game Farm
Zoo to be re-
designed and re-
built at
Kwaggafontein
Game Farm
Completion
Certificates
Construction of
Security Fencing,
including water gates
and entrance gates,
Erection of
Temporary Game
Fencing. Submission
and approval of plans
for Service Delivery
Guard house and
Main Entrance
Complex.
Building of service delivery guard
house and main entrance
complex
No construction
was done due to
on-going EIA
processes by
DESTEA.
Construction of
Security Fencing,
including water gates
and entrance gates,
Erection of
Temporary Game
Fencing. Submission
and approval of
plans for Service
Delivery Guard
house and Main
Entrance Complex (
Improve service
delivery by
provision of –
safe and
secured
cemeteries.
Fencing of
cemeteries
Number of
cemeteries
fenced. (New
addition)
Completion
certificates
3 cemeteries
fenced –
Ratau-1, Ratau-2,
Thaba Nchu
Town Cemetery.
2 cemeteries to be
fenced namely:
Storm-laan (0.63km)
and Bainsvlei
(2.09km) cemeteries.
Erection of razor wire fence in
Stormlaan is 100% completed,
clear-vu fence in the front portion
is 95% completed. Erection of
fence for Bainsvlei is 15%
completed.
Timeous planning
and execution of
procurement
processes.
-85% complete
Improve service
delivery by
provision of -
Accessible
Roads
Construction and
upgrading of
Roads
Channelling of
Storm-water.
Kilometres of
cemetery roads
upgraded
Completion
certificates
1 Cemetery Road
constructed at
South park.
4 cemetery Roads to
be constructed at the
following cemeteries:
1. Botshabelo
Regional Cemetery
2. Botshabelo
Cemetery
3. Bainsvlei
Cemetery
4. Phahameng
Cemetery
(length 0,5 km,
major concrete
storm-water channel
0,3km)
1. New Roads & Storm-water
Botshabelo Regional cemetery –
Desktop studies and wetlands
report finalised, Actual
construction of roads will be
realised in the new financial year.
2. New Roads & Storm-water
Botshabelo cemetery – project is
40% completed.
3. New Roads & Storm-water
Bainsvlei cemetery – project is
45% completed.
4. Upgrading of roads & Storm-
water Phahameng cemetery –
project is 25% completed.
Timeous planning
and execution of
procurement
processes.
-100% complete (.
Botshabelo Regional
Cemetery)
-60% complete (.
Botshabelo
Cemetery)
- 55% complete (.
Bainsvlei Cemetery)
-75% complete (.
Phahameng
Cemetery)
76
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance 2015/16 Corrective Action Variance
Improve service
delivery by
Upgrading of
facilities Improve
service delivery
by increasing
cemeteries.
Construction of
ablution facilities.
Increase of burial
space
Number of
cemeteries with
ablution
facilities (New
addition)
Completion
certificates
1 ablution facility
constructed at
Ratau cemetery (
Thaba Nchu)
1 ablution facility to
be constructed in
South park
cemetery.
Construction of ablution block -
project is 90% completed. There
was a delay in delivery of
materials towards the finalisation
phase of project.
Project to be
finalised during
July 2016 in the
new financial year.
-10% complete
(South Park
Cemetery ablution
facility)
Amount of
cemetery space
available to
cater for future
burials. (New
addition)
Hectares of land
acquired
Registration at the
Deeds Office
2 plots were
acquired for
cemetery
purposes namely:
Klipfontein and
Farm X2727.
Development of a
master plan for the
conversion of the two
acquired plots into
cemeteries.
Not achieved
Commencement of the master
plan was delayed by discussions
with SANRAL which took longer
than anticipated.
Master plan to be
completed in the
new financial year
after new
proposals for both
the entrance of
X2727 and the
revised layout of
klipfontein have
been approved.
-Development of a
master plan for the
conversion of the two
acquired plots into
cemeteries.
3.42.2 OPERATIONAL IDP Objective Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective Action Variance
Promoting a
comprehensive
Library service
Promote literacy in
communities
New library material
per annum acquired
Nr of new children
books acquire
2447 1000 new
children`s books
2697 new children`s
books
None
+1697 Positive
Variance
New library material
per annum acquired
Nr of New non-fiction
books acquired
2828 2000 new non-
fiction books
4844 new non-fiction
books
None
+2844 Positive
Variance
New library material
per annum acquired
Number of new adult
fiction books acquired
per annum
2535 1000 new adult
books
2631 new adult
books
None
+1631 Positive
Variance
Marketing of Library
Services
Number of library
awareness campaigns
conducted
94 50 library
campaigns
conducted per
annum
109 library
campaigns
conducted per
annum
None
+59 Positive
Variance
Library outreach
programmes to
communities
Number of outreach
(interactive)
programmes
conducted
4 872 400 outreach
programmes
conducted
641 outreach
programmes
conducted
None
+141 Positive
Variance
77
Table 3.43: EMPLOYEES: LIBRARIES
Employees: Libraries
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a
% of total posts)
No. No. No. No. %
0 – 3 1 1 1 0 0%
4 – 6 4 5 4 1 20%
7 – 9 17 29 17 12 41%
10 - 12 3 4 3 1 25%
13 - 15 37 51 37 14 27%
16 - 18 6 15 6 9 60%
Total 68 105 68 37 35%
Employees: Zoo & Kwaggafontein Division
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a %
of total posts)
No. No. No. No. %
0 – 3 1 1 1 0 0%
4 – 6 0 0 0 0 0%
7 – 9 3 6 3 3 50%
10 - 12 3 6 3 3 50%
13 - 15 21 26 21 5 19%
16 - 18 2 7 1 6 86%
Total 30 46 29 17 37%
78
Table 3.44: FINANCIAL PERFORMANCE: LIBRARIES; ARCHIVES; COMMUNITY
FACILITIES; OTHER
Financial Performance: Libraries; Archives; Museums; Galleries; Community Facilities; Other
R'000
Details
Year -1
(2014/15) Year 2015/16
Actual Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue
-1,001,482 -266,912 -78,177 -188,734
Expenditure:
Employees 43,814,295 20,543,256 17,071,895 3,471,360
Repairs and
Maintenance
35,114 152,936 32,393 120,543
Other 6,698,910 20,390,320 17,039,502 3,350,817
Total Operational
Expenditure
50,548,318 3,092,331 1,672,147 1,420,183
Net Operational
Expenditure
49,546,837 2,825,419 1,593,970 1,231,449
Table: 3.45: Financial Performance: Libraries; Zoo & Kwaggafontein
Financial Performance: Libraries; Zoo & Kwaggafontein
R'000
Details
Year -1
(2014/15)
Year 2015/16
Actual Original
Budget
Adjustment
Budget
Actual Variance to
Adjustment
Budget
Total Operational
Revenue -2,375,881 -2,849,271 -2,849,271 -3,066,453 217,182
Expenditure:
Employees 8,221,098 32,280,260 28,767,305 24,988,999 3,778,306
Repairs and
Maintenance 408,793 488,731 592,389 457,678 134,711
Other 5,704,815 7,832,140 9,308,482 4,525,440 4,783,042
Total Operational
Expenditure 14,334,706 40,601,131 38,668,176 29,972,117 8,696,059
Net Operational
Expenditure 11,958,825 37,751,860 35,818,905 26,905,664 8,913,241
79
3.10 CHILD CARE, CARE OF THE AGED, SOCIAL PROGRAMMES
Improve services to ameliorate the plight of vulnerable groups such as street children, people with
disability, the elderly, Promote Early Childhood development (ECD). Alleviate poverty through
community projects Promote arts and cultural programmes.
80
Table 3.46: SERVICE DELIVERY OBJECTIVES IN THE IDP FOR CHILD CARE
3.46.1 OPERATIONAL IDP Objective Strategy KPI Unit of Measurement Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Improve services to
ameliorate the plight
of vulnerable groups
such as street
children, people with
disability, the elderly
Wellness
programmes for
the aged including
bio kinetics,
healthy life style
etc.
Number of wellness
programmes for the
elderly
Number of wellness
programmes
implemented
4 4 outreach
Programmes targeting
the aged
7 outreach
Programmes targeting
the aged
None
+3 Positive
Variance
Ensure elderly
shelters are
properly regulated
and well governed
Number of elderly
shelters visited
Number of Inspections
conducted
20 20 visits to elderly
shelters
20 visits to elderly
shelters
None
none
Work with
Organizations
and/or individual
people with
disability to
address their
needs
Support
organisations
dealing with people
with disabilities
Number of
organisations
supported
4 4 centres responsible
for people with
disabilities supported
10 centres responsible
for people with
disabilities supported
None
+6 Positive
Variance
Assist Orphans,
Child headed
households (CHH)
and street children
Number of
vulnerable children,
orphans, CHHs and
street children
supported through
their centres.
Number of orphans,
CHHs supported
20 5 orphans, CHHs and
street children centres
supported
13 orphans, CHHs and
street children centres
supported
None
+8 Positive
Variance
Promote Early
Childhood
development (ECD)
Conduct
inspections on
ECD premises
Number of ECD
premise inspections
conducted
Sustain inspection
programme of ECDs
564 100 inspections
conducted
311 inspections
conducted
None
+211 Positive
Variance
Alleviate poverty
through community
projects.
Facilitate and
support the
development of
poverty alleviation
projects
Number of poverty
alleviation projects
facilitated and or
supported
Number of poverty
alleviation projects
facilitated and/ or
supported
7 4 projects supported
and ensure
sustainability
9 projects supported
and ensure
sustainability
None
+5 Positive
Variance
Promote arts and
cultural programmes
Promote cultural
programmes
Initiate and support
arts and cultural
programmes
Number of arts and
cultural programmes
initiated and supported
29 6 arts and cultural
programmes initiated
and supported
60 arts and cultural
programmes initiated
and supported
None
+54 Positive
Variance
81
Table 3.47: EMPLOYEES: CHILD CARE; CARE OF THE AGED; SOCIAL PROGRAMMES
2015/16
Job Level Posts Employees Vacancies
(fulltime
equivalents)
Vacancies
(as a % of
total posts)
No. No. No. %
0 – 3 0
4 – 6 3 2 1 33%
7 – 9 0
10 – 12 0
13 – 15 0
16 – 18 0
Total 3 2 1 33%
COMMENT ON THE PERFORMANCE OF CHILD CARE; AGED CARE; SOCIAL PROGRAMMES
OVERALL
The City has succeeded in supporting the vulnerable groups in our society.
3.11 BIO DIVERSITY AND LANDSCAPE – PARKS
The main objective of the parks division is to provide a clean, green and healthy environment to the residents
of Mangaung. It is responsible for the horticultural maintenance and development of open spaces, parks, traffic
islands, buffer zones, sports fields, street trees, city gardens and fire belts
The core functions of the Parks unit are:
Greening the city- entrances, parks, planting trees
Maintenance of existing parks
Maintenance of sports fields
Development of new parks
Cemeteries beautification
The main objective of natural resource management is to conserve the natural resources of MMM which consist
of 28, 000 hectares, responsible to the development and maintenance of Naval Hill as a tourist attraction for
local and international visitors
82
The core functions of the Nature Resource Management unit are:
Management of natural open spaces
Naval Hill nature reserve development
Eradication of alien plants
Protection of top –soil/ erosion control
Management of wild animals in Naval Hill Nature Reserve
83
Table 3.48: SERVICE DELIVERY OBJECTIVES OF BIO DIVERSITY; LANDSCAPE AND PARKS
3.48.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/16
Annual Target
2015/16
Actual
Performance
2015/16
Corrective
Action
Variance
Improve service
delivery by
providing
recreation
facilities and
public amenities
to all residents of
Mangaung
Provision of
recreational
facilities to all
residents of
Mangaung
Create a clean and
green environment
Number of regional
parks developed
One Park developed
Completion
Certificate
Phase 1 of the Regional
Park in Thaba Nchu
completed
Phase 1 of the Park in
Botshabelo completed
Second phase of
Regional Park
development in
Thaba Nchu
implemented
Athletic Track
which was part of
second phase of
Regional Park in
thaba Nchu is
100% complete
None -100% of phase 2
Botshabelo Park
One Park developed Completion
Certificate
Phase 1 of the Park in
Botshabelo completed
2nd phase of the
Botshabelo park
development
implemented and
completed
Phase two of
Botshabelo park
was discontinued.
Decision on
which park to
upgrade
-100% of phase 2
Botshabelo Park
84
COMPONENT E: ENVIRONMENTAL PROTECTION
3.12 POLLUTION CONTROL
Pollution control initiatives within the municipality are implemented and managed by an integrated approach
(waste management, environmental management, environmental health, parks, etc.). With regards to the 2
indicators listed we can report that water quality and air pollution programmes are in place. Environmental health
practitioners take water samples on a daily basis from the 2 main reservoirs (Brandkop and Masselspoort) and
on a monthly basis at household points evenly spread amongst all suburbs, our current compliance status is
well within the parameters of SANS 241.
We also monitor the quality of air by means of three (3) air quality stations, with the main focus on sulphur
dioxide emissions. We can safely report that no incidences in this regard were recorded during this reporting
period.
85
Table 3.49: SERVICE DELIVERY OBJECTIVES FOR POLLUTION CONTROL
3.49.1 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target 2015/16 Actual Performance
2015/16
Corrective
Action
Variance
Promote
Environmental
Health
Manage Air
Quality
Respond to all non-
compliance of sulphur
Dioxide emissions therefore
ensure Air Quality Control
Time taken to
respond to
noncompliance of
Sulphur Dioxide
emissions
1 All noncompliance
attended too within 2 days
All non-compliance
attended too within 3
days
None -1 day
Processing of all emission
Licence applications
submitted
Number of Air
Emission Licence
(AEL) applications
handled
5 AEL applications
handled (All)
All AEL applications
handled
All (2)AEL applications
handled
None None
Develop Air Quality
Management Plan (AQMP)
Adoption and
Development of Air
Quality Management
Plan
AQMP as adopted
by Motheo
scrutinized.
Communicated
with internal
stakeholders.
Finalize Draft AQMP Meeting held with
relevant stakeholders,
Environmental
Management
(Planning) to get their
input and finalize the
plan for publication and
public input
By-law has been
submitted to
Mangaung Metro
Municipality
legal service for
their input and
comments,
where after the
by-law will be
published for
public
comments.
Draft AQMP
Handling
Environmental
pollution
complaints
Attend to all Environment
Management pollution
complaints reported to the
municipality
Number of
environmental
pollution related
complaints handled
within 48hrs
24 Environmental pollution
related complaints handled
within 48hrs
251 Number of
environmental
pollution related
complaints handled
within 48hrs
None none
Conduct health
and hygiene
(H&H)
awareness
programmes
Conduct health and hygiene
(H&H) awareness
programmes
Number of H&H
awareness
programmes
conducted EHS
72 10 H&H programmes
conducted
39 &H programmes
conducted
None
+29 Positive
Variance
86
Table 3.50: EMPLOYEES: POLLUTION CONTROL
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a %
of total posts)
No. No. No. No. %
0 - 3 0 0 1 100%
4 - 6 1 0 0 0%
7 - 9 4 2 2 50%
10 - 12 0 0 0 0%
COMPONENT F: HEALTH
3.13 HEALTH INSPECTION, FOOD AND ABBATTOIR
The function of provision of environmental health services within the municipality includes all activities
associated with the provision of municipal health services in terms of the National Health Act (No 61 of 2003)
but does not take into account of poor health services which reside within the jurisdiction of FS provincial
government. Service delivery provision here includes:
1. Water Quality Monitoring
To ensure consumer protection in accordance to (Cosmetic and Disinfectants Act no 54 of 1972) a food
safety programme has been carried out .This has been achieved by regular inspections (including
special events), monitoring, rendering a microbiological laboratory service for the analysis of food stuffs
as per legislative (sampling,)
And compliance (by fulfilling functions of the local trading authority by enforcing the Business Act No
71 of 1991) thus ensuring sustainable health and well-being of citizens.
The Abattoirs were also inspected on a regular basis and there is a daily inspection programme
(including. compliance) of Fresh Produce Market
2. Food Quality Monitoring
Water Quality Monitoring in accordance to Water Services Act and SANS 241 for water quality has
been carried out successfully
Both the food and water safety programmes were sustained successfully
3. Health Surveillance of premises
Surveillance of premises (built environment) has been done in accordance to National Building
Regulations.
87
4. Disposal of the dead
The City continued to provide effective health services in relation to inspection of mortuaries, ensuring
compliance. Furthermore it has continued to carry out its responsibility in ensuring safe disposal of
unidentified bodies in collaboration with Forensic Pathology, in accordance with CHAPTER 10
(Unclaimed bodies or unidentified human Remains) of Regulations relating to Rendering of Forensic
Pathology Services in the Government Notice No.636 of July 2007
88
Table 3.51: SERVICE DELIVERY OBJECTIVES FOR HEALTH INSPECTION, FOOD AND ABBATTOIR
3.51.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Promote
Environmental
Health
Conduct drinking
and recreational
water sampling
according SANS to
241
Number of drinking
water samples taken
Water sample report 1412 drinking water
samples taken
1 300 drinking water
samples taken
1 776 drinking water
samples taken
None +476 Positive
Variance
3.51.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Promote
Environmental
Health
Inspect food
premises
Conduct food premise
inspections as per
provisions of the
foodstuffs, Cosmetics
and Disinfectant Act 54
1972
Number of food
premise inspections
conducted
14 432 food premise
inspections
16000 food premise
inspections
16055 food premise
inspections
None
+55 Positive
Variance
Inspect dairy farms Conduct food premise
inspections as per
provisions of the
foodstuffs, Cosmetics
and Disinfectant Act 54
1972
Number of dairy
farms inspected
42 food premise
inspections
20
dairy farms
inspected
61 food premise
inspections
None
+41 Positive
Variance
Inspect mortuaries Conduct inspections on
all mortuaries as per the
provisions of the Public
Health Act
Number of
mortuaries inspected
42 mortuaries
inspected
40
mortuaries
inspected
74 mortuaries
inspected
None
+34 Positive
Variance
Inspect medical
waste generators
Conduct inspection on
medical waste
generators premises as
per the provisions of the
NEMA
Number of medical
waste generator
premises inspected
567 medical
generator premises
inspected
110 medical
generator premises
inspected
153 medical generator
premises inspected
None
+43 Positive
Variance
89
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Ensuring health
related compliance
of buildings
Inspection of all building
plans for health related
compliance
Number of Building
plans received to be
scrutinized within 3
working days
2174 building plans
received to be
scrutinized for
health compliance
All building plans
received to be
scrutinized for
health compliance
2360 building plans
received to be
scrutinized for health
compliance
None none
Surveillance of
diseases
Attend to all
communicable diseases
reported
Attend to all
communicable
diseases reported
2 cases All communicable
diseases reported
attended too
0 None none
Conduct food
sampling
Take samples annually
in accordance with the
Foodstuffs, cosmetics
and Disinfectants Act 54
1972
Number of food
samples taken
803 food samples
taken
800 food samples
taken
1151 food samples
taken
None
+351 Positive
Variance
Conduct food
sampling
Take samples annually
in accordance with the
Foodstuffs, cosmetics
and Disinfectants Act 54
1972
Number of samples
taken at all major
functions where
applications have
been received
133 samples taken
at all major
functions
Samples taken at all
major functions
where applications
have been received
254 samples taken at
all major functions
None none
Ensure disposal of
dead (burials of
unidentified
persons)
Ensure disposal for the
dead (burials of
unidentified persons)
Number of burials
done within 2 weeks
26 burials done
within 2 weeks after
issuing of the official
order
All burials done
within 2 weeks after
issuing of the official
order
36 burials done within
2 weeks after issuing of
the official order
None none
Regulation of
Initiation Schools
in the Metro
Ensure compliance
with FS Initiation
School Health Act
no 1 of 2004 and
Regulations.
Number of e initiation
school applications
approved in terms of the
FS Initiation School
Health Act 1 2004.
Number of known
Initiation Schools
inspected
34 known Initiation
Schools inspected
Keep record and
ensure compliance
No inspections done
as yet, since it is the
1st week of Initiation
School operations
None none
Promote HIV
/AIDS
prevention
measures
Prevent new HIV/
AIDS infections
Conduct training on
HIV/Aids
Number of HIV/AIDS
courses conducted
19 HIV/AIDS
courses conducted
12 HIV/AIDS
courses conducted
18 HIV/AIDS courses
conducted
None +6 Positive
Variance
Intensify education and
awareness on HIV/Aids
Number of HIV/Aids
seminars to be
conducted
6 HIV/Aids seminars
to be conducted
4 HIV/Aids seminars
to be conducted
9 HIV/Aids seminars to
be conducted
None
+5 Positive
Variance
Preventing the spread of
HIV/Aids
Number of condoms
distributed
3 796 200 condoms
distributed
1 600 000 condoms
distributed
2 200 600 condoms
distributed
None
+600 600
Positive Variance
Encourage the
community to know their
status
Number of people
tested through
Voluntary
Counselling and
Testing (VCCT)
2 552 people tested
through Voluntary
Counselling and
Testing (VCCT)
300 people tested
through Voluntary
Counselling and
Testing (VCCT)
1571 people tested
through Voluntary
Counselling and
Testing (VCCT)
None +1271 Positive
Variance
90
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Conduct HIV/Aids
counselling and outreach
programmes
Number HIV
Counselling and
Testing outreach
programmes
conducted
63 HIV Counselling
and Testing
outreach
programmes
conducted
25 HIV Counselling
and Testing
outreach
programmes
conducted
64 HIV Counselling
and Testing outreach
programmes
conducted
None
+39 Positive
Variance
Assist Home Based Care
Organizations and OVZ
(Orphaned and
Vulnerable Children) on
training, referrals to other
Governmental
Departments and
Information
Dissemination
Number of Home
Base Care (HBC)
assisted
76 Home Base Care
(HBC) assisted
30 Home Base Care
(HBC) assisted
64 Home Base Care
(HBC) assisted
None
+34 Positive
Variance
91
Table 3.52: EMPLOYEES: HEALTH INSPECTION
Employees: Environmental Health
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies
(as a % of
total posts)
No. No. No. No. %
0 - 3 2 2 1 1 50%
4 - 6 5 5 4 1 20%
7 - 9 31 31 20 11 35.48%
10 - 12 7 7 2 5 71.42%
13 - 15 9 9 4 5 55.55%
16 - 18 0 0 0 0 0%
Total 54 54 31 23 42.59%
Table 3.53: FINANCIAL PERFORMANCE: HEALTH INSPECTION AND ETC.
Financial Performance: Health Inspection and Etc.
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustm
ent
Budget
Actual
Variance to
Adjustment
Budget
Total Operational
Revenue
-135,616 -201,158 -562,015 360,857
Expenditure:
Employees 10,503,576 14,195,158 12,783,662 1,411,495
COMMENT ON HEALTH INSPECTION, FOOD AND ABBATTOIR
All food premises are inspected and monitored according to our food inspection programme and this
yields success in health, hygiene and cleanliness. Our biggest challenge is the mushrooming of tuck
shops in residential areas owned by foreigners and mostly illegal which do not comply with health
standards. Haphazard operations and investigations did not yield the expected outcome but a multi-
sector compliance and monitoring team which includes SAPS and Home Affairs was established to
combat non- compliance this programme is sustained.
The City continues in providing drinking water services that is compliant to set water service standard.
For this financial year the municipality sustained a drinking water compliance rate of 98, 2 % well above
the 97% compliance rate. The City continued to provide effective health services in relation to inspection
92
of mortuaries, ascertaining water quality and raising basic hygiene awareness albeit there is a need for
improvements in relation inspection of food premises and inspection of dairy farms.
COMPONENT G: SAFETY AND SECURITY
The objective of the sub directorate is to enhance order and enforce compliance with road traffic rules
in the road network of the MMM and to ensure that Mangaung is a safe and secure place to live in, visit
and do business in. In order to achieve this, the division aims to prevent and minimize all security risks
and threats to municipal property, services and people, crime prevention, enforcement of municipal by-
laws and other applicable legislation and the investigation of municipal related crime.
3.14 INTRODUCTION TO POLICING
Installation of CCTV cameras around the Mangaung Metropolitan Municipality targeting the hotspots
as identified by law enforcement agencies (SAPS, etc.). This will in future be utilised for traffic violations
supplemented by, speed law enforcement cameras. The implementation of such measures has
resulted in a decline of motor accidents and behavioural change of motorists.
77 Traffic officers and 9 Traffic Wardens deployed in the three regions (Bloemfontein, Thaba Nchu and
Botshabelo working on two shifts system, doing speed enforcement, execution of warrants of arrest,
general law enforcement, attending to complaints, escorts of funerals and VIP’s, attending to accident
and community complaints, escorting of political and non-political marches and rerouting of traffic during
events e.g. road races, soccer and rugby.
Law Enforcement
102 Law Enforcement officers are deployed in the three regions (Thaba Nchu, Botshabelo and
Bloemfontein. These units work on a four shift system. Units comprises of the following: - Operational
unit; Shifts; Reaction group; Dog unit; Investigation unit; Administration unit and Social crime prevention
unit
93
Table 3.54: SERVICE DELIVERY OBJECTIVES FOR SAFETY AND SECURITY
3.54.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Improve revenue
collection
Payment of traffic
fines
Fines successfully
finalised and
payment received
Section 71 report 23 633 Fines
successfully
finalised and
payment received
20 000 Traffic fines
paid
20 752 Traffic fines
paid
Nil +752 Positive
Variance
Law enforcement
measures
Establishment of
metro police
Establishment of
metro police
Metro police
established
Develop strategy
and process plan
for establishment
of Metro Police
Appointment of
chief of police,
application of the
establishment and
prepare a business
plan.
Target not achieved Project
transferred to
City Manager's
Office
Appointment of chief
of police, application
of the establishment
and prepare a
business plan.
Law enforcement
measures
Number of crime
prevention
activities targeting
hotspots
Crime awareness
campaigns
operations
conducted
Crime prevention
operations
conducted
12 Crime
prevention
activities
conducted
targeting known
hotspots
12 Crime
prevention
activities
conducted
targeting known
hotspots
A total of 23 Crime
prevention activities at
24 crime hot spots and
attended to by the law
enforcement division.
+11 Positive
Variance
94
3.54.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Law enforcement
measures
Enhance visible
policing
Number of street
trading operations
conducted
Street trading
operations
conducted
29 15 street trading
operations
conducted
32 street trading
operations conducted
None Required
+17
Positive Variance
Number of speed
fines issued.
Number of notices
issued to speeding
transgressors
206998 speed
fines issued.
120 000 speed
fines issued.
172 266 speed fines
issued.
None Required
+52 266
Positive Variance
Ensure road user
safety
Enforce traffic by-
laws
Reduction of un-
roadworthy vehicles
within MMM
Number of notices
issued to motorist
driving un-
roadworthy vehicles
10809 of notices
issued to motorist
driving un-
roadworthy
vehicles
3000 of notices
issued to motorist
driving un-
roadworthy
vehicles
4 566 of notices issued
to motorist driving un-
roadworthy vehicles
None Required
+1 566
Positive Variance
Number of notices
issued to motorists
not wearing
seatbelts
Number of notices
issued to motorists
not wearing
seatbelts
6557 notices
issued to motorists
not wearing
seatbelts
3000 notices
issued to motorists
not wearing
seatbelts
4 529 notices issued to
motorists not wearing
seatbelts
None Required
+1 529
Positive Variance
95
Table 3.55: EMPLOYEES: POLICE OFFICERS/TRAFFIC AND SECURITY OFFICERS
Employees: Traffic
Job Level Year -1
(2014/15) Year 2015/16
Police Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a % of
total posts)
Administra
tors No. No. No. No. %
0 – 3 2 1 1 0 0
4 – 6 7 7 7 0 0
7 – 9 20 20 20 0 0
10 – 12 84 84 84 44 34
13 – 15 13 13 13 3 1.3
16 – 18 3 3 3 3 0.09
Total 129 128 128 50
Employees: Law Enforcement
Job Level Year -1
(2014/15) Year 2015/16
Police Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a % of
total posts)
Administra
tors No. No. No. No. %
4 – 6 5 6 5 1 16%
7 – 9 17 42 17 25 59.5%
10 – 12 38 83 38 45 54.2%
13 – 15 53 160 53 107 66.8%
Total 113 291 113 178 61.1
96
Table 3.56: FINANCIAL PERFORMANCE: POLICE/TRAFFIC AND SECURITY
Operational Budget
Year -2015/2016
Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment Budget
Total Operational Revenue, -74,255,025 -74,220,982 -52,670,499 -21,550,483
Expenditure:
Employees 103,356,622 93,348,045 80,569,157 12,778,888
Repairs and Maintenance 6,621,929 16,221,929 12,917,282 3,304,647
Other 47,335,407 69,133,000 54,264,983 14,868,017
Total Operational Expenditure 157,313,958 178702974 147,751,422 30,951,552
Net Operational Expenditure 83,058,933 104,481,992 95,080,923 9,401,069
Table 3.57: CAPITAL EXPENDITURE: POLICE/TRAFFIC AND SECURITY
Capital Projects
Year 2015/16
Budget Adjustment
Budget
Actual
Expenditure
Variance from
adjustment
budget
Installation of CCTV cameras ,2,200,000 3,200,000 2,518,604 681,396
Traffic Law Enforcement
cameras (fixed) 1,000,000 0 0 1,000,000
Law Enforcement Cameras
(Digital Cameras) 500,000 - 426,809 73,191
OVERRALL PERFOMANCE OF SAFETY AND SECURITY
In the financial year under review the city has conducted (32) street trading operations and (23) crime prevention
activities targeting known (24) crime hotspots to ensure compliance to municipal by-laws and contribute towards
reducing incidents of crime. The city has also met its targets in relation to issuance of notices on varied traffic
violations by issuing 172 266 speed fines, 4 566 of notices to motorist driving un-roadworthy vehicles and 4 529
notices to motorists not wearing seatbelts. Furthermore the city has been successful in the collection 20 752 of
speed fines paid.
3.15 FIRE
The Fire and Rescue Services aims to prevent fires. Focus is thus placed on fire prevention and public education
/ awareness with emergency response being the last line of defence.
97
During the period under review 2 556 inspections were conducted at premises to which the general public has
access. The aim of these inspections is to ensure compliance with statutory fire safety measures. During the
same period 466 Health Care Workers were trained in basic fire safety and evacuation procedures. Focus was
also placed on public fire safety awareness with a total of 22 campaigns being conducted. The Fire and Rescue
Service also participated in the Bloem Show. Thirty (30) Fire Safety awareness contact sessions were
conducted with commerce and industry institutions resulting in 355 persons being exposed to fire safety in the
work place.
Table 3.58: METROPOLITAN FIRE SERVICE DATA
Metropolitan Fire Service Data
Details Year 2014/15 Year 2015/16
Actual No. Estimate No. Actual No.
Total fires attended in the year 915 920 831
Total of other incidents attended in
the year 284 300 739
Average turnout time - urban areas 10 minutes 10 minutes 11 minutes
Average turnout time - rural areas 18 minutes 18 minutes 19 minutes
Fire fighters in post at year end 112 151 112
Total fire appliances at year end 26 26 26
Average number of appliance off the
road during the year 5 5 2
98
Table 3.59: FIRE SERVICE POLICY OBJECTIVES TAKEN FROM THE IDP
3.59.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Prevent or reduce
losses that occur due
to natural or man-
made disaster through
preparedness,
mitigation, response
and recovery
Effective and
efficient
dispatching of
emergency
resources to fire
and rescue calls
Number of fire
and rescue calls
to which
resources were
dispatched
within 3 minutes.
