  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    1/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    PROPOSAL

    Ref: JD/SC.RN/0113/1807/3 21stMarch 2013

    M/S. Anil Verma Consultants

    325, Sai Commercial Bldg,

    Next to Runwal Chambers,

    Deonar, Mumbai- 400088

    Kind Attn: Mr. Devendra Patil

    Subject:Technical offer for Prefabricated Sewage Treatment Plant of Capacity 13 KLD

    Dear Sir,

    We are pleased to submit our Techno- commercial offer for Sewage treatment plant. We

    express our keen interest to be associated with you for this project. The proposed models

    have following highlights:

    We have proposed the GREWA-B (MBBR) for biological treatment of wastewater

    generating from domestic usage.

    Tertiary Treatment comprising of Media Filter with Carbon Filtration System.

    Sizes of tanks considered based on proven technical expertise to ensure smooth

    operation & maintenance

    The proposed model can accommodate flexibility of layout as per site conditions.

    All makes considered are reputed/proven in their own field

    Our offer consists of following sections:

    Section I : Design Basis, Treatment Scheme & Treatment Process

    Section II : Technical notes

    Section III : Scope of work & Supply

    Section IV : Details of Tanks Sizes

    Section - V : Makes of offered equipment

    Section - VI : Terminations & Exclusions/Owner Scope

    Section VII : Commercial Terms & Conditions

    We hope that the above is in line with your requirement. In case you need any further

    clarifications feel free to revert back.

    Thanking you and assuring you our best services at all times.

    For Jaldhara Technologies Pvt. Ltd

    Santosh Chilgar

    Zonal Manager- Sales

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    2/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section I: Design basis, Treatment Scheme & Treatment Process

    Flow rates : 13 m3/day or 0.65 m3/hr.

    Hours of Operation : 20 hours

    Nature of wastewater: Sewage

    Characteristics of Inlet / Outlet of STP:

    Parameters Unit Inlet OutletAfter UF

    (Optional)pH ---- 6.5 - 8.5 7.0 - 8.0 7.0 - 8.0

    BOD mg/l 300 - 350

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    3/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section II: Technical Notes

    STP shall be compact package type, smell free and shall consume less power.

    Bar Screen:The Bar Screen of MSEP material is considered in the scope for better life.The screen of 16 mm spacing is considered with required accessories for lifting &

    cleaning. The screens can be easily removed & cleaned as required.

    Equalization Tank: We have proposed collection cum equalization tank in MSEP

    below/above the ground level & it depends on the invert level of sewage wastewater. All

    other tanks of STP in MS can be built fully above the ground as required. The tanks can

    be covered from the top, if required and access manholes can be provided. The tank is

    provided with air distribution piping with adequate number of air grids.

    GREWA - B (MBBR):The reactor tank is provided with Media of PP material. The media

    is in moving condition. The Sewage Water flows down keeping in contact with media.The air in form of bubbles coming from the bottom of tank comes in contact with Water &

    MBBR media. The tank is provided with air grid distribution piping for the biological

    oxidation of sewage.

    Air Blowers: Air shall be used in MBBR tank and will also be used in collection cum

    equalization tank to avoid the anaerobic conditions, smell problem and sedimentation of

    solids in to the tank.

    Tube Deck Media Clarifier: The overflow of MBBR tank is taken in to the Tube Deck

    Media Clarifier. Here Tube Deck media in PVC is arranged to facilitate solid liquid

    separation.

    Clarified/Clear Water Tank: The clear water from Tube Deck Media Clarifier flows in to

    this tank. A Sodium Hypochlorite solution is dosed in this tank using a metering pump.

    Media Filtration System: The clarified & chlorinated water is pumped to Dual Media

    followed by Activated Carbon Filtration System to further polish the treated water.

    Ultra Filtration System (Optional): Filtered water is passed through the Ultrafiltration

    plant to further reduce suspended solids.

    Sludge removal from Tube settler by gravity & disposed by client.

    Our offer is exclusive of civil work, which includes tanks construction, foundation of

    equipment, drains & trenches, shedding/plant room for the equipment and related MS

    work

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    4/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section III: Scope of work & supply

    Scope of Work:

    Design, Engineering, preparation & submission of drawings, supply, installation, testingand commissioning of STP including mechanical & electrical work as per the detailsgiven in the scope of supply.

    No Civil work with related MS work is considered in our scope. We shall providedimensional GA & section/elevation drawing for civil work based on your site conditions& available space after release of purchase order.

    We shall provide operation training of system for 2 to 3 days to your operational team.

