anaerobic phased solids digester -...

40
Anaerobic Phased Solids Digester Pilot Demonstration Project CALIFORNIA ENERGY COMMISSION Pilot Digester Construction Report CONTRACTOR REPORT August 2008

Upload: tranduong

Post on 15-Jul-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Anaerobic Phased Solids Digester

Pilot Demonstration Project

CALIFORNIA

ENERGY

COMMISSION

Pilot Digester Construction Report

CO

NT

RA

CT

OR

RE

PO

RT

August 2008

Arnold Schwarzenegger, Governor

CALIFORNIA

ENERGY

COMMISSION

Prepared By:

Dave Konwinski, OPS Ruihong Zhang, UC Davis

Scott Archibald, OPS

Hamed El-Mashed, UC Davis Josh Rapport, UC Davis

Iain Clark, UC Davis

Prepared For:

Valentino Tiangco

Project Manager

Ron Kukulka

PIER Program Director

Robert L. Therkelsen

Executive Director

1

Legal Notice

This report was prepared as a result of work sponsored by the California Energy Commission

(Commission, Energy Commission). It does not necessarily represent the views of the

Commission, its employees, or the State of California. The Commission, the State of California,

its employees, contractors, and subcontractors make no warranty, express or implied, and assume

no legal liability for the information in this report; nor does any party represent that the use of

this information will not infringe upon privately owned rights. This report has not been approved

or disapproved by the Commission nor has the Commission passed upon the accuracy or

adequacy of this information in this report.

2

Anaerobic Phased Solids Digester

Pilot Demonstration Project

Construction Specifications and Process Operational Protocol

&

Material Handling, Mechanical & Process Components

Contact Information:

Dave Konwinski

Onsite Power Systems, Inc

Phone: (559) 271-2970 e-mail: [email protected]

Ruihong Zhang

Biological and Agricultural Engineering Department

University of California, Davis

Phone: (530)754-9530, email: [email protected]

3

Executive Summary

The University of California, Davis (UC Davis) received a research grant from the Public

Interest Energy Research (PIER) program of California Energy Commission to develop and

construct a pilot-scale anaerobic digester system based on the Anaerobic Phased Solids

Digester (APS-Digester) technology. The pilot digester system will be used to demonstrate

and test the APS-Digester technology at a larger scale than the bench-scales used in previous

laboratory studies, with regards to material handling, heat transfer, reactor level control and

stability, computer controls, biogas collection and utilization, and digestate collection and

utilization. The knowledge and research data gained from this pilot digester system will be

used to guide the design and construction of a commercial scale APS-Digester system.

The APS-Digester system combines favorable features of both batch and continuous

biological processes in a single biological system and makes it possible to achieve efficient

and stable production of both hydrogen and methane gases from a variety of organic solid

and liquid wastes, including grass clippings, food leftovers, food processing byproducts, crop

residues, and animal wastes. The pilot digester system is housed in the newly developed UC

Davis Biogas Energy Plant and has a capacity of treating 3 to 8 tons per day organic waste

with expected biogas production of producing 11,400-22,900 ft3

per day biogas. It has

employed innovative design features and state of the art equipment and control technologies

that provide optimum conditions for fast microbial degradation of organic wastes and

efficient material handling. At present, the biogas is used for electricity and heat generation.

Additional capability can be added to purify and compress the biogas for producing

compressed or liquefied fuels.

The research team for the development of the pilot digester system consists of members from

the University of California, Davis and Onsite Power Systems, Inc. The capital for design

and construction of the pilot digester system is provided by the research grants from

California Energy Commission and University of California, Davis and in-kind and cash

funds provided by Onsite Power Systems. The following companies have also made

contributions to the development and construction of the pilot digester system,

Brown and Caldwell (Computer controls design)

Rockwell Engineering (Material processing and hydraulic mixing)

Mazzie Injectors (Hydraulic mixing)

Kouba Engineering (Engineering design review)

GraybaR (Instrumentation and controls components)

Advanced Food Technologies (Material processing equipment and design)

Wonderware (Computer control and data collection programs)

4

Table of Contents

Acronyms / Abbreviations ........................................................................................................ 5 List of Figures ........................................................................................................................... 6 1. Introduction ....................................................................................................................... 7

2. Project Overview .............................................................................................................. 7 2.1. APS-Digester technology overview .......................................................................... 7

3. Pilot Digester Construction Specifications ....................................................................... 9 3.1. Concrete pad ............................................................................................................. 9 3.2. Reactor vessels .......................................................................................................... 9

3.3. Boilers and Heat exchangers ................................................................................... 11 3.3.1. Heat Exchangers ............................................................................................. 12

4. Material Handling and Digester Operational Equipment ............................................... 13 4.1. Hydrolysis reactor loading ...................................................................................... 13

4.2. Liquid circulation process ....................................................................................... 17 4.3. Internal hydraulic mixing system – HT 1 and HT 2 ............................................... 18