Logged fire and
rescue calls
9.0 out of 10 8 out of 10 8.59 out of every 10
calls, resource
dispatched within 3
minutes
+0.59 Positive
Variance
To limit the number of
fire deaths resulting
from accidental fires in
residential buildings
Delivery of
Operational Fire
and Rescue
Services in the
entire MMM area
complying to
SANS 10090
Number of fire
and rescue
emergency
responded to in
compliance with
SANS 10090
i.r.o:
Weight of
response
Turn out time
Report on fire and
rescue emergency
responded to in
compliance with
SANS 10090 i.r.o
8.5 out of 10 7.5 out
of 10
8.7 out of 10 (729 out
of 831)
None required
99
3.59.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
To limit the
number of fire
deaths resulting
from accidental
fires in
residential
buildings
Delivery of a pro-
active Fire Safety
Service to MMM
through regular
inspections and
scrutiny of building
plans
Fire safety
inspections at High
Risk Premises to
determine level of
compliance with
statutory fire safety
measures and
approved building
plans
Number of fire safety
inspections at High
Risk Premises
113 fire safety
inspections at High
Risk Premises
90 fire safety
inspections at High
Risk Premises
95 fire safety
inspections at High
Risk Premises
None
+5 Positive
variance
Delivery of a pro-
active Fire Safety
Service to MMM
through regular
inspections and
scrutiny of building
plans
Fire safety
inspections at
Moderate Risk
Premises to
determine level of
compliance with
statutory fire safety
measures and
approved building
plans
Number of fire safety
inspections at
Moderate Risk
Premises
256 of fire safety
inspections at
Moderate Risk
Premises
250 of fire safety
inspections at
Moderate Risk
Premises
306 of fire safety
inspections at
Moderate Risk
Premises
None
+56 Positive
Variance
Delivery of a pro-
active Fire Safety
Service to MMM
through regular
inspections and
scrutiny of building
plans
Fire safety
inspections at Low
Risk Premises to
determine level of
compliance with
statutory fire safety
measures and
approved building
plans
Number of fire safety
inspections at Low
Risk Premises
1722 fire safety
inspections at Low
Risk Premises
1800 fire safety
inspections at Low
Risk Premises
2155 fire safety
inspections at Low
Risk Premises
None
+355 Positive
Variance
Delivery of a pro-
active Fire Safety
Service to MMM
through regular
inspections and
scrutiny of building
plans
Conducting Fire
Safety Compliance
Certificate
inspections
Percentage of Fire
Safety Compliance
Certificates
inspections
conducted within 2
working days after
receipt of request
98% of Fire Safety
Compliance
Certificates
inspections
conducted within 2
working days after
receipt of request
70% of Fire Safety
Compliance
Certificates
inspections
conducted within 2
working days after
receipt of request
100% (320 out of 320)
of Fire Safety
Compliance
Certificates
inspections conducted
within 2 working days
after receipt of request
None
+20% Positive
variance
100
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
To limit the
number of fire
deaths resulting
from accidental
fires in
residential
buildings
Educating key
target groups such
as health care
workers, learners
at school and
vulnerable
members of the
community in fire
safety and disaster
management
Training of Health
Care Facility staff
members in fire
safety and
evacuation
procedures
Number of Health
Care Facility staff
members trained
448 Health Care
Facility staff
members trained
250 Health Care
Facility staff
members trained
206 Health Care
Facility staff members
trained
None
- 44
Health Care
Facility staff
members trained
Educating key
target groups such
as health care
workers, learners
at school and
vulnerable
members of the
community in fire
safety and disaster
management
Conducting public
outreach events
aimed at creating
public awareness in
respect of Fire safety
Number of public
outreach events
conducted
18 public outreach
events conducted
6 public outreach
events conducted
30 public outreach
events conducted
None +24 Positive
variance
Provide formal fire
training persons
from the industrial
and commercial
community that
Training of persons
from the industrial
and commercial
community in fire
safety
Number of persons
trained
433 persons trained 200 persons trained 466 persons trained None
+216 Positive
variance
Skills
enhancement and
maintenance of
Fire fighting staff
Presenting training
courses in relation to
fire fighting and/or
rescue and/or
hazardous materials
Number of training
courses presented
3 training courses
presented
3 training courses
presented
22 training courses
presented
None
+16 Positive
variance
101
Table 3.60: EMPLOYEES: FIRE SERVICES
Employees: Fire Services
Job Level Year -1
(2014/15) Year 2015/16
Fire Fighters Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a
% of total posts)
Administrators No. No. No. No. %
0 – 3 1 1 1 0 0%
4 – 6 4 8 4 4 50%
7 – 9 31 69 31 38 55%
10 – 12 112 169 112 57 34%
13 – 15 0 6 0 6 100%
16 – 18 9 17 9 8 47%
Total 157 270 157 113 42%
Table 3.61: FINANCIAL PERFORMANCE: FIRE SERVICES
Financial Performance Year: Fire Services
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue -592 -775,678 -458,052 -514,018 55,966
Expenditure:
Fire fighters 42,825 66,809,534 60,158,910 54,226,370 5,932,540
Repairs and
Maintenance 426 714,338 714,338 436,509 277,829
Other 1,960 5,603,856 6,403,856 3,181,118 3,222,738
Total Operational
Expenditure 45,211 73,127,728 67,277,104 57,843,997 9,433,107
Net Operational
Expenditure 44,619 72,352,050 66,819,052 57,329,979 9,489,073
102
Table 3.62: CAPITAL EXPENDITURE: FIRE SERVICES
Capital Projects
Year 2015/16
Budget Adjustment
Budget
Actual
Expenditure
Variance from
adjustment
budget
New Southern Region Fire Station 0 R 1 725 565 R 1 454 338 R 271 226
COMMENT ON THE PERFORMANCE OF FIRE SERVICE OVERALL
The City continues to provide effective fire service and all the set performance target were met for the period
under review. Construction of an additional fire station in the south eastern area has been completed and when
opened will considerably reduce response times to incidents in the area. Four specialist emergency vehicles
were replaced during the period under review which contributed positively to the fleet availability.
3.16 DISASTER MANAGEMENT
The Disaster Management sub directorate is performing its functions and duties in accordance with the Disaster
Management Act 2005 (57/2002). MMM established a Disaster Management Centre that is the focal point for
all disaster related management activities. It effectively renders a critical service to the community relating to
call receiving and dispatching emergency resources to all types of emergency and disaster incidents. The centre
is making use of an Intelligence Information Management System (IIMS) to capture all information. Call Centre
Operators are deployed 24/7 on a shift system. Ninety two percent (92%) of all calls received relating to
emergency incidents were dispatched within 3 minutes to emergency functionaries (Fire & Rescue and Public
Safety).
The top 3 service delivery priorities are:
a) Enhance emergency preparedness
b) Ensure prompt and appropriate response to emergency incidents
c) Ensure prompt and appropriate post incident recovery
Disaster Management encompasses a continuous, integrated, multi-sectoral and multi-disciplinary process of
planning and implementation measures incorporating strategies for pre disaster risk reduction as well as post
disaster recovery, aimed at:
preventing or reducing the risk of disasters
mitigating the severity or consequences of disaster
emergency preparedness
rapid and effective response to disasters
post disaster recovery and rehabilitation
103
Checklists and measurements were implemented to ensure compliance with standards set to ensure service
delivery. Disaster Management staff are involved in public education programmes to enhance community
resilience against disasters and negative effects thereof. The City is in its strides to comply with National
Legislation relating to risk reduction and response and has complied and completed the following:
Disaster Management Plan
Disaster Management Framework
Risk and Vulnerability Assessment
During the period under review a hundred and sixty six (166) assessments of individual properties affected by
unplanned events (e.g. severe weather, fire, etc.) were conducted to give effect to rapid and effective response
to emergency incidents. To ensure compliance to Section 18 of the SA Sports & Recreation Events Act
(SASREA Act), 2010, the sub directorate conducted sixty nine (69) Safety and Grading assessments and
attended forty seven (47) Joint Operating Centres & a hundred and six (106) Event planning meetings.
104
Table 3.63: SERVICE DELIVERY OBJECTIVES FOR DISTASTER MANAGEMENT
3.63.1 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Prevent or
reduce losses
that occur due to
natural or man-
made disaster
through
preparedness,
mitigation,
response and
recovery
Attendance of
Joint Operations
Centre (JOC) at
public events at:
All stadia in MMM;
All venues
(capacity more
than 2000
persons)
Percentage of JOC
attendance at public
events
JOC attendance at
public events
100% 90% 100% None
+10% Positive
Variance
Customer
satisfaction with
services rendered
by the Control
Centre.
Number [percentage] of
callers polled indicating
their satisfaction with the
service rendered by the
Control Centre.
Customer
Satisfaction survey
Report
9 out of 10 9 out of 10 10 out of 10 [100%] None +1 out of 10 Positive
Variance
Recruitment and
training of Disaster
Management
Volunteers
Number of Volunteers
recruited and trained
Number of
volunteers recruited
and trained
New 100 volunteers
recruited and trained
100 volunteers
recruited and trained
None none
Educating the
public on Disaster
risk management
Number of Disaster Risk
Management Education
and Awareness
Campaigns conducted
Number of Disaster
Risk Management
Educations
Awareness
Campaigns
conducted
New 6 campaigns
conducted
8 campaigns
conducted
None
+2 Positive Variance
105
Table 3.64: EMPLOYEES DISASTER MANAGEMENT
Employees: Disaster Management, Animal Licensing and Control, Control of Public Nuisances, Etc.
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees
Vacancies
(fulltime
equivalents)
Vacancies (as a
% of total posts)
No. No. No. No. %
0 – 3 0 1 1 0 0
4 – 6 1 3 0 3 100
7 – 9 9 14 8 6 42,8
10 – 12 8 19 7 12 63,1
13 – 15 1 3 1 2 66,6
16 – 18 0 0 0 0 0
Total 19 40 17 23 57,5
Table 3.65: FINANCIAL PERFORMANCE DISASTER MANAGEMENT
Financial Performance: Disaster Management, Animal Licensing and Control, Control of Public
Nuisances, Etc.
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue 0 -74,225,025 -74,220,982 -52,670,499 -21,550,483
Expenditure:
Employees 8,674 103,356,622 93,348,045 80,569,157 12,778,888
Repairs and
Maintenance 66 6,621,929 16,221,929 13,096,925 3,125,004
Other 251 47,335,407 69,133,000 54,264,983 14,868,017
Total Operational
Expenditure 8,717 157,313,958 178,702,974 147,931,065 30,771,909
Net Operational
Expenditure 8,717 83,088,933 104,481,992 95,260,566 9,221,426
106
COMMENT ON THE PERFORMANCE OF DISASTER MANAGEMENT OVERALL
The City is performing well in relation to disaster management services and the set measurable performance
targets are being met. Ninety two (92%) of calls received are dispatched within 3 minutes. This is well above
the 80% target, enhancing emergency services to respond quickly to incidents.
COMPONENT H: SPORTS AND RECREATION
3.17 INTRODUCTION TO SPORT
Mangaung Metropolitan Municipality has set itself a lofty ideal of being a “Sporting Mecca” through supporting
sport development. The SRSA has undertaken to deal only with recognized legitimate structures and people
interested in sport need to belong to such a structure.
The City has the responsibility of initiating programmes. Delivery of sport is the competency of the various
federations, and delivering mass based sport is the function of Government.
NSRDP (National Sport & Recreation Development Plan) is the guiding and working document in SA
107
Table 3.66: SERVICE DELIVERY OBJECTIVES FOR SPORTS AND RECREATION
3.66.1 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Regulation of
Initiation Schools
in the Metro
Ensure
compliance with
FS Initiation
School Health Act
no 1 of 2004 and
Regulations.
Number of e initiation
school applications
approved in terms of
the FS Initiation
School Health Act 1
2004.
Number of known
Initiation Schools
inspected
34 known Initiation
Schools inspected
Keep record and
ensure compliance
No inspections done
as yet, since it is the
1st week of Initiation
School operations
None none
Promote and
support sports
and recreation in
the Metro
Promote and
support sports
and recreation
Host and support
sporting code
programmes
Number of sporting
code programmes
supported
71 sporting code
programmes
supported
4 sporting code
programmes
supported
19 sporting code
programmes
supported
None
+15 Positive
Variance
Promote and
support sports
and recreation in
the Metro
Promote and
support sports
and recreation
Implement sporting
code programmes
Number of sporting
code programmes
implemented
New - Add Please 4 programmes and
codes implemented
23 sporting code
programmes
implemented
None
+19 Positive
Variance
108
Table 3.67: EMPLOYEES: SPORT
Job Level
2015/16
Posts Employees
Vacancies
(fulltime
equivalents)
Vacancies (as
a % of total
posts)
No. No. No. %
0 – 3 0 0 0 0%
4 – 6 5 4 1 20%
7 – 9 3 1 2 66.66%
10 – 12 6 5 1 16.66%
13 – 15 0 0 0 0%
16 – 18 0 0 0 0%
Total 14 10 4 28.57%
Table 3.68: FINANCIAL PERFORMANCE SPORTS AND RECREATION
Financial Performance: Sport and Recreation
R'000
Details
30/06/2015 30/06/2016
Actual
Original
Budget
Adjustment
Budget
Actual Variance to
Adjustment
Budget
Total Operational
Revenue -658,617 -5,914,660 -5,914,660 -7,301,883 1,387,223
Expenditure:
Employees 2,582,944 74,934,309 57,562,069 51,897,522 5,664,547
Repairs and
Maintenance 254 9,421,440 10,313,480 8,030,731 2,282,749
Other 2,088,674 65,799,055 73,183,042 46,890,555 26,292,487
Total Operational
Expenditure 4,671,871 150,154,804 141,058,591 106,818,808 34,239,783
Net Operational
Expenditure 4,013,254 144,240,144 135,143,931 99,516,925 35,627,006
109
COMPONENT I: CORPORATE POLICY OFFICES AND OTHER SERVICES
INTRODUCTION TO CORPORATE POLICY OFFICES
The role of the unit is to provide the following services:
To ensure effective management of the city addressing agreed political priorities.
To ensure that the operation of the city is restructured to deliver effectively.
To ensure that citizens are given sufficient information, opportunity and encouragement to
participate in and influence the affairs of the municipality.
To ensure that the municipality will use information and communication technology effectively to
assist in decision making, in working efficiently , and in delivering services more effectively to clients.
To promote the overall wellness of MMM staff and provide support systems to maintain such.
3.18 EXECUTIVE AND COUNCIL
To ensure that MANGAUNG has an Integrated Development Plan (IDP) and Budget agreed with
all stakeholders, and in which communities have participated, which addresses the challenges of
growth and redistribution.
To ensure that residents are aware of the policies, services and activities of the municipality.
To ensure that residents are aware of the activities of the municipality.
110
Table 3.69: SERVICE DELIVERY OBJECTIVES OF EXECUTIVE AND COUNCIL
3.69.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Strengthening
International
relations
Liaison with foreign
diplomats
Invitation of BRICS and
African Diplomats to
MMM
MOU with BRICS
Cities and African
City
0 2 MOU’s with BRICS
Cities and African
city
0 More
engagements
with BRIC’s and
identified African
city
-2 MOU’s with
BRICS Cities and
African city
Strengthen
community
involvement to
participate in the
affairs of the
municipality and
influence resource
allocation
Enhance public
participation in the
affairs of the
municipality
49 ward development
plans developed and
approved by council
Develop and
approve clustered
wards base plans
0 10 clustered ward
based plans
0 Provide on-
going
capacitation on
ward based
planning
-10 clustered ward
based plans
111
3.69.2 OPERATIONAL
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target 2015/16 Actual Performance
2015/16
Corrective
Action
Variance
Provide strategic
leadership and
planning with well-
defined targets
aligned to the
budget
Provide strategic
leadership,
involvement and
planning
Reviewed Integrated
Development Planning,
SDBIP and business
plans
2015/16 reviewed
IDP approved by
council
Reviewed IDP and
SDBIP 2015/16
Reviewed IDP 2016/17 Reviewed IDP 2016/17 none none
Service delivery and
budget implementation
plan (SDBIP) compiled
annually
SDBIP developed
and approved
Service delivery
and budget
implementation
plan (SDBIP)
compiled annually
2016/17 SDBIP
developed and approved
by the Executive Mayor
28 days after the
approval of the IDP and
budget
2016/17 SDBIP
developed and
approved by the
Executive Mayor 28
days after the approval
of the IDP and budget
none none
Mid-year budget and
performance
assessment report
developed
Mid-year budget and
performance
assessment report
approved
Mid-year budget
and performance
assessment report
developed
2015/16 mid-year budget
and performance
assessment report
2015/16 mid-year
budget and
performance
assessment report
none none
Strengthen
performance
management
system
Improve
performance
management and
accountability
Performance
management system is
embedded within the
institution through
training and induction
Performance
Reports Approved
5 performance
reports developed
5 performance reports
developed
5 performance reports
developed
none none
Strengthening
Intergovernmental
Relations
Start collaborating
on planning of
projects
There will be
cooperation
agreements entered
into.
MoU’s with provincial
departments and
other institutions
N/A 2 MoU’s with provincial
departments and other
institutions
MoU signed with the
Central University of
Technology
Fast-track formal
engagements
with strategic
departments
-1 MoU
outstanding
112
3.19 FINANCIAL SERVICES
INTRODUCTION TO FINANCIAL SERVICES
The office coordinates all the functions such as budgeting, accounting, analysis, financial reporting, cash
management, debt management, supply chain management, financial management, etc.
Table 3.70: DEBT RECOVERY
Debt Recovery
Details of the types of
account raised and
recovered
2015/16 in R’000
Budget for the year
Actual accounts
billed in year
Proportion of
accounts value
billed that were
collected%
Property Rates 745,311 752,220 150.33%
Electricity 2,275,719 2,064,276 95.00%
Water 663,676 646,025 51.52%
Sanitation 197,101 281,783 54.07%
Refuse 89,486 116,029 52.25%
Other 1,376,731 784,472 80.03%
Total 5,348,024 4,644,805
113
Table 3.71: SERVICE DELIVERY OBJECTIVES OF FINANCE IN THE IDP
3.71.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target 2015/16 Actual Performance
2015/16
Corrective Action Variance
Prudent fiscal
management
Implement
clean audit
initiatives
An improved audit
outcome
Audit report Financially unqualified
Audit Report
Financial Unqualified
Audit Report
Financial Unqualified
Audit Report
None None
Prudent fiscal
management
Improved
Credit Rating
Long term and
short term credit
rating
Section 71 report A3.za rating Maintain A3.za rating Long Term Issuer Rating
– Ba1
Engage with
Moody’s Investors
Service to conduct
comprehensive
assessment
Revenue
Enhancement
Collect all
collectable
revenue and
Leverage
alternative
sources of
funding
Amount of
externally sourced
funds
Increasing
revenue base by
accounting for
unaccounted
services
Section 71 report R 600 Million R 750 million Tender for R500 million
loan advertised
Growth and
Development
Strategy be
developed and
clear Long Term
Financial Plan and
Strategy be
aligned to strategic
objectives
-R250
million
Revenue
Enhancement
Identification of
additional
revenue
streams
100%
implementation of
revenue
enhancement
strategies
Section 71 report 100% implementation of
long term enhanced
revenue strategy
100% implementation of
long term Revenue
Enhancement Strategy
80% implementation of
long term Revenue
Enhancement Strategy
Engage with
management to
reconsider
municipal bond
issuance
-20%
Improve revenue
collection
Implement
credit control
measures
Collection rate to
be improved to
95%
Percentage of
collection of debt
91% 95% collection rate 87.06% Full
implementation of
Credit Control and
Debt Collection
By-Laws
-7.94%
Percentage
increase in the
number of handed
over accounts
successfully
collected
Number of
accounts handed
over to attorneys
successfully
collected
-
15 000
21 372
None
None
114
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target 2015/16 Actual Performance
2015/16
Corrective Action Variance
Percentage
increase in the
number of
defaulting
businesses
litigated
Number of
businesses
litigated
- 500 293 Attachment/
Auction properties
207
Percentage
increase in the
number of
defaulting
domestic
customers
garnished
Number of
defaulting
domestic
customers
garnished
4 000 2 658 Full
implementation of
Credit Control and
Debt Collection
By-Laws
-1 342
115
3.71.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual Performance 2015/16 Corrective Action Variance
Improve customer
satisfaction
Improve billing
system
Number of
customers
receiving accurate
bills
Percentage of
customers
receiving
accurate bills
22%
0%
Reduce the interim
meter readings to
20%
19% of accounts estimated None None
Register 10 000
customers to
receive their
accounts through
mms/email
5 627 New accounts were
registered on emails as well as
approximately 3 400 people
additionally received their
accounts by MMS
Additional options
are being
developed to
include more email
addresses per
customers and to
make emails more
easily available to
consumers.
-973
Customer queries
resolved within 7
days
95% of customers
queries raised and
resolved within 7
days
% of customer
queries resolved
N/A
95%
70%
Separate registers
for queries to be
introduced for all
departments.
Monitoring of
outstanding
queries and
improve
turnaround times
to resolve the
queries within 4
days.
-30%
Improve revenue
collection
Collection rate to
be improved to
95%
% collection of
debt
91% 95% collection
rate
87.06% Full
implementation of
Credit Control and
Debt Collection
By-Laws
-7.94%
Percentage
increase in the
number of handed
over accounts
successfully
collected
Number of
accounts handed
over to attorneys
successfully
collected
N/A 15 000 21 372 None None
116
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual Performance 2015/16 Corrective Action Variance
Improve customer
satisfaction
Improve revenue
collection
Percentage
increase in the
number of
defaulting
businesses
litigated
Number of
businesses
litigated
N/A 500 293 Attachment/
Auction properties
-207
Percentage
increase in the
number of
defaulting
domestic
customers
garnished
Number of
defaulting
domestic
customers
garnished
N/A 4 000 2 658 Full
implementation of
Credit Control and
Debt Collection
By-Laws
-1 342
Prudent fiscal
management
Quality and
frequent financial
reporting
95% operation
and capital
expenditures
against the budget
(from 80% )
% spent against
the budget
N/A 95%
98%
None
None
Prudent fiscal
management
To ensure
procurement
processes which
complies fully with
the SCM policy
All risk of awarding
tenders to
employees of state
is eliminated
% of awarded
contracts in line
with SCM
regulations
N/A 100% compliance
100% compliance
None
None
Reduce irregular
expenditure from
100% of 2014
incurred irregular
expenditure
% of irregular
expenditure
N/A 0% Irregular
Expenditure
0% Irregular Expenditure
In Finance Directorate
None None
SCM reports
submitted to
Mayor and Council
Number reports
submitted
N/A 4 Reports 4 Reports None None
Prudent fiscal
management
Cost Coverage
(NKPI)
Month(s)
Coverage
Number of
months
N/A > 3 months 0.57 months Full
implementation of
Credit Control and
Debt Collection
By-Laws
Cost cutting
measures to be
implemented
-2.43
months
117
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual Performance 2015/16 Corrective Action Variance
Prudent fiscal
management
Pay creditors on
time as per MFMA
Number of days it
takes to pay
creditors
% of creditors
paid within 30
days
N/A 100% 78% Departments to
submit invoices
and claims
timeously to allow
appropriate cash
flow monitoring
-22%
Prudent fiscal
management
Budget prepared
and submitted in
line with MFMA
requirement
Number of
budgets submitted
to National
Treasury
Number of
budgets
submitted
N/A Credible and
funded Draft,
Revised and Final
Budget submitted
Credible and funded Draft,
Revised and Final Budget
submitted
None
None
Develop and
review out-dated
policies in the
directorate
Number of
reviewed policies
approved by
Council
Number of
policies
N/A Number of
reviewed policies
approved by
Council
14 Budget Policies considered
and/ or revised with the Budget
None None
Revenue
Enhancement
Develop new
valuation roll
based on the site
and any
improvements
made
Number of
Valuation roll
compiled and
revisions made
annually
Appeals finalized
and accounts
adjusted
accordingly
Updated valuation
roll
Number of
appeals concluded
by valuation
appeal board
N/A 2000 appeals
concluded by
valuation appeal
board
5 381 appeals completed
None None
Number of Interim
valuation roll
prepared and
implemented bi-
annually
Interim valuation
rolls implemented
bi-annually
Number of Interim
valuation rolls
implemented
N/A 2 Interim valuation
rolls implemented
bi-annually
1 Interim Valuation Roll
implemented
Update and avail
information for
compilation of
Interim Valuation
Rolls and
implement in the
second quarter of
the 2016/17
financial year
-1 Interim
valuation roll
General Valuation
Roll process
initiated and
valuer appointed
General Valuation
Roll completed
and implemented
% completion in
appointment of
municipal valuer
N/A Municipal Valuer
appointed
DDP Valuers appointed None None
Develop an
effective asset
management
programme
Develop a Fixed
Asset Register
which records all
municipal Assets
Fixed Asset
Register is
compiled and
updated monthly
Number of
updates
N/A 12 updates/ asset
additions
processed on
Asset Register
Other Assets updated on a
monthly basis. CAPEX spending
captured on a monthly basis and
unbundled in July 2016.
None None
118
IDP Objective Strategy KPI Unit of
Measurement
Past Year Performance
2014/15
Annual Target
2015/16
Actual Performance 2015/16 Corrective Action Variance
Develop an Asset
Management
Policy and
Procedure Manual
to cover the
acquisition,
maintenance and
disposal of assets
Asset
Management
procedure is
compiled in line
with legislation
and council policy
Number of
reviewed policies
and procedures
Reviewed Asset
Management
Policy and
procedure manual
Asset management policy
unchanged Asset management
sytem methodology and
procedure manual developed
None None
Periodic physical
asset counts and
impairment tests
Report on the
annual asset
count submitted
to council
Number of asset
count conducted
Complete count of
all movable and
immovable assets
mid-year and at
year-end (2 Bi-
annual counts).
Verification of all movable assets
were done during 2015/2016
None None
119
Table 3.72: EMPLOYEES FINANCIAL SERVICES
Employees: Financial Services
Job Level
Year -1 Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as
a % of total
posts)
No. No. No. No. %
0 - 3 17 18 18 0 0%
4 - 6 46 93 46 47 51%
7 - 9 74 108 79 29 27%
10 - 12 129 138 115 23 17%
13 - 15 8 94 16 78 83%
16 - 18 20 22 10 12 55%
Total 294 473 284 189 40%
Table 3.73: FINANCIAL PERFORMANCE: FINANCIAL SERVICES
Financial Performance: Financial Services
R'000
Details
30/06/2015 30/06/2016
Actual
Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue -177,359,428 -1,347,952,606 -1,175,608,361
-
1,119,600,769 -56,007,592
Expenditure:
Employees 92,387,012 127,244,408 127,244,408 103,862,839 23,381,569
Repairs and
Maintenance 3,395,437 3,412,988 1,000,596 77,051 923,545
Other 119,413,794 234,525,746 227,540,062 212,932,871 14,607,191
Total Operational
Expenditure 215,196,244 365,183,142 355,785,066 316,872,761 38,912,305
Net Operational
Expenditure 37,836,815 -982,769,464 -819,823,295 -802,728,008 -17,095,287
Table 3.74: CAPITAL EXPENDITURE FINANCE
Capital Projects 2015/16
Budget Adjustment
Budget
Actual
Expenditure
Variance from
adjustment
budget
Total All
New Office Block Mangaung 0 4,854,670 6,399,220 -1,544,550
Asset Management System 750,000 0 0 750,000
3.20 HUMAN RESOURCES SERVICES
120
The strategic objective of human resource management is to lead, manage and direct human resource functions
within the MMM through the following:
a) Labour relations
b) Occupational health and wellness
c) HR benefits
d) Work study
e) Job evaluation
f) Payroll Management
g) Safety and loss control
h) HR Systems
i) Individual performance Management
j) Employment
Table 3.75: EMPLOYEES HUMAN RESOURCES SERVICES
Employees: Human Resource Services
Job Level
Year -1
(2014/15) Year 2015/16
Employees Posts Employees Vacancies (fulltime
equivalents)
Vacancies (as a % of
total posts)
No. No. No. No. %
0 - 3 13 11 2 15%
4 - 6 37 26 11 29%
7 - 9 24 23 1 45%
10 - 12 24 15 9 37.5%
13 - 15 3 1 2 66%
16 - 18 1 1 0 0 %
Total 102 77 25 24%
121
Table 3.76: FINANCIAL PERFORMANCE: HUMAN RESOURCE SERVICES
Financial Performance: Human Resource Services
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget Actual
Variance to
Adjustment
Budget
Total Operational
Revenue -1,965,254 -1,965,254 -1,965,254 -1,605,345
Expenditure:
Employees 25,451,674 24,088,363 - 19,694,165
Repairs and
Maintenance - 30,802 - 30802
Other 1,122,861 2,979,909 - 865281
Total Operational
Expenditure 26,574,535 330,589,17 - 24,391,719
Net Operational
Expenditure 24,609,281
122
Table 3.77: SERVICE DELIVERY OBJEVTIVES FROM THE IDP HUMAN RESOURCES
3.77.1 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Improved labour
relations
management
Foster good
relationship with
organised labour
and conclude all
outstanding labour
disputes
Number of
consultative
meetings held with
organised labour
Number of LLF
Meetings held
12 meetings 12 meetings with
Organised Labour
9 - -
Retention of
scarce skills
Identification of
critical scarce skills
and creation of
development plans
for each
Number of Critical
scarce skills
identified and
development plans
created
None 5 Critical positions
identified and
development plans
created (Piloting in
Engineering Services)
5 scarce and critical
positions identified,
mode of interventions
in place to address
shortages
None N/A
Compilation of a
work skills plan
Compiling a work
place skills plan by
July each year
Done Approved work skills
plan
Analysis was made,
consultations with
relevant stakeholder,
information
consolidated, captured
electronically and
submitted on time for
2016/17 WSP/ATR
None N/A
Compilation of
monitoring and
evaluation report by
Sep 2015 and March
2016.
Number of
Monitoring Reports
sub to LGSET.
Done 2 Monitoring Reports
2015-2016 WSP
Implementation
Three visits were
conducted for 2015/16.
Already we have 1 visit
for 2016/17.
None N/A
Implementation of
learnership
programmes
Number of
learnership
implemented
4 6 Take in to
consideration the SCM
Processes, procedures
and time frames.
6 Submitted the sub-
directorate
acquisition plan for
2016/17 with SCM.
Good
Governance
Review and
development of job
descriptions for all
positions
%of job descriptions
reviewed, updated
and compiled
% of job descriptions
compiled
Nil 50% of all job posts 25% achieved as
planned
N/A None
123
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual Performance
2015/16
Corrective
Action
Variance
Good
Governance
Design and
development of
Individual
Performance
Management
system
1 x IPMS Developed Council approved
Policy in place
Nil 1 x IPMS developed
and approved by
Council
Draft policy presented
only at HR Policies
Forum
Effective and
efficient
recruitment
management
system
HR Management
System
1 x Recruitment and
Selection
Management
System Developed
and Implemented
Manuals in place Recruitment and
Selection Management
System Developed
and Implemented
None To be approved
at LLF
Pilot System
124
COMMENT ON PERFORMANCE OF HUMAN RESOURCES SERVICES OVERALL
The City has succeeded in restoring and improving labour relations. Workplace Skills Development
Plan has been developed, ratified by labour and subsequently approved by the Local Government
Sector Education Training Authority (LGSETA). In pursuit of developing its Human Capital, the City has
implemented 80% of its workplace skills plan. Five (5) training programmes approved by LGSETA have
been implemented.
The City has not succeeded in meeting set performance targets in relation to convening of LLF and
reduction of labour disputes. A number of policies related to HR as depicted in Table 4.4 have been
developed and approved whilst others are currently serving at the Local labour Forum and its HRD Sub
Committee. The City has not also met is targets in relation to providing learnership approved by
LGSETA.
3.21 INFORMATION AND COMMUNICATION TECHNOLOGY (ICT)
The ICT Sub Directorate serves as the focal point for technology advancement in the institution. The
ICT Sub Directorate provides control in areas of planning, operation, and maintenance of technology
infrastructure, systems, and applications, provide value-added ICT services and solutions to all of the
Mangaung Metropolitan Municipality that enhances service delivery to the Metro.
In broad the ICT Sub Directorate is responsible for the institution’s communications and computer
systems, which include voice, and computer-based technologies. These services and technologies
provide the MMM with the tools essential to effectively carry out day to day operations to support the
overall MMM mission and goals.
The ICT Sub Directorate operates in a collaborative relationship with user departments by facilitating
the identification of the appropriate technology and assisting users and management with the
implementation of that technology. Although management should have the final say in application-
specific decision, the ICT Sub Directorate should guide the selection process by defining standards.
These standards are not hard and fast rules; rather a framework within which range of solutions are
feasible, both from the functional perspective as well as ICT Sub Directorate technical support
capabilities.
The ICT Sub Directorate shall work with all departments to develop Service Level Agreements to
document the roles and responsibilities of the ICT Sub Directorate as well as those of the departments.
Additionally shall the ICT Sub Directorate manage and measure its performance based on the roles
and responsibilities defined.
125
Table 3.78: SERVICE DELIVERY OBJECTIVES OF ICT ROM IDP
3.78.1 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance 2014/15
Annual Target
2015/16
Actual Performance 2015/16 Variance Corrective
Action
Enhance IT
governance and
strategy and
formulate
governance
plans and
strategies, as
well as
accompanying
policies and
procedures, to
concurrently
enable the
municipality to
achieve its
strategic vision,
support audit
requirements,
manage risk,
and exhibit
responsible
financial
management
Develop and monitor
an IT Governance
Framework
Formal IT
Governance
Framework
Quarterly status
report
IT Strategy, IT Steering
Committee
implemented as
required. Policies
developed
IT Governance
Framework.
Draft Governance Framework
Document submission to IT
Steering Committee
None none
Review of the
approved IT Strategy
Overall IT Strategy
Review
Quarterly status
report
IT Strategy, IT Steering
Committee
implemented as
required.
Reviewed and
revised IT Strategy
Draft Governance Framework
Document submission to IT
Steering Committee
None none
Review of IT Master
Systems Plan
ITMSP reviewed
and monitored
Quarterly status
report
IT Master Systems Plan
has been drafted in
relation to the approved
IT Strategy.
Revised IT System
Master plan
submitted
Draft Governance Framework
Document submission to IT
Steering Committee
None None
Internet Connectivity
Penetration
Number of municipal
buildings that are Wi-
Fi enabled and
connected to Wi-Fi
Municipal buildings
enabled with Wi-Fi.
Network tender was
approved to procure
network hardware,
additional Wi-Fi
Management Solution
to be scoped.