    Scope of Supply:

    TECHNICAL DATA SHEET

    S.N. Details of Equipment Unit Value/ Description

    A. Biological Treatment -

    01 Bar Screen Coarse No. 01Flow M3/hr 2.0Type Flats / BarsMOC MSEPClear spacing mm 16 mm

    02 Sewage Transfer Pump No. 02 (1W + 1S)

    Make CRI/Kirloskar or Equiv.Type Non clog Hor. centrifugalCapacity M3/hr 0.65Head meter 12MOC Cast Iron Construction

    03 Air Blowers No. 02 (1W + 1S)Type Twin lobe with rotary gears

    MakeEverest /Usha / KPT orEquivalent

    Operating Pressure Kg/cm2 0.5Operating Discharge Flow rate M3/hr 15

    Operating speed RPM 1450

    04 Air Grid for Equalization Tank Lot 01

    TypeUPVC perforated pipe gridof suitable size

    Make Jaldhara TechnologiesMOC of Header & laterals UPVC

    05 Air Grid for Aeration Tank Lot 01

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    5/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    (MBBR Reactor)

    TypeUPVC perforated pipe gridof suitable size

    Make Jaldhara Technologies

    MOC of Header & laterals UPVC

    06Synthetic Media For GREWA-B(MBBR )

    Lot 01

    MakePassco / Usha Ruba /Shreedevi or Equivalent

    MOC PPType of Media Moving

    07Synthetic Media For TubeSettler

    Lot 01

    MakeMM Aqua / Cooldeck orEquivalent

    MOC PVCType Square Tube

    08 Electrical Control Panel No 01Make Power wise or Equiv.

    TypeNon Compartmental Wallmounted/Stand Mounted

    MOC

    Ms Fabricated powdercoated box with internalcomponents of L & T orSiemens

    09Power Cable (for rotaryequipment)

    lot 01

    Type & MakePVC Insulated Armored Al& Cu cablePolycab or equivalent

    10 Instrumentation & ControlStarter & Control Panel Lot 01Level switch Lot As per requiredPressure Gauges Lot As required

    11 Piping & fittings - UPVC Lot Supreme/Astral/Prince

    12Valve Lot

    Normex/Supreme/Astral/Prince

    B. Tertiary Treatment

    01Hypo Dosing Pump With Tank(for Pre chlorination)

    No. 01

    Make Seko or EquivalentType Electronic Diaphragm

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    6/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Capacity LPH 0 4Tank capacity LTRS 50MOC of Tank LDPE

    02 DMF Feed Pumps No. 02 (1W + 1S)Make CRI/ Kirloskar or equivalentType Horizontal Centrifugal,Capacity M3/hr 0.65 m3/hr @ 2.6 kg/cm2

    MOCCasing & Impeller CI,Shaft CS

    03 Dual Media Filter No. 01Make Aquanomics or equivalentMOC FRPDiameter Inch 10HOS Inch 54

    Capacity / Flow M3/hr 0.65Working Pressure Kg/cm2 2.6

    Type of Media LotPebbles, gravels, Sand ,Anthracite

    04 Activated Carbon Filter No. 01Make Aquanomics or equivalentMOC FRPDiameter Inch 10HOS Inch 54Capacity / Flow M3/hr 0.65Working Pressure

    Kg/cm2

    2.6

    Type of Media Lot

    Gravels, Sand , ActivatedCarbon

    C. Ultra filtration (Optional)

    01 UF Feed cum CIP Pump No. 01 WMake CRI/ Kirloskar or equivalentType Horizontal Centrifugal,Capacity M3/hr 0.65 m3/hr @ 2.0 kg/cm2

    MOCCasing & Impeller CI,Shaft CS

    02 UF Backwash Pump No. 01 WMake CRI/ Kirloskar or equivalentType Horizontal Centrifugal,Capacity M3/hr 2.0 m3/hr @ 2.0 kg/cm2

    MOCCasing & Impeller CI,Shaft CS

    03 Hypo Dosing Pump With Tank No. 01

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    7/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Make Seko or EquivalentType Electronic DiaphragmCapacity LPH 0 4Tank capacity LTRS 50

    MOC of Tank LDPE

    04 UF Module No. 01Cartridge Filter Nos 01Rating Micron 50Membrane Lot 01Make AquaplusFlow M3/hr 0.65Recovery % 90Rotameters Nos 3Piping Lot I UPVC

    05 CIP System Nos 01

    CIP Tank Nos 01Capacity Ltrs 200MOC HDPEMake Sintex or EquivalentPiping & Valves Lot 01Piping MOC UPVC

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    8/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section -IV: Details of Tanks Sizes