4.4. Hydraulic internal mixing system – HT 3 and HT 4 .............................................. 19 4.5. Hydraulic internal mixing system - GT .................................................................. 19

4.6. Solids residue and water recovery .......................................................................... 20 4.7. Tank pressure/vacuum equalization ........................................................................ 21 4.8. Safety pressure relief valve ..................................................................................... 21

4.9. Limiting introduction of air into the system ........................................................... 22 4.10. Computer control system ........................................................................................ 22

4.11. OPS proprietary computer controls software and process protocol ........................ 25 5. Biogas Collection and Processing System ...................................................................... 26

5.1. Biogas collection ..................................................................................................... 26

5.2. Biogas compression ................................................................................................ 28

5.3. Electrical generator ................................................................................................. 29 5.4. Safety biogas flare................................................................................................... 30

6. Safety and Environmental Considerations ...................................................................... 30

6.1. Safety considerations .............................................................................................. 30 6.2. Environmental considerations ................................................................................. 31

7. Equipment and Cost of UC Davis Biogas Energy Plant ................................................. 32 8. References ....................................................................................................................... 36

9. Acknowledgement .......................................................................................................... 36

5

Acronyms / Abbreviations

ADS = anaerobic digester system

APS = anaerobic phased solids

BTGT = buffer tank biogasification tank

BT = buffer tank

Btu = British thermal unit

CEC = California Energy Commission

CDS = commercial demonstration system o F = degree Fahrenheit

DV = decant valve

RWT = reclaimed water tank

RWV = reclaimed water valve

ft2 = square foot

ft3 = cubic foot

FSD = facilities services department

gals = gallons

GT = tank

H1 = hydrolysis tank 1

H2 = hydrolysis tank 2

H3 = hydrolysis tank 3

H4 = hydrolysis tank 4

HMV = hydraulic mixing valve

HT = hydrolysis tank

IIPP = injury illness prevention program

in = inches

IV = inlet valve

kW = kilowatt

kWh = kilowatt hour

lb = pounds

MIV = Mazzie injector valve

OPS = Onsite Power Systems, Inc.

PBM = pressure balanced manifold

PM = project manager

psi = pounds per square inch

reqd = required

RV = relief valve

SCADA = supervisory control and data acquisition

SS = stainless steel

TRV = top re-circulation valve

TS = total solids

UC = University of California

UCD-RT = University of California, Davis research team

VS = volatile solids

Xfer = transfer

6

List of Figures

Figure 1. A schematic of APS-Digester System ....................................................................... 8

Figure 2 . Main frontal view of digester system with loading dock ......................................... 9

Figure 3. Five anaerobic reactors including four hydrolysis reactors and one biogasification

reactor ............................................................................................................................. 10

Figure 4. Buffer tank located between hydrolysis and biogasification reactors ..................... 11

Figure 5. Dual boiler systems ................................................................................................. 11

Figure 6. Propane operated boiler for system start-up ............................................................ 12

Figure 7. GT external heat exchanger system ......................................................................... 12

Figure 8. Air fin heat exchanger system ................................................................................. 13

Figure 9. Delivery of bins containing feedstock materials ..................................................... 13

Figure 10. Bins of waste materials delivered for loading ....................................................... 14

Figure 11. Forklift dumps bin into receiving hopper .............................................................. 14

Figure 12. Receiving hopper metering feedstock into conveyor system ................................ 15

Figure 13. Conveyor delivers feedstock to hydraulic piston pumps ....................................... 15

Figure 14. Hydraulic piston pump located at HT 3 and HT 4 ................................................ 16

Figure 15. Hydraulic piston pump located at HT 1 and HT 2 ................................................ 16

Figure 16. Valve system for HT loading ................................................................................ 17

Figure 17 Screen filter, self cleaning system .......................................................................... 17

Figure 18. pH meter and circulation buffer tank ..................................................................... 18

Figure 19. In-line chopper pipe and pipe system .................................................................... 18

Figure 20 Hydraulic mixing pump HT 3 and HT 4 ................................................................ 19

Figure 21 GT hydraulic mixing pump and pipe system ......................................................... 19

Figure 22. HT drain valve and connection to drain system .................................................... 20

Figure 23. Drain section to be connected to pump and screw press unit ................................ 21

Figure 24. Pressure relieve units and flame arrester ............................................................... 22

Figure 25 Process flow monitoring screen.............................................................................. 23

Figure 26. Spread spectrum wireless data transmission boxes ............................................... 24

Figure 27. Biogas flow, Biohydrogen flow and pH meters .................................................... 24

Figure 28. Motor control cabinet with HMI interface panel ................................................... 25

Figure 29. One of three magnetic flow meters ....................................................................... 25

Figure 30. Biogas collection manifold .................................................................................... 26

