Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment ANC 7D Meeting June 10, 2014

Upload: anacostiawaterfront

Post on 19-Jan-2016

144 views

Category:

Documents


0 download

DESCRIPTION

Presentation on the Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment delivered during the ANC 7D Meeting on June 10, 2014

TRANSCRIPT

Page 1: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

Anacostia Riverwalk TrailKenilworth Aquatic Gardens SegmentANC 7D MeetingJune 10, 2014

Page 2: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

2

Project Team

EJ Simie, P.E.DDOT Project Manager

Josh GormerCH2M HILL – Project Manager

Bryon JohnstonAWI Public Information Manager

Stephanie LewisAWI Workforce Development Manager

Page 3: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

3

Agenda

• AWI Program Update

• Anacostia Riverwalk Trail Overview

• Kenilworth Segment Design

• Construction Progress and Schedule

• DBE and Workforce Management

• More Information

Page 4: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

4

• 30-Year, $10 Billion Program

• Created by March 2000 Memorandum of Understanding Between the District and 19 Other Federal and Regional Agencies

• 5 Key Themes:

o Restore: A clean and active river.

o Connect: Eliminating barriers and gaining access.

o Play: A great riverfront park system.

o Celebrate: Cultural destinations of distinct character.

o Live: Building strong waterfront neighborhoods.

Creating a World-Class Waterfront

Page 5: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

5

AWI Transportation Projects

Page 6: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

6

Anacostia Riverwalk Trail• Backbone of Anacostia

Waterfront

• 15 of 28 Planned Miles of

Trail Open

• Will Connect Tidal Basin

with Northeast Maryland

Border

• Seamless Pedestrian and

Bicycle Travel Between

Popular Destinations and

16 Neighborhoods

• $33 Million of Anticipated

$50 Million Invested to

Date

Page 7: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

7

Kenilworth Trail Segment

• Connects Benning Road in the District with Bladensburg Park in Maryland

• Missing link in 70-mile Regional Trail Network

• 3.9 miles of asphalt-paved trail and ancillary structures

o 3.4 miles in the District

o 0.5 miles in Maryland

Page 8: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

8

Key Project Features • 5 Prefabricated

bicycle/pedestrian bridges

• 1,250 feet of heavy-duty boardwalk

• 2.11 acres of soil restoration and reforestation in Maryland

• Minimal excavation

• Work in Amtrak right-of-way

• Environmental Restrictions Included in Contract

Page 9: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

9

Existing Hayes/Jay Street NE

Page 10: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

10

Future Hayes/Jay Street NE

Page 11: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

11

Project Milestones and Schedule

• Notice to Proceed January 2014

• Construction Start March 2014

• Project Completion Spring 2016

Page 12: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

12

Construction Progress

Erosion Control Near Jay Street NE

Construction Progress Near Jay Street NE

Tree Protection Fencing and Erosion ControlNear Deane Ave. NE

Construction Entrance Near Deane Ave.

Construction Entrance Near Deane Ave.

Page 13: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

13

Disadvantaged Business Enterprise (DBE) Goals

• DBE goal is 15% for both Maryland and the District. Separate DBE plans will be required for each jurisdiction.

• DBE goal must be met in each jurisdiction independently, and no “double-dipping” is allowed.”

• Adherence to DBE goals will be monitored and audited

Page 14: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

14

Workforce Development

• 5 employee training positions are required as part the DC portion of the project:o 2 landscape workers,o 1 laborer,o 1 electrical worker, and o 1 traffic control worker

Page 15: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

15

Good-neighbor Construction

o Limit Impacts to Neighbors and Environment

o Daytime Construction

Safety At All Times

o Dust Control

o Construction Worker Parking in Staging Areas

Minimizing Construction Impacts

Page 16: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

16

More Information

• For more information, visit www.anacostiawaterfront.org/KenilworthSegment

• To receive project updates, ask questions or comment:

o Sign up for the project email list

o Email: [email protected]

o Call: 202-741-8528

Page 17: Anacostia Riverwalk Trail Kenilworth Aquatic Gardens Segment Presentation - ANC 7D Meeting

QUESTIONS?