analisa pek pondasi

Upload: ujang-ayi-winarya

Post on 07-Mar-2016

8 views

Category:

Documents


0 download

DESCRIPTION

Satuan Analisa Pekerjaan Pondasi

TRANSCRIPT

  • C. ANALISA HARGA SATUAN PEKERJAAN PONDASI

    No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA

    (Rp) (Rp)

    C-01 1 M3 Pasanag Pondasi batu Kali adk 1pc : 3 ps

    - Batu Belah M3 1.1 205,500.00 226,050.00

    - Semen Portland Kg 202 1,406.00 284,012.00

    - Pasir Pasang M3 0.485 233,400.00 113,199.00

    - Pekerja Oh 1.5 42,000.00 63,000.00

    - Tukang Batu Oh 0.6 65,000.00 39,000.00

    - Kepala Tukang Oh 0.06 75,000.00 4,500.00

    - Mandor Oh 0.075 80,000.00 6,000.00

    Jumlah 735,761.00

    Dibulatkan 735,761.00

    C-02 1 M3 Pasang Pondasi Batu kali adk 1pc : 4ps

    - Batu Belah M3 1.1 205,500.00 226,050.00

    - Semen Portland Kg 163 1,406.00 229,178.00

    - Pasir Pasang M3 0.52 233,400.00 121,368.00

    - Pekerja Oh 1.5 42,000.00 63,000.00

    - Tukang Batu Oh 0.6 65,000.00 39,000.00

    - Kepala Tukang Oh 0.06 75,000.00 4,500.00

    - Mandor Oh 0.075 80,000.00 6,000.00

    Jumlah 689,096.00

    Dibulatkan 689,096.00

    C-03 1 M3 Pasang Pondasi Batu kali adk 1pc : 5ps

    - Batu Belah M3 1.1 205,500.00 226,050.00

    - Semen Portland Kg 136 1,406.00 191,216.00

    - Pasir Pasang M3 0.544 233,400.00 126,969.60

    - Pekerja Oh 1.5 42,000.00 63,000.00

    - Tukang Batu Oh 0.6 65,000.00 39,000.00

    - Kepala Tukang Oh 0.06 75,000.00 4,500.00

    - Mandor Oh 0.075 80,000.00 6,000.00

    Jumlah 656,735.60

    Dibulatkan 656,736.00

    C-04 1 M3 Pasang Pondasi Batu Kosong (aanstamping)

    - Batu Belah M3 1.2 205,500.00 246,600.00

    - Pasir Urug M3 0.3 175,300.00 52,590.00

    - Pekerja Oh 0.78 42,000.00 32,760.00

    - Tukang Batu Oh 0.39 65,000.00 25,350.00

    - Kepala Tukang Oh 0.039 75,000.00 2,925.00

    - Mandor Oh 0.039 80,000.00 3,120.00

    Jumlah 363,345.00

    Dibulatkan 363,345.00