4 Wi-Fi Enabled
Municipal Building
4 Buildings
Chris De wet, Bram Fischer,
Regional Office, Supply Chain
None None
Upgrading of Bram
Fischer telephone
system
Upgraded VoIP
system operational
No of Municipal
Buildings migrated to
VOIP
New VoIP system has
been installed, ICT has
experienced numerous
challenges regarding
the existing back bone
network on which the
system is deployed,
and therefore the
supporting network
needs to be upgraded
for an efficient VoIP
telephone system.
Complete
migration to VoIP
telephony for
Targeted 4 x
Municipal Buildings
VoIP telephony for Targeted 4
x Municipal Buildings
None None
Deploy an effective
Electronic Document
Management system
(EDMS)
An Enterprise wide
Electronic Document
Management system
Operational
Electronic Document
Management system
NIL 2 Core Modules
deployed
Sharepoint Production and
QA environment provisioned
(2 core modules) and Intranet
Portal Upgrade
None None
126
Table 3.79: EMPLOYEES: ICT SERVICES
Employees: ICT Services
Job Level
Year -1 Year 2014/15
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as a
% of total
posts)
No. No. No. No. %
0 - 3 4 1 3 75%
4 - 6 21 11 10 47%
7 - 9 41 23 18 43%
10 - 12 12 9 3 25%
13 - 15 2 2 0 0%
16 - 18
Total 80 46 34 42.5%
Table 3.80: FINANCIAL PERFORMANCE: ICT
Financial Performance: ICT Services
R'000
Details
30/06/2015 30/06/2016
Actual Original
Budget
Adjustment
Budget
Actual Variance to
Adjustment
Budget
Total Operational
Revenue 0 0 0 0 0
Expenditure: 0 0 0 0 0
Employees 19,042,662 24,145,264 23,760,264 19,042,662 4,717,602
Repairs and
Maintenance 1,844,582 1,505,000 729,500 1,844,582 -1,115,082
Other 44,134,266 47,878,245 52,507,355 44,134,266 8,373,089
Total Operational
Expenditure 65,021,510 73,528,509 76,997,119 65,021,510 11,975,609
Net Operational
Expenditure 65,021,510 73,528,509 76,997,119 65,021,510 11,975,609
127
Table 3.81: CAPITAL EXPENDITURE ICT SERVICES
Capital Projects Year 2015/16
Budget Adjustment
Budget
Actual
Expenditure
Variance
from
adjustment
budget
PRIVATE CLOUDWARE 200,000 0 0 200,000
DESKTOPS AND LAPTOPS 1,000,000 2,589,850 1,884,851 744,999
ICT SECURITY EQUIPMENT 500,000 0 0 500,000
RADIO LINKS 700,000 0 0 700,000
COMMENTS ON INFORMATION AND COMMUNICATION TECHNOLOGY (ICT)
The strategic use of ICT resources to provide the most value to:
Enable Council and employees to best serve their clients
Increase the efficiency of our resources
Deliver information and services to colleagues and the community
Increase community access to information
Ensure the availability and security of the network and systems
Enable ease of obtaining and sharing of information
Offer flexibility in the workplace
Achieve ICT standardization where possible
Better enable disaster recovery and business continuity of critical systems
The ICT has successfully provided (4) Buildings Chris De wet, Bram Fischer, Regional Office, Supply
Chain with Wi-Fi and VoIP telephony for Targeted (4) Municipal Buildings SharePoint Production and
QA environment provisioned (2 core modules) and Intranet Portal Upgrade.
3.22 LEGAL, RISK MANAGEMENT AND INTERNAL AUDIT SERVICES
Internal Audit
The municipality has established a functional Internal Audit Unit in terms of section 165(1) of the
Municipal Finance Management Act, 56 0f 2003 (MFMA). To this end, the unit has carried out its
functions as outlined in its Charter and section 165(2) of the MFMA.
128
Risk Management
The Municipal Finance Management Act (MFMA), Act 56 of 2003 stipulates that the municipality must
maintain an effective, efficient, transparent and accountable system of Risk Management.
Legal Services
The Legal Services Sub-Directorate’s main purpose is to provide a professional legal advice and
assistance service to the municipality to ensure the proper protection of the municipality’s interests and
compliance with its obligations.
Table 3.82: PRINCIPLES, AIMS AND OBJECTIVES
LITIGATION BY-LAWS
Civil Criminal Labour Revised Newly Developed
17 0 10 14
129
Table 3.83: SERVICE DELIVERY OBJECTIVES FOR LEGAL, RISK MANAGEMENT AND INTERNAL AUDIT SERVICES
3.83.1 STRATEGIC IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target 2015/16 Actual Performance
2015/16
Corrective
Action
Variance
Maintaining strong and
effective oversight
structures
Compliance to good
governance through
Enterprise Wide Risk
Management
Establishment of
effective,
functioning Audit,
Oversight and
Public Accounts
Committees
consisting of
knowledgeable
persons
Audit Committee fully
operational and
meeting at least 4
times annually
Fully operational
Audit Committee
4 Meetings Held At least four (4)
meetings held
6 Meetings
27/08/15
09/10/15
06/11/15
03/12/15
27/01/16
29/03/16
none +2
Pro Active Risk
Management
governance
framework and
processes
Review and
implementation of
Risk management
Policy, Strategy,
implementation plan
Reduce and manage
Risks to acceptable
appetite
0 5 reports on
implementation of Risk
Management and action
plan
3 governance
documents reviewed
- 2015/16 Strategic
Risk Registers
reviewed and updated
-2
Effective Anti-
Fraud and
Corruption
prevention and
response
Review ,
development and
Implementation of
Policy, Strategy,
whistle Blowing and
Prevention Plan
Zero tolerance to
Fraud and
Corruption
14 Reports Investigate all reported
allegations of fraud and
corruption incidences 16
reports developed and
issued
3 Reports on Irregular
Expenditure issued
-13
3.83.2 OPERATIONAL IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
2014/15
Annual Target
2015/16
Actual
Performance
2015/16
Corrective
Action
Variance
Functional
Internal Audit
Activity,
Fully capacitated
Internal Audit
Activity consisting
of competent and
knowledgeable
staff
Functional Internal audit
activity operating
according to the IIA
Standards and approved
risk based three year
rolling strategic audit
plan
Completion of all
planned annual
internal audit
assignments.
All planned audit
assignments
completed with the
exception of IT Audit.
A total of 31 Internal
Audit Reports have
been issued.
Allocate
adequate
resources for
Information
Technology
audits in the
2016/17
Financial Year.
none
130
Table 3.84: EMPLOYEES INTERNAL AUDIT
Internal Audit
Job Level
Year -1 Year 2015/16
Employees Posts Employees Vacancies
(fulltime
equivalents)
Vacancies (as
a % of total
posts)
No. No. No. No. %
0 - 3 1 1 1 0 0%
4 - 6 8 13 8 5 38%
7 - 9 1 9 1 8 89%
10 - 12 1 1 1 0 0%
13 - 15 0 0 0 0 0%
16 - 18 0 0 0 0 0%
Total 11 24 11 13
COMMENT ON THE PERFORMANCE OF LEGAL, RISK MANAGEMENT AND INTERNAL AUDIT
SERVICES OVERALL
Internal Audit
For the 2015/16 financial year, the Unit has completed all its planned allocated audit assignments according to
the approved Internal Audit Plan with the exception of the Information and Communication Technology Audit
which was to be outsourced. For the period under review, the Unit has issued thirty one (31) Internal Audit
reports covering areas audited. Areas audited during the financial year include Supply Chain, Expenditure
Management and Creditors Control, Quarterly SDBIP Reports, Traffic and Parking Garages, Call Centre
Operations, Billing, Outdoor Advertising, Land Use Management, Land and property management, Payroll,
Human Resources Management, Overtime, Loss Control and Fleet and Asset Management
The Unit has supported the municipality’s Audit Committee during the period under review by providing
secretariat services to the six (6) Audit Committee meetings held during the 2015/16 financial year and compiled
two (2) Audit Committee reports that were submitted to Council for discussion.
Risk Management
The following achievements of the city are also worth noting:
The Metro has developed and approved 12 reports on all reported allegations of fraud and corruption
incidences
The Metro has undertaken 100% investigations on all reported cases of irregular, fruitless and wasteful
expenditure
131
Legal Services
The provision of legal advice and assistance to the Council and the administration of the
municipality to ensure the proper protection of the municipality’s interests, and compliance by the
municipality with its legal obligations and responsibilities.
Compilation and promulgation of new and amendments to existing by-laws of the municipality to
ensure that the municipality’s by-laws cover all activities and areas that need regulation, are
constantly reviewed and updated and properly, for the financial year under review the city revised
(10) by-laws and newly developed (14).
Handling of the litigation process for criminal or civil cases in which the municipality, councillors or
officials may become involved in their official capacity to ensure that the municipality’s interests are
properly protected for the financial year under review the city had (17) litigation for civil and (0)
criminal.
3.23 COMPREHENSIVE REPORT ON SDBIP 2015/16
EXECUTIVE SUMMARY OF REPORT
1. This report sets out performance against the Integrated Development Plan (IDP) and Service Delivery
and Budget Implementation Plan (SDBIP) for the period of 2015/16 financial year, i.e. 01 July 2015 to
June 30, 2016. Performance is accounted based on the delivery of projects and/or services in the IDP
and SDBIP for which the Mangaung Council is responsible.
2. The Service Delivery and Budget Implementation Plan (SDBIP) for 2015/16 identifies 84 Strategic
performance measures with key projects and/or services that need to be implemented during the financial
year. Each Department has its number of performance measures to be implemented as depicted below:
Directorates Performance Measures
Planning and Economic Development 15
Engineering Services 22
Strategic Projects 11
Social Service 15
Finance 8
Human Settlement 6
OCM 5
Corporate Services 2
Total 84
132
PURPOSE OF THE REPORT
3. This report on Service Delivery and Budget Implementation Plan (SDBIP) sets out performance against
the Municipality’s Integrated Development Plan as well as Service Delivery and Budget Implementation
Plan for the period of 2015/16 financial year, i.e. 01 July 2015 to June 30, 2016.
BACKGROUND
8. The Integrated Development Plan is the key strategic, inclusive, and responsive performance driven
document for the Municipality which extends over the five-year period. The Integrated Development Plan
is focused on delivering the Council’s eight delivery agenda points or strategic objectives, namely:
a) Poverty eradication, rural and economic development and job creation;
b) Financial sustainability (e.g. revenue enhancement, clean audit);
c) Spatial development and the built environment;
d) Eradication of bucket system and VIP toilets in Botshabelo, Mangaung and Thaba Nchu, focus on
the basics, building solar farming, power plant feasibility study, safety and security;
e) Human settlement;
f) Public transport;
g) Environmental management and climate change;
h) Social and Community Services.
9. The Integrated Development Plan 2015/16 identifies projects and services which contribute to the
achievement of the Municipality’s objectives over the remaining term of Council. These projects and
services are delivered using the approved Council service delivery and budget implementation plan
(SDBIP), which has been used successfully to improve performance in the previous financial years in
strategic areas of Council’s work. The Service Delivery Budget Implementation Plan also contains a
series of performance targets, projects and services, and measures to monitor the success in delivering
improved outcomes for residents and stakeholders in Mangaung municipal area.
133
QUARTERLY PROJECTIONS OF SERVICE DELIVERY TARGETS AND PERFORMANCE INDICATORS
3.23.1 PLANNING
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA
Poverty eradication, rural and economic development and job creation
Public transport
Environmental Management
Spatial development and the built environment
IDP Objective Strategies KPI Unit of
Measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Economic
Development
Rejuvenation of the
CBDs within the
municipality
Number of
Hawking Stalls
developed at
Botshabelo
Completion certificates 100% detailed
designs completed
44 of Hawking Stalls
developed at Botshabelo
79, 55% or 35 Hawking
Stalls developed at
Botshabelo
Extension of time was
granted. The contractor
will endeavour to increase
their number of
resources.
-21.45% or -9 Hawking
Stalls developed at
Botshabelo
Number of
Hawking Stalls
developed at
Thaba Nchu
Completion certificate 100% detailed
designs completed
20 of Hawking Stalls
developed at Thaba
Nchu
Preliminary designs
completed. Service
Provider Paid.
Project halted. Project to
continue after completion
of the Thaba Nchu CBD
Master plan.
-20 of Hawking Stalls
developed at Thaba Nchu
134
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA
Poverty eradication, rural and economic development and job creation
Public transport
Environmental Management
Spatial development and the built environment
IDP Objective Strategies KPI Unit of
Measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Rural
Development
Formulating
Rural
Development
through Agri–
Park
Facilitating rural
development and
supporting rural
enterprises
100%
implementation
of Phase 1 of
Thaba –Nchu
Agri-Park
Project Completion
Certificates
New Indicator 100% implementation of
Phase 1 of Thaba –Nchu
Agri-Park
Competition of the
business plan
Accelerate the
implementation of the
Business Plan
-100% implementation of
Phase 1 of Thaba –Nchu
Agri-Park
Spatial
Integrations
Unlock N8 Nodal
development
Percentage
implementation
of the
Botshabelo/Tha
ba Nchu
economic node
Detailed town
planning designs
80% Concept
designs of the two
nodes
100% completion of
town planning designs
and surveying of
nodes
Not Achieved Accelerate procurement
processes and clarity
institutional arrangement
for co-ordinatiion
-100% completion of town
planning designs and
surveying of nodes
Implementatio
n of the N8
Development
Node
Approved SG plans 95% completion of
the designs,
100% Completion of
surveying and
approved SG plans
Not Achieved Accelerate
procurement processes
and clarity institutional
arrangement for co-
ordinatiion
-100% Completion of
surveying and approved
SG plans
Project Completion
Certificates
95% completion of
the design
95% completion of civil
services
Not Achieved Accelerate procurement
processes and clarity
institutional arrangement
for co-ordinatiion
--95% completion of civil
services
Project Completion
Certificates
95% completion of
the design
100% completion of bulk
services
Not Achieved Accelerate procurement
processes and clarity
institutional arrangement
for co-ordination
-100% completion of bulk
services
135
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA
Poverty eradication, rural and economic development and job creation
Public transport
Environmental Management
Spatial development and the built environment
IDP Objective Strategies KPI Unit of
Measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Implementatio
n of 7 land
parcels
Promotion of
mixed land use
development
Vista Park
extension 2
Detailed engineering
designs
Completion
certificates
Urban design, lay
out plan, signed
lad availability
grant and service
level agreement
100% completed
engineering designs
(Urban design layout
plan)
20% implementation
of phase 1
Urban Designs finalised
and GP calculations and
pegging still in process.
The designs for the
following services have
been finalised:
Roads and storm water,
waste management plan
and broadband
Electricity: The
Preliminary Designs
Report (PDR) for the
MV, LV and House
connections has
been completed in
terms of the Centlec
guidelines and
regulations.
The PDR has been
submitted for evaluation
and approval
Accelerate
implementation according
to the revised
programme indicates the
estimated project duration
and phases
Vista Park
extension 3
Detailed designs 95% planning
completed – SLA
signed, township
application lodged
100% completion of town
planning and approved
SG Plans
The land surveyor
appointed by Calgro M3
has pegged Extensions
256, 257 and 261.
The General Plans for Ext
256, 257 & 261 together
with the approved
Conditions of
Accelerate
implementation according
to the revised
programme indicates the
estimated project duration
and phases
136
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA
Poverty eradication, rural and economic development and job creation
Public transport
Environmental Management
Spatial development and the built environment
IDP Objective Strategies KPI Unit of
Measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Establishment were
submitted with the SG for
approval.
The approved General
Plan for Vista Park Ext
256 was issued on 29
June 2016.
Completion certificates 95% planning
completed – SLA
signed, township
application lodged
100% installation of civil
services
Once the traffic impact
study has been finalised
and approved, and formal
confirmation of bulk
services availability has
been obtained,
installation of services for
the Vista Park Ext 256,
257 and 261 townships
can commence
Accelerate
implementation according
to the revised
programme indicates the
estimated project duration
and phases
-100% installation of civil
services
Completion certificates 95% planning
completed – SLA
signed, township
application lodged
100% installation of
electricity services
Once the traffic impact
study has been finalised
and approved, and formal
confirmation of bulk
services availability has
been obtained,
installation of services for
the Vista Park Ext 256,
257 and 261 townships
can commence
Accelerate
implementation according
to the revised
programme indicates the
estimated project duration
and phases
-100% installation of
electricity services
137
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA
Poverty eradication, rural and economic development and job creation
Public transport
Environmental Management
Spatial development and the built environment
IDP Objective Strategies KPI Unit of
Measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Formalisation of
Brandkop 702
Lodged application
for township
establishment
95% planning
completed for
Brandkop 702;
100% completion of town
planning and approved
SG Plans
Lodged township
establishment application
Township establishment
to be completed
General plan outstanding
100%
completion of
Hillside View
Phase one
Number of social
Rental houses
completed
Construction of
Phase 1.1. has
commenced
Application for
Township Re-layout
lodged
Design of services
completed
940 social rental housing
units completed
100% completion of
Phase 1
Construction for 405
units which is phase 1
has commenced and is
at wall plate level with
no final completions
done due to funding
challenges
Contractors moved out
of sites due to lack of
funding. The Human
Settlements Directorate
continue to engage the
DHS to unlock the
challenges facing the
Social and CRU projects
-940 social rental housing
units completed
Formalisation of
Cecilia Park
Lodged application
for township
establishment
Cecilia Park 95%
planning
completed
100% completion of town
planning and approved
SG plans
Topographical survey is
complete
Township establishment
to be completed
General plan outstanding
Improve Public
Transport
Network
Implementation of
Integrated Public
Transport Network
(IPTN) with Non-
Motorised
Transport Initiatives
100%
completion of
Phase 1 of IPTN
Percentage of
completion of
Operations-and
Business Plan and
infrastructure designs
of phase 1 of IPTN
Procurement of
professional
consultants
100% completion of
IPTN Operations Plan
and Business Plan
100 % upgrading of
Maphisa Road that
constitute phase 1 of
IPTN
The Upgrading of
Maphisa Project is 82%
complete.
The contractual project
completion date is
November 2016 and
according to the
programme, the
construction is ahead of
the projected progress
and will be completed
before the actual
completion date.
In accordance to the set
targets, the variance is -
18%.
138
3.23.2 ENGINEERING SERVICES
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
Municipal KPA Eradication of bucket system, VIP toilets in Bots, Mangaung and TN, focus on the basics, building solar farming, power plant feasibility study,
safety & security
IDP Objective Strategy KPI Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Address roads
conditions
Tar gravel
roads
Km of 7m wide
gravel roads tarred
Completion
certificates for gravel
roads tarred
5.8km 8 km of Gravel Road
tarred
5,29 km of Gravel
Road tarred
N/A -2.71 km of Gravel
Road tarred
Paving of
gravel roads
Km 7m wide
gravel roads
paved
Completion
certificates for gravel
roads paved
3.719 km derived
from 2nd and 3rd Q
3 km of gravel road
paved
5,489 km of gravel
road paved
N/A +2.489
Tarred + Paved =10.7
Heavy
rehabilitation
of existing
main tar roads
Km of 7m wide
roads rehabilitated
Completion
certificates for roads
rehabilitated
36.16 km obtained
from all Quarters of
the last FY
4 km of roads
resurfaced
6,2 km of roads
resurfaced
N/A +2.2 km of roads
resurfaced
Resurfaced
(resealed)
roads
Km of 7m wide
roads resurfaced
Completion
certificates for roads
resurfaced
(resealed)
36.16 km obtained
from all Quarters of
the last FY
14km Resurfaced
(resealed) roads
14,428 km Resurfaced
(resealed) roads
N/A +0.428 km Resurfaced
(resealed) roads
Install storm-
water drainage
Length (Km) of
Storm-water
drainage installed
Completion
certificates for storm-
water drainage
installed
1.27 km obtained
from all Quarters of
the last FY
7km of storm water
drainage installed
6,114 km of storm
water drainage
installed
N/A -0.886 km of storm
water drainage
installed
Eradicate water
backlog
Ensure that
there is
reliable water
supply from
source
Completed
bankable feasibility
study on Gariep
Dam to
Bloemfontein
pipeline
Bankable Feasibility
Study Reports
Pre-feasibility study
in accordance with
the National
Treasury Guidelines
completed.
Bankable feasibility
study 100% completed
100% approved
designs for the
pipeline
Not achieved Accelerate
implementation in new
FY
- 100%
Bankable feasibility
study
Number of water
service points
installed for informal
settlement dwellers
within a 200m radius
Completion certificates 113 communal
standpipes
10 communal standpipes
providing a basic level of
potable water above
RDP standard
2 communal
standpipes providing a
basic level of potable
water above RDP
standard
Standpipes are installed
as per ward councillors'
request
-8 communal
standpipes providing a
basic level of potable
water above RDP
standard
139
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
Municipal KPA Eradication of bucket system, VIP toilets in Bots, Mangaung and TN, focus on the basics, building solar farming, power plant feasibility study,
safety & security
IDP Objective Strategy KPI Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
100% refurbishment
of Maselspoort Water
Treatment Works
Completion certificates N/A 8 pumps installed at
Maselspoort Water
Treatment Works
5 pumps installed at
Maselspoort Water
Treatment Works
To be accelerated in
new FY
-3 pumps installed at
Maselspoort Water
Treatment Works
Kilo metres of water
supply systems
refurbished
Completion certificates N/A 4 km of water supply
system refurbished
(Zastron street pipeline
4 km of water supply
system refurbished
(Zastron street pipeline
none none
Eradicate
sanitation
backlogs
Expand bulk
sanitation
infrastructure
Percentage
expansion of North
Eastern Waste
Water Treatment
Work capacity
Completion
certificates
Phase One
Commissioned
1.1 km outfall sewer
constructed
1.1 km outfall sewer
constructed
none
none
Percentage
extension of
Botshabelo of Waste
Water Treatment
Work capacity
Completion certificates N/A 100% completion of
Phase 1 to extend the
capacity of Botshabelo of
Waste Water Treatment
Work
Not achieved Implementation
approach of building a
new WWTW to be
considered
-100% completion of
Phase 1 to extend the
capacity of Botshabelo
of Waste Water
Treatment Work
Percentage
extension of Thaba
Nchu Waste Water
Treatment Work
capacity
Completion certificates N/A 100% completion of
Phase 1 to extend the
capacity of Thaba Nchu
Waste Water Treatment
Works
100% completion of
Phase 1
None none
100% Upgrading of
Bloemspruit Waste
Water Treatment
Works
Completion
certificates
N/A Construction of 6
digesters
21.50% Works to be completed
in first quarter of 2016-
17
- 78.50%
construction
of 6
digesters
140
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
Municipal KPA Eradication of bucket system, VIP toilets in Bots, Mangaung and TN, focus on the basics, building solar farming, power plant feasibility study,
safety & security
IDP Objective Strategy KPI Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Provide formal
stands with
waterborne
sanitation to
eradicate VIP
and Pit toilets
Provide
formal
stands with
waterborne
sanitation
to eradicate
VIP and pit
toilets
Number of
formal stands
with waterborne
sanitation and
to eradicate
VIP and pit
toilets
Completion
certificates
8281 Erven
provided with
waterborne
sanitation
6410 VIP toilets
eradicated
4065 Funding constrains
problematic. Poor
performing contractors
to be assisted.
-2 345 VIP toilets
eradicated
Accelerate waste
removal
Provide
households
with weekly
kerb-side
waste removal
services in
formal areas
Number of
households with
weekly kerb-side
waste removal
services in formal
areas
Collection schedule 165 464 households
with weekly kerbside
waste removal
service
178 367 households
with weekly kerbside
waste removal service
211 461 households
with weekly kerbside
waste removal service
N/A +33 094
Address electricity
backlog
Formal
households
with access to
basic electricity
Number of formal
households with
access to basic
electricity
Completion
Certificate
1264 Households + 200 000 formal
household access
basic electricity
188979 formal
household access
basic electricity
Accelerate basic
electricity services
-11021 formal
household access
basic electricity
Provide new
households
with electricity
connections
Number of new
households
provided with
electricity
connections
Completion
Certificate
545 1866 273 New households
connections
Upon the confirmation by
the applicant that the
houses are completed,
CENTLEC will facilitate
the connections.
-1593 New households
connections
Provide
households
with access to
free basic
electricity
Number of
households
provided with
access to free
basic electricity
Completion
Certificate
+ 18 000 35 000 15 899 on-going process of
identification of
tampered meters.
-19101
141
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
Municipal KPA Eradication of bucket system, VIP toilets in Bots, Mangaung and TN, focus on the basics, building solar farming, power plant feasibility study,
safety & security
IDP Objective Strategy KPI Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Provide a
reliable supply
of electricity
100% Completed
132/11kV 20MVA
Fichardtpark
Distribution Centre
Completion
Certificates
N/A 100% completed
distribution Centre
commissioned.
The tender has been
advertised and has
served in the
evaluation committee.
Speed up the internal
processes such that the
consultant can be
appointed.
100% Completed
132/11kV 30MVA
Cecilia Distribution
Centre
Completion
Certificates
N/A 100% completed
distribution Centre
commissioned.
Boundary wall 100%,
Earth mat 100%, Fire
wall 95%, Control
Building 95%, Internal
Pave 100%, Steel gate
95%, HV & Gantry
foundations 100%, HV
VT's is 80% installed.
2x132/11kV
transformers have
been delivered on site
and contractor is busy
assembling
transformers, cable
trench is 60%
complete.
None, Project is on
schedule
132 KV Northern
Ring from Noordstad
to Harvard DC
Completion
Certificates
100% completed
distribution Centre
commissioned.
Phase 1
Stringing of overhead
conductor to Cecilia is
completed. Phase 2
Design have been
approved Contractor
has started with
relocation of a coupler
and incorporation of
two feeder bays at
Harvard.
None
142
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
Municipal KPA Eradication of bucket system, VIP toilets in Bots, Mangaung and TN, focus on the basics, building solar farming, power plant feasibility study,
safety & security
IDP Objective Strategy KPI Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Elite Substation
(Airport
Development Node)
Completion
Certificates
100% completed
distribution Centre
commissioned.
Design drawings have
been approved by
CENTLEC. The
engineering
department has
proposed a new
position for a
substation from council
and the department is
currently waiting for an
approval.
None
143
3.23.3 STRATEGIC PROJECTS AND SERVICE DELIVERY REGULATIONS
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Municipal KPA Municipal Transformation and Good Governance
IDP Objective Strategy KPI Unit of measurements Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Monitoring and
reporting on
service delivery
Service delivery
regulatory,
monitoring and
evaluation
Developed
monitoring and
Evaluation
System
Monitoring reports 0 Monitoring and evaluation
system implemented in all
regions
Quarterly monitoring
reports developed
92% Addressed the
challenges in Thaba
Nchu Region and
reporting has
improved during the
4th Quarter
-8%
Management
and
Coordination
of Grant
Development,
management
and custodian of
all grant funding
Compilation of
Built Environment
Performance
Plan(BEPP
2015/16)
BEPP 2015/16
approved by
Council
Approved BEPP
2015/16
Final BEPP 2016/17 N/A N/A N/A
Compliance to grant
conditions (USDG)
Percentage
compliance to grant
requirements
100% 100% 100% N/A N/A
Percentage
spending of Grant
expenditure on
the approved
projects
Close out reports
and developed
compliance reports
86% spending of
grant expenditure
on the approved
projects
95 % spending of grant
expenditure on the
approved projects
82% This figure is based
on preliminary
figures. Finance
Directorate is still
busy with year end
processes and once
completed final
USDG figures will be
available
-13%
Compliance to grant
conditions (NDPG)
Percentage
compliance to grant
requirements
New 100% Compliance to
grant conditions (NDPG) 100%
N/A N/A
144
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Municipal KPA Municipal Transformation and Good Governance
IDP Objective Strategy KPI Unit of measurements Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Compliance to
grant conditions
(EPWP)
Percentage
compliance to grant
requirements
New 100% 100% N/A N/A
Implementation
of key strategic
projects
Implementation
of NDPG funded
project
Report approved by
Council
Design Completed Implementation of
Phase 1 of Waaihoek
90%
1. Design approved
internally and by
Transnet
2. Tender
Specifications for
phase 1 completed
and presented to
BSC
3. Received Approval
for additional four
projects within the
Precinct and funding
transferred MMM
which indicates that
National treasury is
satisfied with
progress on this
project
Process halted by
National Treasury
which is currently
performing the due
diligence on the
Bridge and an
independent
valuation of the
properties to be
purchased alongside
the bridge.
-10%
Implementation of
National Training
Centre programme
Report approved by
Council
Design Completed 100% Arthur Nathan
swimming pool
upgraded
20% Completed
Conditional
assessment of Arthur
Nathan Swimming
pool and preliminary
designs
MMM to Finalise
design and
commence with
procurement
-80%
145
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Municipal KPA Municipal Transformation and Good Governance
IDP Objective Strategy KPI Unit of measurements Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Implementation
status of EPWP
Policy & EPWP
Grant funded
projects
Report approved by
Council
Approved policy Fully implemented
EPWP social sector
projects
100% N/A N/A
Management of
Municipal Entity
Report approved by
Council
Draft Service
Delivery Agreement
with Centlec
Approved 5 year
business plan
Business plan for the
entity for 5 year
period has been
adopted by Council
during the 2014/15
financial year
N/A N/A
Execute and/or
manage
strategic
events of
Council
Strategic Events
as allocated by
Council from time
to time
Successful
implementation of
Events delivered as
per operational plan
Hosting of
International
Beach Volleyball
Tournament
Strategic Events
delivered per
operational plan
100%
Successfully
implemented the
2015 Mangaung
Cycling Tour and the
2015 Edition of the
South African Sport
Awards which were
hosted by the City
N/A N/A
146
3.23.4 SOCIAL SERVICES
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
MTAS Indicator Promote awareness and education on environmental issues
Municipal KPA Social and community services
IDP Objective Strategy KPI Unit of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Improve service
delivery by
providing
recreation facilities
and public
amenities to all
residents of
Mangaung
Provision of
recreational
facilities to all
residents of
Mangaung
Create a clean
and green
environment
Number of
regional parks
developed
Completion
Certificates
Phase 1 of the Regional
Park in Thaba Nchu
completed
Second phase of
Regional Park
development in Thaba
Nchu implemented
Athletic Track which
was part of second
phase of Regional
Park in thaba Nchu is
100% complete
Positive Variance N/A
100% completion of
project was not
realised by the end of
the financial year due
to complexity of
designs required and
late payments to
contractor.
Funds to be rolled over
to the new financial year
in order to finalise the
project.
N/A
One Park
developed
Completion Certificate
Phase 1 of the Park in
Botshabelo completed
2nd phase of the
Botshabelo park
development
implemented and
completed
Phase two of
Botshabelo park was
discontinued.
None N/A
Relocation of the
Zoo to
Kwaggafontein
Game Farm
Zoo to be re-
designed and re-
built at
Kwaggafontein
Game Farm
Completion
Certificates
Construction of Security
Fencing, including water
gates and entrance gates,
Erection of Temporary
Game Fencing.
Submission and approval
of plans for Service
Delivery Guard house and
Main Entrance Complex.
Building of service
delivery guard house
and main entrance
complex
No construction was
done due to on-going
EIA processes by
DESTEA.
Consultations with
DESTEA to continue in
the new financial year for
finalisation of the EIA
processes and issuance
of the Right Of
Development (ROD).
N/A
147
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
MTAS Indicator Promote awareness and education on environmental issues
Municipal KPA Social and community services
IDP Objective Strategy KPI Unit of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Relocation of the
Zoo to
Kwaggafontein
Game Farm
Zoo to be re-
designed and re-
built at
Kwaggafontein
Game Farm
Completion
Certificates
Construction of Security
Fencing, including water
gates and entrance gates,
Erection of Temporary
Game Fencing.
Submission and approval
of plans for Service
Delivery Guard house and
Main Entrance Complex.
Provision of bulk
services – water,
electricity, sewerage,
roads.
No construction was
done due to on-going
EIA processes by
DESTEA.
Consultations with
DESTEA to continue in
the new financial year for
finalisation of the EIA
processes and issuance
of the Right Of
Development (ROD).
N/A
Improve service
delivery by
provision of –safe
and secured
cemeteries.
Fencing of
cemeteries
Number of
cemeteries
fenced. (New
addition)
Completion certificates 3 cemeteries fenced –
Ratau-1, Ratau-2, Thaba
Nchu Town Cemetery.
2 cemeteries to be
fenced namely:
Storm-laan (0.63km)
and Bainsvlei (2.09km)
cemeteries.
Erection of razor wire
fence in Stormlaan is
100% completed,
clear-vu fence in the
front portion is 95%
completed. Erection of
fence for Bainsvlei is
15% completed.
Timeous planning and
execution of
procurement processes.
N/A
Improve service
delivery by
provision of -
Accessible Roads
Construction and
upgrading of
Roads
Channelling of
Storm-water.
Kilometres of
cemetery roads
upgraded
Completion certificates 1 Cemetery Road
constructed at South park.
4 cemetery Roads to
be constructed at the
following cemeteries:
1. Botshabelo
Regional Cemetery
2. Botshabelo
Cemetery
3. Bainsvlei Cemetery
4. Phahameng
Cemetery (length 0,5
km, major concrete
storm-water channel
0,3km)
1. Upgrading of roads
& Storm-water
Phahameng cemetery
– project is 25%
completed.