    Tanks of following sizes would be required:

    Sr. No. Name of Treatment Unit Size in meters (L x W x H)

    01.Bar screen chamber coarse(MSEP)

    1.0 x 0.5 x 0.2 m swd

    02. Oil & grease Chamber (MSEP) 1.2 x 0.4 x 0.7 m swd

    03. Equalization Tank (MSEP) 1.0 x 1.0 x 2.7 m swd + 0.3 m F.B

    04.GREWA-B (MBBR) Tank (MSEP) 1 No. Compartmental

    1.0 x 1.0 x 4.0 m swd + 0.3 m F.B

    05. Tube Deck Clarifier Tank (MSEP) 0.6 x 0.6 x 2.7 m swd + 0.3 m F.B06. Chlorine Contact Tank (MSEP) 0.6 x 0.6 x 2.2 m swd + 0.3 m F.B

    07.Treated water/UF Feed Tank(HDPE)

    500 liters

    08. UF Treated Water Tank (Optional) As required (Clients Scope)

    08.Plant Room / Shedding ForEquipment

    Suitable (Client Scope)

    09. Foundation for equipment Suitable (Client Scope)

    NOTE:

    The above sizes are indicative only based on standard practices. The sizes of

    treatment units may be changed as per site conditions.

    All MSEP tanks as mentioned above will be in our scope while RCC tanks and

    other related works in RCC/brick work will be in client scope.

    The vents, puddles & insertions shall be provided as per our guidelines.

    All tanks should be provided with manholes & steel bars runs/ladders for ease

    of maintenance. ( clients scope )

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    9/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section V: Makes of offered equipment

    Sr. No. Name of Equipment Makes offered

    1. Submersible Pumps Kirloskar /KSB/ CRI and Equivalent

    2.Horizontal Centrifugal Pump,Self-Priming pumps

    Kirloskar/CRI /Nangfang or Equivalent

    3. Electric motors ABB/ Siemens/C&G or Equivalent

    4. Blowers Everest/Usha/KPT or Equivalent

    5. Tube settler - Media MM Aqua/Cooldeck or Equivalent

    6. MBBR - Media Passco/UshaRuba/Shreedevi or Equivalent

    7. Valves - Butterfly Normex/ CRI or equivalent

    8. Valves Ball Sant or Equivalent

    9. Electrical Control Panel Power wise or Equivalent

    10. Level Switch Minilec or Equivalent

    11. Pressure gauges H.Guru/Iota or Equivalent.

    12. Air Diffusers Southern Cogen/Jay or Equivalent

    13. Dosing Pumps Seko or Equivalent

    14. PVC Pipes & Fittings Prince/Supreme or equivalent

    15. Electric cables Polycab /Finolex or Equivalent

    16. Electrical Switch gears L&T/Equivalent

    17. MS / GI Piping Jindal Star / Equivalent

    18. FRP Vessels Aquanomics/Aventura or Equivalent

    19. GI fitting Unik/Equivalent

    20. HDPE Tank Sintex or Equivalent

    21. UF module Aquaplus

    Note: Jaldhara Technologies reserves right to offer from any of these makes.

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    10/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section VI: Terminations & Exclusions/ Owners scope

    Termination Points:

    Sewage incoming pipeline at the inlet of Screen chamber.

    Sludge removal by gravity from the Tube settler to be disposed of by client.

    Treated water at a distance of 2 m from the outlet Carbon filtration System.

    Treated water at a distance of 2 m from the outlet of Ultra filtration System (Optional)

    Collection tank - at a distance of 2 m from the Proposed Sewage Treatment Plant.

    Electric incoming power supply with proper earthing to STP panel on continuous basis.

    Exclusion Points:

    Approach to site and storage of our equipment.

    Unloading & Safe Storage of material at site.

    Security & Painting at site.

    Pollution control Board charges

    Chemical consumptions for trials & operation also.

    Lab testing for Inlet & outlet parameters

    Electricity during the erection work.

    Fresh water connection, Lighting & Drainage arrangement in STP area.

    Sludge disposal.

    Civil work related structures, gratings, foundation of equipments, plant room, sheddingfor equipment.

    All Inter Connecting pipe related to the civil work ie. Puddle pipes, nozzles, hand railing,walkways & ladders.

    Treated water transfer pumps in the client scope.

