annie griffith & chris fears september 2007 uk link technology refresh
TRANSCRIPT
Annie Griffith & Chris Fears Annie Griffith & Chris Fears September 2007September 2007
UK Link Technology RefreshUK Link Technology RefreshUK Link Technology RefreshUK Link Technology Refresh
Progress since last update
Key progress made since last update:
Development and Unit testing completed
Installation and configuration of all servers and networks at Peterborough Data Centre and Wellingborough completed
Network Operations Centre (NOC) set up in Bangalore and operational
System testing started
Operational Acceptance testing Started
Overall Testing Progress
Full code migration and upgrade completed
OAT – 2 phases Jun-Oct ’07 & Oct-Jan ‘08 OAT1 – machine build confirmation – Ahead of schedule OAT2 – performance testing, operational schedules, support processes, fall
back and recovery etc.
System testing : Started mid Aug and ahead of schedule Users involved in testing of critical business components to gain greater levels
of assurance ahead of UAT
UAT : Nov – end Jan To include Shipper Trials : late Nov - early Dec Detailed UAT planning underway
Full scale trial migration completed – Minimum of 2 further full scale trial migrations planned to allow for tuning
Shipper Trials
Initial suggestion was that only file routing tests to be executed, limited to sample files only
As a result of UKLC July 07 request, revised approach is to test: Nomination file (NOM) – inbound and Nomination response (NMR)
outbound Commodity Invoices (COS) – outbound, with inbound delivery receipt Datalogger Read files (MDR) – outbound
Involvement is optional
Code of Conduct: The test environment is not to be used for any other activities ie: enquiries other than the scenarios and data agreed by each Shipper
Shipper Trials
Trial environment will be a copy of production data as of 1st October 2007
Shippers to save selected copies of production NOM files between 1/10 – 12/10 and rename Between 3 and 5 NOM files are to be saved for future processing Use standard test file naming convention: xxx01.TN123456.NOM Earlier files will result in fewer queries due to better alignment with data-cut
Submission of files to take place before 12 noon
Response files will be processed and sent back the following day by 10.00am (The test file turn-a-round time will not be representative of Production)
Test files to be submitted in date order
No xoserve validation of rejections at MPRN level will take place
Shipper Trials
18th Sep Invitation to Shippers to participate
2nd Oct Deadline for response from Shippers
1st -12th Oct Shippers collect selected NOM files for later testing
11th Oct xoserve contacts confirmed for each Shipper
15th Oct – 9th Nov
Engage with participating shippers to confirm test schedules
16th Nov Finalised test schedule agreed with Shippers via email
26th Nov Test execution starts
13th Dec Pre close- out report to UKLC
14th Dec Test execution finishes
17th Dec Publish final report
Shipper Trials
Assurance & Sign-off Individual Daily Test Reports will be produced by the Test
Coordinator and issued at end of day
On conclusion of the Shipper Trial phase xoserve will confirm final test position (by e-mail) with each participating Shipper
Teleconference meeting to take place at the end of testing Capture lessons learnt Confirm any outstanding issues Discuss remedial action plans (if necessary)
Cut-over and Implementation
Outage of 3 - 4 days as previously indicated Detailed implementation planning activities ongoing Looking at cut-over activities and catch-up processing Timescales being challenged, seeking alternative approaches and
tuning to reduce outage Minimum of 2 further full scale trial migrations planned over summer
MOD proposal being drafted to include: 2 non-effective days for SPA processing (25th & 26th Feb) 4 days relief from data logger liabilities (24th-27th Feb)
Cutover Approach
Data cutover Likely to start 3 weeks in advance of main cutover, then will require
“delta” data updates This will have no effect upon the operational service
Final cutover starts 22nd/23rd February 2008 REC invoice to be issued early on Friday 22nd – due dates will be
unchanged Other production runs on 22nd will be unchanged
Outage start time Start after Datalogger issue on Saturday 23rd confirmed as optimal
approach
High Level Timetable (Draft)
Invoices Friday 22nd - REC Invoice issued early, due dates unchanged
Non-effective Days Mon 25th Feb - Tuesday 26th Feb Relief from DM Read liabilities Sun 24th –Weds 27th
Datalogger files Issued from OLD UK Link Sat 23rd
Suspend daily issue of data logger files Sun 24th – Weds 27th Issued from NEW UK Link Thursday 28th
Transfers Last files processed 11pm Friday 22nd Feb on OLD UK Link Next Transfer Run – Weds 27th Feb on NEW UK Link
Next Steps
Completion of OAT Phase 1
Complete trial migration 2
Invitations issued for Shipper Trials
Continue with more in depth Implementation Planning Firm up on outage timings Understand catch-up and return to normal operation Dates when other systems will be brought back on-line/in-step
Report back at October UKLC