2. New Roads &
Storm-water
Botshabelo Regional
cemetery –Desktop
studies and wetlands
report finalised, Actual
construction of roads
Timeous planning and
execution of
procurement processes.
N/A
148
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
MTAS Indicator Promote awareness and education on environmental issues
Municipal KPA Social and community services
IDP Objective Strategy KPI Unit of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
will be realised in the
new financial year.
3. New Roads &
Storm-water
Botshabelo cemetery –
project is 40%
completed.
4. New Roads &
Storm-water Bainsvlei
cemetery – project is
45% completed.
Improve service
delivery by
Upgrading of
facilities
Improve service
delivery by
increasing
cemeteries.
Construction of
ablution facilities.
Increase of
burial space
Number of
cemeteries with
ablution facilities
(New addition)
Completion certificates 1 ablution facility
constructed at Ratau
cemetery ( Thaba Nchu)
1 ablution facility to be
constructed in South
park cemetery.
Construction of
ablution block -project
is 90% completed.
There was a delay in
delivery of materials
towards the finalisation
phase of project.
Project to be finalised
during July 2016 in the
new financial year.
-10%
Amount of
cemetery space
available to cater
for future burials.
(New addition)
Hectares of land
acquired
Registration at the
Deeds Office
2 plots were acquired for
cemetery purposes
namely: Klipfontein and
Farm X2727.
Development of a
master plan for the
conversion of the two
acquired plots into
cemeteries.
Commencement of the
master plan was
delayed by
discussions with
SANRAL which took
longer than
anticipated.
Master plan to be
completed in the new
financial year after new
proposals for both the
entrance of X2727 and
the revised layout of
klipfontein have been
approved.
N/A
149
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
MTAS Indicator Promote awareness and education on environmental issues
Municipal KPA Social and community services
IDP Objective Strategy KPI Unit of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Prevent or reduce
losses that occur
due to natural or
man-made
disaster through
preparedness,
mitigation,
response and
recovery
Effective and
efficient
dispatching of
emergency
resources to fire
and rescue calls
Number of fire
and rescue calls
to which
resources were
dispatched within
3 minutes.
Logged fire and
rescue calls
9.0 out of 10 8 out of 10 8.59 out of every 10
calls, resource to be
dispatched within 3
minutes
+0.59 Positive
Variance
To limit the
number of fire
deaths resulting
from accidental
fires in residential
buildings
Delivery of
Operational Fire
and Rescue
Services in the
entire MMM area
complying to
SANS 10090
Number of fire
and rescue
emergency
responded to in
compliance with
SANS 10090
i.r.o:
Weight of
response
Turn out time
Report on fire and
rescue emergency
responded to in
compliance with SANS
10090 i.r.o
8.5 out of 10 7.5 out
of 10
8.7 out of 10 (729 out
of 831)
None required +1.2
Improve revenue
collection
Payment of
traffic fines
Fines
successfully
finalised and
payment
received
Section 71 report 23 633 20 000 Traffic fines
paid
20 752 +752 Positive
Variance
Law enforcement
measures
Establishment of
metro police
Establishment of
metro police
Metro police
established
Develop strategy and
process plan for
establishment of Metro
Police
Appointment of chief of
police, application of
the establishment and
prepare a business
plan.
Target not achieved Project transferred to
City Manager's Office
150
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Basic Service Delivery
MTAS Indicator Promote awareness and education on environmental issues
Municipal KPA Social and community services
IDP Objective Strategy KPI Unit of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual
Performance
Corrective Action Variance
Law enforcement
measures
Number of crime
prevention
activities
targeting
hotspots
Crime awareness
campaigns
operations
conducted
Crime prevention
operations conducted
12 Crime prevention
activities conducted
targeting known hotspots
12 Crime prevention
activities conducted
targeting known
hotspots
A total of 23 Crime
prevention activities at
24 crime hot spots and
attended to by the law
enforcement division.
+11 Positive
Variance
Promote
Environmental
Health
Conduct drinking
and recreational
water sampling
according SANS
to 241
Number of
drinking water
samples taken
Water sample report 1412 1 300 1776 +476 Positive
Variance
151
3.23.5 FINANCE
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
MTAS Indicator Good Governance Public Participation
Municipal KPA Financial Management
IDP Objective Strategy KPI Units of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Prudent fiscal
management
Implement
clean audit
initiatives
An improved audit
outcome
Audit report Financially unqualified Audit
Report
Financial
Unqualified Audit
Report
Financial Unqualified
Audit Report
None None
Prudent fiscal
management
Improved
Credit
Rating
Long term and short
term credit rating
Section 71 report A3.za rating Maintain A3.za
rating
Long Term Issuer
Rating – Ba1
Engage with Moody’s
Investors Service to
conduct
comprehensive
assessment
Revenue
Enhancement
Collect all
collectable
revenue and
Leverage
alternative
sources of
funding
Amount of externally
sourced funds
Increasing revenue
base by accounting
for unaccounted
services
Section 71 report R 600 Million R 750 million Tender for R500
million loan advertised
Growth and
Development Strategy
be developed and
clear Long Term
Financial Plan and
Strategy be aligned to
strategic objectives
-R250 million
Revenue
Enhancement
Identification
of additional
revenue
streams
100%
implementation of
revenue
enhancement
strategies
Section 71 report 100% implementation of long
term enhanced revenue
strategy
100%
implementation of
long term Revenue
Enhancement
Strategy
80% implementation
of long term Revenue
Enhancement
Strategy
Engage with
management to
reconsider municipal
bond issuance
-20%
Improve revenue
collection
Implement
credit
control
measures
Collection rate to be
improved to 95%
Percentage of
collection of debt
91% 95% collection rate 87.06% Full implementation of
Credit Control and
Debt Collection By-
Laws
-7.94%
Percentage increase
in the number of
handed over
accounts
successfully
collected
Number of accounts
handed over to
attorneys
successfully
collected
-
15 000
21 372
None
None
152
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
MTAS Indicator Good Governance Public Participation
Municipal KPA Financial Management
IDP Objective Strategy KPI Units of
measurements
Past Year Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Percentage increase
in the number of
defaulting
businesses litigated
Number of
businesses litigated
- 500 293 Attachment/ Auction
properties
207
Percentage increase
in the number of
defaulting domestic
customers
garnished
Number of
defaulting domestic
customers
garnished
4 000 2 658 Full implementation
of Credit Control and
Debt Collection By-
Laws
-1 342
153
3.23.6 HUMAN SETTLEMENTS
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Good Governance Public Participation
MTAS Indicator
Municipal KPA Human settlements
IDP
Objective Strategy KPI
Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Address
housing
backlog
Provide Housing
Opportunity
Number of informal
settlements
upgraded
Completion
certificates
Happy letters
N/A 2 informal
settlements
upgraded
(Magashule
Square and
Botshabelo
Section R)
7 (seven) Informal Settlements
upgraded with installation of services
(MK Square- 482); Sonderwater 1-92;
Sonderwater 2 - 130 Kgotsong-1448;
Bloemside 4 - 581; Bloemside 2- 271;
Bloemside 3- 139; Three (3) Informal
Settlements upgraded only leve1
(designs)- Magashule-48; Section R-
2530; Namibia 27921 and 2777-52
None None
Number of Title
Deeds transferred
to eligible
beneficiaries
Number of Title
Deeds transferred
1230 2 000 Title Deeds 2965 Title Deeds transferred +965 Title Deeds
transferred
Construction of
new affordable
rental/social
housing units
Number of new
affordable
rental/social
housing units
constructed
Rental/Social
housing units
constructed
N/A 40 units – White
City
1 000 Social &
CRU
0
0
There was a delay in the finalisation of
the contract between the contractor and
the municipality and this has led to a
project not being completed on the set
time. The contract has now been
finalised and the contractor is granted
two months to recover time lost.
Contractors moved out of sites due to
lack of funding. The department will
engage the DHS to unlock the
challenges facing the Social and CRU
projects
-40
-1000
154
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Good Governance Public Participation
MTAS Indicator
Municipal KPA Human settlements
IDP
Objective Strategy KPI
Unit of
measurements
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Acquisition of
land for
Human
Settlements
Promotion of
mixed use
development in
Estoire
Redesign of Estoire
layout plan
New layout plan
promoting mixed-
use in Estoire
1 layout plan 0 Bid withdrawn subject to Council
resolution
-1
Refurbishment of
rental stock
Refurbishing of
rental schemes
Completion
certificates
100%
refurbishment of
scheme
100% Complete refurbishment
None none
Acquisition of
land for burial
space
Hectares of land
acquired
Number of
hectares acquired
203 hectares 203,3136 hectares acquired none +0.3136
155
3.23.7 OFFICE OF THE CITY MANAGER
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Good Governance Public Participation
MTAS Indicator Public participation
Governance
Municipal KPA Good governance
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective
Action
Variance
Strengthening
International relations
Liaison with foreign
diplomats
Invitation of BRICS and
African Diplomats to MMM
MOU with
BRICS Cities
and African City
0 2 MOU’s with BRICS
Cities and African city
0 More
engagements
with BRIC’s and
identified African
city
-2 MOU’s with
BRICS Cities and
African city
Maintaining strong and
effective oversight
structures
Establishment of
effective, functioning
Audit, Oversight and
Public Accounts
Committees consisting
of knowledgeable
persons
Audit Committee fully
operational and meeting at
least 4 times annually
Fully operational
Audit Committee
4 Meetings Held At least four (4)
meetings held
6 Meetings
27/08/15
09/10/15
06/11/15
03/12/15
27/01/16
29/03/16
N/A
+2
Compliance to good
governance through
Enterprise Wide Risk
Management
Pro Active Risk
Management
governance framework
and processes
Review and
implementation of Risk
management Policy,
Strategy, implementation
plan
Reduce and
manage Risks to
acceptable
appetite
0 5 reports on
implementation of Risk
Management and
action plan
3 governance
documents reviewed
- 2015/16 Strategic
Risk Registers
reviewed and updated
None -2
Effective Anti-Fraud and
Corruption prevention
and response
Review , development and
Implementation of Policy,
Strategy, whistle Blowing
and Prevention Plan
Zero tolerance to
Fraud and
Corruption
14 Reports Investigate all reported
allegations of fraud
and corruption
incidences
16 reports developed
and issued
3 Reports on Irregular
Expenditure issued
-13
156
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Good Governance Public Participation
MTAS Indicator Public participation
Governance
Municipal KPA Good governance
IDP Objective Strategy KPI Unit of
Measurement
Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective
Action
Variance
Strengthen community
involvement to participate
in the affairs of the
municipality and
influence resource
allocation
Enhance public
participation in the affairs
of the municipality
49 ward development
plans developed and
approved by council
Develop and
approve
clustered wards
base plans
0 10 clustered ward
based plans
0
-10
157
3.23.8 CORPORATE SERVICES
ALIGNMENT AND LINKAGE No OBJECTIVES AND INDICATORS PERFORMANCE TARGETS
National Outcome 9 A responsive, accountable, effective and efficient local government system
National KPA Municipal Institutional Development and Transformation
Good Governance Public Participation
MTAS Indicator Public participation
Governance
Municipal KPA Good governance
IDP Objective Strategy KPI Unit of Measurement Past Year
Performance
(2014/15)
Annual Target
2015/16
Actual Performance Corrective Action Variance
Enhance the
facilities
maintenance
programme
Upgrading and
rehabilitating
Municipal Buildings
Number of
municipality buildings
to be upgrade in line
with the maintenance
programme
Completion certificates 1 3 Initial project
completed, however
scope was increased
complete the entire
project
none
Maximize usage
of sports facilities
Rehabilitating of
existing sports
facilities
Number of sports
facilities to be
rehabilitated
Completion certificates 5 Sports and social
amenities
rehabilitated
7 Sports and social
amenities rehabilitated
Two projects
completed
Poor performance
was due to Bid
Committees not
seating
-5 Sports and social
amenities rehabilitated
158
CHAPTER 4 - ORGANISATIONAL DEVELOPMENT PERFORMANCE
COMPONENT A: INTRODUCTION TO MUNICIPAL PERSONELL
The attainment of a capable and developmental state as envisioned in the National Development Plan (NDP)
hinges amongst others on the right quality and quantity of human resources. The delivery of quality enhanced
services in a sustainable manner to the broader populace of Mangaung is also influenced by the creation of an
adequately balanced and skilled workforce that espouses the ideals of Batho Pele. MMM continually strives for
establishing an “appropriately sized” institutions with a balance of skills related to our core functions and
administrative support.
The table below reflects
4.1 EMPLOYEE TOTALS, STAFF TURNOVER AND VACANCIES 2015/16
Table 4.1: EMPLOYEES
Description Year 2015/16
Employees Vacancies
No. No.
Water & Sanitation 544 629
Electricity 375 336
Solid Waste 357 254
Housing 184 126
Roads and Storm water 228 422
Planning 101 172
Local Economic Development 23 41
Community & Social Development 94 79
Health& Environmental Health 33 11
Security and Safety 279 371
Sport and Recreation 17 1
Corporate Services and Other 1897 1104
Totals 4132 3546
159
Table 4.2: VACANCY RATE
Designations Total No
Approved Posts
No Vacancies
Municipal Manager 1 1
CFO 1 0
Other S57 Managers (excluding Finance Posts) 11 4
Other S57 Managers (Finance posts) 0 0
Traffic officers 195 119
Fire fighters 169 59
Senior management: Levels 002-003 (excluding Finance Posts) 65 17
Senior management: Levels 002-003 (Finance posts) 6 1
Highly skilled supervision: levels 004-006 (excluding Finance
posts) 654 442
Highly skilled supervision: levels 004-006 (Finance posts) 113 42
Total 1215 684
Staff Turnover across the municipality relates to all terminations (dismissals, resignations, retirements, medical
terminations etc.) for the period under review.
Table 4.3: STAFF TURN-OVER RATE
Details Total Appointments
as of beginning of
Financial Year
Terminations during
the Financial Year
Turn-over
Rate*
No. No.
Year - 2015/16 3898 179 4.5%
COMPONENT B: MANAGING WORKFORCE
Note: MSA 2000 S67 requires municipalities to develop and adopt appropriate systems and procedures to
ensure fair; efficient; effective; and transparent personnel administration in accordance with the Employment
Equity Act 1998.
Work force Management within MMM is compliant with all legislative requirements governing the workplace
together with collective agreements concluded by the parties at the SALGBC. There is an extensive consultation
process with organized labour on issues of mutual interest at the Local Labour Forum.
160
This is done through Management of the recruitment process, selection and placement of staff; so that the best
suited candidates are employed.
Employee benefits including sick leave are administered in terms of applicable labour legislation, Conditions of
Service, Collective Agreements and policies by means of an integrated Electronic Human Resource
Management System.
Progress made in the development of policies entails the drafting of these policies that are submitted to the
EMT, Section 80 Committee and the LLF for consultation.
Table 4.4: HR POLICIES AND PLANS
HR Policies and Plans
Name of Policy Completed Reviewed Date adopted by
council or
comment on failure
to adopt
14/12/15 SALGA Job Evaluation Policy 100%
Adopted by Council
on 14/012/2015
2013
and
2016 Code of Conduct for Municipal Staff 100%
Communicated to all
MMM staff.
29/04/16
Employment Equity and Transformation
Policy 90%
Presented to LLF on
11/03/2016.
Approved by Section
80, on 29/04/2016.
24/06/16 Employment Equity Plan 90% Referred to LLF.
24/06/16 Career Planning Policy 90% Referred to LLF
29/04/16 HRD Strategy 90%
Presented to LLF on
11/03/2016.
Approved by Section
80, on 29/04/2016
24/06/16 Succession Planning Policy 90% Referred to LLF.
24/06/16
Internship and Work Integrated Learning
Policy 90% Referred to LLF.
29/04/16 Recognition of Prior Learning (RPL) 90%
Presented to LLF on
11/03/2016.
161
HR Policies and Plans
Name of Policy Completed Reviewed Date adopted by
council or
comment on failure
to adopt
Approved by Section
80, on 29/04/2016
14/06/16 Occupational Health and Safety Policy 80%
Referred to HRD
Sub- Committee of
LLF.
14/06/16
Personal Protective Equipment Policy
(PPE) 80%
Referred to HRD
Sub- Committee of
LLF.
14/06/16 Organizational Design Policy 80%
Referred to HRD
Sub- Committee of
LLF.
14/06/16 Employee Wellness Policy 80%
Referred to HRD
Sub- Committee of
LLF
14/06/16 Bereavement Policy 80%
Referred to HRD
Sub- Committee of
LLF
14/06/16
Firearm and Operational Procedures
Policy 80%
Referred to HRD
Sub- Committee of
LLF
14/06/16 Sexual Harassment Policy 80%
Referred to HRD
Sub- Committee of
LLF
14/06/16
Recruitment Selection and Appointment
Policy 80% 100%
Reviewed Policy
referred to HRD
Sub-Committee of
LLF.
29/04/16 Workplace Skills Development Plan 100%
Submitted to
LGSETA on 29 April
2016 as per
162
HR Policies and Plans
Name of Policy Completed Reviewed Date adopted by
council or
comment on failure
to adopt
legislative
requirement.
30/06/16 HIV/ Aids STI and TB Policy 80%
Referred to HRD
Sub- Committee of
LLF
14/06/16
Education Training and Development
Policy 80%
Referred to HRD
Sub- Committee of
LLF
26/04/16 Anti-Discrimination Policy 80%
Referred to HRD
Sub-Committee of
LLF.
The Human Resource Management Sub-Directorate established an internal HR Policy Forum and has
developed a number of policies that have to be submitted to EMT. A number of policies as indicated in the table
above have already been referred to Section 80 Committee for consideration. These will be submitted to the
LLF for consultation to be later approved and adopted by Council.
Table 4.5: NUMBER AND COST OF INJURIES ON DUTY
Number and Cost of Injuries on Duty
Type of injury Injury Leave
Taken
Employees
using injury
leave
Proportion
employees using
sick leave
Average
Injury Leave
per employee
Total
Estimated
Cost
Days No. % Days R
Required basic
medical attention
only 273 47 1,12 5,81 R722 283,12
Approved Section
24 Cases 107 6 0,14 17,83 R5 996,64
Temporary total
disablement 0 0 0 0 Not applicable
163
Number and Cost of Injuries on Duty
Type of injury Injury Leave
Taken
Employees
using injury
leave
Proportion
employees using
sick leave
Average
Injury Leave
per employee
Total
Estimated
Cost
Days No. % Days R
Permanent
Disablement 0 0 0 0 Not applicable
Fatal 0 0 0 0 R14 539,00
Total 380 53 1,26 7,17 R742 818,76
Table 4.6: NUMBER OF DAYS AND COST OF SICK LEAVE
Number of days and Cost of Sick Leave (excluding injuries on duty)
Salary band
Total
sick
leave
Proportion
of sick leave
without
medical
certification
Employees
using sick
leave
Total
employees
in post*
*Average
sick leave
per
Employee
s
Estimated
cost
Days % No. No. Days R
Lower skilled
(Levels 016-
018)
10374 18.23 1256 1510 6.87 3,755,626.48
Skilled (Levels
013-015) 1691 23.71 221 198 8.54 682,930.76
Highly skilled
production
(levels 007-
012)
14298 23.16 1876 1639 8.72 11,248,417.38
Highly skilled
supervision
(levels 004-
006)
3762 20.57 477 417 9.02 5,403,183.31
Senior
management
(Levels 002-
003)
319 13.17 37 54 5.91 685,212.00
MM and S57 24 4.17 3 7 3.43 184,679.26
Total 30468 21.07 3870 3825 7.97 21,960,049.20
Injuries: The classification under type of injury does not clearly make provision to capture serious injury on
duty cases, where the injured was of duty 14 days or longer some up to 6 months, but the employee returned
to his work after rehabilitation. Therefore we added another classification namely, approved Section 24 cases.
164
The total estimated cost not only includes the injury on duty cases, but also the sundry payments for injury on
duty pensioners. Furthermore cognisance should be taken that an injury on duty case run over a two year period
and whilst the injury on duty date was not in the financial year cost can still be payable in the next year
Examination of injury on duty cases
Examination of injury on duty cases are done by a doctor who treated the patient as determined /required by
the Compensation for Occupational Injuries and Diseases act, If the injured was treated by the Doctor at our
clinic then that doctor will be responsible for all follow-ups.
Table 4.7: NUMBER AND PERIOD OF SUSPENSIONS
Table 4.8: DISCIPLINARY ACTION TAKEN ON CASES OF FINANCIAL MISCONDUCT
Position Nature of Alleged
Misconduct and Rand
value of any loss to
the municipality
Disciplinary action taken Date
Finalised
1 x General Worker Accepted bribe Disciplinary hearing held on 17/08/2016
1 x Accounting Officer Fraud and Corruption Disciplinary hearing held to be held on
Sept 2016
1 x General Worker Fraud and Corruption Prosecutor to provide a new date
Number and Period of Suspensions
Position Nature of
Alleged
Misconduct
Date of
Suspension
Details of Disciplinary
Action taken or Status of
Case and Reasons why
not Finalised
Date Finalised
1 x Manager Fraud and
Corruption
Investigation is underway
1 x Inspector Assault March 2015
1 x Inspector Fraud and
Corruption
New investigation is
underway
165
COMPONENT C: CAPACITATING THE WORKFORCE
One of the key challenges around an integrated process of skills development within the municipality has been
a lack of a comprehensive, holistic and integrated framework for human capital development that will guide and
integrate key processes such as training needs analysis, career pathing and planning, succession planning,
management and leadership development, knowledge exchange and innovation. To this end a draft succession
planning policy was developed with a view of consolidating all the key mandatory processes for effective human
capital development, albeit the strategy must go through the internal approval processes that will culminate
with Council approval of the document.
During the year under review the municipality also complied with the Skills Development Act requirement of
submitting to the Local government SETA (LGSETA) the Workplace Skills Plan (WSP) on the due date of 30th
April 2015.
Table 4.9: FINANCIAL COMPETENCY DEVELOPMENT
Description A.
Total number
of officials
employed by
municipality
(Regulation
14(4)(a) and
(c))
B.
Total number
of officials
employed by
municipal
entities
(Regulation
14(4)(a) and
(c)
Consolidate
d: Total of A
and B
Consolidated:
Competency
assessments
completed for
A and B
(Regulation
14(4)(b) and (d))
Consolidated:
Total number of
officials whose
performance
agreements
comply with
Regulation 16
(Regulation
14(4)(f))
Consolidate
d: Total
number of
officials that
meet
prescribed
competency
levels
(Regulation
14(4)(e))
Accounting
officer
1 1 2 1 1 1
Chief financial
officer
1 1 2 1 1 1
Senior
managers
7 7 14 6 6 6
Any other
financial
officials
192 192 384 80 80 80
Supply Chain
Management
Officials
31 31 62 31 31 31
Heads of
supply chain
1 1 2 1 1 1
166
Description A.
Total number
of officials
employed by
municipality
(Regulation
14(4)(a) and
(c))
B.
Total number
of officials
employed by
municipal
entities
(Regulation
14(4)(a) and
(c)
Consolidate
d: Total of A
and B
Consolidated:
Competency
assessments
completed for
A and B
(Regulation
14(4)(b) and (d))
Consolidated:
Total number of
officials whose
performance
agreements
comply with
Regulation 16
(Regulation
14(4)(f))
Consolidate
d: Total
number of
officials that
meet
prescribed
competency
levels
(Regulation
14(4)(e))
management
units
Supply chain
management
managers
2 2 4 2 2 2
TOTAL 235 235 470 122 122 122
All targeted Officials are currently being trained on the Unit Standards constituting the Required Competency
Levels. Training within Mangaung is scheduled to be concluded during February 2016. Competency
Assessments are being conducted continuously upon completion of every Unit Standard covered and credits
awarded for competence.
EMPLOYEE EXPENDITURE
It is extremely important to control workforce expenditure since it is one of the largest single
expenditure items on the operational budget of the Municipality. Spending is controlled by means of
the approved staff establishment and budget control. Expenditure on overtime is limited according to
the “Collective Agreement”.
Total Employee Costs 2015/16 = R1, 423 526 305.
167
CHAPTER 5 - FINANCIAL PERFORMANCE
5.1 STATEMENT OF FINANCIAL PERFORMANCE
The table 5.1.1 below gives an overview of municipal performance against the budget.
Table 5.1.1: RECONCILIATION OF TABLE A1 BUDGET SUMMARY
RECONCILIATION OF TABLE A1
BUDGET SUMMARY
Description
Current Year 2015/16
Original Budget Adjusted
Budget Final Budget Actual Outcome
Actual as % of
Final Budget
Actual as % of
Original Budget
R thousands
Financial Performance
Property rates 913,073 (167,762) 745,311 810,477 109% 89%
Service charges 3,615,605 (389,623) 3,225,982 2,892,013 90% 80%
Investment revenue 154,382 (83,241) 71,141 45,387 64% 29%
Transfers recognised - operational 615,255 17,792 633,047 655,808 104% 107%
Other own revenue 1,420,979 (43,977) 1,377,002 475,251 35% 33%
Total Revenue (excluding capital
transfers and contributions)
6,719,294 (666,811) 6,052,483 4,878,936 81% 73%
Employee costs 1,711,051 (268,532) 1,442,519 1,414,715 98% 83%
Remuneration of Councillors 54,216 – 54,216 53,472 99% 99%
Depreciation & asset impairment 527,384 (35,508) 491,877 697,170 142% 132%
Finance charges 224,941 (82,471) 142,470 141,059 99% 63%
Materials and bulk purchases 2,152,071 13,228 2,165,299 2,239,717 103% 104%
Transfers and grants 117,571 (37,528) 80,042 13,794 17% 12%
Other expenditure 1,419,692 142,095 1,561,787 1,406,266 90% 99%
168
RECONCILIATION OF TABLE A1
BUDGET SUMMARY
Description
Current Year 2015/16
Original Budget Adjusted
Budget Final Budget Actual Outcome
Actual as % of
Final Budget
Actual as % of
Original Budget
R thousands
Total Expenditure 6,206,926 (268,716) 5,938,210 5,966,193 100% 96%
Surplus/(Deficit) 512,368 (398,095) 114,273 (1,087,257) -951% -212%
Transfers recognised - capital 754,004 106,862 860,866 793,435 92% 105%
Contributions & Contributed assets 20,953 0 20,953 37,763 180% 180%
Surplus/(Deficit) after capital
transfers & contributions
1,287,325 (291,233) 996,092 (256,059) -26% -20%
Share of surplus/ (deficit) of
associate 0 0 0 0
Surplus/ (Deficit) for the year 1,287,325 (291,233) 996,092 (256,059) -26% -20%
Taxation 0 0 0 4,287
Surplus/ (Deficit) for the year after
taxation 1,287,325 (291,233) 996,092 (251,772) -25% -20%
Capital expenditure & funds
sources
Capital expenditure 1,793,891 57,289 1,851,179 1,630,343 88% 91%
Capital transfers recognised 754,004 106,862 860,865 793,435 92% 105%
Public contributions & donations 20,953 – 20,953 37,763 180% 180%
Borrowing 514,256 14,673 528,929 390,240 74% 76%
Internally generated funds 504,678 (64,246) 440,432 408,905 93% 81%
Total sources of capital funds 1,793,891 57,289 1,851,179 1,630,343 88% 91%
Financial position
Total current assets 3,409,171 (511,145) 2,898,026 2,097,954 72% 62%
169
RECONCILIATION OF TABLE A1
BUDGET SUMMARY
Description
Current Year 2015/16
Original Budget Adjusted
Budget Final Budget Actual Outcome
Actual as % of
Final Budget
Actual as % of
Original Budget
R thousands
Total non current assets 14,227,264 728,917 14,956,181 16,223,844 108% 114%
Total current liabilities 1,884,610 (72,430) 1,812,180 2,362,344 130% 125%
Total non current liabilities 1,791,639 – 1,791,639 2,464,682 138% 138%
Community wealth/Equity 13,960,186 290,201 14,250,388 13,494,772 95% 97%
Cash flows
Net cash from (used) operating 1,770,697 (399,675) 1,371,022 1,092,400 80% 62%
Net cash from (used) investing (1,587,741) (10,374) (1,598,115) (1,195,824) 75% 75%
Net cash from (used) financing 47,864 15,669 63,534 116,192 183% 243%
Cash/cash equivalents at the
month/year end 680,156 (297,549) 382,606 325,679 85% 48%
170
The Budget Summary Table is divided into three components namely:
A. Statement of Financial Performance
B. Spending against Capital Budget
C. Other Financial Matters.
COMPONENT A: STATEMENT OF FINANCIAL PERFORMANCE
A. Total Revenue
The municipality achieved 81% of its adjusted revenue budget of R 4,88 billion for the year. The main
variance on the final budget can be attributed to the following:
Investment revenue was less than the target by 36% (R 25,8 million);
Service charges underperformed by 10% (R 333,9 million)
Other own revenue underperformed by 65% (R 901,7 million) of the Adjustment Budget. .
B. Total Expenditure
The municipality’s actual expenditure stood at R 5,96 billion, representing 100.4% of the adjusted
expenditure budget of R 5,93 billion. The main variance on the final budget can be attributed to the
following:
Favourable variance of R27.8 million (-2%) due to unfilled vacancies. However overtime
continues to be a risk factor in the management of pay costs.
Unfavourable variance of R74,4 million (3%) on expenditure on Materials and bulk purchases,
amount spend R2,23 million.
Unfavourable variance of R205.2 million (42%) on depreciation and asset impairment, amount
spend R697,1 million.
Other Expenditure actual spend was 90% of the allocated adjusted budget.
C. Surplus / (Deficit)
The deficit was R1,087,257 million mainly due to underperformance on other revenue for the year.
171
COMPONENT B: SPENDING AGAINST CAPITAL BUDGET
The actual spending on the capital expenditure is R 1, 63 billion, representing 88% of the Adjustment
Budget for 2016 (R1,85 billion). The greater area of under spending as per the funding source is on
projects financed through the Integrated National Electrification Grant (Eskom) and Human Settlement
Grant (Provincial)
COMPONENT C: CASH FLOWS MANAGEMENT AND INVESTMENTS
The municipal cash and investments balances stood at R 325,679 which is R 56,927 (15%) less than
the adjusted budget.
172
5.2 GRANTS
A. Operating Grants
Table 5.2.1: Operating Grants
Grants Performance
2015/2016 Year 0 Variance
Description Budget
Adjustments
Budget Actual Original Budget
Adjustments
Budget
R'000
Operating Transfers and Grants
National government 918,086 933,430 917,546 99.94% 98.30%
Equitable Share 596,652 596,652 596,652 100.00% 100.00%
Other 1,300 1,300 1,300 100.00% 100.00%
Fuel Levy Grant 260,928 260,928 260,928 100.00% 100.00%
Sports, Arts, Culture and recreation - 400 709 0.00% 177.25%
Neighbourhood Development Grant 20,000 20,000 21,536 107.68% 107.68%
National Electrification 30,000 30,000 30,000 100.00% 100.00%
Municipal Human Settlements Capacity 9,206 9,206 6,421 69.75% 69.75%
Public Transport - 14,944 - 0.00% 0.00%
Provincial Government 5,000 6,898 2,315 46.30% 33.56%
Other - - - 0.00% 0.00%
173
Grants Performance
2015/2016 Year 0 Variance
Description Budget
Adjustments
Budget Actual Original Budget
Adjustments
Budget
R'000
Housing 5,000 6,898 2,315 46.30% 33.56%
District Municipality: - - - 0.00% 0.00%
Motheo-Environmental Health Grant - - - 0.00% 0.00%
Other Grant providers - 550 301 0.00% 54.73%
Kellogs Foundation - - - 0.00% 0.00%
City of Ghent - 550 301 0.00% 54.73%
National Lottery - - - 0.00% 0.00%
Golden Shield Heritage Award - - - 0.00% 0.00%
Other - - - 0.00% 0.00%
Total Operating Transfers and Grants 923,086 940,878 920,162 99.68% 97.80%
174
The municipality is a recipient of the Operating Grants and Subsidies from the National and Provincial
Government’s respectively. For the reporting period the actual spending against the adjusted budget
is 97.80%.
B. Capital Grants
The adjusted total capital expenditure budget stood at R 1, 85 billion, with the National Government’s
contribution being 46.6%. The major grant source is the Urban Settlement Development Grant at
R 771 million.
175
Table 5.2.2: CONDITIONAL GRANTS RECEIVED: EXCLUDING MIG
Capital Financing Source
Approved Adjusted Actual % variation on % variation on
Budget Budget Original Budget
Adjustments
Budget
Integrated City Development Grant (National) 10,157 10,157 10,061 99.05% 99.05%
Urban Settlement Development Grant 693,847 771,383 712,739 102.72% 92.40%
Public Transport Infrastructure and Systems Grant - 26,128 63,072 0.00% 241.40%
Department of Sports Arts and Culture - 600 - 0.00% 0.00%
Human Settlement Grant - Provincial - 2,598 1,002 0.00% 38.57%
EPWP Incentive Grant 3,097 3,097 3,136 101.26% 101.26%
TOTAL 707,101 813,963 790,010 111.73% 97.06%
176
5.3 REPAIRS AND MAINTENANCE
Table 5.3.1: REPAIRS AND MAINTENANCE
Repair and Maintenance Expenditure: Year 2015/16
R' 000
Original
Budget
Adjustment
Budget Actual Budget variance
Repairs and Maintenance
Expenditure 423,657 436,885 491,164 (54,279)
Repairs and Maintenance Budget constituted 6.83% of the original budget for 2015/16 and 7,36% of
the Adjustment Budget of R 5,9 billion The municipality has spent 112,42 % of its allocated adjusted
budget, thus overspend the budget by R54.2 million.