Figure 31. Hydrogen sulfide filter with SulfaTreat ................................................................ 27

Figure 32: Coalescent filter, expansion tank and drain traps (located on ground) ................. 27

Figure 33 Biogas pressure regulator system ........................................................................... 28

Figure 34. Biogas blower unit ................................................................................................. 28

Figure 35. Engine-generator system with control switch box ................................................ 29

Figure 36. Engine-generator system with control switch box ................................................ 30

7

1. Introduction

The UC Davis Biogas Energy Project is funded by California Energy Commission to scale-

up, test, and demonstrate a new anaerobic digestion technology called the Anaerobic Phased

Solids Digester system (APS-Digester) (U.S. patent 6,342,378). The APS-Digester

technology was developed at the University of California, Davis and is an advanced

technology with innovative design features that optimize the microbial degradation of

organic wastes, provide efficient material handling solutions, and combine the favorable

features of both batch and continuous operations in a single biological system. The APS-

Digester system has been proven to be reliable and stable at the laboratory level for

converting various types of organic wastes to biogas. The pilot digester system is developed

to examine the material handling, actual waste stream characteristics, digester performance,

residual material characteristics and value at a larger scale. The knowledge and research data

gained from the pilot digester system will be used to design and build a commercial APS-

Digester system. A pilot-scale APS-Digester has been constructed on the campus of UC

Davis according to the engineering design described in a previous report submitted to

California Energy Commission (Zhang et al., 2005). This report documents the equipment

and components, and construction process that have been built into the pilot digester system

at UC Davis Biogas Energy Plant.

2. Project Overview

2.1. APS-Digester technology overview

The APS-Digester developed at UC Davis is a multiple reactor, two-phased, sequenced,

batch fed solids digester capable of producing a fairly constant biogas production rate.

Normal (commercial scale) system operation will be described, followed by the operating

differences for the pilot scale plant.

The APS-Digester is a high solids, high rate digester capable of handling most organic

materials regardless of moisture content or physical characteristics. Figure 1 shows the

schematic of the APS-Digester System. The system is divided into two phases with a semi-

continuous circulation of liquid between the vessels. Feed material is loaded into the

hydrolysis reactor, acted on by extra-cellular enzymes and acidogenic bacteria, thereby

liquefied and converted to simple organic acids. These acids are transferred to the bio-

biogasification reactor, where they are converted further into biogas by methanogenic

bacteria. The biogas is a flammable mixture of methane (CH4) and carbon dioxide (CO2).

Multiple hydrolysis reactors allow for sequential loading such that each reactor is at a

different stage of acidogenesis. The combined organic acids remain relatively constant,

contributing to a level biogas production rate in the methanogenic reactor despite the batch

loading schedule.

The APS-Digester system is designed for the organic material to be loaded into one of

several hydrolysis reactors over a period of days. The nominal system operation is designed

for a 12-day retention time in each hydrolysis reactor. During nominal operation, one of the

four hydrolysis reactors is loaded and sealed every three days. The material is saturated with

pre-heated water and warmed to the operating temperature, digestion begins, and the reactor

8

liquid is circulated to the bio-gasification reactor. A hydrolysis reactor for a commercial

system would be loaded daily, for three days, and then sealed after the final load. Depending

on the feedstock and operating conditions, methane production can occur in both the

hydrolysis and bio-gasification reactors. This may be due to transferring of methanogenic

bacteria in the liquid re-circulated to the hydrolysis reactors. The feedstock material is

retained in the hydrolysis reactor for a predetermined period of time (12 days nominal) and

then after digestion, the remaining material is removed through a screw press for residual

solids dewatering and water recovery.

LIQUID RECIRCULATION FROM BIOGASIFICATION REACTOR

BUFFER

TANK

HYDROLYSIS

R 4

BIOGASIFICATION

REACTOR

HYDROLYSIS

R 2

HYDROLYSIS

R 3

HYDROLYSIS

R 1

Solids

Liquid

RESIDUAL

MATERIAL

DRAINED

FROM

REACTORS

SOLIDS

SEPARATER

LIQUID FED TO

BUFFER TANK

BIOGAS

(CH4+CO2)

FEED

BIOGAS

(H2+CO2))

Figure 1. A schematic of APS-Digester System

The APS-Digester pilot plant at UC Davis will be operated similarly to a commercial size

system with only minor differences due to reactor scale. The digester system will be loaded

either every day or up to three days based on the types of materials to be tested. The loading

sequence will begin by draining the oldest hydrolysis reactor through a screw press. The

solids will be placed in empty bins for return to the compost facility for further handling

while the liquid is transferred to a holding tank. This water will be heated over the next 16

hours to raise the temperature of the feed material to the system operating temperature. The

hot water will be used to transfer the required warm-up heat to the cold feed while helping

carry it into the reactor. After the determined digestion time, the reactor will be drained,

solids removed and the cycle repeated. Each hydrolysis reactor will be similarly cycled with

a one to three day separation between loadings.