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    11/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    Section VII: Pricing & Commercial Terms

    PARTICULARS GREWA-B (MBBR) BASED PREFAB. STP

    Design Capacity 13 KLD

    Price (Ex-works)for design,engineering & supply of STP

    Rs. 8,20,000/-(Rupees Eight Lakhs Twenty Thousand Only)

    Price (Ex-works)for design,engineering & supply of UltraFiltration System (Optional)

    Rs. 2,50,000/-(Rupees Two Lakhs Fifty Thousand Only)

    Supervision of Erection &Commissioning

    Included

    Packing & Forwarding Extra @ 2%

    Excise Duty Extra @ actual(as applicable at time of despatch)

    Service Tax on E&C Charges Extra @ actual(as applicable at time of despatch)

    Transportation Charges for deliveryat the purchasers plant site byroad

    Extra @ actual

    Transit Insurance Extra @ actual

    Sales Tax, VAT/WCT/Any otherGovt. taxes, levies & duties

    Extra @ actual

    Octroi / Entry Tax (if applicable) Extra @ actual

    Statutory VariationsExtra @ actual as per the prevailing rates if & as per

    applicable variations

    PAYMENT TERMS: 50% Advance along with Techno-commercially clear Purchase

    Order.

    45% against Pro-forma Invoice prior to delivery (against each

    unit).

    5% before commissioning of each plant

    (In the event Erection or Commissioning gets delayed beyond 30

    days from date of delivery of the plant to site, entire amount shall

    be released at the end of 30 days from date of supply).

    E&C SUPERVISION : To & fro travel, Boarding & lodging in clients scope. Unskilled

    labours for site fabrication (if any) & pre-commissioning activity tobe provided by the client.

    DELIVERY : 12-16weeks from date of receipt of PO and Advance, whichever

    is later.

    VALIDITY : 30 days from the date of offer.

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    12/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    WAREHOUSING:In case of delay in receipt of balance payment within 10 days from date of our intimation of

    readiness of plant, a charge for warehousing @ 1% of PO value per week, subject to a

    maximum of 5% of PO value shall be levied. Thereafter, warehousing charges shall be

    adjusted against the advance received and plant would be diverted to other customers.

    WARRANTY FOR EQUIPMENT:Liability with respect to any defect in failure of equipment supplied by us or any loss, injury or

    damage attributable thereto, is limited to making good by replacement or repairs; defects

    which under proper use appear therein, provided the equipment is operated and maintained

    in accordance with our instructions and arise totally from proved faulty design, material or

    workmanship, within a period of 12 months from the date of commissioning of equipment or

    18 months from the date of supply, whichever is earlier, at the termination of which period,

    all liability on our part shall cease.

    This warranty is applicable under the following conditions:

    a. Any replacement / repairs required to be made under the provisions of the abovewarranty will be carried out at our option, either at site or at our works. In the latter

    case, you shall arrange to promptly return the defective parts to us, at your cost.

    b. After repairs/replacement, the period of warranty for the entire equipment including

    replaced/repaired parts shall limit itself to the unexpired portion of the total warranty

    period.

    c. Bought out components are warranted only to the extent of warrantees extended to

    us by our suppliers. Electrical components such as heaters, motors, contactors etc.,

    rubber components and instruments such as pressure gauges, thermometers, etc.

    are however, not covered under this warranty.

    d. In respect of the equipment where despatch after readiness is delayed due to

    specific instructions or lack of instructions from you, the warranty shall be limited to18 months from the date of readiness for despatch of equipment, as notified by us.

    e. No repairs or replacements, unless authorised by us in writing, shall be carried out by

    any other party on our equipment during the warranty period or otherwise.

    The warranty period shall not cover the following:

    i. Normal wear and tear.

    ii. Damages/defects arising out of mal-operation of the plant by the purchaser

    and accidents.

    FORCE MAJEURE:In all cases where a time schedule for dispatch, delivery erection or completion has been

    specified, the time for all these shall be extended by a reasonable period if the delay iscaused by lack of instruction from the Purchaser or any industrial disputes, war, strikes,

    lockout, fire, accident, defective materials, approval of drawings, statutory restriction or any

    causes whatsoever beyond our and our Suppliers/subcontractors reasonable control. No

    liability shall be acceptable due to above reasons.

    LIABILITYIn no case shall we be liable for any loss of anticipated profits as well as consequentialdamages, loss by reason of plant shutdown, non-operation, or increased cost of operation,

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    13/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    or another consequential loss or damage of any nature. In other words, our liability under thecontract shall be solely restricted to the framework of our performance guarantee subject toall conditions stipulated therein.

    DRAWINGS, DESIGNS AND PATTERNS

    All specifications, drawings, designs, data information, ideas methods conceived, developed

    or acquired, incidental or produced and /or carried out, shall be the sole property of

    Jaldhara Technologies Pvt Ltd.and shall not be used by the Purchaser or any other Party

    associated with the Purchaser for any other project. Unless otherwise agreed drawings are

    not subject to Purchasers approval. All Specifications are subject to changes during detail

    Engineering.