5.4 SPENDING AGAINST CAPITAL BUDGET
Table 5.4.1 CAPITAL EXPENDITURE
R’000 Original Budget Adjustment Budget Actual
Capital Expenditure 1,793,890,542 1,851,179,485 1,630,343,006
Operating Expenditure 6,206,925,712 5,938,209,512 5,966,193,380
Total expenditure 8,000,816,254 7,789,388,997 7,596,536,386
Capital Expenditure % 22.42% 23.77% 21.46%
The gross municipal expenditure budget, incorporating the operating and capital budget was set at R 7,
78 billion for 2015/16, following the adjustment budget. Capital expenditure budget constituted
23.77%of the gross expenditure the adjustment budget. For the year ended 30 June 2016, capital
expenditure was R 1.63 billion of the gross expenditure amount of R 7.59 billion. Thus taking up only
21.46% of the total expenditure.
A. Sources of Funding
For the year under review, the municipality’s adjusted expenditure budget of R1, 8 billion was funded
out of mainly three (3) sources. These are:
a) External loans to the extent of R 528, 9 million for financing of mainly long-term infrastructure
projects and the yellow fleet. The actual spending for the year was R 390, 2 million.
a) Grants and subsidies amounting to R 881, 8 million was budgeted and R 831, 1 million was
spent.
b) Other sources of funds are funds generated out of surplus funds from the working capital. R440,
4 million was budgeted of which R408, 9 million was used
177
Table 5.4.2: CAPITAL EXPENDITURE FUNDING SOURCES
B. Projects Funded.
Funds earmarked for capital expenditure programmes are used mainly to address basic community
service delivery expectation of water and sanitation, electricity, roads and storm-water.
Capital Expenditure Funding Sources
Year -
2014/2015 Year 2015/2016
Actual Original
Budget (OB)
Adjustment
Budget (AB) Actual
Actual to
AB
Variance
(%)
Adjustment
to
OB
Variance
(%)
Source of
finance
External loans 5,189,078 514,256,000 528,929,228 390,239,730 36% 32%
Public
contributions
and donations
22,608,870 20,952,879 20,952,879 36,603,064 -45% -45%
Grants and
subsidies 800,012,042 754,004,000 860,865,581 790,009,562 8% -5%
Other 259,509,050 504,677,663 440,431,797 394,408,592 8% 23%
Total 1,087,319,040 1,793,890,542 1,851,179,485 1,611,260,948 14% 10%
Percentage of
finance
External loans 0,48% 28.67% 28.57% 23.94%
Public
contributions
and donations
2,08% 1.17% 1.13% 2.32%
Grants and
subsidies 73,58% 42.03% 46.50% 48.67%
Other 23,87% 28.13% 23.79% 25.08%
Water and
sanitation
Electricity
178
C. Capital Spending on 5 Largest Projects
Funds amounting to R 245, 8 million from the adjusted budget of R 1, 8 billion financed the five largest
projects as detailed on table 5.4.3.
Table 5.4.3: CAPITAL EXPENDITURE OF 5 LARGEST PROJECTS
Capital Expenditure of 5 largest projects*
R' 000
Name of Project
Current: Year 2015/16 Variance: Current Year
2015/16
Original
Budget
Adjustment
Budget
Actual
Expenditure
Original
Variance
(%)
Adjustmen
t variance
(%)
A - SMART
STREETLIGHTS 40,000,000 35,000,000 42,691,340 -6.73% -21.98%
B - AIRPORT
DEVELOPMENT
NODE 46,000,000 46,000,000 18,791,041 59.15% 59.15%
C -
REFURBISHME
NT OF WATER
SUPPLY
SYSTEMS: A 50,000,000 45,000,000 20,062,844 59.87% 55.42%
D - NORTH
EARSTERN
WWTW PHASE 2 51,783,461 28,599,420 28,274,822 45.40% 1.13%
E - NEW
VEHICLE
LEASING 91,256,000 91,256,000 68,458,341 24.98% 24.98%
TOTAL 279,039,461 245,855,420 178,278,389 36.54%% 23.74%
PROJECTS WITH THE HIGHEST CAPITAL EXPENDITURE IN YEAR 2014/2015
Name of Project – A Smart Street Lights
Objective of Project To install energy saving street lights to ensure
visibility even when there is load-shedding
and saving on the cost of electricity
Delays None
Future Challenges None
179
Anticipated citizen benefit Reliable provision of street lighting and
possible contribution towards the reduction of
crime
Name of Project – B Airport Development Node
Objective of Project To install the requisite municipal
infrastructure services to support the
development of Airport Development Node
Delays Unforeseen planning matters that delayed the
project
Future Challenges None
Anticipated citizen benefit Access to employment opportunities, access
to housing opportunities and access to
learning institutions
Name of Project C –Refurbishment of water
system
Objective of Project To refurbish ageing water systems in the City
that is made of decrepit cement asbestos
pipes that are prone to bursting
Delays None
Future Challenges None
Anticipated citizen benefit Provision of effective water services and
reduction of non-revenue water
Name of Project-D – North Eastern Waste Water
Treatment Works
Objective of Project To build a new Waste Water Treatment Work
Delays None
Future Challenges None
Anticipated citizen benefit Provision of effective sanitation services and
support development along N8 Corridor
Development
Name of Project – E Vehicle leasing
Objective of Project To acquire additional white and yellow fleet
for City
Delays Some of the yellow fleet had to be customised
Future Challenges
Anticipated citizen benefit Effective service delivery
180
D. Capital Expenditure by Class
Appendix Capital M-(II) provides an overview of Capital Expenditure by Asset Class and it is broken
down into New Asset Programme and Upgrade/Renewal Programme.
In terms of the budget spent on new assets acquired/included in the municipal asset register amounted
to R1.1 Billion. Whereas maintenance of existing infrastructure and facilities cost R476,2 million.
5.5 CASHFLOW MANAGEMENT AND INVESTMENTS
Table 5.5.1: CASH FLOW OUTCOMES
Description
2014/15
Current
Year
2015/16
Audited
Outcome
Original
Budget
Adjusted
Budget
Year TD
actual
R thousands
CASH FLOW FROM OPERATING ACTIVITIES
Receipts
Property rates, penalties, collection charges, service
charges and other income 3,159,289 5,166,173 4,721,275 3,332,543
Government - operating 1,429,005 615,255 613,226 918,762
Government - capital 754,004 746,344 790,009
Interest 201,760 325,460 172,182 188,038
Dividends – – –
Payments
Suppliers and employees -3,919,465 -4,841,808 -4,764,686 -4,131,748
Finance charges -4 -205,371 -112,999 -8
Transfers and Grants -43,016 -4,320 -5,196
NET CASH FROM/(USED) OPERATING
ACTIVITIES 870,584 1,770,697 1,371,022 1,092,400
CASH FLOWS FROM INVESTING ACTIVITIES
Receipts
Proceeds on disposal of PPE 6,537 540 – 176
Decrease (Increase) in non-current debtors – –
1,654
181
Description
2014/15
Current
Year
2015/16
Audited
Outcome
Original
Budget
Adjusted
Budget
Year TD
actual
R thousands
Decrease (increase) other non-current receivables 231 – –
254,897
Decrease (increase) in non-current investments -126,904 – –
32,549
Payments
Capital assets -1,219,195 -1,588,280 -1,598,115 -1,485,100
NET CASH FROM/(USED) INVESTING
ACTIVITIES -1,339,331 -1,587,740 -1,598,115 -1,195,824
CASH FLOWS FROM FINANCING ACTIVITIES
Receipts
Short term loans – – –
Borrowing long term/refinancing 400,322 173,000 173,000 173,000
Increase (decrease) in consumer deposits 23,651 6,000 1,999 59,803
Payments
Repayment of borrowing -45,330 -131,136 -111,465 -65,687
Interest paid 0 0 0 -50,924
NET CASH FROM/(USED) FINANCING
ACTIVITIES 378,644 47,864 63,534 116,192
NET INCREASE/ (DECREASE) IN CASH HELD -90,104 230,821 -163,559 12,768
Cash/cash equivalents at beginning: 452,268 449,335 546,165 312,911
Cash/cash equivalents at month/year end: 362,164 680,156 382,606 325,679
References
1. Material variances to be explained in Table SC1
182
5.6 BORROWING AND INVESTMENTS
A. Actual Borrowings
Table 5.6.1: ACTUAL BORROWINGS – YEAR 2012/2013 TO YEAR 2015/2016
Actual Borrowings: Year -2012/13 to Year 2015/16
R' 000
Instrument Year - 2013 Year - 2014 Year - 2015 Year 2016
Municipality
Long-Term Loans
(annuity/reducing balance) 179,085,650 191,863,468 592,185,576 774,057,923
Long-Term Loans (non-
annuity)
Local registered stock
Instalment Credit
Financial Leases 7,155,895 143,210,786 108,626,102 63,267,454
PPP liabilities
Finance Granted By Cap
Equipment Supplier
Marketable Bonds
Non-Marketable Bonds
Bankers Acceptances
Financial derivatives
Other Securities
Municipality Total 186,241,545 335,074,254 700,811,678 837,325,377
Municipal Entities
Long-Term Loans
(annuity/reducing balance)
Long-Term Loans (non-
annuity)
Local registered stock
Instalment Credit
Financial Leases 392,128 304,782 1,712,287 1,885,865
PPP liabilities
Finance Granted By Cap
Equipment Supplier
183
Actual Borrowings: Year -2012/13 to Year 2015/16
R' 000
Instrument Year - 2013 Year - 2014 Year - 2015 Year 2016
Marketable Bonds
Non-Marketable Bonds
Bankers Acceptances
Financial derivatives
Other Securities
Entities Total 392,128 304,782 1,712,287 1,885,865
Total 186,633,673 335,379,036 702,523,965 839,211,242
The consolidated municipal borrowing have grown on a yearly basis from a low position of R 186 634
million in June 2013, to R 702 524 million in 2015 and the current position of R 839 211 in 2016. The
funds were used mainly for infrastructure projects, being water reticulation, reservoirs and road and
storm-water projects.
184
Investments
Table 5.6.2: MUNICIPAL AND ENTITY INVESTMENTS
Municipal and Entity Investments
R' 000
Investment* type
Year -
2012/13
Year -
2013/14 Year - 2014/15
Year -
2015/16
Actual Actual Actual Actual
Municipality
Securities - National Government
Listed Corporate Bonds
Deposits – Bank 204,062,484 99,321,305 224,833,758 71,967,778
Deposits - Public Investment
Commissioners
Deposits - Corporation for Public
Deposits
Bankers Acceptance Certificates
Negotiable Certificates of Deposit
– Banks
Guaranteed Endowment Policies
(sinking)
Repurchase Agreements – Banks
Municipal Bonds
Other
Municipality sub-total 204,062,484 99,321,305 224,833,758 71,967,778
Municipal Entities
Securities - National Government
Listed Corporate Bonds
Deposits – Bank 255,245,328 466,764,374 450,792,807 361,530,142
Deposits - Public Investment
Commissioners
Deposits - Corporation for Public
Deposits
Bankers Acceptance Certificates
Negotiable Certificates of Deposit
– Banks
185
Municipal and Entity Investments
R' 000
Investment* type
Year -
2012/13
Year -
2013/14 Year - 2014/15
Year -
2015/16
Actual Actual Actual Actual
Guaranteed Endowment Policies
(sinking)
Repurchase Agreements – Banks
Other
Entities sub-total 255,245,328 466,764,374 450,792,807 361,530,142
-
Consolidated total: 429,307,812 566,085,679 675,626,565 433,497,920
The consolidated investments balance has decreased from position of R 676 million in 2014/15 to
R 433 million as at 30 June 2016.
186
CHAPTER 6 - AUDITOR GENERAL REPORTS 2015/16
COMPONENT A: AUDITOR GENERAL OPINION OF CONSOLIDATED FINANCIAL STATEMENT 2015/16
187
COMPONENT B: AUDITOR GENERAL OPINION OF MANGAUNG METROPOLITAN STAND ALONE FINANCIAL STATEMENT 2015/16
188
COMPONENT C: AUDITOR GENERAL OPINION OF CENTLEC (SOC) LIMITED FINANCIAL STATEMENTS 2015/16
189
CHAPTER 7 - AUDIT COMMITTEE REPORT ON THE ANNUAL REPORT 2015/16
MANGAUNG METROPOLITAN MUNICIPALITY
REPORT OF THE AUDIT COMMITTEE FOR THE YEAR ENDED 30 JUNE 2016
190
APPENDICES
APPENDIX A: COUNCILLORS, COMMITTEES ALLOCATED AND COUNCIL ATTENDANCE
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
Clr Bacela GM PT Section 80:
Planning
Ward
Councillor
ANC
72% 0
Clr Botes FR PT
Section 80:
Engineering
Services and
energy
Ward
Councillor
DA
84% 16%
Clr Britz JF PT
Section 80:
Finance
Section 79:
MPAC
Proportional
Councillor
DA
96% 4%
Clr Davies M PT
Section 80:
Corporate
Services &
Section 79:
Remuneratio
ns
Proportional
Councillor
DA
64% 36%
Clr Dennis ME PT Section 80:
Finance
Ward
Councillor
DA
56% 44%
Clr Dibeco-Masuku MD PT
Section 80:
Engineering
Services and
energy &
Corporate
Services
Ward
Councillor
ANC
64% 8%
Clr Ditabe RP PT
Proportional
Councillor
DA
76% 8%
Clr Dyosiba S PT Section 79:
MPAC
Ward
Councillor
ANC
76% 8%
Clr Eti MJ PT
Section 80:
IDP and
Strategic
Projects &
Section 79:
Remuneratio
ns
Ward
Councillor
ANC
76% 8%
Clr Hlujane MD PT
Section 80:
Finance &
Section 79:
Remuneratio
Ward
Councillor
ANC
88% 0
191
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
ns
Clr Jacobs TA PT
Section 80:
Social
Services &
Community
Safety
Proportional
Councillor
ANC
96% 0
Clr Jacobs TB PT
Section 80:
Finance &
Chairperson
Section 79:
Remuneratio
ns
Ward
Councillor
ANC
84% 0
Clr July LR PT
Section 80:
Economic
Development
and Spatial
Planning &
Economic
and Rural
Development
&
Chairperson
Section 79:
Rules
Proportional
Councillor
DA
96% 0
Clr Kaliya SG PT
Section 80:
Engineering
Services and
energy &
Section 79:
Rules
Ward
Councillor
ANC
100%
Clr Khi ZT PT
Section 80:
Environment
al and waste
Management
&
Section 79:
MPAC &
Section 79:
Remuneratio
ns
Ward
Councillor
ANC
88% 0
Clr Kotze GDP PT
Section 80:
Community
Safety &
Environment
al and waste
Management
Ward
Councillor
DA
92% 8%
Clr Kuape PA PT Section 80: Ward 72% 4%
192
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
Environment
al and waste
Management
& Section 79:
Rules
Councillor
ANC
Clr Lala TS PT Section 80:
Finance
Ward
Councillor
ANC
64% 4%
Clr Lazenby JAA PT
Proportional
Councillor
DA
48% 48%
Clr Lebitsa GG PT
Proportional
Councillor
DA
100%
Clr Leech D PT
Section 80:
IDP and
Strategic
Projects
Ward
Councillor
DA
48% 52%
Clr Lekgela LE PT
Section 80:
Corporate
Services &
IDP and
Strategic
Projects &
Section 79:
Public Places
and Street
Naming
Proportional
Councillor
COPE
92% 8%
Clr Lephoi MJ PT
Section 80:
Human
Settlement &
Section 79:
Public Places
and Street
Naming
Ward
Councillor
ANC
96% 0
Clr Litabe TK PT
Section 80:
Engineering
Services and
energy
Proportional
Councillor
DA
80% 16%
Clr Madela BNV PT Section 80:
Planning
Ward
Councillor
ANC
84% 4%
Clr Makhele ET PT Section 80:
Finance
Ward
Councillor
ANC
92% 0
Clr Malebo MC PT Section 80:
Economic
Proportional
Councillor 91% 9%
193
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
and Rural
Development
DA
Clr Mangcotywa ZE FT Chief Whip
Proportional
Councillor
ANC
84% 16%
Clr Manyoni TM FT Executive
Mayor
Proportional
Councillor
ANC
76% 24%
Clr Masoetsa LA FT
MMC:
Engineering
Services and
energy
Proportional
Councillor
ANC
80% 20%
Clr Masoeu TD PT
Proportional
Councillor
DA
100%
Clr Mathobisa ML PT
Section 80:
Corporate
Services &
Section 79:
Public Places
and Street
Naming
Ward
Councillor
ANC
80% 8%
Clr Matsemelela MV PT
Section 80:
Engineering
Services and
energy
Ward
Councillor
ANC
96% 4%
Clr Matsoetlane MJ FT MMC: Social
Services
Proportional
Councillor
ANC
76% 20%
Clr Mbange MB PT
Section 80:
Finance &
Economic
and Rural
Development
& IDP and
Strategic
Projects
Proportional
Councillor
ANC
64% 36%
Clr Mfazwe TM PT
Section 80:
Social
Services &
Community
Safety
Proportional
Councillor
ANC
68% 16%
Clr Minnie H PT
Section 80:
Human
Settlement
Proportional
Councillor
DA
71% 29%
Clr Moeng MA FT MMC:
Planning
Proportional
Councillor 100%
194
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
ANC
Clr Mofokeng MJ PT
Section 80:
Environment
al and waste
Management
Ward
Councillor
ANC
68% 0
Clr Mogamise ID PT
Section 80:
Social
Services &
Community
Safety &
Section 79:
Public Places
and Street
Naming
Proportional
Councillor
ANC
84% 8%
Clr Moilwa ME PT
Section 80:
Engineering
Services and
energy &
Human
Settlement &
Section 79:
Remuneratio
ns
Proportional
Councillor
ANC
68% 8%
Clr Mokoloko PR PT
Section 80:
Social
Services
Ward
Councillor
ANC
48% 4%
Clr Mokone KO PT
Section 80:
Social
Services
Proportional
Councillor
DA
36% 36%
Clr Modisaesi NG FT MMC:
Finance
Proportional
Councillor
ANC
84% 16%
Clr Moloabi RLAE PT Section 79:
MPAC
Ward
Councillor
ANC
86% 8%
Clr Monnakgori SA FT
MMC:
Economic
and Rural
Development
Proportional
Councillor
ANC
64% 28%
Clr Mononyane MB PT
Section 80:
Planning &
Human
Settlements
& Section 79:
Remuneratio
ns
Proportional
Councillor
COPE
96% 4%
Clr Moopelo TM PT Section 80: Ward 92% 0
195
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
Human
Settlement
Councillor
ANC
Clr Mophethe TA PT
Section 80:
IDP and
Strategic
Projects &
Section 79:
Rules
Proportional
Councillor
ANC
88% 8%
Clr Moroe TCL PT
Section 80:
Environment
al and waste
Management
Ward
Councillor
ANC
80% 8%
Clr Moruri MM PT
Section 80:
Corporate
Services &
Economic
and Rural
Development
Ward
Councillor
ANC
88% 0
Clr Morutle SS PT
Section 80:
Social
Services
Ward
Councillor
ANC
88% 8%
Clr Moshwadiba PZ PT
Section 80:
Social
Services
Section 79:
MPAC
Proportional
Councillor
APC
72% 12%
Clr Mosiuoa TA PT
Section 80:
IDP and
Strategic
Projects
Proportional
Councillor
DA
81% 19%
Clr Motladile MZ PT
Section 80:
Community
Safety &
Section 79:
Public Places
and Street
Naming
Ward
Councillor
ANC
68% 4%
Clr Motlatsi HJ PT
Section 80:
Community
Safety &
Section 79:
Public Places
and Street
Naming
Ward
Councillor
ANC
96% 0
Clr Mpakathe TS PT
Section 79:
Public Places
and Street
Proportional
Councillor
DA
72% 12%
196
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
Naming
Clr Mpeqeka MS PT Section 80:
Planning
Proportional
Councillor
ANC
36% 16%
Clr Mtshiwane KJ PT
Section 80:
Engineering
Services and
energy &
Section 79:
Rules
Ward
Councillor
ANC
92% 0
Clr Naile TJ PT
Section 80:
Human
Settlement &
Section 79:
MPAC
Ward
Councillor
ANC
76% 0
Clr Ndamane SS PT
Section 80:
IDP and
Strategic
Projects
Ward
Councillor
ANC
100%
Clr Nkoe MJ PT Section 79:
MPAC
Ward
Councillor
ANC
92% 0
Clr Nothnagel J PT
Section 80:
Planning &
Corporate
Services
Proportional
Councillor
ANC
80% 20%
Clr Olivier GJ PT
Section 80:
Economic
and Rural
Development
&
Environment
al and waste
Management
Proportional
Councillor
ANC
68% 20%
Clr Parkie TD PT
Section 80:
Economic
and Rural
Development
Proportional
Councillor
ANC
60% 24%
Clr Pato TWG PT Section 79:
MPAC
Proportional
Councillor
ANC
92% 4%
Clr Petersen JE PT-later FT
Section 80:
Engineering
Services and
energy &
Human
Settlement &
Proportional
Councillor
ANC
88% 12%
197
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
MMC:
Environment
al and waste
Management
Clr Phajane MA PT
Section 80:
Social
Services
Proportional
Councillor
DA
92% 8%
Clr Phokoje SD PT
Section 80:
Community
Safety
Ward
Councillor
ANC
96% 0
Clr Phupha NA PT
Section 80:
Human
Settlement &
Section 79:
Rules
Ward
Councillor
ANC
72% 8%
Clr Pongolo XD FT MMC: Human
Settlement
Ward
Councillor
ANC
92% 8%
Clr Powell JD PT
Section 80:
Engineering
Services and
Energy &
Finance
Section 79:
MPAC
Proportional
Councillor
FFP
52% 48%
Clr Pretorius C PT
Section 79:
Remuneratio
ns
Ward
Councillor
ANC
88% 8%
Clr Pretorius JC PT Section 79:
Rules
Ward
Councillor
DA
88% 12%
Clr Rabela KN FT-later PT
Section 80:
Environment
al and waste
Management
& Section 79:
Remuneratio
ns
Proportional
Councillor
ANC
68% 8%
Clr Rametse MA PT
Section 80:
Community
Safety &
Environment
al and waste
Management
Proportional
Councillor
COPE
84% 4%
Clr Ramokotjo FP PT Section 79:
MPAC
Ward
Councillor
ANC
92% 0
198
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
Clr Rampai CLM FT
Deputy
Executive
Mayor
MMC: IDP
and Strategic
Projects
Proportional
Councillor
ANC
79% 21%
Clr Rantai JH PT
Proportional
Councillor
DA
100%
Clr Ratsiu NA PT
Section 80:
Planning &
Chairperson
Section 79:
Public Places
and Street
Naming
Ward
Councillor
ANC
96% 0
Clr Sebothelo ME PT
Section 80:
IDP and
Strategic
Projects &
Section 79:
Public Places
and Street
Naming
Ward
Councillor
ANC
84% 8%
Clr Sekakanyo DM FT-later PT
MMC:
Community
Safety
Section 80:
Human
Settlements
Proportional
Councillor
ANC
100%
Clr Selaledi M PT
Section 80:
Finance &
Economic
and Rural
Development
Proportional
Councillor
ANC
88% 12%
Clr Siyonzana MA FT Speaker
Proportional
Councillor
ANC
100%
Clr Snyman van
Deventer E PT
Section 80:
Economic
Development
and Spatial
Planning &
Economic
and Rural
Development
& Section 79:
Proportional
Councillor
FFP
64% 36%
199
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
Rules
Clr Teko ED PT
Section 80:
Corporate
Services
Ward
Councillor
ANC
96% 0
Clr Terblanche AP PT
Section 80:
Community
Safety
Ward
Councillor
ANC
84% 16%
Clr Thipenyane GM PT-later FT
MMC:
Section 80:
Community
Safety
Proportional
Councillor
ANC
88% 4%
Clr Thwala ZT PT
Proportional
Councillor
DA
100%
Clr Titi-Odili LM PT- later FT
Chairperson:
Section 79:
MPAC
Proportional
Councillor
ANC
92% 0
Clr Toba AL PT
Section 80:
Social
Services &
IDP and
Strategic
Projects &
Section 79:
Rules
Proportional
Councillor
ANC
100%
Clr Tobie EC PT
Section 80:
Human
Settlement
Ward
Councillor
DA
57% 33%
Clr Tsomela MM FT
MMC:
Corporate
Services
Proportional
Councillor
ANC
92% 4%
Clr van Biljon PJJ PT
Section 80:
Planning &
Section 79:
MPAC
Ward
Councillor
DA
92% 8%
Clr van der Merwe R PT
Section 80:
Corporate
Services &
Section 79:
Remuneratio
ns
Ward
Councillor
DA
96% 4%
Clr van der Walt T PT
Section 80:
Environment
al and waste
Management
Proportional
Councillor
DA
72% 28%
Clr van Niekerk HJC PT Section 80:
Planning
Ward
Councillor 92% 4%
200
Councillors, Committees Allocated and Council Attendance
Council Members Full Time /
Part Time
Committees
Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies
for non-
attendance
FT/PT % %
DA
Clr Viviers BJ PT Section 79:
Rules
Ward
Councillor
DA
96% 8%
Clr Ward VW PT Section 80:
Planning
Ward
Councillor
ANC
100%
Clr Zerwick AS PT
Section 79:
Public Places
and Street
Naming
Proportional
Councillor
ANC
76% 24%
Clr Zophe NM PT
Proportional
Councillor
ANC
33% 52%
Note: * Councillors appointed on a proportional basis do not have wards allocated to them.
Councillors who were removed before end of term.
Councillors who replaced Councillors removed.
Councillor deceased
201
APPENDIX B: COMMITEE AND COMMITEE PURPOSE
Committees (other than Mayoral / Executive Committee) and Purposes of Committees
Municipal
Committees
Purpose of Committee
Section 79
Committee
Committees are established by the Council from among its members. Council
determines the functions of the committee and may delegate powers and duties
to it. The Committees report directly to Council.
Section 80 Committees are established by the Council from its members to assist the
Executive Mayor. The Executive Mayor appoints a chairperson for each
committee from the Mayoral Committee and may delegate powers and duties.
The various committees consider and approve the reports and policies. These
reports and policies are forwarded to the Mayoral Committee for consideration.
It is then referred to Council for approval. They are advisory committees to the
Executive Mayor.
Audit Committee Committee is appointed by Council in terms of the Municipal Finance
Management Act No. 56 of 2003 (“the Act”), Section 166, to assist Council, in
discharging its oversight responsibilities. It is an independent advisory body to
Council.
Budget steering
committee
The mayor of a municipality establish a budget steering committee to provide
technical assistance to the mayor in discharging the responsibilities as set out in
section 168 of the MFMA.
IDP Steering
Committee
The mayor of a municipality establish IDP steering committee to provide
technical assistance to the mayor in discharging the responsibilities as set out in
section 30 of the Municipal Systems Act.
Ward
Committees
They are committees meant to encourage participation by the community – their
job is to make municipal council aware of the needs and concerns of residents
and keep people informed of the activities of municipal council.
LLF Section 2.8.11 of the Main Collective Agreement of the SALGBC dictates that
every employer must establish a Local Labour Forum with equal representation
from the trade unions (SAMWU and IMATU) and the employer to strengthen the
relationship between the two.