The engineering design and construction of the pilot plant is based on the operational

sequence cited above. All effort has been made to minimize differences in the design and

operation of the pilot plant from the commercial scale concept. The largest difference will be

9

in the reactor heat loads. The surface area to volume ratio improves with larger tanks and will

result in decreased heat loss per reactor volume.

3. Pilot Digester Construction Specifications

The pilot digester plant was constructed on a concrete pad. Each sub-system is described

below with critical design criteria and operating parameters.

3.1. Concrete pad

A concrete pad was constructed to accommodate the pilot digester system. This area consists

of two sections, one that is 35 feet x 58 feet and an adjoining section that is 47 feet x 70 feet.

The larger section will be used to hold the material receiving, processing and residue

recovery equipment. A section of this area contains a sloped area that will allow the floor at

the back end of the roll-off to be level with the rest of the pad and allow a skid-steer to enter

the bin without a ramp. Typical roll-off bin floors are 8 inches off ground level. The

designated area is 21 feet x 20 feet. The sloped area begins 5 feet south of the north access

road and slopes down to the south for 20 feet to a drop of 5 inches. The sloped area begins 5

feet from the east side of the pad and continues 21 feet to the west.

The third section located at the South section is 17 feet by 26 feet area houses the biogas

storage tank, clean-up & processing equipment and generator system. The generator was

installed within a metal screen enclosure for personnel safety and equipment security.

Figure 2 . Main frontal view of digester system with loading dock

3.2. Reactor vessels

The physical design of the system is based on using four Hydrolysis Reactors (HT); each

with a working volume of 8,500 gallons. The selected tanks are 10 feet-8 inches in diameter

10

and 16 feet high and set the total system capacity at 3 tons per day for green wastes. The bio-

biogasification reactor volume is equivalent to one of the HT reactors and a suitable used

vessel was identified and procured. All five tanks are installed on the west side of the pad.

The hydrolysis reactors have sloped bottoms and each contains a full-height water jacket. All

the tanks are insulated with foam insulation and all the pipes and fittings that will contain the

warm digester liquids are insulated with ceramic paint. The tanks are mounted on steel stands

that allow a minimum of two feet of clearance under the tanks for construction and future

modifications.

Figure 3. Five anaerobic reactors including four hydrolysis reactors and one biogasification

reactor

To accommodate the blending of water containing organic acids from each hydrolysis reactor

and to control the loading of organic acids into the biogasification reactor, a 900 gallon

stainless steel buffer tank was installed and is located between the reactor and the first

hydrolysis reactor.

11

Figure 4. Buffer tank located between hydrolysis and biogasification reactors

3.3. Boilers and Heat exchangers

The installed boiler system includes two boiler units. The first is a 260,000 Btu boiler that

will operate on propane and will be used in the digester start-up. The second boiler system is

a 700,000 Btu boiler that is designed to operate on the biogas produced. Both boilers are

interconnected to the heat exchanger loop.

Figure 5. Dual boiler systems

12

Figure 6. Propane operated boiler for system start-up

3.3.1. Heat Exchangers

Maintaining a system temperature of 135 °F is critical to the production of biogas and life of

the thermophilic bacteria. To avoid the potential destruction of bacteria, reactor fluids should

not be exposed to heat exchanger surfaces that exceed 150 °F. An independent shell & tube

heat exchanger system was installed for the biogasificationreactor and is connected to the

main hot water loop. The designed heat exchanger is installed at the GT and a dedicated

circulation pump is used to connect the heat exchanger and heat source piping systems.

Figure 7. GT external heat exchanger system

The remaining HT are connected to the main hot water loop and each HT has a full water-

jacket to serve as the tank heat exchanger component. The boiler system heat provides the

hot water source to the tank water jackets. Heating of each HT is controlled through the

13

computer system and was designed with the ability of heating one or more HT

simultaneously. When digester system heating is not required and the engine-generator is off

line for maintenance and /or repairs, excess biogas will continue to be burned in the biogas

boiler. To allow continuous operation of the biogas boiler during this period, an air fan heat

exchanger was installed to allow full operation of the biogas boiler

system.

Figure 8. Air fin heat exchanger system

4. Material Handling and Digester Operational Equipment

4.1. Hydrolysis reactor loading

The demonstration plant is designed to use different proportions of grass and food waste as

the primary feedstock. The operational plan is to load one HT reactor either daily, or every

three days based on feedstock materials and provide for a predetermined solids retention

time.

Figure 9. Delivery of bins containing feedstock materials

14

The feedstock materials will be collected and delivered to the digester in plastic bins, each

bin is 48 inches x 48 inches and 28 inches high and bins have a snap on cover. This allows

for clean delivery of feedstock materials and provides the ability to examine materials, take

samples and monitor material weights and volumes to be loaded.