    DOCUMENTATION

    Unless otherwise mutually agreed, in writing, only two copies of foundation/Layout/general

    arrangement drawings, P& I diagrams, operation and maintenance manuals shall be

    provided free of cost.

    INSPECTION

    If desired, necessary visual inspection may be carried out by the Purchaser or his authorized

    representative at Purchasers cost at our works/ go-down/ subcontractors works before

    despatch. Intention of the Purchaser to inspect any equipment / systems must be specified

    by the Purchaser so as to be properly taken care of in the Purchase Order clause. Wet or

    dry tests shall be charged for as an extra item.

    CONSENTS FROM STATE POLLUTION CONTROL BOARD OR ENVIRONMENT DEPT

    Approvals or consents from the Central / State Pollution Control Board or Department of

    Environment, Municipal Authorities, Industrial development Corporations or Safety

    Inspectorate shall not be in our scope unless specified elsewhere in our quotation or formallyagreed to by us. There shall be a separate, mutually agreed fee for this service, which shall

    be paid to us along with a Work Order.

    ALTERATIONS TO EQUIPMENT SUPPLIED

    Purchaser shall not make any repairs, alterations or replacement in regard to the equipment

    supplied without written authorization from Jaldhara Technologies Pvt Ltd.

    HANDING OVER

    Unless otherwise specified in the order and accepted, handing over of the equipment and /

    or installation would be considered as completed and a formal completion certificate shall be

    issued by the purchaser/ user if :

    The material has been supplied as per the terms of scope of supply or with agreed

    deviations, if any. Erection if involved has been completed generally as per the terms of

    order or with unavoidable deviations. The equipment and /or installation have been put to

    commercial use either with or without the help of our engineer.

    The Purchaser / user shall put the equipment to commercial use only after issuing a formal

    completion certificate. Our responsibility in term of warranty shall cease straightaway if the

  • 7/25/2019 Anil Verma Consultant. Offer - Prefab. STP - 13 KLD - MBBR - 21.03.13 (1)

    14/14

    Jaldhara Technologies Pvt Ltd

    701 / 702, Trade World B Wing, Kamala City

    Senapati Bapat Marg, Lower Parel, Mumbai 400 013, India

    Tel: +91-22-4334 5000 fax: +91-22-4334 5020

    equipment is put into operation without formal taking over. Installation of equipment shall be

    started only after all payments / dues against supply have been cleared by the Purchaser.

    NON-PAYMENT

    In case any payment remains outstanding for more than 60 days from date of supply or 30days from date of commissioning whichever is earlier, Jaldhara Technologies Pvt. Ltd.

    reserves the right to opt for legal recourse for recovery of dues or / and take back your asset

    (plant).

    STORAGE

    The Purchaser shall be responsible to protect the equipment against damage from weather

    or other causes and for any costs in connection with storage and reconditioning of the plant

    once supplied.

    DEFAULT, INSOLVENCY OR BANKRUPTCY

    If the buyer refuses to lift the material when ready or accept the material after it has beendispatched, we reserve the right to retain all advances received as compensation for costs

    incurred by us and to resell the material for and on behalf of the buyers and to reserve from

    the buyers the deficiency between the price of such a safe (less all necessary costs thereof)

    and costs incurred in manufacturing the said equipment.

    In case of an order where the buyer has stipulated pre-delivery inspection as a condition in

    case buyer fails to carry out inspection within 15 (fifteen) days of our giving notice of

    readiness of material in a storage / warehousing charge of 1% of the value of material per

    month. If the inspection is not carried out within 3 (three) months of our notice in writing, the

    course of action as given the above paragraph will be followed by us.

    In the event the buyer become insolvent commits an act of bankruptcy or default in the

    performance of his proposal, the entire unpaid amount / portion of the order value shall

    without motive or demand immediately become due and payable. In such an event, we at

    out option shall without notice or demand be entitled to sue for the said balance amount and

    for a reasonable attorneys fees out of pocket expenses plus interest and / or take immediate

    possession of the said equipment or any portion thereof and enter any place and remove the

    same without legal process, all trespass and damage resulting therefore being waived by the

    buyer.

    We shall have the right to retain all payments made therefore as compensation for the use of

    the said equipment and or resell the said equipment at private or public sale without notice

    of demand for and on behalf of buyer and to receive from the buyer deficiency between the

    price of such resale (less all necessary costs and expenses thereof) and the balance then

    due to us for the said equipment.