202
APPENDIX C: TWO TIER STRUCTURE
Department City Manager and Heads of Department
Office of the City Manager Municipal Manager, Me Sibongile Mazibuko
Centlec Chief Executive Officer: Mr Andries Mgoqi
Corporate Services Head of Department, Ms M Ramaema
Engineering Services Head of Department, Mr LX Ntoyi
Finance CFO, Mr EM Mohlahlo
Human Settlement Head of Department Mr MM Mokoena
Planning and Economic Development Acting Head of Department, Mr Makiso
Khumalo
Social Services Head of Department, Ms EH Radebe
Strategic Projects & Service Delivery Regulation Head of Department, Mr MG Mohlakoana
203
APPENDIX D: FUNCTIONS OF THE MUNICIPALITY/ ENTITY
Municipal / Entity Functions
MUNICIPAL FUNCTIONS
Function
Applicable to
Municipality
(Yes / No)*
Function
Applicable to
Entity
(Yes / No)
Constitution Schedule 4, Part B functions:
Air pollution Yes
Building regulations Yes
Child care facilities Yes
Electricity and gas reticulation Yes ( Centlec)
Fire fighting services Yes
Local tourism Yes
Municipal airports No
Municipal planning Yes
Municipal health services Yes
Municipal public transport Yes
Municipal public works only in respect of the needs of
municipalities in the discharge of their responsibilities to
administer functions specifically assigned to them under this
Constitution or any other law
Yes
Pontoons, ferries, jetties, piers and harbours, excluding the
regulation of international and national shipping and matters
related thereto
No
Storm water management systems in built-up areas Yes
Trading regulations Yes
Water and sanitation services limited to potable water
supply systems and domestic waste-water and sewage
disposal systems
Yes
Beaches and amusement facilities No
Billboards and the display of advertisements in public places Yes
Cemeteries, funeral parlours and crematoria Yes
Cleansing Yes
Control of public nuisances Yes
Control of undertakings that sell liquor to the public No
Facilities for the accommodation, care and burial of animals
204
Municipal / Entity Functions
MUNICIPAL FUNCTIONS
Function
Applicable to
Municipality
(Yes / No)*
Function
Applicable to
Entity
(Yes / No)
Constitution Schedule 4, Part B functions:
Fencing and fences
Licensing of dogs
Licensing and control of undertakings that sell food to the
public Yes
Local amenities Yes
Local sport facilities Yes
Markets
Municipal abattoirs Yes
Municipal parks and recreation Yes
Municipal roads Yes
Noise pollution Yes
Pounds Yes
Public places Yes
Refuse removal, refuse dumps and solid waste disposal Yes
Street trading Yes
Street lighting Yes ( Centlec)
Traffic and parking Yes
205
APPENDIX E: WARD REPORTING
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
1 Moholo Itumeleng Solomon Yes
NONE NONE NONE
Phillips Everstone No
Moholo Constance Yes
Sebela Thobadi Joseph Yes
Motlosa Subueng Elizabeth No
Ngcobo Mbuleni Yes
Nteo Betty Motlalepule Yes
Moshoeu Elliot Yes
Shuping Mpho Mary No
Lethumile Moloele Yes
2 Rapelang Jeffrey Phekonyane Yes
1 3
Moroe Gladys Moleboheng Yes
Moeng Masebatha Maureen Yes
Mziwande Conference Majola Yes
Sebidi Theodora Mpho Yes
Nthahane lebohang Simon No
Selai Thabo Micheal Yes
Mosime Madigana Charlotte Yes
Kgosi Tebogo Victor Yes
Moahlodi Florence Mantshabeng Yes
3 Tshiame Mpho Jeminah Yes
5 2
Malakoane Mosala Shadrack No
Mosieleng Setshego Annah No
Luphongolo Nomarasia Portia Yes
Tubane Matswene Sarah Yes
Nomalanga Ntombizodwa
Gladys Yes
Mpuru Bernice Mamorwa Yes
206
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Monare Stanley Kgosimang Yes
Mathe KonzampiMichael Yes
Didiza Thoreka Elizabeth Yes
4 Moshodi James Kesiloe Yes
0 2
Hlakanyane Mable Vava Yes
Mokgele Jonas Lejone Yes
Thamae Kenalemang Frieda Yes
Lekhu Lebogang Moses Yes
Mothupi Sebueng Agnes Yes
Lesia Nthabiseng Lucia Yes
Makwetla Dimakatso Elsie Yes
Nomandla Velile Coronation Yes
Sethunya Yvonne Mosili Yes
Sithembile Lawrence
5 Ralikhomo Selloane Irene Yes
NONE NONE NONE
Qotho John Tshaka Yes
Qokole Ntombizanele Rosy Yes
Nduma Zimela Sylvia Yes
Johannes Thabeeapelo
Phike Mzimkulu Amos Yes
Qobo Mmolayeng Regina Yes
Maxakato Badirwang William Yes
Nophali Wezile Matthews Yes
Makgalemela Buti Lucas Yes
6 Nthabiseng Joyce Nkane Yes
NONE 4
Yeko Maria Vuyelwa Yes
Ntsane Mwenda Yes
Dlamini Bongani Petros Yes
Petrus Phumelelo Ben Yes
Mavuya Lucas Xhalisile Yes
207
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Letsosa Nonceba Lenah Yes
Mosaqa Isaac Lehlohonolo No
Litsesane Matsietsi Angelina Yes
Handana Thembinkosi Yes
7 Ramodula Pule Johannes Yes
3 6
Masiu James Molete Yes
Mosiane Georgia Dieketseng Yes
Motema Sechaba Ezekial Yes
Tjotjo Mamoloko Sarah Yes
Nokoane Mothibi Ishmael Yes
Mosia Anna Matseliso Yes
Phakoe Lekula Napoleon Yes
Masimong Rebecca Matseliso Yes
Maxakato Brian Mongesi Yes
8 Koaho Tshediso Petros Yes
4 3
Mafatie Lefa Joseph Yes
Seepamore Lebogang Solomon No
Nyaphudi Likeleli Julia No
Nyapoli Sefohle Claas Yes
Conjwa Databa Yes
Nyezi Ligwa Belinda Yes
Nkhabu Mabatho Cecilia Yes
Mabina Pakiso Grace No
Mogwera Botlhokwane Emily No
9 Letebele Lyndon Gaurutwe Yes
NONE NONE
Mosepele Martha Lieketseng Yes
May Benjamin Lehlohonolo Yes
Phiri Emmah Mamotshidisi Yes
Motshidisi Phalole Yes
Sefotlhelo Oupa Abraham Yes
208
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Hlalele Itumeleng Adelina Yes
Kotso Pamela Nontsikelelo Yes
Ramabitsa Merriam
Tombezonke Yes
Matsane Mpotseng Maria Yes
Kelebogile Ellen Masia
10 Setsipane Welhimina
Motswamasimo Yes
NONE NONE
Rampai Dina Kedisaletse Yes
Motlhanke Makoto Emily Yes
Namane Jacob Tsietsi Yes
Wesi John Bushman Yes
Ditlakanyane Taunyane Andries Yes
Mokhele Nnuku Emily Yes
Molelekoa Annah Dikeledi Yes
Kgotle Amelia Mpontsheng Yes
Seekoei Anna Masennelo Yes
11 Rankhala Moliehi Thereza Yes
3 3
Moeng Moeketsi David Yes
Lekoa Mohlouwa Samuel Yes
Majoro Sizakele Godfrey Yes
Rapulane Motshedisi Paulina Yes
Akata Mokola Ephraim Yes
Madito Madikesane Paul Yes
Tshanku Moretiemang Lydia Yes
Makhetha Thikgoe Ishmael Yes
Morake Mosele Sinah Yes
12 Matlaletsa Mamokete Sophia Yes
1 2 Motlomelo Alfred Tshepo Yes
Mathibedi Khotso Yes
209
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Thabana Jienny Yes
Tonizi Johannes Velile Yes
Masawa Paulus Yes
Moletsane Ithapeleng No
Mutsi Bernice Mateboho No
Motsumi Dipuo Eliza Yes
Mphulanyane Refiloe Yes
13 Tshehlo David Yes
NONE NONE NONE
Mototo Phenyo Samuel Yes
Peter Petrus Mbekiselwa Yes
Moletsane Florence Disebo Yes
Plaatjie Elias Tenteng Yes
Seliane Abel Limpho Yes
Mashale Lisema Petrus Yes
Plaatjie Julia Mohanioa Yes
Mahlase Phofane Mathews Yes
Mokokolisi Jeremiah Mantsane Yes
14 Mothupi James Tona Yes
NONE NONE NONE
Lekgatla Kedibone Joyce
Kotelo Sannah Nthabiseng Yes
Moeng Galeboe Jacob Yes
Moroosele Lucia Lipuo Yes
Ramokhula Alinah Mangaka Yes
Lebusho Contstance Diyakabeng Yes
Maleho Segalo Johannes Yes
Modiri Rosy Ntabeleng Yes
Mogoje Dipuo Yvonne
15 Nthene Sheila Yes
4 3 Mokate Julia Ntseliseng No
Moipolai Josephine Mmasana No
210
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Mapitse Tumo Khauhelo Yes
Kgatlane Andrew Orebotse Yes
Molefi Maria Ntswaki Yes
Litable Pieter Magaudisi Yes
Dumezweni Boniswa Alinah Yes
Mokobe Rosaypan Martha Yes
Makidela thandiwe Idah Yes
16 Van Staaden Elizabeth Yes
NONE 1
Beck Kelvin Sydney No
Parker Roseline Brenda Yes
Davis Esmerelda Joice No
Jansen Johnnie Yes
Jordaan Elsie No
Lorraine Gouws No
Smith Andries Abraham Yes
Sinra Reginald Yes
Brumilda Matthews Evodia Yes
Ndaba Nduna -
17 Mosoeu Sello Johannes Yes
NONE NONE
Staat Anna Mmamaketa Yes
Motumi Innocentia Dibokanyo Yes
David Cornelissen Yes
Sejane Monica Mankotseng Yes
Mzwake Dineo Yes
Mahlatsi Eric Mokanelo Yes
Tlhakudi Lucas Gabutlwelwe Yes
Molantoa Agnes Moselantja Yes
Tshefa Moleko Richard Yes
18 Sello Moeketsi Petrus Yes
NONE NONE Buffel Themba Johannes No
211
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Tana Vuyiwe Evellyn No
Tsie Peter Yes
Ntamo Mary Stella Yes
Adoons Masabata Pollah Yes
Phatsa Mothepana Violet Yes
Seeco Phegelle Caleb Yes
Masakala Matshidiso Emily Yes
Van Rooi Isaac Kabelo Yes
19 Maleleka Patrick Tshebeletso Yes
2 3
Maele Leah Mamofolo Yes
Mohlabane Khotso Sam Yes
Katu Sanah Yes
Mojatau Motlalepule Ruth Yes
Mothabeng Donald Dingaan Yes
Motse Naomi Mantele Yes
Mohapi Molefi Lucas Yes
Phetlu Phillip Modisaotsile Yes
20 Muller Andries Johannes Griesel Yes
2 1
Lubbe Coenraad Hendrik Yes
Van Biljon Johanna No
Myburgh Mathias Frederick Yes
Swart Coenraad Johannes Yes
VanVuuren Karlien Janse No
Lubbe Gezina Cornelia Yes
Groenewald Elize Yes
Steenkamp Glaudina Maria No
Botha Frederik Thomas Yes
21 Horn Jacomina Gerharda Yes
NONE 2
Erasmus Jan Yes
Russel Dorothy Charmaine Yes
212
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Prior Claudette Geraldine Yes
Stephanus Jacobs Van Heerden Yes
Jacobs Michael Johannes Yes
Mofoli Moipone Florence Yes
Jan Lodewyk Smith Yes
Herman Conradie Petrus
Jacobus Yes
Phohleli Kedibone Violet Yes
22 Theron Stephanus Ferreira Yes
1 7
Lubbe Willem Frederik Yes
Moorcroft Henry Sutton Yes
Van Der Westhuizen Sarah Yes
Coetzee Josef Adriaan Yes
Botha Monica Lorraine Yes
Wyngaard Paul Jacobus Yes
Mostert Johanness Albertus Yes
Fourie Frikkie Benjamin Yes
Morey Tammy Yes
23 Fouche Gert Stefanus Yes
3 3
Kitching Christo Yes
Taljaard Jaques Yes
Letsoara Thabiso Joseph Yes
Clayton William Yes
Thabane Tom Motsoahae Yes
Jordaan Marthinus Johannes Yes
Jordaan Marie Anna Elizabeth Yes
Cilliers Isabella Jacomina Yes
Hammond Michelle No
24 Theron Pieter Willem Yes 2 1
Scholtz Marlene Yes
213
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Bester Johannes Yes
Erasmus Lourens Daniel No
Venter Phillippus Arnoldus Yes
Du Toit Johanna Hendrina Yes
Roets Thomas Barker No
Viljoen Jansen Petrus Yes
Kotze Dirk Petrus Gerhardus No
Du Toit Frederik Jacobus Yes
25 Van Amstel Pieter Ploos No
NONE NONE
Beukes Pieter No
Swart Lucas No
Mocke jacobus Johannes
Botha Dawid Matthys Beukes No
Visser Deon No
Scorgie Leonard Ivan No
De Jager Cecilia Johanna No
Viljoen Hendrik Chritoffel No
De Bruin Jacob Daniel No
26 Wentzel Jacoba Elizabeth No
1 NONE
Wessels Sebastiaan Jacobus No
Wessels Johannes Marthinus No
Maartens Jacobus Meitjies No
Van Vuuren Schalk Petrus No
Gouws Cornelius Francois No
Germishuys Willem Jacobus No
Malan Pieter Jacobus No
Praekelt Herman Ernest
Wessels Matheus Hendricus No
27 Nompondo Mamaki Elizabeth Yes NONE NONE
Tshetlhe Grace Dikeledi Yes
214
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Machaba Linda Yes
Litabe Ditshewane Paulina Yes
Motjakotja Lekhotla Augustinus Yes
Mpakanyane Maserona
Elizabeth Yes
Motjotji Tshokolo Johannes Yes
Lemphane Thabo Andrias Yes
28 Ncangiwe Wittes Yes
2 2
Limakatso Rapolaki Yes
Martha Morake Yes
Petrus Tlokotsi Mpuru Yes
Teboho Salemane Yes
Lefu Nkake Yes
Mabatho Setouto Yes
Dipolelo Madona Yes
Lehlohonolo Seepe Yes
Lelala Moipone Yes
29 Ratsoeu Ernest Seokolo Yes
3 4
Litlhakanyane Valestina
Ntaoleng No
Letooane Rebecca Yes
Mohapi Raboroko Yes
Smile Bongiwe No
Nkgodi Itumeleng Yes
Motsokobi Kabelo Yes
Mpulenyane Mathabo No
Ntulini Boniswa Yes
Tseki Clement No
30 Ndara Puleng Sophy Yes 1 1
Nthathise Selinah Filita Yes
215
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Khoantle Mariam Yes
Ncamane Zinhle Nomvula Yes
Tsoelesa Kekeletso Yes
Mei Elizabeth Yes
Lentoa Selloane Yes
Lebitsa Joalane Merriam Yes
Toso Gaelebale Kate Yes
Mahupela Keitumetse Joseph Yes
31 Nkoqa Precious Tshirone Yes
3 2
Mohokare Joalane Yes
Nthatisi Annah Masabatha Yes
Mokhothu Piet Kali Yes
Ellen Masia Yes
Mannini Fiavian Makgaretho Yes
Tshwari Adelina Diketso Yes
Yaso Isaac Nkosinathi No
Selebeli Malefane Godfrey No
Mokatsanyane Martin Serame No
32 Msabe Sindiwe Jane Yes
NONE NONE
Maroele Mimithi Cecilia Yes
Mhlakaza Thabita Mampolai No
Ntamane Malefu Eveline Yes
Matsoso Jan Mosiwa No
Phitsane Moeketsi Samson Yes
Matjelemane Morena Yes
Lekhooa Jacob Letlaka Yes
Nzapheza Simanga Jacob Yes
Gcinisa Mbuiselo Elias Yes
Nowezile Maphetshana
33 Jakane Steven Songezo Yes 3 1
216
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Pitseng Makoester Mitta Yes
Moeketsi Gladys Moipone Yes
Masimong Tefo Elias Yes
Dashe Martha Buyiswa Yes
Sello Geelbooi Yes
Sesing Musi Samuel Yes
Mosala Magadibolae Elizabeth Yes
Fubane Nthabiseng Jane Yes
Mohono Tshidiso Augustine Yes
34 Mohlabane Esther Mpho Yes
NONE NONE
Lekitlane Cornelius Sekoto Yes
Nthonyane Justinah Tebello Yes
Ntipe Victoria Dieketseng Yes
Sakaone Julia Angeline Yes
Mohokare Agnes Dineo Yes
Pholoana Tsietsi Yes
Letube Mamontsheng Yes
Moeketsi Jouber Monere Yes
Motjetje Shamali Yes
35 Mamome Masomi George Yes
NONE NONE
Tsolo Mamokete Suzzet Yes
Koloi Tsietsi Daniel Yes
Khookhoo Martha Nomathemba Yes
Moshaoa Maria Makgokolotso Yes
Pesa Masehau Belina Yes
Molebatsi Lucy Mantwa Yes
Mphane Mampho Eugenia Yes
Masoabi Makotoko Isaac Yes
Mphana Pheello Petros Yes
36 Kobeli Steven Sefabatho Yes 1 1
217
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Nkati Winfred Matshiliso No
Moloi Peter Mokete Yes
Moiloa Sara Joalane Yes
Kuku Jane No
Behle Alina Yes
Kgaphetsi Issac Parkies Yes
Motlhale Disebo Margaret Yes
Mohlanyane William Sizani Yes
Lerumo Charle Yes
37 Molaolwa Caroline Lizzie Yes
NONE NONE
Nowezile Maphetshana Yes
Ntomane Bereng Hendrick Yes
Makhela Mojalefa Samuel Yes
Matiisetso Sarah Nkhahle Yes
Sekati Maletebele Elizabeth Yes
Thupeng Selina Yes
Gras Kedibone Yes
Leifo Tseleng Julia Yes
Lekau Vitlace Sylveste Yes
38 Ramainoane Thete David Yes
NONE NONE
Dumbela Sampi Jack
Makatse Puleng Theresa Yes
Moticoe Kamohelo Paulina Yes
Ssampie Jack Dumela Yes
Porota Seeiso Sebastian Yes
Mokgosi Eliza Mmantuni Yes
Mamokeli Sebolelo Caroline Yes
Tlome Hadio Adolphina Yes
Moticoe Kamohelo Paulina Yes
39 Ndaba makcaye Yes NONE NONE
218
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Moraloki Molefi Solomon No
Mogapi Ntsoaki Aphaphia Yes
Mojau Lenka Elias Yes
Finger Bathobile Elizabeth Yes
Moleme Tebogo Sylvester Yes
Moreng Mothusi Ishmael Yes
Moea Tankiso Julius Yes
Matekane Moleboheng Sannah
Mantshane Elizabeth
Tombizodwa
40 Mohapi Gladys Keitumetse Yes
3 1
Saki Tsubane Phillip Senkie Yes
Booysen Kedibone Elizabeth Yes
Sebitloane Gertrude Kedisaletse Yes
Sephecolo Keonethebe
Abednego Yes
Molahloe Eunice Mansnekele Yes
Mothupi Sylvia Magoyane Yes
Nkopane Dimakatso Martha No
Motshabi Emily No
Sebitlwane Sarah Machere No
41 Sekhoane Malebusho Jeanett Yes
NONE NONE
Mohutsiwa Victor Pule Yes
Nzamo Vuyo Godfrey Yes
Lekitlane Mantja Agnes Yes
Motsalane Mamosa Arcilia Yes
Moraile Motshegiwa Alinah Yes
Setilo Ramekoa Isaac Yes
Moleko Tshokolo Elvis Yes
Mbangula Sithembile Stephen Yes
Seroalo Rasepalo Lazarus Yes
219
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
42 Motsoane Malitlhare Suzan Yes
NONE NONE
Seseane Thato walter Godwill Yes
Matlakala Amelia Mamoshe Yes
Rabanye Pulane Suzen Yes
Moepeng Campbell Kgosiemang Yes
Olifant Margreth Matsie Yes
Hugo Andries Fumanekile Yes
Moshodi Tseleng Elizabeth Yes
Tshabalala Solomon
Qhobosheane Yes
Moikangoa Thabo Alexis Yes
43 Moqolo Lehlohonolo Joseph Yes
NONE NONE
Mmusetsi Nthabiseng Suzan Yes
Moriri Josephine Mosidi Yes
Liefo Dikeledi Frangelinah Yes
Matosa Maverik Ntsikelelo Yes
Nyokong Ntwabotshelo
Righeous Yes
Ralejwana Mantwa Sarah Yes
Goitsemodimo Molebogeng Yes
Putsoa Modise Shadrack Yes
Mthwalo Patricia Kedibone Yes
44 Van Der walt Stephanus Tjaart
NONE NONE
Tetewe Pulane Eveline Yes
Kwatala Kedisaletse Adelina Yes
Tlhodi Lineo Eveline Yes
Kasselman Batholomew Yes
Lichtenstein Rene Yes
Lotter Mattheus Gerhardus Yes
Nel Riaan Yes
220
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
Kemp Gabre Yes
Van Der Walt Tjaart Botha Yes
45 Thubela Malefatsane Jacob Yes
NONE NONE
Mifi Emily Masabata Yes
Sithole Lefu James Yes
Cuze Pinky Yes
Tseki Modupe Frans Yes
Maroi Dilahloane Augustina Yes
Lesige Mahadi Agnes Yes
Kenkana Tshotleho Oupa Yes
Mophethe Bokang Olga. Yes
Maduna Dingaan David Yes
46 Koloane David Gorekwang
NONE NONE
Vaphi Lehlonolo
Phofolo Annah Zondiwe
Ximba Nosipho Esther
Nieuwenhuizen Francinah
Phakasi Kefuwe Agness
Booi Jane Thenjiwe
Molehe David Tebogo
Lemaoane Tshediso Prince
Motopi Tsekiso Samuel
47 De Wee Precilla
NONE NONE
Sehole Mpho
Mazengane Petrus
Ndaba Jabulile
Pulumo Thupa
Amanda Mangalie
Meyer Sarah
Davids Richard
Peterson Jakoba
Claasen Heini
221
Functionality of Ward Committees
Ward
Number
Name of Ward Councillor and
Elected Ward Committee
Members
Committee
Established
(Yes/No)
Number of
Monthly
Committee
Meetings Held
During the Year
Number of
Monthly reports
Submitted to
Speakers
Office on Time
Number of
Quarterly
Public Ward
Meetings Held
During Year
48 Bandenhorst Jan Hendrik
NONE NONE
Britz Andries
Smit Adriaan Andreas
Rafferty Margret Mary
Smith Louis
Booysen Ditaba Petrus
Ntsioa Anasenta Sekao
Leeuw Dipuo Evelyn
Mogapi Elizabeth
Ngwedi Merriam
49 Mothibi Moholo Daniel
NONE NONE
Papane Matshediso Evodia
Litsoane Thabang Johannes
Nzondo Langa Abial
Nakedi Manninni Emily
Mabitle Hendrik Goitsemang
Saaiman Abel Letsoai
Setshego Johannes Sabata
Mangwegape Constance
Motlalepule
Matlhoko Sello Lawrence
222
APPENDIX F: WARD INFORMATION
Capital Expenditure of 5 largest projects*
R' 000
Name of Project
Current: Year 2015/16 Variance: Current Year
2015/16
Original
Budget
Adjustment
Budget
Actual
Expenditure
Original
Variance
(%)
Adjustmen
t variance
(%)
A - SMART
STREETLIGHTS 40,000,000 35,000,000 42,691,340 -6.73% -21.98%
B - AIRPORT
DEVELOPMENT NODE 46,000,000 46,000,000 18,791,041 59.15% 59.15%
C - REFURBISHMENT
OF WATER SUPPLY
SYSTEMS: A 50,000,000 45,000,000 980,785 98.04% 97.82%
D - NORTH EARSTERN
WWTW PHASE 2 51,783,461 28,599,420 28,274,822 45.40% 1.13%
E - NEW VEHICLE
LEASING 91,256,000 91,256,000 68,458,341 24.98% 24.98%
TOTAL 279,039,461 245,855,420 159,196,330 42.95% 35.25%
PROJECTS WITH THE HIGHEST CAPITAL EXPENDITURE IN YEAR 2015/2016
Name of Project – A Smart Street Lights
Objective of Project To install energy saving street lights to ensure
visibility even when there is load-shedding and
saving on the cost of electricity
Delays None
Future Challenges None
Anticipated citizen benefit Reliable provision of street lighting and possible
contribution towards the reduction of crime
Name of Project – B Airport Development Node
Objective of Project To install the requisite municipal infrastructure
services to support the development of Airport
Development Node
223
Delays Unforeseen planning matters that delayed the
project
Future Challenges None
Anticipated citizen benefit Access to employment opportunities, access to
housing opportunities and access to learning
institutions
Name of Project C –Refurbishment of water
system
Objective of Project To refurbish ageing water systems in the City that
is made of decrepit cement asbestos pipes that are
prone to bursting
Delays None
Future Challenges None
Anticipated citizen benefit Provision of effective waterservices and reduction
of non-revenue water
Name of Project-D – North Eastern Waste Water
Treatment Works
Objective of Project To build a new Waste Water Treatment Work
Delays None
Future Challenges None
Anticipated citizen benefit Provision of effective sanitation services and
support development along N8 Corridor
Development
Name of Project – E Vehicle leasing
Objective of Project To acquire additional white and yellow fleet for City
Delays Some of the yellow fleet had to be customised
Future Challenges
Anticipated citizen benefit Effective service delivery
224
APPENDIX G: RECOMMENDATIONS OF THE MUNICIPAL AUDIT COMMITTEE
Municipal Audit Committee Recommendations
Date of Committee
and Meeting
No.
Committee recommendations during Year 2015/16 Recommendations
adopted (enter Yes)
If not adopted
(provide
explanation)
01/2015-16/38
27 August 2015
AG Audit Strategy
The Audit Committee resolved to approve the audit strategy
Yes
01/2015-16/38
27 August 2015
Mangaung Metro Annual Financial Statements for 2014/15
The Audit Committee resolved to approve that the Annual Financial
Statements be submitted to AGSA for auditing
Yes
03/2015-16/40
9 October 2015
Three year Internal Audit Plan 2015/16 – 2017/18
The Audit Committee resolved to approve the three year Internal
Audit plan 2015/16 – 2017/18.
Yes
03/2015-16/40
9 October 2015
2015/16 Schedule of Audit Committee meetings
The Audit Committee resolved to approve the 2015/16 schedule of
meetings as submitted by the Internal Auditor.
Yes
04/2015-16/41
6 November 2015
ICT Status Report
The Audit Committee resolved to make the ICT status reports a
standing item of the Audit Committee meetings.
The Audit Committee resolved that the future ICT status reports
should be verified by the Internal Audit Unit before they are
submitted to the Audit Committee.
Yes
04/2015-16/41
6 November 2015
Risk Management Report
The Audit Committee resolved that risk management reports should
serve at every Audit Committee meeting.
Yes
04/2015-16/41
6 November 2015
1st Quarter SCM Quarterly Report
The Audit Committee resolved to take note of the 1st quarter SCM
Quarterly Report.
Yes
225
Municipal Audit Committee Recommendations
Date of Committee
and Meeting
No.
Committee recommendations during Year 2015/16 Recommendations
adopted (enter Yes)
If not adopted
(provide
explanation)
The Audit Committee resolved that a report/register with all irregular
expenditure be submitted to the Audit Committee meetings.
04/2015-16/41
6 November 2015
1st Quarter MFMA Section 52 Report
The Audit Committee resolved to note the 1st Quarter MFMA Section
52 Report.
Yes
04/2015-16/41
6 November 2015
1st Quarter SDBIP Progress Report
The Audit Committee resolved to note the 1st Quarter SDBIP
Progress Report and the fact that this report will be subjected to
verification by the Internal Audit Unit.
Yes
04/2015-16/41
6 November 2015
4th Quarter Dashboard Report
The Audit Committee resolved to note the 4th Quarter Dashboard
Report and urged management to work on the yellow (in progress)
and to maintain the green (good) assessments.
Yes
04/2015-16/41
6 November 2015
Legislative Compliance Checklist (Q4 of 2014/15 and Q1 of
2015/16)
The Audit Committee resolved that management should sensitise
political leadership about compliance requirements.
Yes
04/2015-16/41
6 November 2015
4th Quarter of 2014/15 Internal Audit Quarterly Report
The Audit Committee resolved to note the 4th Quarter of 2014/15
Internal Audit Quarterly Report and the progress reported on the
completion of projects against the yearly internal audit plan.
Yes
04/2015-16/41
6 November 2015
1st Quarter of 2015/16 Internal Audit Quarterly Report
The Audit Committee resolved to note the 1st Quarter of 2015/16
Internal Audit Quarterly Report and urge management to address
findings raised by the Internal Auditor.
Yes
226
Municipal Audit Committee Recommendations
Date of Committee
and Meeting
No.
Committee recommendations during Year 2015/16 Recommendations
adopted (enter Yes)
If not adopted
(provide
explanation)
05/2015-16/42
3 December 2015
Auditor-General report on the standalone Annual Financial
Statements for 2014/15
The Audit Committee resolved to note the Audit Report for the
2014/15 Annual Financial Statements.
The Audit Committee resolved that the Audit Action Plan developed
from the Audit Report and Management Letter must be a standing
item on all ordinary meeting agendas of the audit committee.
The Audit Committee resolved that the Internal Audit Plan must be
revised to include follow-up on the implementation of the Audit Action
Plan’s corrective action.
The Audit Committee resolved that management should sensitise
the executive Mayor and Council with regards to their responsibilities
to ensure compliance to legislation as reported in the Auditor-
General report on the Annual Financial Statements of 2014/15.
Yes
05/2015-16/42
3 December 2015
Audit Committee report to Council for the 2014/15 financial year
The Audit Committee resolved that the Audit Committee report to
Council for the 2014/15 financial year must be finalised for
submission to Council.
Yes
06-2015/16-43
27 January 2016
Auditor-General report on the Consolidated Annual Financial
Statements for 2014/15
The Audit Committee resolved that the report of Centlec on irregular
expenditure reported in the Annual Financial Statements as well as
any corrective action taken to prevent future irregular expenditure be
presented to the committee.
Yes
227
Municipal Audit Committee Recommendations
Date of Committee
and Meeting
No.
Committee recommendations during Year 2015/16 Recommendations
adopted (enter Yes)
If not adopted
(provide
explanation)
The Audit Committee resolved to note the consolidated Audit Report
received from the Auditor-General for the financial year ended 30
June 2015.
07-2015/16-44
29 March 2016
ICT Status Report
The Audit Committee resolved to note progress reported by ICT to
date.
Yes
07-2015/16-44
29 March 2016
Risk Management Report
The Audit Committee resolved that the strategic risk register be
provided to the Audit Committee by 31 March 2016.
Yes
07-2015/16-44
29 March 2016
Audit Action plan
The Audit Committee resolved that the document submitted at the
next audit committee meeting should include information with
regards to progress to date as well as whether the progress has
been verified by Internal Audit.
Yes
07-2015/16-44
29 March 2016
Mid-year MFMA Section 72 Report (financial)
The Audit Committee resolved to note the report with concern to the
rising debtors’ amount.
Yes
07-2015/16-44
29 March 2016
Mid-year SDBIP Progress Report
The Audit Committee resolved to note the Mid-year SDBIP Progress
Report and urged management to ensure that KPIs and targets are
smart and that progress claimed is appropriate to achievements.
Yes
07-2015/16-44
29 March 2016
2nd Quarter SCM Quarterly Report
The Audit Committee resolved to note the 2nd quarter SCM quarterly
report.
Yes
07-2015/16-44
29 March 2016
2nd Quarter Dashboard Report
Yes
228
Municipal Audit Committee Recommendations
Date of Committee
and Meeting
No.
Committee recommendations during Year 2015/16 Recommendations
adopted (enter Yes)
If not adopted
(provide
explanation)
The Audit Committee resolved to note the 2nd quarter dashboard
report.
07-2015/16-44
29 March 2016
Legislative Compliance Checklist (Q2 of 2015/16)
The Audit Committee resolved to note the report with the concern
that the municipality is not achieving total compliance to legislation.
Yes
07-2015/16-44
29 March 2016
2nd Quarter of 2015/16 Internal Audit Quarterly Report
The Audit Committee resolved to note the 2nd quarterly Internal
Audit report.
Yes
07-2015/16-44
29 March 2016
Audit Committee in year Report to Council
The Audit Committee resolved that the updated report will be
circulated to members for final input and finalised by the chairperson
for submission to Council.
Yes
229
APPENDIX H: MUNICIPAL ENTITY/SERVICE PROVIDER PERFORMANCE SCHEDULE
MUNICIPAL ENTITY/SERVICE PROVIDER SCHEDULE
Name of Entity &
Purpose
(a) Service
Indicators
2015/2016
(b) Service Targets
Target
Current Year Actual;
(i) (ii) (iii) (iV)
Centlec
Number of formal
households with
access to basic
electricity
+200 000 formal
households access
basic electricity
193 858 formal households
access basic electricity service
Number of new
households provided
with electricity
connections
1866 new households
provide with electricity
connections
537 new households provide with
electricity connections
Number of
households provided
with access to Free
Basic Electricity
35 000 households
provided with access to
Free Basic Electricity
15 927 households provided with
access to Free Basic Electricity
ice
Number of high mast
lights installed in
informal settlements
28 erected and
commissioned high
mast lights within
Mangaung by 30 June
2016
34 High Masts have been erected
and 26 have been commissioned
230
APPENDIX I: DISCLOSURE OF FINANCIAL INTERESTS
(Information provided in compliance with the provisions of paragraph 7 of the Code of Conduct for Councillors’ as contained in Schedule 1 to the Local Government: Municipal
Systems Act No 32 of 2000)
No submissions received for year under review
financial year
Resigned / Passed Away during financial year
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Bacela GM None None None None None None None None None None None
Botes FR Old Mutual Sanlam None None None None Shoprite/
Checkers &
Freshmark
House None None None
Britz JF None None Bloemed
Health
Trust
Samba
Koop
None None None 33 Ronch
Cres
Fichardpark;
Ipanama 7
Van
Iddekingelaan
Fichardpark
None None None
231
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Davies M Satrix
shares
none Marais
familie trust
none none none mmm Properties in
Marsis Familie
Trust.
none none none
Dennis ME None None None None None None M.M.M Husband
owns House
GPF
R3900.00
PM
None None
Dibeco DM None None None None None None None None None None None
Ditabe RP None None None None None None None None None None None
Dyosiba S None Thabo &
Topkin
None None None None None None None None None
Eti MJ None None None None None None None None None None None
Horn W None None JMW
Property
Trust (60%)
None Horn & Van
Rensburg
Attorneys
(37,5%)
None Self (Horn &
Van
Rensburg)
Councillor
Unit 18
Kwando Park
32 Capt
Dawson Str,
Bfn
None None None
Hlujane MD None None None None None Old Mutual None None None None None
Jacobs TA None None None None None None None None None None None
232
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Jacobs TB Oneness
Social dev
Club
Oneness
Social dev
Club
None None None None None None None None None
Janse Van
Vuuren DE
None None Die Janse
Van Vuuren
Familie
Trust
None None Christo
Dippenaar
Attorneys
None 21 Gen;
Hertzog
Str,Dan
Pienaar
Willow Flair
100, Willows
MMM None None
July LR None None None None None None None None None None None
Kaliya SG None None None None None None None None None None None
Khi Z None None None None None None None None None None None
Kotze PA none none none none none none University of
free state,
mmm
none none none none
Kuape PA None None None None None None None None None None None
Lala TS None Prestine
General
Trading
100%
Diatla
Dikopane
CC Farm
40%
None None None None None None None None
233
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Lazenby
JBA
None None None None None None University
Free State
Bloemfontein
Residential
Home,
Langenhoven
park
None None None
Leech D None None None None None None Councillor
Reality 1
LHP Afree
oord 10
Avignon 12
7A AG Visster
Street
None None None
Lekgela LE None None None None None None D O H
(R240
000.00)
None None None None
Lephoi MJ None Yes,
Doment
Yes None None None None None None Land
restitution
beneficiary
Kopanong
Mun.
Xhariep
Litabe TK None None None None None None None None None None None
Madela BNV None None None None None None None None None None None
234
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Makhele ET None None None None None None None None None Yes (GPF) None
Malebo MC None None None None None None None None None None None
Mangcotywa
Z
None None None None None None None None None None None
Manyoni TM None None None Moaho
Investments
(PTY LTD)
None None Mangaung
Metro
Municipality
None None None Mini Solo-
Light Bar-
R 266.64
Solar Kit-
15w Solar
Panel +
5w Dc Led
Tube-
R1939.20
Moet &
Chandon
Champag
ne-
R349.99
235
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Masoetsa
LA
Ubuntu
Botho
None None None None None None None Yes
Special
Pension
None None
Mathobisa
LM
None None None None None None None None None None None
Matsemelela
MV
None None Multipurpos
e
Institution,
Bolokanang
HBC
Basadi
Tirong
Cooperativ
e
None None None None None None None None
Matsoetlane
MJ
None None None None None None None None None None None
236
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Mbange MB None None None None None None None 4700B Moliko
Str (R126 000)
642
Mokholwane
Str (R41 000)
10312
Manyane Str
(R132 000)
9919
Singonzo Str
(R79 000)
Standard
Bank /
Momentu
m (R1
677,42)
Old
Mutual
(R1
554,08)
Momentu
m (R1
089,52)
None None
Mfazwe TM None None None None None None None None None None None
237
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Minnie H None None MCPFS as
Trustee
None None None Afcom PTY
LTD MCPF
MMM
5585 Peter
Swarts House
55 Angelier
Str House
9367
Bloemside
Phase2 -
Church
Provident
Fund (not
on
pension
yet)
None None
Moeng MA None None Papeng
Trust
None None None None None None None None
Mofokeng
MJ
None None None None None None None None None None None
Mogamise ID None None None None None None Nursing
Health
Department
None None None None
Moilwa ME Xchange None None None None None None None None None None
Mokoloko PR None None None None None None MMM None None None None
Mokone KO None None None None None None None None None None None
Mokotjo NG None Distha
Trading
None None None None None None None None None
238
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Moloabi LR None None None None None None None None None None None
Monnakgori
SA
None None None None None None None None None None None
Mononyane
MB
None UMonde
CC 502
M.B
Mononyane
Family
Trust
None None Phuleng Inn
Tavern/Store
Plot 165
Meadows
Rd
Mangaung
ClR
Plot 165
Meadows
Road
Grassland
None None None
Moopelo TM None Yes, but
dysfunctio
nal
None None None None None None None None None
Mophete TA None None None None None None None None None None None
Moroe TCL None None None None None None None None None None None
Moruri MM None None Paul Moruri
Family
Trust
None None None None None None None None
Morutle SS None None None None None None None None None None None
Moshwadiba
PZ
none none none none none none none none none none none
239
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Mosiuoa TA T.A
Mosiuoa
Labour
Consultant
s CC
T.A
Mosiuoa &
Associates
100%
(dormant)
None None None None None None None None None
Motladile ZM None None None None None None None None None None None
Motlatsi HJ None None None None None None Remuneratio
n from Health
None Widows
pension
None None
Mpakathe TS None None None None None None MMC PR
R16 000
None None None None
Mpeqeka MS None None None None None None Educator
R12 000.00
None None None None
Mtshiwane K None None None None None None None None Sanlam None None
Naile TJ None None None None None None None None None None None
Ndamane NS None Ka Rona
Trading
639 CC
None None None Tavern
Nozizwe
owner
None None None None None
240
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Nkoe MJ Global
Work
Investment
Co-
operation
None None None None None None None None None None
Nothnagel J None None None None None None Councillor,
Mangaung
CUT
Seavale Drive
4, Seavale,
Buffalo City
(50%) Erf
28741,
Woodlands
Hills, BFN
None None None
Olivier TG None None None None None Owner of
Afrilingo &
Lingo
Software IP
Founder of
Qala Tala
None Residential
Residence
owned by
spouse
None None None
Parkie TD None None None None None None MMM None None None None
241
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Pato TW None None None None None None None None GEPF
R13 000
None None
Petersen JE None None None None None None None None Dept. of
Educatio
n
None None
Phajane MA MTN-
Shares
Sanlam
Shares
None None None None None SANDF.