Figure 10. Bins of waste materials delivered for loading

Once the material is delivered to the site, the bins will be dumped into a receiving hopper that

allows for metering of the materials into either an enclosed drag chain conveyor or a

Vaughan chopper pump system. Loading options will be determined based on feedstock

characteristics.

Figure 11. Forklift dumps bin into receiving hopper

15

Figure 12. Receiving hopper metering feedstock into conveyor system

The conveyor system carries the material to two hydraulic piston pumps. One pump is

located between HT 1 and HT 2, the second pump is located between HT 3 and HT 4. The

conveyor discharges material into the selected hydraulic pump based on which HT is to be

loaded. Once the material is delivered to the piston pump; it is then loaded into the selected

HT.

Figure 13. Conveyor delivers feedstock to hydraulic piston pumps

16

Figure 14. Hydraulic piston pump located at HT 3 and HT 4

Figure 15. Hydraulic piston pump located at HT 1 and HT 2

17

Figure 16. Valve system for HT loading

4.2. Liquid circulation process

Two self-cleaning screen filter systems were installed on both HT 3 and HT 4, and one self-

cleaning screen filter system was installed on both HT 1 and HT 2. Two types of circulation

pumps were installed to provide the ability to test various circulation processes. Each valve

and pump will be connected to the main computer control system and will operate according

to circulation operational protocol.

Figure 17 Screen filter, self cleaning system

During the circulation process, water containing organic acids is extracted from each HT and

delivered to a buffer tank. The pH of water collected from each HT is monitored using

instrumentation that provides real time readouts and sends monitoring data to the SCADA

system through wireless transmission. All readings may be monitored from an instrument

panel while SCADA is performing control operations and data collection in the control room.

This provides information on HT performance and allows controlled circulation of the

organic acids to the GT, allowing for pH control.

18

Figure 18. pH meter and circulation buffer tank

4.3. Internal hydraulic mixing system – HT 1 and HT 2

During the circulation process, water and feedstock material will be drawn from the HT

through a stainless steel pineline and fed to a Vaughan in-line chopper pump. The material

will then be returned to the same HT through a feed line to mixing nozzles installed inside

each HT. Mixing nozzles are installed that can be positioned to provide total mixing of the

HT. This ensures suspension of feedstock materials and prevents crust formation on the

liquid surface.

Figure 19. In-line chopper pipe and pipe system

19

4.4. Hydraulic internal mixing system – HT 3 and HT 4

During the circulation process, water will be decanted through screen units through a

stainless steel line and fed to a pump. Only water will be extracted and circulated while

mixing HT 3 and HT 4.

Figure 20 Hydraulic mixing pump HT 3 and HT 4

4.5. Hydraulic internal mixing system - GT

An independent mixing system identical to the HT 3 and HT 4 mixing systems was

constructed for the GT. The GT system will utilize a dedicated pump and nozzles located at

the bottom level of the tank.

Figure 21 GT hydraulic mixing pump and pipe system

20

Each circulation pump has a dedicated drive installed that is either manually operated or

operated through the main computer control system. Each air actuated valve has been

connected to the main computer control system and will be operated according to the

designated operational protocol. A main air controller system was installed inside the

computer control building.

4.6. Solids residue and water recovery

At the end of each retention cycle, the selected HT will be drained and the solids extracted

from the working fluid using a mechanical screw press. The press will be installed on the

north end of the main drain line providing a straight line to the press. Water extracted from

this process will be sent to the existing reclaimed water tank (RWT). The solids will be

transferred to the empty roll-off bin, which will be picked during the next transfer of

feedstock cycle. The existing reclaimed water tank will provide enough storage capacity for

the reclaimed water recovery process.

Each HT and the GT will be connected to the drain line through a manual gate valve. The

main drain line will exhibit a required slope to the north section on digester site.

Figure 22. HT drain valve and connection to drain system

21

Figure 23. Drain section to be connected to pump and screw press unit

A trash pump will be installed at the end of the drain system to meter the flow of water and

materials into the material recovery system. Just after the trash-pump, the drain line will

connect to a screw press. It was determined that the press will provide solids with a moisture

content that will not drip liquid when transferred to the roll-off box. The water recovery drain

from the screw press will be routed to the RWT through a stainless steel pipe system. A

secondary water line from the RWT will be connected to the south end of the main 8-inch

drain line to provide the ability to flush out the feed/drain system into the press in a closed

loop water transfer cycle.

4.7. Tank pressure/vacuum equalization

To assure that all tanks remain at their design pressure or vacuum, their head pressures are

equalized when fluid is transferred from one tank to another. To accomplish this, each tank’s

head space is connected via the biogas collection system piping. Pressure transducers have

been installed on each digester tank and will be monitored by the computer control system.

4.8. Safety pressure relief valve

Over-pressure and vacuum limitations are designed through the installation of a spring-

loaded valve in the top of each tank. These specially designed valves do not allow the tank to

exceed safe operating pressures or vacuums. Venting of the tank occurs if the pressure

exceeds 54-inches of water column. As an additional safety factor, a flame arrester has been

installed on each digester reactor.

22

Figure 24. Pressure relieve units and flame arrester

4.9. Limiting introduction of air into the system

Every effort is made to avoid introducing air into the tanks and manifolds that contain

methane. During initial filling some air is introduced with the feedstock in the tank. Filling

the tank as full as possible with water after introducing the feedstock is recommended to

minimize the head of air at the onset of digestion. A natural safety feature in the digestion

process is that carbon dioxide is prevalent at the beginning of the digestion cycle and

consequently, explosive methane and air mixtures are more difficult to form. The level of

each tank is monitored by the SCADA computer, which in turn controls the specific levels

through the control of the water supply valves.

4.10. Computer control system

A comprehensive computer monitoring and control system was designed for the CDS

project. A centralized computer control center was constructed within the main operations

building. The computerized control system is designed to monitor all mechanical components

and various processes in the CDS operation from this location. Lighted and animated control

panels will provide indication of the operational status of all mechanical, operational and

process components. The CDS operator(s) will control and oversee the various processes

from this location and make required adjustments and changes as needed. The computer

control software and process protocol is proprietary to OPS and OPS will retain ownership of

all computer software and process protocols.

23

Figure 25 Process flow monitoring screen

The overall digestion process is designed to operate almost entirely automatically by a

computer control system and automated controls components. Various circulations and

hydraulic mixing cycles will be scheduled based on various types of feedstock through a

preset sequence of tanks and processes. Various process protocols identified earlier have

been incorporated into the main computer control system. Each of the circulation and

hydraulic mixing cycles are programmed for automatic performance at required intervals.

Computer control components are designed into all of the valve assemblies, pump and motor

systems and piping sub-assemblies with signal and data connections going to a main

computer control center located in the CDS operations building.

In addition to the control components, a comprehensive sensor and monitoring system has

been designed into numerous components of the CDS tanks, assemblies and sub-assemblies.

This will enable continuous monitoring of the entire CDS and system processes. Monitoring

sensor components have been incorporated into the CDS design to monitor:

Solid and liquid levels in all CDS tanks

Temperature sensors in all CDS tanks

Process flows through circulation piping systems and assemblies

Position indicators on all valve assemblies

Operational performance of hydraulic mixing processes

Operation performance of heat exchanger systems

Gas pressure in all CDS tanks

Sensor and monitoring components on other various CDS assemblies, sub-systems,

mechanical and operational components

CDS component, process and equipment performance and failure notification system

Designed computer controls components include, but are not limited to:

Level sensor systems

Motor starters and variable speed motor controls

24

Valve assembly relays and position indicators

Air operational controls components

ADS processes control and operational components

Safety system valves, pressure relief and emergency operational sensors and

components

Figure 26. Spread spectrum wireless data transmission boxes

Figure 27. Biogas flow, Biohydrogen flow and pH meters

25

Figure 28. Motor control cabinet with HMI interface panel

Figure 29. One of three magnetic flow meters

4.11. OPS proprietary computer controls software and process protocol

Operational components and computer protocol were installed to facilitate remote monitoring

and control capabilities. A USB wireless air card will be used for remote access to the

computer control system. This monitoring and sensor system will send signals to the

computer control system to take any appropriate action, such as emergency shutdown,

changes in operational schedules, diversions of liquid and material flows, gas flow diversions

and as well as notifications to appropriate personnel of the location of any problem.T his

computer monitoring and control system will have the capability to be monitored and

operated remotely by authorized personnel with various levels of passwords and access

codes. Dr. Ruihong Zhang, and her research staff at UCD, will monitor the CDS for process

and operational performance and biological processes and will have to ability to make

adjustments or corrections to the operation remotely. Onsite Power Systems will monitor and

modify the CDS for optimal mechanical and operational performance. This monitoring

system will also provide early detection of potential mechanical problems within the system.

26

5. Biogas Collection and Processing System

As a project requirement, the daily production of biogas will be measured and recorded. The

chemical composition of the biogas will be measured periodically by taking gas samples

from ports installed in the hydrolysis and biogasificationreactor biogas collection lines and

analyzing them with a gas chromatograph (GC). A detailed gas analysis will be used to verify

measured readings and gas composition through the periodic collection and analysis of

samples. Additionally, a gas flow meter will continually monitor the gas production and

record the values at a central supervisory control and data acquisition (SCADA) computer.

5.1. Biogas collection

Each reactor vessel in the system will generate biogas. The biogas quantity and composition

will vary as the digestion process progresses though each cycle. In the early stages of

decomposition, primarily carbon dioxide is generated in the hydrolysis reactors. As time

progresses, the methane content of the biogas increases to approximately 60 to 70% by

volume. As the hydrolysis reactors are sequentially batch loaded, each will exhibit a different

gas composition, while the biogas generated in the bio-gasification reactor remains relatively

constant.