R5000.00
None None None None
Phokoje SD None None None None None None None None None None None
Phupha NA None None None None None None None None None None None
Pongolo XD None None None None None None None 3341 Freedom None None None
Powell JD None None None None None None VF Plus 3 Bakers Str
Wilgehof, Bfn
None None None
Pretorius C None None None None None None None None None None None
242
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Pretorius JC None Ginger
Cherry CC
reg no.
2011/0986
01/23
None None None Xgrafies
Freelance
Business
Sa Truck
Bodies
Senior
Graphic
Designer.
R22000.00
Dias Single 7
Dan Pienaar
None None None
Rabela KN
Rametse MA None None None None None None None None None None None
Ramokotjo
FP
None None None None None None None None None None None
Ramona TM None None None None None None None None None None None
Rampai CLM None None None Deputy
Chairperson
of Hospital
Board
None None Mangaung
Metro Metro
None None None None
Ratsiu NA None Yes, but
Dysfunctio
nal
None None None Part time in
Lesedi FM
None None None None None
Sebothelo
ME
None None None None None None None None None None None
243
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Sekakanyo
MP
None None None None None None None None None None None
Selaledi M MTN Motheo
Womens
Credit &
Saving
and
Iketseng
Bufala
Basadi
Cooperativ
e
None None None None None None None None None
Siyonzana
MA
(Copy)
None Inqhina
Civil &
Building
Company
Proflex
PTY.LTD
None Razor bill
Property
PTY.LTd
None None None 16 Morris
Street,
Hillsbrow,
Bloemfontein
Metropolit
an
None Jazz
Festival –
Tickets,
flights,
accommo
dation &
shuttle
services.
244
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Snyman van
Deventer
None None None None None None UFS Pollenys
Place6,
Pellissier
None None None
Teko ED None Yenza
Trading
536 CC
None None None None None Yes Plot 125
Voortrekkerlaa
n
None None None
Terblanche
AP
None None None None None None Boxer Super
Store
37 Louis Loaf
Avis Pellissier
None None None
Thipenyane
GM
None GNO
Printing &
Stationery
None None GNO
Printing &
Stationery
None Councillor None None None None
Titi LM Manziline None None Owner None None None None None None None
Toba AL None Mantella
Trading
486 CC
NERPO/
AFASA
None None Mokgodisan
o
None None None Mokgodisan
o / Stockvel
None
Tobie EC None None None None None None None None None None None
Tsomela MM None None None None None None None None None None None
245
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Van Biljon
PJJ
Old Mutual
1000
shares
None Cottaja
Lane
Family
Trust
None Own
business
Principal of
town
planning
practice(Pier
re van
Biljon)
Town
Planning
Consultancy
R180000.00
p.a
17 Stratford
Str (own
residence)
4A Louw
Wepener Str
(renting out)
None None None
Van der
Merwe R
None CC
92/04801/2
3 Tempe
Motors +/-
R50000
Fief van der
Merwe
Trust
(92197699
65) R1.8m
None None None None See Annexure
Heideihof,
Mareberg,
Doringkop,
Catalania,
Rayton View,
Waverley
Park,
Delamont,
UFS
R23000.0
0 P/M
None None
246
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Van der Walt
TB
None None None Executive
Director of
Qala
Phelang
Tala Non
Profit
Company
(no
remuneratio
n)
None None None None None None None
Van Niekerk
HJ
None Yes R350
000
(Triangle
Granite
(R200 000)
None None 50%
(Triangle
Granite)
None None 15 Akkoorde
Cres, Bfn
Personal
House (R950
000)
None None None
247
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Viviers BJ Goodrick
Franklin
Snr
2003/0311
98/21
23%
Umbelos
12CC 49%
None Geelred
Frerklik Snc
None None Goodrick &
Franklin
Centre in
Wival 95 A
centre
None None None
Ward VW None Mangaung
Stories
Deregister
ed
Barry
Pietersen
Trust
None Ward
Building
Contractors
None None -
10047Graslan
d
-29 Einstein
Str
- Plot 15
Levins
-Plot 27
Hoëveld
None None None
Zerwick AS None None None None None None Dept. Health
C.U.T (part
time)
Own Home None None None
248
Councillors Shares
and
securities
in any
company
Membersh
ip of any
close
corporatio
n
Interest in
any trust
Directorshi
ps
Partnershi
ps
Other
financial
interest in
any
business
Employment
and
remuneratio
n
Interest in
property
Pension Subsidies,
grants and
sponsorshi
ps
Gifts
received
Zophe NM None none none none none none Dep of
Justice and
correctional
Own home none none none
249
APPENDIX J: REVENUE COLLECTION PERFORMANCE BY VOTE
Vote Description
2014/15 Budget Year 2015/16 % Year 2015/16 Variance
Actual Original Budget
Adjusted Budget
Year T D actual
Original Budget
Adjustment Budget
Vote 1 - City Manager - - - - 0,00% 0,00%
Vote 2 - Executive Mayor - - - - 0,00% 0,00%
Vote 3 - Corporate Services 6,219,113 13,304,124 13,304,124 6,661,143 50,07% 50,07%
Vote 4 - Finance 1,392,413,884 1,269,360,839 1,101,599,141 1,209,802,482 95,31% 109,82%
Vote 5 - Social Services 89,177,044 81,544,982 81,178,831 62,064,891 76,11% 76,45%
Vote 6 - Planning 27,271,036 28,189,621 28,189,621 27,959,415 99,18% 99,18%
Vote 7 - Human Settlement and Housing 26,290,876 364,266,750 364,266,750 36,753,881 10,09% 10,09%
Vote 8 - Economic and Rural Development - 556,899 556,899 3,672 0,66% 0,66%
Vote 9 - Engineering Services 593,995,420 357,012,611 318,854,005 346,064,495 96,93% 108,53%
Vote 10 - Water Services 740,333,009 975,462,824 762,953,572 724,220,325 74,24% 94,92%
Vote 11 - Waste and Fleet Management - 265,979,913 262,327,671 257,448,476 96,79% 98,14%
Vote 12 - Miscellaneous Services 790,905,231 1,490,438,519 1,622,418,659 1,256,713,774 84,32% 77,46%
Vote 13 - Regional Operations - - - - 0,00% 0,00%
Vote 14 - Strategic Projects & Service Delivery Regulation - - - - 0,00% 0,00%
Vote 15 - Electricity - Centlec (Soc) Ltd 2,124,650,867 2,648,133,981 2,378,651,692 2,196,305,332 82,94% 92,33%
Total Revenue 5,791,256,481 7,494,251,063 6,934,300,965 6,123,997,886 81,72% 88,31%
250
APPENDIX K: CONDITIONAL GRANTS RECEIVED: EXCLUDING MIG
Capital Financing Source
Approved Adjusted Actual % variation on % variation on
Budget Budget Original Budget
Adjustments
Budget
Integrated City Development Grant (National) 10,157 10,157 10,061 99.05% 99.05%
Urban Settlement Development Grant 693,847 771,383 712,739 102.72% 92.40%
Public Transport Infrastructure and Systems Grant - 26,128 63,072 0.00% 241.40%
Department of Sports Arts and Culture - 600 - 0.00% 0.00%
Human Settlement Grant - Provincial - 2,598 1,002 0.00% 38.57%
EPWP Incentive Grant 3,097 3,097 3,136 101.26% 101.26%
TOTAL 707,101 813,963 790,010 111.73% 97.06%
251
APPENDIX L: CAPITAL EXPENDITURE – NEW & UPGRADE / RENEWAL PROGRAMMES
Capital Expenditure - New Assets Programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual Original Budget
Adjustment Budget
Actual Expenditure 2015/16 2016/17 2017/18
Capital expenditure by Asset Class
Infrastructure – Total 707,994 881,277 873,974 817,927 881,277 1,195,176 1,054,907
Infrastructure: Road transport – Total 79,400 201,080 172,800 147,400 201,080 290,069 250,814
Roads, Pavements & Bridges 79,400 201,080 172,800 147,400 201,080 290,069 250,814
Storm water
Infrastructure: Electricity – Total 282,577 215,598 167,747 162,918 215,598 200,019 179,633
Generation
Transmission & Reticulation 282,577 215,598 167,747 162,918 215,598 200,019 179,633
Street Lighting
Infrastructure: Water – Total 109,062 61,063 100,456 92,871 61,063 174,029 94,000
Dams & Reservoirs
Water purification
Reticulation 109,062 61,063 100,456 92,871 61,063 174,029 94,000
Infrastructure: Sanitation - Total 234,314 398,337 431,770 414,738 398,337 525,694 524,800
Reticulation
Sewerage purification 234,314 398,337 431,770 414,738 398,337 525,694 524,800
252
Capital Expenditure - New Assets Programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual Original Budget
Adjustment Budget
Actual Expenditure 2015/16 2016/17 2017/18
Infrastructure: Other – Total 2,641 5,200 1,200 - 5,200 5,365 5,660
Waste Management 2,641 5,200 1,200 - 5,200 5,365 5,660
Transportation
Gas
Other
Community – Total 76,024 130,736 108,953 100,189 130,736 81,364 87,118
Parks & gardens 44,177 45,539 22,454 14,922 45,539 33,866 18,000
Sports fields& stadia 9,604 8,040 6,169 2,147 8,040 9,909 9,000
Swimming pools 6,393 10,000 18,775 17,185 10,000 8,000 12,000
Community halls
Libraries
Recreational facilities
Fire, safety & emergency
Security and policing
Buses
Clinics
Museums & Art Galleries
Cemeteries 4,000 - 35,000 4,000 - -
Social rental housing 50,000 61,555 30,935 50,000 13,800 21,900
Other 15,850 13,157 - - 13,157 15,789 26,218
253
Capital Expenditure - New Assets Programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual Original Budget
Adjustment Budget
Actual Expenditure 2015/16 2016/17 2017/18
Heritage assets - Total - - - - - - -
Buildings
Other - - -
Investment properties - Total - - - - - - -
Housing development - - - - - - -
Other - - - - - - -
Other assets 156,631 259,935 263,759 172,626 259,935 271,838 221,232
General vehicles 57,461 91,256 91,256 68,458 91,256 79,849 57,035
Specialized vehicles
Plant & equipment 14,961 2,396 2,366 2,824 2,396 3,574 2,510
Computers - hardware/equipment
Furniture and other office equipment 5,048 18,050 21,895 5,095 18,050 19,177 16,662
Abattoirs
Markets
Civic Land and Buildings 18,427 44,743 49,998 42,168 44,743 68,168 51,725
Other Buildings 102,920 97,694 54,081 102,920 101,070 92,500
Other Land 58,898 -
Surplus Assets - (Investment or Inventory)
Other 1,836 570 550 - 570 - 800
254
Capital Expenditure - New Assets Programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual Original Budget
Adjustment Budget
Actual Expenditure 2015/16 2016/17 2017/18
Agricultural assets
List sub-class
Biological assets - - - - - 2,000 -
List sub-class - - - - - 2,000 -
Intangibles
Computers - software & programming
Other (list sub-class)
Total Capital Expenditure on new assets 940,649 1,271,948 1,246,687 1,090,742 1,271,948 1,550,378 1,363,258
255
Capital Expenditure - Upgrade/Renewal programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual
Original
Budget
Adjustment
Budget
Actual
Expenditure 2015/16 2016/17 2017/18
Capital expenditure by Asset Class
Infrastructure – Total 390,915 517,500 593,706 509,948 517,500 823,443 813,825
Infrastructure: Road transport – Total 101,946 110,040 184,865 171,265 110,040 154,048 101,950
Roads, Pavements & Bridges 101,946 110,040 184,865 171,265 110,040 154,048 101,950
Storm water - - - - - - -
Infrastructure: Electricity – Total 7,850 109,759 78,376 78,675 109,759 126,695 143,369
Generation - - - - - - -
Transmission & Reticulation 7,850 109,759 78,376 78,675 109,759 126,695 143,369
Street Lighting - - - - - - -
Infrastructure: Water – Total 201,104 234,000 216,642 143,084 234,000 437,500 460,750
Dams & Reservoirs - - - - - - -
Water purification - - - - - - -
Reticulation 201,104 234,000 216,642 143,084 234,000 437,500 460,750
Infrastructure: Sanitation - Total 67,664 54,000 100,488 105,580 54,000 95,000 97,000
Reticulation - - - - - - -
256
Capital Expenditure - Upgrade/Renewal programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual
Original
Budget
Adjustment
Budget
Actual
Expenditure 2015/16 2016/17 2017/18
Sewerage purification 67,664 54,000 100,488 105,580 54,000 95,000 97,000
Infrastructure: Other – Total 12,351 9,700 13,335 11,344 9,700 10,200 10,756
Waste Management 12,351 9,600 11,600 9,609 9,600 10,100 10,656
Transportation - - 1,735 1,735 - - -
Gas - - - - - - -
Other 100 - - 100 100 100
Community – Total 860 - 870 743 - 2,340 3,600
Parks & gardens - - - - - - -
Sports fields& stadia - - - - -
Swimming pools - - 870 536 2,340 3,000
Community halls - - - - - - -
Libraries - - - - - - -
Recreational facilities - - - - - - -
Fire, safety & emergency - - - - - - -
Security and policing - - - - - - -
Buses - - - - - - -
Clinics - - - - - - -
257
Capital Expenditure - Upgrade/Renewal programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual
Original
Budget
Adjustment
Budget
Actual
Expenditure 2015/16 2016/17 2017/18
Museums & Art Galleries - - - - - - -
Cemeteries 860
Social rental housing - - - - - - 600
Other - - - 207 - - -
Heritage assets - Total - - - - - - -
Buildings - - - - - - -
Other - - - - - - -
Investment properties - Total - - - - - - -
Housing development - - - - - - -
Other - - - - - - -
Other assets 4,639 4,443 9,707 5,191 4,443 15,736 6,574
General vehicles - - - - - - -
Specialized vehicles - - - - - - -
Plant & equipment - 3,143 6,733 2,910 3,143 5,436 4,074
Computers - hardware/equipment - - - - - - -
Furniture and other office equipment 2,519 800 2,474 2,155 800 5,800 2,000
258
Capital Expenditure - Upgrade/Renewal programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual
Original
Budget
Adjustment
Budget
Actual
Expenditure 2015/16 2016/17 2017/18
Abattoirs - - - - - - -
Markets - - - - - - -
Civic Land and Buildings 2,120 500 500 126 500 500 500
Other Buildings - - - - - 4,000 -
Other Land - - - - - - -
Surplus Assets - (Investment or
Inventory) - - - - - - -
Other - - - - - - -
Agricultural assets - - - - - - -
List sub-class - - - - - - -
Biological assets - - - - - - -
List sub-class - - - - - - -
Intangibles - - - - - - -
Computers - software & programming - - - - - - -
259
Capital Expenditure - Upgrade/Renewal programme*
R '000
Description 2014/15 2015/16 Planned Capital expenditure
Actual
Original
Budget
Adjustment
Budget
Actual
Expenditure 2015/16 2016/17 2017/18
Other (list sub-class) - - - - - - -
Total Capital Expenditure on renewal of
existing assets 396,414 521,943 604,283 515,882 521,943 841,519 823,999
Appendix M totals 1,337,063 1,793,891 1,851,179,485 1,630,343,006 1,793,891 2,391,897 2,187,256
Ledger/Budget totals 1,793,891 1,851,179,485 1,630,343,006 1,793,891 2,391,897 2,187,256
Difference - - - - - -
260
APPENDIX M: CAPITAL PROGRAMME BY PROJECT (2015/2016)
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
CONSTRUCTION OF 20X30 SWIMMING
POOL THAB 3,000,000 6,934,039 2,080,277 - 6,513,464 420,575 93.93%
REHABILITATION OF FREEDOM SQUARE
SPORT C 2,500,000 1,500,000 - - 100,583 1,399,417 6.71%
UPGRADING OF BILLY MURISON STADIUM 1,500,000 1,000,000 1,302 - 891,351 108,649 89.14%
REHABILITATION OF ARTHER NATHAN
SWIMMING - 662,961 581 - 658,918 4,043 99.39%
UPGRADING OF MMABANA STADIUM - 503,313 - - 32,878 470,435 6.53%
JOHNSON BENDILE STADIUM
CONSTRUCTION 3,000,000 3,000,000 668 - 1,122,626 1,877,374 37.42%
UPGRADING OF BILLY MURISON STADIUM - 165,876 - - - 165,876 0.00%
NEW OFFICE BLOCK: MANGAUNG 300,000 300,000 - - - 300,000 0.00%
NEW OFFICE BLOCK - BOTSHABELO 1,000,000 1,000,000 - - - 1,000,000 0.00%
NEW OFFICE BLOCK: MANGAUNG 4,000,000 4,000,000 225,601 - 3,725,601 274,399 93.14%
REHABILITATION OF ARTHER NATHAN
SWIMMING 2,000,000 - - - - - 0.00%
261
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
RENOVATION OF HISTORICAL BUILDING:
CITY 1,000,000 500,000 - 104,798 - 500,000 0.00%
UPGRADING OF MMABANA STADIUM 1,040,313 - - - - - 0.00%
MULTI PURPOSE CENTRE GRASSLAND 2 5,000,000 4,940,000 - - 4,826,953 113,047 97.71%
NEW OFFICE BLOCK - MANGAUNG - 4,854,670 1,349,443 - 6,399,220 (1,544,550) 131.82%
MULTI PURPOSE CENTRE: GRASSLAND 2 - 6,237,909 61,743 - 5,185,713 1,052,196 83.13%
PRIVATE CLOUDWARE 200,000 - - - - - 0.00%
ICT SECURITY EQUIPMENT 500,000 - - - - - 0.00%
RADIO NETWORK EXPANSION 2,000,000 800,000 (775,885) - - 800,000 0.00%
NETWORK SWITCHES (UPGRADE TO PoE
SWITCHE 100,000 1,660,000 - - - 1,660,000 0.00%
RADIO LINKS (WAN REDUNDANCY
BACKUP) 700,000 - - - - - 0.00%
SERVER ROOMS 700,000 150,150 - - - 150,150 0.00%
DESKTOPS AND LAPTOPS 1,000,000 2,589,850 782,884 - 1,844,851 744,999 71.23%
SUB TOTAL 29,540,313 40,798,768 3,726,615 104,798 31,302,159 9,496,609 76.72%
BURSTER STACKER AND SLITTER 405,000 195,000 - - 86,276 108,724 44.24%
DESKTOP COMPUTERS - 210,000 (46,072) - - 210,000 0.00%
262
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
PRESURE SEALER 320,000 320,000 - - - 320,000 0.00%
HANDHELD METER READING DEVICES - - 1,922,258 - 1,922,258 (1,922,258) 0.00%
OFFICE FURNITURE 4,129,699 4,129,699 1,878,298 - 4,024,450 105,249 97.45%
ASSET MANAGEMENT SYSTEM 750,000 750,000 - - - 750,000 0.00%
SUB TOTAL 5,604,699 5,604,699 3,754,484 - 6,032,984 (428,285) 107.64%
BP LEINAENG LIBRARY -3M BOOK
SECURITY SY - 300,000 208,549 - 208,549 91,451 69.52%
BAINSVLEI LIBRARY - 3M BOOK SECURITY
SYS - 300,000 208,549 - 208,549 91,451 69.52%
EXPANDING THE TWO WAY RADIO
NETWORK OF E - 150,000 - - - 150,000 0.00%
BACKUP POWER GENERATOR - 110,000 - - - 110,000 0.00%
EXTENTION OF BAYSWATER
LABORATORY - 4,376,478 392,003 - 2,815,004 1,561,474 64.32%
RESCUE BOAT - 20,000 (13,975) - - 20,000 0.00%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
263
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
COLLAPSIBLE / FOLDING LADDER 14,000 14,000 11,615 - 11,615 2,385 82.96%
FIRE STATION BOTSHABELO 7,000,000 1,300,000 1,138,306 - 1,138,306 161,694 87.56%
HAND CONTROLLED FIRE NOZZLE 9,500 9,500 (5,577) - - 9,500 0.00%
HAND CONTROLLED FIRE NOZZLE 9,500 9,500 (5,577) - - 9,500 0.00%
HAND CONTROLLED FIRE NOZZLE 9,500 9,500 (5,577) - - 9,500 0.00%
HAND CONTROLLED FIRE NOZZLE 9,500 9,500 (5,577) - - 9,500 0.00%
HAND CONTROLLED FIRE NOZZLE 9,500 9,500 (5,577) - - 9,500 0.00%
HAND CONTROLLED FIRE NOZZLE 9,500 9,500 (5,577) - - 9,500 0.00%
JAWS OF LIFE 490,000 490,000 (141,940) - 347,927 142,073 71.01%
FLOATING PUMP 42,000 42,000 - - 23,090 18,910 54.98%
FLOATING PUMP 42,000 42,000 - - 23,090 18,910 54.98%
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
264
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
FOAM BRANCH COMPLETE WITH
INDUCTOR 20,000 20,000 8,539 - 8,539 11,461 42.70%
POSITIVE PRESSURE VENTILATOR 48,500 48,500 - - 34,750 13,750 71.65%
POSITIVE PRESSURE VENTILATOR 48,500 48,500 - - 34,750 13,750 71.65%
POSITIVE PRESSURE VENTILATOR 48,500 48,500 - - 34,750 13,750 71.65%
SKID UNIT 30,500 30,500 - - 28,560 1,940 93.64%
SKID UNIT 30,500 30,500 - - 28,560 1,940 93.64%
SKID UNIT 30,500 30,500 - - 28,560 1,940 93.64%
BOTSHABELO FIRE STATION MULTI GYM - 135,000 (9,776) - 124,364 10,636 92.12%
BAYSWATER FIRE STATION MULTI GYM - 135,000 (9,776) - 124,364 10,636 92.12%
CENTRAL FIRE STATION MULTI GYM - 135,000 (9,776) - 124,364 10,636 92.12%
265
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
BREATHING APPARATUS COMPRESSOR - 220,000 - - 219,461 539 99.76%
UPGRADING/ REPLACEMENT EXISTING
FENCE BL - 870,000 536,102 - 536,102 333,898 61.62%
NEW SOUTHERN REGION FIRE STATION - 1,725,565 98,729 - 1,454,339 271,226 84.28%
LAW ENFORCEMENT CAMERAS (DIGITAL
CAMERAS 500,000 500,000 - - 426,809 73,191 85.36%
TRAFFIC LAW ENFORCEMENT CAMERAS
(FIXED) 1,000,000 - - - - - 0.00%
CCTV 2,200,000 3,200,000 1,012,188 - 2,518,604 681,396 78.71%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
266
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
9MM PISTOL 10,000 10,000 - - 8,910 1,090 89.10%
RELOCATION OF ZOO 20,274,706 12,424,706 - - 9,268,061 3,156,645 74.59%
FENCING OF PHAHAMENG CEMETERY - 2,474,000 - - 2,155,178 318,822 87.11%
ABLUTION BLOCK SOUTH PARK
CEMETERY 800,000 1,200,000 264,411 - 724,884 475,116 60.41%
DEVELOPMENT OF A MASTER-PLAN FOR
THE CON 1,542,000 4,208,120 2,338,702 - 3,561,570 646,550 84.64%
NEW ROADS & STORMWATER BAINSVLEI
CEMETE 2,000,000 3,000,000 960,982 - 1,526,787 1,473,213 50.89%
NEW ROADS & STORMWATER
BOTSHABELO REGIO 5,000,000 1,000,000 - - 715,877 284,123 71.59%
PERIMETER FENCE BAINSVLEI
CEMETERY 3,000,000 3,000,000 952,057 - 1,376,848 1,623,152 45.89%
PERIMETER FENCE STORMLAAN
CEMETERY 1,000,000 800,000 752,725 - 752,725 47,275 94.09%
267
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
NEW ROADS & STORMWATER
BOTSHABELO CEMET 4,000,000 5,600,000 330,090 - 1,997,875 3,602,125 35.68%
UPGRADING ROADS & STORMWATER
PHAHAMENG C 1,000,000 2,200,000 571,846 - 1,038,898 1,161,102 47.22%
SKATE PARK - NEW REGIONAL PARK
SELOSESHA - 6,000,000 2,272,158 - 2,797,420 3,202,580 46.62%
DEVELOPMENT OF NEW PARK IN
BOTSHABELO B 7,000,000 1,500,000 - - 472,156 1,027,844 31.48%
FENCING OF HAMILTONPARK 650,000 650,000 30,180 - 30,180 619,820 4.64%
NEW REGIONAL PARK THABA NCHU - IN
SELOS 9,350,000 14,200,000 925,563 - 11,621,315 2,578,685 81.84%
HIGH BAND PORTABLE TWO WAY RADIO 4,840 4,840 - - - 4,840 0.00%
HIGH BAND PORTABLE TWO WAY RADIO 4,840 4,840 - - - 4,840 0.00%
HIGH BAND PORTABLE TWO WAY RADIO 4,840 4,840 - - - 4,840 0.00%
HIGH BAND PORTABLE TWO WAY RADIO 4,840 4,840 - - - 4,840 0.00%
HIGH BAND PORTABLE TWO WAY RADIO 4,840 4,840 - - - 4,840 0.00%
ESTABLISHMENT/CONSTRUCTION OF
PURPOSE BU - 564,645 - - - 564,645 0.00%
SUB TOTAL 67,600,906 73,582,714 12,927,128 - 48,800,060 24,782,654 66.32%
268
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
PEDESTRIANISATION PARK ROADS - 2,000,000 - - 1,807,466 192,534 90.37%
AIRPORT DEVELOPMENT NODE 46,000,000 46,000,000 5,611,739 - 18,791,041 27,208,959 40.85%
BOTSHABELO DEVELOPMENT NODE 25,000,000 - - - - - 0.00%
THABA NCHU DEVELOPMENT NODE 10,700,000 15,700,000 (3,637,544) 15,386,526 - 15,700,000 0.00%
TOWNSHIP ESTABLISHMENT CECILIA
PARK 20,000,000 15,000,000 7,286,163 - 7,457,419 7,542,581 49.72%
TOWNSHIP ESTABLISHMENT BRANDKOP 16,000,000 16,000,000 - - 2,725,026 13,274,974 17.03%
TOWNSHIP ESTABLISHMENT: NEW
TOWNSHIP 4,000,000 6,000,000 (2,628,615) 3,302,094 - 6,000,000 0.00%
TOWNSHIP ESTABLISHMENT
BOTSHABELO - 600,000 - - 383,318 216,682 63.89%
TOWNSHIP ESTABLISHMENT BFN SOUTH - 4,000,000 2,497,904 - 2,497,904 1,502,096 62.45%
TOWNSHIP ESTABLISHMENT THABA
NCHU - 1,000,000 - - - 1,000,000 0.00%
PEDESTRIANISATION ELLA STREET 9,000,000 242,316 - - - 242,316 0.00%
BEAUTIFICATION OF CITY ENTRANCES N8 29,188,788 2 - - - 2 0.00%
TOWNSHIP ESTABLISHMENT BRANDKOP - 2,474 - - 2,474 - 100.00%
269
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
TOWNSHIP ESTABLISHMENT CECILIA
PARK - 2,078,540 - - 2,078,540 - 100.00%
AIRPORT DEVELOPMENT NODE - 13,753,987 - - 13,753,987 - 100.00%
REDEVELOPMENT OF HOFFMAN SQUARE - 1,734,972 - - 1,734,972 - 100.00%
TOWNSHIP STABLISHMENT BOTSHABELO
WEST EX - 2,717,211 - - 1,720,414 996,797 63.32%
BEAUTIFICATION OF CITY ENTRANCES N8 - 753,761 - - 31,033 722,728 4.12%
SERVICES RETICULATION OF MMM LAND
WITHIN - - 153,343 - 153,343 (153,343) 0.00%
ESTABLISHMENT OF GIS SYSTEM
IMPLEMENTIN 6,000,000 6,000,000 (141,000) 141,000 - 6,000,000 0.00%
ESTABLISHMENT OF GIS SYSTEM
IMPLEMENTING - 4,275,055 (4,275,055) 4,275,055 - 4,275,055 0.00%
NAVAL HILL PHASE 2 - FUNICULAR - 5,966,183 3,828,775 - 5,842,755 123,428 97.93%
NAVIL HILL THE EDGE RESTAURANT - 280,859 (15,903) 15,903 - 280,859 0.00%
FENCING OF CAMPS VARIOUS VILLAGES
& MUNI - - 206,985 - 206,985 (206,985) 0.00%
PUBLIC INFRASTRUCTURE & SYSTEMS
GRANT B - - 3,056,050 - 3,056,050 (3,056,050) 0.00%
270
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
SUB TOTAL 165,888,788 144,105,360 11,942,844 23,120,577 62,242,727 81,862,633 43.19%
TWO DIESEL GENERATORS - 2,000,000 - - - 2,000,000 0.00%
REFRESH SERVERS & SOFTWARE 250,000 250,000 - - - 250,000 0.00%
MARKET HALL ROOF & GUTTERS 500,000 500,000 125,693 - 125,693 374,307 25.14%
SUB TOTAL 750,000 2,750,000 125,693 - 125,693 2,624,307 4.57%
WHITE CITY TOP INFRATRUCTURE
(REFURBISHI 10,000,000 10,000,000 2,509,424 - 3,378,876 6,621,124 33.79%
REFURBISHMENT OF RENTAL STOCKS 4,000,000 4,000,000 - - 3,855,370 144,630 96.38%
ACQUISITION OF LAND FOR CEMETERIES 4,000,000 - 35,000,000 - 35,000,000 (35,000,000) 0.00%
REDESIGNS ESTOIRE 6,000,000 - - - - - 0.00%
INTERNAL SERVICES (LAND PREP;
WATER & SA 4,500,000 - - - - - 0.00%
INTERNAL SERVICES (WATER & SAN;
STREET L 2,700,000 - - - - - 0.00%
INTERNAL SERVICES (WATER AND
SANITATION) 3,000,000 - - - - - 0.00%
271
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
INTERNAL SERVICES (WATER & SAN;
STREET L 2,700,000 - - - - - 0.00%
INTERNAL SERVICES (WATER AND
SANITATION) 18,300,000 - - - - - 0.00%
SONDERWATER - BASIC SANITATION - 22,092,650 - - 22,092,649 1 100.00%
MK SQUARE - BASIC SANITATION - 15,425,768 641,979 - 15,425,768 - 100.00%
RUDIMENTARY SERVICES BOTSHABELO