To assure the proper operation of the engine fuelled by the biogas, it is necessary to achieve a

relatively constant volume and quality of biogas throughout the process. This is achieved by

mixing the biogas output from each reactor into a common manifold.

Each reactor has a 2-inch black iron collection pipe installed at the apex of its conical lid,

which is connected to a common gas manifold linking all digester tanks. The biogas

collection manifold is located along the tops of the digester tanks and runs to the gas clean-up

system at the south end of the facility. A manual valve has been installed at each HT and the

GT to allow for gas sample collection.

Figure 30. Biogas collection manifold

27

Each hydrolysis reactor has valves controlled by SCADA to isolate reactors from

biohydrogen (blue pipe) and biomethane (red pipe). Any reactor may be isolated from other

reactors. All reactors are normally open to each other allowing pressure equalization during

filling and emptying operations.

The biogas collected from the HT reactor is passed through and blended with the biogas

produced in the GT. The biogas is then directed from the GT through a water separator with

drain and into a hydrogen sulfide scavenging filter containing iron SulfaTreat material.

Figure 31. Hydrogen sulfide filter with SulfaTreat

Several moisture drain traps were installed throughout the biogas collection system to allow

for the removal of condensate. Biogas from the hydrogen sulfide filter passes through a

coalescent filter trapping small particles and removing more water vapor from biogas stream.

Figure 32: Coalescent filter, expansion tank and drain traps (located on ground)

28

The biogas is then sent through an expansion tank to a pressure regulator , which allows for

14 inches of water column output pressure

Figure 33 Biogas pressure regulator system

5.2. Biogas compression

To assure the best engine-generator performance, biogas must be supplied at a relatively

constant pressure and flow. Pipe losses and filter backpressures may reduce the supply

pressure below the engine’s required value. To assure proper gas flow through the system,

and proper line pressure to the engine, a blower was installed after the filtration system to

raise the biogas pressure to approximately 5 psig. An inline regulator then reduces the

pressure to the working value dictated by the engine load.

Figure 34. Biogas blower unit

29

5.3. Electrical generator

One of the primary goals of the project is to generate electricity from the produced biogas. It

will be considered a design goal to deliver about 22 kW (528 kWh per day) of electric energy

to the grid. The electrical energy delivered to the grid will be measured by the

instrumentation and metering equipment installed on the Cummins generator system .

The generator system will be operated on a full-time basis when feasible, but may not

continuously provide power to the project. During demonstrations or daily operations, the

material processing and loading equipment may be operated using power from the generator

and / or the electric grid. The nominal electrical generating capacity of the system is

anticipated to be 528 kWh per day, with some reduction as required to meet thermal loads

during peak heat requirements.

Figure 35. Engine-generator system with control switch box

30

Figure 36. Engine-generator system with control switch box

5.4. Safety biogas flare

All of the ADG will be used to run the engine/generator, or provide supplemental heating

through a standard gas fired hot water heater. Biogas not used through the generator will be

used in the boiler system. In case of shut-down of both the engine-generator and boiler and/or

the cessation of biogas consumption occurs, a pressure relief valve on the inlet manifold to

the engine will send the biogas to a flare. This will prevent raw biogas from being released

into the atmosphere. A flame arrester check valve is placed in the main gas line going to the

flare and the engine-generator. It is specifically designed to handle low to medium Btu

biogas and extinguish any flame that might back-flash from either source.

6. Safety and Environmental Considerations

6.1. Safety considerations

Operation and maintenance of the digester system may require handling high temperature

water (140 oF), explosive gases (methane), and noxious gases (hydrogen sulfide, and carbon

dioxide). The Report describes the engineering of the Safety Flare, Tank Pressure/Vacuum

Equalization hardware; limiting introduction of air into the system; biogas compression

system; and the computer control system in the section entitled: "Tank Pressure/Vacuum

Monitoring & Equalization." The Pilot Digester Final Report will define the appropriate

operating procedures, which are consistent with California Code of Regulations, Title 8

Sections 5156 and 5158 for Confined Space Entry Program.

Operator safety during plant operation must be insured throughout the 3-ton per day digester

pilot plant. This Report has defined the location of installed Safety Relief Valves in the

"Tank Pressure/Vacuum Monitoring & Equalization" section. This Report also describes the

fencing that encloses the engine generator in Existing Pad Expansion of the "Component

System Specification" section. The Pilot Digester Final Report will define appropriate "Lock-

out - Tag Out" procedures.