SECTION - 4,000,000 - - - 4,000,000 0.00%
WATER RETICULATION AND INTERNAL
CONNECTI 5,000,000 4,681,582 4,667,850 - 4,667,850 13,732 99.71%
SUB TOTAL 60,200,000 60,200,000 42,819,253 - 84,420,513 (24,220,513) 140.23%
CONCEPT AND DETAIL DESIGN NAVAL
HILL 117,207 - - - - - 0.00%
KIOSK NAVAL HILL 664,250 - - - - - 0.00%
NAVAL HILL PHASE 2 3,922,929 3,240,136 157,390 - 157,390 3,082,746 4.86%
NAVAL HILL THE EDGE RESTAURANT 992,046 992,046 (23,974) 23,974 - 992,046 0.00%
INCUBATION FARM 2,000,000 - - - - - 0.00%
MUNICIPAL POUND BOTHSHABELO 1,000,000 1,000,000 - - - 1,000,000 0.00%
272
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
HAWKING STALLS BOTSHABELO CBD 7,157,000 9,507,000 2,634,943 - 9,410,766 96,234 98.99%
HAWKING STALLS THABA NCHU CBD 3,000,000 650,000 - - 650,000 - 100.00%
SUB TOTAL 18,853,432 15,389,182 2,768,359 23,974 10,218,157 5,171,025 66.40%
NGYCAY RD - 844,280 - - 834,291 9,989 98.82%
BATHO 60 - 84,550 - - 84,550 - 100.00%
MAN RD 103 - 105,569 - - 105,569 0 100.00%
MAN RD 475 UPGRADING OF STREET &
STORMWA 1,000,000 36,300 - - 36,300 - 100.00%
BOT RD 1055 UPGRADING OF STREET &
STORMW - 10,000 - - 9,540 460 95.40%
MAN RD 474 UPGRADING OF STREET &
STORMWA 1,000,000 308,055 - - 308,055 0 100.00%
MAN RD 473 UPGRADING OF STREET &
STORMWA 1,000,000 876,674 - - 876,673 1 100.00%
BRANDWAG 1 UPGRADING OF STREETS
AND STOR 1,000,000 6,096,570 1,161,050 - 5,294,498 802,072 86.84%
273
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
TURN LANES AT MASELSPOORT ROAD
UPGRADING 9,000,000 7,085,634 - - 7,085,598 36 100.00%
ROAD 6 (PHASE2) UPGRADING OF
STREET & S 1,849,510 2,527,636 - - 1,396,460 1,131,176 55.25%
THA RD 2033 UPGRADING OF STREET &
STORMW 2,400,000 2,400,000 - - 2,396,256 3,744 99.84%
TSUENE ST UPGRADING OF STREET &
STORMWAT 1,000,000 663,451 - - 663,450 1 100.00%
MAPHISA UPGRADING OF STREET &
STORMWATER 11,310,684 - - - - - 0.00%
THA RD 2035 UPGRADING OF STREET &
STORMW 2,050,000 5,746,195 - - 5,744,230 1,965 99.97%
BOT RD 350 UPGRADING OF STREET &
STORMWA 7,229,922 11,262,309 - - 8,665,561 2,596,748 76.94%
LESSING UPGRADING OF STREET &
STORMWATER 4,207,500 - - - - - 0.00%
MAN RD 176: UPGRADING OF STREET &
STORMW 3,595,500 - - - - - 0.00%
MAN RD 199: UPGRADING OF STREET &
STORMW 1,606,500 - - - - - 0.00%
274
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
MAN RD 200: UPGRADING OF STREET &
STORMW 1,912,500 131,314 - - 131,214 100 99.92%
MAN RD 196: UPGRADING OF STREET &
STORMW 4,131,000 - - - - - 0.00%
MAN RD 197: UPGRADING OF STREET &
STORMW 994,500 435,049 - - 415,640 19,409 95.54%
MAN RD 778: UPGRADING OF STREET &
STORMW 4,793,891 - - - - - 0.00%
7TH ST: UPGRADING OF STREET &
STORMWATER 5,000,000 232,050 - - 232,050 - 100.00%
ROAD K 13: UPGRADING OF STREET &
STORMWA 4,035,339 300,333 - - 300,333 1 100.00%
ROAD 68: UPGRADING OF STREET &
STORMWATE 1,454,355 29,223 - - 29,222 1 100.00%
UPGRADING STREETS & SW: AM LOUW
STREET: 2,700,000 1,219,930 - - 500,000 719,930 40.99%
UPGRADING STREETS & SW: ROSE
AVENUE: GRA 2,000,000 - - - - - 0.00%
KHAMPEPE STREET UPGRADING
STREETS & STOR 2,000,000 - - - - - 0.00%
275
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
LESSING: UPGRADING OF STREET &
STORMWATE 13,740,666 3,601,789 765,486 - 3,474,574 127,215 96.47%
NAZO ST (PHASE 2): UPGRADING OF
STREET & 1,000,000 608,101 - - 608,101 0 100.00%
REALINGMENT OF CURVE DAN PIENAAR
DRV: UP 7,000,000 18,734,647 3,660,525 - 16,863,297 1,871,350 90.01%
STORM AVENUE UPGRADING OF STREET
& STORM 50,000 104,616 - - 104,616 0 100.00%
THABA NCHU STREET UPGRADING
STREETS & ST 5,000,000 6,252,312 1,687,594 - 5,810,176 442,136 92.93%
UPGRADING STREETS & SW: MAN RD 702
TURFL 3,750,000 - - - - - 0.00%
NEW TRAFFIC LIGHTS 400,000 - - - - - 0.00%
De BRUYN UPGRADING OF STREET &
STORMWATE 10,000,000 1,981,699 123,338 - 1,894,048 87,651 95.58%
BLOEM RD 149 UPGRADING OF STREET &
STORM 10,000,000 9,343,322 847,465 - 9,282,972 60,350 99.35%
UPGRADING STREET & SW: SLABBERT
STREET: 250,000 90,083 - - 226,343 (136,260) 251.26%
276
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
BATHO: GONYANI ST: UPGRADING OF
STREET & 500,000 2,441,145 561,043 - 2,441,145 0 100.00%
BOT RD 304: UPGRADING OF STREET &
STORMW 202,419 185,892 - - 185,892 0 100.00%
BOT RD 305: UPGRADING OF STREET &
STORMW 548,708 71,819 - - 71,818 1 100.00%
BOT RD 308: UPGRADING OF STREET &
STORMW 627,443 - - - - - 0.00%
BOT RD 437: UPGRADING OF STREET &
STORMW 1,200,000 1,164,546 574,517 - 1,164,544 2 100.00%
BOT RD 601: UPGRADING OF STREET &
STORMW 1,200,000 1,176,862 - - 1,176,862 0 100.00%
BOT RD 648: UPGRADING OF STREET &
STORMW 1,200,000 - - - - - 0.00%
BOT RD 719 & 718: UPGRADING OF
STREET & 5,000,000 464,100 - - 464,100 - 100.00%
BOTCHABELA: BOGACH ST: UPGRADING
OF STRE 8,711 1,133,456 - - 1,133,455 1 100.00%
BUITESIG BRIDGE WAAIHOEK 1,000,000 - - - - - 0.00%
277
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
FIRST AVENUE PEDESTRIAN BRIDGE 5,000,000 1,443,651 1,193,651 - 1,443,651 - 100.00%
HILLSIDE VIEW UPGRADING OF ROADS
AND STO 5,000,000 7,753,900 - - 7,753,899 1 100.00%
NELSON MANDELA BRIDGE 1,500,000 2,856,349 2,514,267 - 2,856,348 1 100.00%
STORMWATER: BAINSVLEI MOOIWATER
STORMWA 2,000,000 360,000 - - 358,402 1,598 99.56%
THA RD 2029: UPGRADING OF STREET &
STORM 382,500 234,112 234,112 - 234,112 0 100.00%
THA RD 2031: UPGRADING OF STREET &
STORM 399,500 - - - - - 0.00%
THA RD 2044: UPGRADING OF STREET &
STORM 204,000 - - - - - 0.00%
UPGRADING INTERSECTION ST GEORGE
ST & PR 250,000 - - - - - 0.00%
UPGRADING STREET & SW: TIBBIE
VISSER: ES 225,000 21,739 - - 416,873 (395,134) 1917.63%
UPGRADING STREETS & SW: BATHO
(LEARNERSH 2,500,000 20,142,568 5,362,337 - 20,142,409 159 100.00%
278
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
UPGRADING STREETS & SW: BOT RD
3824: BOT 1,000,000 29,223 - - - 29,223 0.00%
UPGRADING STREETS & SW: BOT RD B16
& 903 569,600 568,054 568,054 - 568,054 (0) 100.00%
UPGRADING STREETS & SW: MAN RD
11388 & 400,000 - - - - - 0.00%
UPGRADING STREETS & SW: MAN 10786:
BERGM 5,000,000 881,280 - - 881,279 1 100.00%
UPGRADING STREETS & SW: MAN RD
11548: KA 250,000 262,095 - - 241,898 20,197 92.29%
UPGRADING STREETS & SW:
TURFLAAGTE 1 (LE 2,500,000 - - - - - 0.00%
VERENIGING AVENUE EXTENTION
BRIDGE OVER 450,000 450,000 448,471 - 448,471 1,529 99.66%
VISTA PARK UPGRADING OF ROADS AND
STORMW 5,000,000 259,463 (66,293) - 96,585 162,878 37.22%
UPGRADING STREET & SW: HOOF
STREET: ESTO 2,500,000 500,000 - - 500,000 - 100.00%
REHABILITATION OF WALTER SISULU
ROAD 10,000,000 10,140,000 1,444,309 - 11,051,653 (911,653) 108.99%
279
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
UPGRADING STREETS & SW: FRANS
KLEYNHANS 2,000,000 - - - - - 0.00%
HEAVY REHABILITATION OF DAN
PIENAAR DRV 10,000,000 10,000,000 (671,375) - 9,866,399 133,601 98.66%
HEAVY REHABILITATION OF MC GREGOR
STREET 10,000,000 7,415,614 1,630,079 - 7,812,328 (396,714) 105.35%
SOUTH PARK CEMETERY ENTRANCE
ROAD 7,500,000 7,500,000 (7,646) - 6,977,850 522,150 93.04%
COMPUTER EQUIPMENT 30,000 - - - - - 0.00%
HEAVY REHABILITATION OF KENNETH
KAUNDA R 10,000,000 17,383,686 556,561 - 17,383,685 1 100.00%
UPGRADING OF ST GEORGES & FIRST
AVENUE I 6,500,000 4,590,700 (674,624) - 4,590,702 (2) 100.00%
MAPHISA UPGRADING - 26,128,000 2,353,280 - 17,680,926 8,447,074 67.67%
BLOEMSPRUIT SW CANAL
REHABILITATION 500,000 1,222,848 161,037 - 1,222,847 1 100.00%
HEAVY REHABILITATION OF NELSON
MANDELA S 1,000,000 920,108 - - 920,108 0 100.00%
280
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
HEAVY REHABILITATION OF ZASTRON
STREET 1,000,000 612,542 - - 612,542 - 100.00%
REHABILITATION OF WALTER SISULU
ROAD - 12,672,748 3,550,808 - 13,280,197 (607,449) 104.79%
REHABILITATION OF STORMWATER
CANALS 3,000,000 5,606,610 - - 5,364,934 241,676 95.69%
HEAVY REHABILITATION OF DAN
PIENAAR DRV - 9,553,437 4,703,009 - 9,453,437 100,000 98.95%
HEAVY REHABILITATION OF MC GREGOR
STREET - 9,393,026 3,947,513 - 9,556,668 (163,642) 101.74%
REHABILITATION OF ROAD B3
BOTSHABELO 10,000,000 4,169,337 666,539 - 4,835,875 (666,538) 115.99%
REPLACEMENT OF OBSOLETE AND
ILLEGAL SIGN 2,000,000 - - - - - 0.00%
SOUTH PARK CEMETERY ENTRANCE
ROAD - 2,839,881 662,496 - 3,375,187 (535,306) 118.85%
STORMWATER DRAINAGE BOCHABELA 3,000,000 - - - - - 0.00%
STREETS AND STORMWATER
MANAGEMENT SYSTE 800,000 - - - - - 0.00%
281
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
UNFORESEEN STORMWATER
IMPROVEMENTS 6,000,000 6,590,000 399,982 - 6,348,957 241,044 96.34%
UPGRADING OF TRAFFIC
INTERSECTIONS 5,000,000 - - - - - 0.00%
VICTORIA & KOLBE INTERSECTION 127,380 339,390 (0) - 339,389 1 100.00%
SLEEPER REPLACEMENT AND THERMIT
WELDS 100,000 - - - - - 0.00%
RESEALING OF STREETS 14,412,979 45,089,323 603,198 - 36,977,619 8,111,704 82.01%
HEAVY REHABILITATION OF KENNETH
KAUNDA R - 13,878,197 1,964,536 - 11,109,666 2,768,531 80.05%
UPGRADING OF ST GEORGES & FIRST
AVENUE I - 4,332,908 1,908,552 - 4,332,905 3 100.00%
REHABILITATION OF BRIDGES 3,000,000 2,471,722 (0) - 2,471,720 2 100.00%
SOUTH PARK CEMETERY ENTRANCE
ROAD - 343,394 - - 343,394 - 100.00%
ROAD 51 - 1,310,458 - - 1,215,480 94,978 92.75%
BATHO R5 - 2,246,689 - - 1,873,644 373,045 83.40%
STORMWATER BAINSVLEI MOOIWATER
STORMWATE - 106,870 - - 106,870 - 100.00%
282
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
ABDURAMAN 2 UPGRADING OF STREETS
AND STO - 3,254,092 - - 3,140,999 113,093 96.52%
SUB TOTAL 281,050,107 333,623,525 42,833,872 - 308,199,393 25,424,132 92.38%
TWO WAY RADIOS 200,000 - - - - - 0.00%
DEVELOPMENT OF A NEW LANDFILL SITE 2,000,000 - - - - - 0.00%
DEVELOPMENT OF WASTE DROP-OFF
AREAS IN M 1,000,000 - - - - - 0.00%
REFUSE RECEPTACLES FOR THE WASTE
DROP-OF 1,000,000 - - - - - 0.00%
REFUSE STORAGE BINS FOR THE 3 CBDs 1,000,000 - - - - - 0.00%
COMPUTER EQUIPMENT 100,000 - - - - - 0.00%
UPGRADING AND CONSTRUCTION OF
NORTHERN 1,500,000 - - - - - 0.00%
UPGRADING AND CONSTRUCTION OF
SOUTHERN 1,500,000 - - - - - 0.00%
UPGRADING AND REHABILITATIONS OF
BOTSHAB 1,500,000 - - - - - 0.00%
283
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
DEVELOPMENT OF TRANSFER STATION
IN THABA 5,000,000 - - - - - 0.00%
SUB TOTAL 14,800,000 - - - - - 0.00%
TEMPE MAIN SEWER TO ERADICATE
LUCAS STEY 2,585,200 - - - - - 0.00%
BOTSHABELO SANITATION PROJECT
ADDITIONA - - - - (124,961) 124,961 0.00%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 28,737,040 302,023 - 27,250,799 1,486,241 94.83%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 24,160,000 79,461 - 22,726,001 1,433,999 94.06%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 39,778,921 333,589 - 39,672,392 106,529 99.73%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 38,043,790 12,362 - 37,553,685 490,105 98.71%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 16,029,553 1,242,818 - 15,448,246 581,308 96.37%
284
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 19,155,816 698,986 - 18,633,164 522,652 97.27%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,000,000 18,300,000 - - 17,352,173 947,827 94.82%
BASIC SANITATION AND INTERNAL BULK
SERVI 24,714,800 20,889,941 99,261 - 18,409,831 2,480,110 88.13%
EXTENSION BOTSHABELO WWTW 20,000,000 2,064,758 - - 4,691,057 (2,626,299) 227.20%
MECHANICAL AND ELECTRICAL WORKS
FOR NORT 1,000,000 1,000,010 - - 1,000,001 9 100.00%
NORTH EARSTERN WWTW PHASE 2 1,000,000 999,990 - - 990,270 9,720 99.03%
NORTH EARSTERN WWTW PHASE 2 51,783,461 28,599,420 6,181,488 - 28,274,822 324,598 98.87%
RAYTON MAIN SEWER 2,600,000 - - - - - 0.00%
MECHANICAL AND ELECTRICAL WORKS
FOR NORT 30,453,115 18,385,806 1,779,967 - 19,207,486 (821,680) 104.47%
BASIC SANITATION AND INTERNAL BULK
SERVI 25,000,000 38,831,920 558,542 - 38,750,234 81,686 99.79%
BASIC SANITATION AND INTERNAL BULK
SERVI 25,000,000 2,273,512 74,755 - 2,045,414 228,098 89.97%
ADDITION TO STERKWATER WWTW 30,000,000 10,470,892 572,000 - 10,558,825 (87,933) 100.84%
285
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
EXTENSION THBA NCHU WWTW
(SELOSESHA) 20,000,000 4,000,000 62,355 - 3,142,165 857,835 78.55%
REFURBISHMENT OF BLOEMSPRUIT
WWTW 20,000,000 32,650,000 4,744,560 - 37,394,560 (4,744,560) 114.53%
REFURBISHMENT OF SEWER SYSTEMS 5,000,000 5,000,000 1,507,436 - 6,402,130 (1,402,130) 128.04%
REFURBISHMENT OF SEWER SYSTEMS 14,000,000 14,000,000 1,583,693 - 14,014,669 (14,669) 100.10%
REFURBISHMENT OF BLOEMSPRUIT
WWTW 15,000,000 32,223,000 1,017,442 - 32,449,042 (226,042) 100.70%
THABA NCHU SEROALO BULTFONTEIN 3 -
UPGRA - 739,282 20,831 - 722,780 16,502 97.77%
BOTSHABELO SECTION K- UPGRADING
OF VIP T - 136,518 86,518 - 86,518 50,000 63.37%
BOTSHABELO SANITATION PROJECT -
ADDITION - 4,078,073 - - 3,430,578 647,495 84.12%
REFURBISHMENT OF SEWER SYSTEMS - 4,057,600 2,585,200 - 3,492,215 565,385 86.07%
REFURBISHMENT OF BLOEMSPRUIT
WWTW - 746,374 - - 746,374 - 100.00%
BOTSHABELO SECTION J- UPGRADING
OF VIP T - 327,095 - - - 327,095 0.00%
286
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
OUTFALL FROM BLOEMSPRUIT WWTW
TO THE RAC - 1,242,153 - - - 1,242,153 0.00%
WATERBORNE SANITATION IN RATAU &
MOROKA - 2,893,519 - - 654,144 2,239,375 22.61%
WATERBORNE SANITATION IN
BULTFONTEIN 2 3 - 1,702,381 - - 1,372,244 330,137 80.61%
BOTSHABELO SECTION K BASIC
SANITATION - 1,007,752 - - 1,007,752 0 100.00%
BOTSHABELO BULK SEWER LINE SEC F
BASIC S - 450,831 - - - 450,831 0.00%
BOTSHABELO SECTION F AND F EXT
BASIC SAN - 134,141 - - - 134,141 0.00%
BOTSHABELO SECTION J BASIC
SANITATION - 384,624 - - 120,300 264,324 31.28%
BOTSHABELO SECTION J BASIC
SANITATION - 277,617 - - - 277,617 0.00%
BOTSHABELO SECTION K BASIC
SANITATION - 825,590 - - 520,638 304,952 63.06%
WATERBORNE SANITATION IN
BULTFONTEIN 2 3 - 525,223 81,714 - 481,606 43,617 91.70%
287
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
BOTSHABELO SANITATION PROJECT -
ADDITION - 9,889,137 52,744 - 9,889,137 0 100.00%
REFURBISHMENT OF BLOEMSPRUIT
WWTW - 822,761 - - 822,761 - 100.00%
BASIC SANITATION & INTERNAL BULK
MANGAUN - 10,583,851 - - 10,583,747 104 100.00%
BASIC SANITATION & INTERNAL BULK
BOTSHAB - 39,939,362 - - 39,939,360 2 100.00%
BASIC SANITATION & INTERNAL BULK
THABA N - 13,707,734 1,960,263 - 15,656,397 (1,948,663) 114.22%
REFURBISHMENT OF SEWER SYSTEM - 282,895 - - 282,854 41 99.99%
UPGRADE BULK SEWER FOR BRANDWAG
PROJECT - 554,194 - - - 554,194 0.00%
REFURBISHMENT OF SEWER SYSTEMS - 125,595 - - - 125,595 0.00%
OUTFALL FROM BLOEMSPRUIT WWTW
TO THE RAC - 217,125 - - - 217,125 0.00%
BOTSHABELO SECTION J - UPGR OF VIP
TOILE - 877,239 - - 313,430 563,809 35.73%
SUB TOTAL 456,136,576 492,123,035 25,638,008 - 485,964,839 6,158,196 98.75%
288
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
LONGRIDGE RESERVOIR SUPPLY LINE
8.3 KM 1,000,000 5,058,976 941,879 - 4,887,567 171,409 96.61%
BOTSHABELO AND THABA NCHU
INTERNAL BULK - - - - (67,147) 67,147 0.00%
NAVAL HILL RESERVOIR PHASE 2 10,000,000 1,342,000 - - 1,067,239 274,761 79.53%
BOTSHABELO AND THABA NCHU
INTERNAL BULK 17,062,870 22,031,891 1,785,652 - 16,473,141 5,558,750 74.77%
GARIEP DAM WATER SUPPLY 7,000,000 6,279,142 1,187,583 - 6,279,141 1 100.00%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS - 13,546,886 10,080,599 - 12,422,720 1,124,166 91.70%
MASELSPOORT REFURBISHMENT 14,977,286 14,977,286 - - - 14,977,286 0.00%
MASELSPOORT WATER RECYCLING 9,000,000 7,963,900 - - 2,640,010 5,323,890 33.15%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS 23,720,800 24,756,900 4,159,301 - 24,756,599 301 100.00%
MASELSPOORT REFURBISHMENT 25,022,714 5,241,000 - - - 5,241,000 0.00%
RAYTON BULK WATER SUPPLY 8,000,000 - - - - - 0.00%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS 26,279,200 33,249,323 4,928,390 - 33,502,612 (253,289) 100.76%
289
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
REPLACE PUMPS MASELSPOORT 2,000,000 10,120,692 2,217,764 - 10,389,313 (268,621) 102.65%
MASELSPOORT WATER RECYCLING 10,000,000 - - - - - 0.00%
WATER NETWORKS TO STANDS - 4,154,981 - - 3,657,036 497,945 88.02%
REPLACE PUMPS MASELSPOORT - 1,288,007 - - 1,288,007 - 100.00%
LONGRIDGE RESERVOIR SUPPLY LINE
8.3KM - 1,000,000 98,086 - 824,820 175,180 82.48%
BOTSHABELO AND THABA NCHU
INTERNAL BULK - 675,746 - - 267,169 408,577 39.54%
GARIEP DAM BULK WATER SUPPLY - 3,727,544 92,542 - 3,727,543 1 100.00%
MASELSPOORT WATER RECYCLING - 1,109,517 - - - 1,109,517 0.00%
BASIC WATER TO STANDS BW - 42,183,794 10,504,578 - 39,321,605 2,862,189 93.21%
BOTSHABELO AND THABA NCHU
INTERNAL BULK - 1,171,257 - - 1,103,019 68,238 94.17%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS: R 6,000,000 6,000,000 - - 5,872,497 127,503 97.87%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS: A 50,000,000 45,000,000 (17,030,711) 19,625,011 20,062,844 24,937,156 44.58%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS TE 5,000,000 5,000,000 862,339 - 4,854,535 145,465 97.09%
290
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
REPLACEMENT/REFURBISHMENT OF
VALVES IN B 10,000,000 23,000,000 - - 23,714,340 (714,340) 103.11%
REPLACE WATER METERS AND FIRE
HYDRANTS 30,000,000 15,900,000 - - 15,769,244 130,756 99.18%
REPLACE WATER METERS AND FIRE
HYDRANTS - 9,081,018 880,928 - 7,477,317 1,603,701 82.34%
REFURBISHMENT OF WATER SUPPLY
SYSTEMS AU - 218,428 - - - 218,428 0.00%
REPLACEMENT/ REFURBISHMENT OF
WATERMAINS - 2,188,817 30,925 - 2,146,353 42,464 98.06%
METERING OF UNMETERED SITES - 4,766,373 - - 4,766,372 1 100.00%
SUB TOTAL 255,062,870 311,033,478 20,739,854 19,625,011 247,203,898 63,829,580 79.48%
TWO WAY RADIOS - 200,000 - - - 200,000 0.00%
REFUSE STORAGE BINS FOR THE 3 CBDs - 1,000,000 - - - 1,000,000 0.00%
COMPUTER EQUIPMENT - 100,000 - - - 100,000 0.00%
UPGRADING AND CONSTRUCTION OF
NORTHERN - 1,500,000 226,518 - 1,512,987 (12,987) 100.87%
291
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
UPGRADING AND CONSTRUCTION OF
SOUTHERN - 4,200,000 1,003,251 - 3,784,808 415,192 90.11%
UPGRADING AND REHABILITATIONS OF
BOTSHAB - 800,000 - - 347,220 452,780 43.40%
DEVELOPMENT OF TRANSFER STATION
IN THABA - 5,000,000 234,548 - 3,963,563 1,036,437 79.27%
NEW VEHICLE LEASING 91,256,000 91,256,000 2,655,471 - 68,458,341 22,797,659 75.02%
REPLACE WORKSHOP DOORS AT
BLOEMFONTEIN - 200,000 - - - 200,000 0.00%
ADDITIONAL OFFICES AT FLEET
MAINTENANCE - 100,000 - - - 100,000 0.00%
FURNITURE AND EQUIPMENT FOR
ADDITIONAL S - 220,000 - - - 220,000 0.00%
CLIENT WAITING ROOM AT TESTING
CENTRE 500,000 - - - - - 0.00%
ERECTION OF STEEL STRUCTURE AND
ROOF TO 350,000 350,000 - - - 350,000 0.00%
LUBRICATION MANAGEMENT SYSTEM
FOR SERVIC 550,000 550,000 - - - 550,000 0.00%
292
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
PAVE BOTSHABELO WORKSHOP YARD
EASTERN A 300,000 300,000 - - - 300,000 0.00%
PAVING OF PARKING AREA 50,000 50,000 - - - 50,000 0.00%
REPAVING AT RECEPTION 20,000 20,000 - - - 20,000 0.00%
WORK BENCHES AND STORAGE
CUPBOARDS BOTSH 20,000 - - - - - 0.00%
SUB TOTAL 93,046,000 105,846,000 4,119,788 - 78,066,918 27,779,082 73.76%
WAAIHOEK PRECINCT REDEVELOPMENT 20,000,000 20,000,000 3,619,127 - 21,535,723 (1,535,723) 107.68%
SUB TOTAL 20,000,000 20,000,000 3,619,127 - 21,535,723 (1,535,723) 107.68%
MARKETING & COMMUNICATION 5,000,000 3,000,000 668,338 - 1,566,233 1,433,767 52.21%
IMPLEMENTATION OF BUSINESS
CONTINUITY AN 2,982,194 1,491,097 - - 904,442 586,655 60.66%
UPGRADE AND REFURBISHMENT OF
CENTLEC COM 1,023,990 2,023,990 - - 2,009,821 14,169 99.30%
VENDING BACK OFFICE 9,660,286 4,842,138 - - 402,561 4,439,577 8.31%
WEBSITE 193,206 96,603 - - - 96,603 0.00%
SCOA IMPLEMENTATION PROJECT 11,592,343 1,248,190 - - - 1,248,190 0.00%
293
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
UPGRADE OF CURENT PABX TO VOIP
TELCOMMS 2,047,981 6,047,981 990,602 - 4,664,744 1,383,237 77.13%
PUBLIC ELECTRICITY CONNECTIONS - - - - 15,630 (15,630) 0.00%
ELECTRIFICATION PROJECTS - 6,500,000 5,280,268 - 10,988,609 (4,488,609) 169.06%
INSTALLATION OF PUBLIC LIGHTING - 5,500,000 1,742,859 - 14,325,933 (8,825,933) 260.47%
EXTENSION AND UPGRADING OF THE
11KV OVER 9,003,318 7,003,318 3,682,541 - 6,417,588 585,730 91.64%
ELITE SUBSTATION (AIRPORT NODE) 21,000,000 21,000,000 - - 10,823,860 10,176,140 51.54%
132KV NORTHERN RING FROM
NOORDSTAD DC TO - 4,000,000 - - 5,256,171 (1,256,171) 131.40%
SERVITUDES AND LAND (INCLUDING
INVESTIGA 1,060,000 530,000 32,447 - 167,245 362,755 31.56%
CECELIA DC: 132KV/11KV 30MVA DC 13,000,000 13,000,000 10,813,750 - 36,501,286 (23,501,286) 280.78%
FICHARDTPARK DC: 132KV/11KV 20MVA
DC 13,000,000 4,000,000 - - - 4,000,000 0.00%
SMART STREETLIGHTS 40,000,000 35,000,000 - - 42,691,340 (7,691,340) 121.98%
GROENVLEI DC 132KV/11KV 20MVA 7,888,330 7,888,330 835,127 - 6,933,641 954,689 87.90%
MAPHIKELA DC 132/11KV 3,000,000 3,000,000 - - - 3,000,000 0.00%
ELECTRIFICATION CONNECTIONS DME 26,315,789 26,315,789 3,093,488 - 26,315,711 78 100.00%
294
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
PUBLIC ELECTRICITY CONNECTIONS - 20,952,879 - - - 20,952,879 0.00%
ELECTRRIFICATION PROJECTS 9,500,000 - - - - - 0.00%
INSTALLATION OF PUBLIC LIGHTING 15,500,000 - - - - - 0.00%
NETWORK CATALYST PROJECTS 11,000,000 - - - - - 0.00%
TRANSFORMER REPLACEMENT 20,300,000 5,650,000 (1,704,126) - 5,473,818 176,182 96.88%
INSTALLATION OF OF PREPAID METERS
(INDIG 1,100,000 1,100,000 7,142 - 39,743 1,060,257 3.61%
REFURBISHMENT OF THE TAP CHANGER
CONTROL 212,000 - - - - - 0.00%
REFURBISHMENT OF PROTECTION AT
BAYSWATER 576,467 - - - - - 0.00%
METER PROJECT 17,000,000 29,042,380 4,320,137 - 33,236,925 (4,194,545) 114.44%
REPLACEMENT OF DECREPIT 11KV
CABLE 3,498,000 3,498,000 342,540 - 2,351,857 1,146,143 67.23%
PUBLIC ELECTRICITY CONNECTIONS 20,952,879 - 38,714 - 15,097,571 (15,097,571) 0.00%
AUTOMATED MAINTENANCE SYSTEM 563,452 281,726 - - 170,075 111,651 60.37%
132KV NORTHERN RING FROM
NOORDSTAD DC TO 15,000,000 - - - - - 0.00%
295
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
CLOVER & VISTA DCs PARK ACCESS
CONTROL 394,416 - - - - - 0.00%
TIBBIE VISSER RIPPLE CONTROL 394,416 - - - - - 0.00%
REPLACEMENT OF BRITTLE OVERHEAD
CONNECTI 788,833 788,833 - - 780,436 8,397 98.94%
REPLACEMENT OF OIL PLANT 732,488 - - - - - 0.00%
REPLACEMENT OF DECREPIT HAMILTON
SUBSTAT 2,253,809 1,730,218 689,174 - 1,506,348 223,870 87.06%
REPLACEMENT OF 11KV SWITCHGEARS
FOR MAGI 1,352,285 - - - - - 0.00%
REPLACEMENT OF 32V BATTERIES 394,416 - - - - - 0.00%
REPLACEMENT OF 110V BATTERIES FOR
EAST Y 507,107 - - - - - 0.00%
REPLACEMENT OF LOW VOLTAGE
DECREPIT 24 1,690,356 90,356 - - 85,065 5,291 94.14%
REFURBISHMENT OF THE TAP CHANGER
CONTROL - 106,000 - - - 106,000 0.00%
REFURBISHMENT OF PROTECTION AT
BAYSWATER - 288,233 495,997 - 495,997 (207,764) 172.08%
296
Approved Adjusted Current YTD
% on
Adjustment
Description Budget Budget Mth Exp
Commitment Movement Balance Budget
PARK WEST 132/33 T2B 45MVA 5,071,069 5,428,685 (1,428,601) - 3,333,403 2,095,282 61.40%
REMEDIAL WORK 132KV SOUTHERN
LINES 4,507,617 3,478,174 (2,717,700) - - 3,478,174 0.00%
REPLACEMENT OF 2 &4 WAY FIBREGLAS
BOX IN 1,126,904 526,904 (71,370) - 166,859 360,045 31.67%
VEHICLES 7,000,000 6,000,000 1,785,199 - 7,594,437 (1,594,437) 126.57%
TRAINING & DEVELOPMENT 1,772,897 1,772,897 37,606 - 256,944 1,515,953 14.49%
RE-ENIGNEERING OF OLD
POWERSTATIONS 1,000,000 500,000 (89,119) - - 500,000 0.00%
REVITALIZATION OF OLD
POWERSTATIONS (FOR 3,800,000 3,800,000 (318,799) - - 3,800,000 0.00%
OFFICE BUILDING 8,000,000 8,000,000 198,484 - 1,226,096 6,773,904 15.33%
FURNITURE AND OFFICE EQUIPMENT 2,600,000 600,000 84,479 - 544,157 55,843 90.69%
SUB TOTAL 325,356,848 246,122,721 28,809,177 - 246,229,941 107 220 100%
TOTAL 1,793,890,539 1,851,179,482 203,824,202 42,874,359 1,630,343,006 220,836,476 88%
297
VOLUME II
Mangaung Metropolitan Municipality Consolidated Annual Financial Statements for the year ended 30 June 2016
Mangaung Metropolitan Municipality stand- alone Annual Financial Statements for the year ended 30 June 2016
Centlec (Soc) Limited Annual Financial Statements for the year ended 30 June 2016