31

An operator-training program for loading and residue recovery will be developed as a

component of the Pilot Digester Final Report. The UC Davis Campus Office of

Environmental Health and Safety has inspected the plant and will review the operational

program as well as the entire safety program described as required. This Office requires an

Injury Illness Prevention Program Manual to be on site at all times. This manual has been

developed and is currently located in the Computer Room at the existing pilot digester plant.

The UC Davis Campus, Facilities Services Department, will perform oversight of all

operations at the pilot digester plant. All personnel working at the digester location will be

required to review the Injury Illness Prevention Program Manual and be aware of the location

of the posted "Emergency Contact Information."

6.2. Environmental considerations

Air emission and/odors are potential concerns when the feedstock is loaded into the digestion

reactor vessels and the effluent liquids and solids are removed. This report describes the

engineering for Hydrolysis Reactor Loading, Gas Collection and Processing Systems, Biogas

Collection and Tank Isolation, and Biogas Measurement, in the "Component Design

Specification" section. The prompt placement of the feedstock into a water stream which is

pumped into the Hydrolysis Tank will minimize the potential for air emission. The

engineering of the tank pressure/vacuum equalization system, safety relief valves, safety

flares, and air introduction reduction system is described in the "Tank Pressure/Vacuum

Monitoring & Equalization" section, which shows a closed system design.

Air emissions from the engine generator are discussed in two sections of the Report. The

engineering of the Biogas Clean-up and Electric Generator is described in the “Component

Design Specification" section. The engine generator is to be operated under the Solano-Yolo

Air Quality Management District's Rule 412 for Stationary Internal Combustion Engines.

The air emission from the Safety Flare is described in two sections of this report. The

engineering of the Biogas Clean-up is described in the “Component Design Specification"

section. The engineering of the Safety Flare is described in the "Tank Pressure/Vacuum

Monitoring & Equalization" section. Biogas Clean-up and Safety Flare design comply with

Solano-Yolo Air Quality Municipal District's emissions rules.

The liquid effluent from the pilot digester will be directed to the UC Davis Campus Waste

Water Treatment Plant. The engineering for water recovery is described in the Solids Residue

and Water Recovery section of the "Component Design Specifications" section.

The solids residues from the pilot digester will be transported to the Hay Road Compost

Facility of Norcal Waste System, Inc. in Dixon, California. The engineering for the sludge

recovery is described in the Solids Residues and Water Recovery section of the "Component

Design Specifications" section.

32

7. Equipment and Cost of UC Davis Biogas Energy Plant

This document provides a list of equipment and structures that have been built into the UC

Davis Biogas Energy Plant with a total cost of $1,713,747. The items listed under Equipment

Purchased for UC Davis and Equipment Donated to UC Davis have ownership to UC Davis

and have a total cost of $793,084. These include the equipment and services purchased with

UC Davis fund of $192,199. The items listed under Equipment Purchased and Owned by

Onsite Power Systems have ownership to Onsite Power Systems and have a total estimated

cost of $920,663.

33

34

35

36

8. References

US Patent 6,342,378. Biogasification of Solid Wastes by Anaerobic Phased Solids Digester

System. Issued in January, 2002. Inventors: Zhang, R.H. and Z. Zhang

Zhang, R.H., D. Konwinski, K. Hartman, S. Archibald, H. El-Mashed, G. Matteson. 2005.

Anaerobic Phased Solids Digester Demonstration Project – Pilot Digester Design and Test

Plan. Report submitted to Public Interest Energy Research (PIER) program of California

Energy Commission. March 2005.

9. Acknowledgement

The capital for design and construction of the pilot digester system is provided by the

research grants from California Energy Commission and University of California, Davis and

in-kind and cash funds provided by Onsite Power Systems.

APS-Digester Design and Development Team Members

Onsite Power Systems

Dave Konwinski (President)

Scott Archibald (CEO)

University of California, Davis

Ruihong Zhang (Principal Investigator)

Hamed El-Mashad (Post Doctoral Researcher)

Josh Rapport (Graduate Research Assistant)

Iain Clark (Graduate Research Assistant)

The following companies have made contributions to the design, development and

construction of the digester project.

Brown and Caldwell (Computer controls design)

Rockwell Engineering (Material processing and hydraulic mixing)

Mazzie Injectors (Hydraulic mixing)

Kouba Engineering (Engineering design review)

GraybaR (Instrumentation and controls components)

Advanced Food Technologies (Material processing equipment and design)

Wonderware (Computer control and data collection programs)

37

PLANT LAYOUT

216 F Street, No. 3 Davis, CA 95616 Tel: 559-270 5760 Fax: 530-758-2909

Drawn By: Scott Archibald

UC DAVIS BIOGAS ENERGY PROJECT

1000100NoneScale: 1 of 1

0DDave KonwinskiChecked By:

Released Date:

Date: 01/12/08

01/16/08

01/16/08Date:

Engineer: Scott Archibald

Drawing Title:

Project:

Appendix 1. Layout Diagram of UC Davis Biogas Energy Demonstration Plant