West Des Moines Community School District

Community Workshop 26February 2002

Estimating School Facility CostsProcess

• What is Included in a Construction Budget ?

• Construction Budget vs. Total Project Budget?

Frequently Asked Questions

Frequently Asked Questions

•Quality Standards used?

•Typical budget variables ?

Frequently Asked Questions

How could it get so expensive??

Why do costs look lowerin other district projects??

Budgeting… Apple vs. Bite

West Des Moines Community School District

Project Budget

Construction Budget

Process…from general to specific…

INPUT

FINAL PRODUCT

Typical School Consultant Team

Architect

Interior Design

Landscape Architects

Civil Engineering

Mechanical Engineering

Electrical Engineering

Structural Engineering

Specialty Consultants

Construction Management

Educational Programming

Food Service Design

Theater/Acoustical Design

Code Review

Special Inspections

Hazardous Material

• RDG Consult Inc.

• Capital Resource Group LLC

• RDG Bussard Dikis Inc.

• The Weitz Company Inc.

• KJWW Engineering Consultants PC

• Siemans Building Technologies Inc.

• IBM /Exp@nets

Consultant Team (Ten Year Planning Team)

West Des Moines Community School District

BUDGET

West Des Moines Community School District

BuildingConstruction

(building only)

Site Purchases/Easements/

Re-zoning costs

SiteUtilities

SiteImprovements

Furnishings(moveable) Fixed

Equipment

Fees

SurveysTesting

Filing Fees

InterimFinancing/

DebtServicesSupplies/

Materials/Moving Costs

Contingency/Reserve

BUDGET

West Des Moines Community School District

The Magic Formula

Quantity x Quality = Costs

(area) x (value) = (budget)

(gross sf)x (cost/sf) = dollars

QU

AN

TIT

Y

QUALITY

CO

STS

1. Architect & Engineers fees

2. Project Manager's fee

3. Reimbursable costs

4. Technology design fees Soil

Testing

5. Traffic Studies

Owner’s Costs

West Des Moines Community School District

Budgeted at 9%

6. Surveys

7. Asbestos Abatement

8. Life cycle cost analysis

9. Commissioning (if used)

10.Environmental studies and testing

11.Special consultants or testing

required

12.Legal fees

Owner’s CostsBudgeted at 9%

Program

• Student teacher ratios

• Schedule/occupancy expectations

• Curriculum expectations/offerings

• Arts, Activities, Athletic offerings

• Site, pools, auditoriums, spectator

counts, support

• Food Service expectations

• Technology

Budget Variables that Effect Cost Models

Climate/Geography• Footings, soils• Interior or exterior hallways• Mechanical systems• Insulation/vapor barriers• Wind/structural/storm/seismic• Roof/enclosure specifications

Budget VariablesCompared to National project data base

•Reputation as Leaders in Learning, facilities that support that ambition

• If national recognition is to be pursued it will be for the assimilation of design as it supports the pursuit of the learning program

Quality/Aesthetic and Life CycleWDM Design Guidelines

West Des Moines Community School District

Quality/Aesthetic and Life Cycle

West Des Moines Community School District

•Cleanable, washable, easy to maintain

• Energy efficient

• Sustainable, Durable

• Long Term Pay Backs

•Materials selected for their “Timelessness”

• Foundations and Substructures

• Superstructures (columns, beams, etc)

• Exterior Enclosures (“skin” ) Roofing

• Interior Construction (walls, ceilings)

What is included in a Construction Budget?

West Des Moines Community School District

Building only, typically estimated in 16 specification divisions

•Conveying (elevators, equipment)

•Mechanical

• Electrical

• Specialties (“chalk” boards, etc.)

•Contractors costs (Mgmt., Gen. Cond.)

What is included in a Construction Budget?Building only, typically estimated in 16 specification divisions

Costs of “Typical New” School Zones

• Classrooms $115-130/

sf

• Auditoriums

house/stage

$175-215/sf

support

$115-130/sf

• Kitchen $150-180/

sf

• Gyms $ 95-125/sf

• Wrestling $ 90-110/sf

• Mech Rooms $ 70-85/sf

Costs of “Remodel” School Zones

* Usually includes mechanical/electrical

Demolition $3-6/sf

New Construction last

slide

Level L-1 Remodel

$10-20/sf

Level L-2 Remodel

$25-50/sf

Level L-3 Remodel

$50-70/sf

Tech/Data /Telcom $2/sf

Contingency/Project Reserve

CO

ST

TIME

15%

15% 35% 75% 100% complete

3.5%

Design Construction

New Construction $120.00 15,000 $1,543,108Comm./Fire Alarm/Technology $2.00 24,000 $48,000Reno Level 1 (Finishes) $20.00 24,000 $480,000Reno Level 2 $50.00 24,000 $1,200,000Reno Level 3 $70.00 24,000 $1,680,000Elevator est. est. $65,000Site (Sod, no new playfields) est. est. $250,000Sub-Total One $ 5,266,108

Contingency (15% of Sub Total One) 15% $ 789,916

Owner’s Costs (9% of Subtotal One plus reserve) 9% $545,042

Furniture/Equipment (project specific estimate) $500,000

Total Project Costs $7,101,066

(Quality) (Quantity) Total Est.Description Unit Cost Area Cost

Remodel Budget (Generic Example)

X =

Total Total Est.Description Unit Cost Quantity Cost

New Construction Budget (Generic Example)

New Construction (Academic Area) $120.00 50,000 $6,000,000New Construction (Auditorium) $200.00 16,000 $3,200,000Telecom/data $2.00 66,000 $132,000

Site (Lump Sum Estimate) est. est. $400,000

Sub-Total One $ 9,732,000

Contingency/Reserve (15% of Sub Total One) 15% $1,459,800

Owner’s Costs (9% of Subtotal One plus reserve) 9% $1,007,262

Furniture/Equipment est. $500,000

Total Project Costs $12,699,062

West Des Moines Community School District

Budgeting…

Project Budget vs.

Construction Budget

West Des Moines Community School District

West Des Moines Community School District

West Des Moines Community School District

Building Area: Net vs. Gross

Net

Gross

Typically 70% of building areaequals “programmed” space

30% = halls, toilets, walls, stairs, mechanical rooms, etc…

Classrooms

Typical Design Team Time Allocations

Doing the Real Project

Schematic

15%

Design Development 20%

Construction Documents 40%

Bidding

5%

Construction

20%

Master Planning/Programming

Budgeting:

West Des Moines Community School District

The Magic Formula

QU

AN

TIT

Y

QUALITY

CO

STS

West Des Moines Community School District

The Magic Formula

QU

AN

TIT

Y

QUALITY

CO

STS

West Des Moines Community School District

a. Storage of furniture, fixtures & equipment

b. Watchmen/security

c. Building permit & special permits

d. Printing costs

e. Insurance - Builders risk & general liability

f. Performance bonds

g. Material & special testing

h. Test & balance of HVAC system

i. Hook up or connection fees to City services

General Conditions

a. Storage of furniture, fixtures & equipment

b. Watchmen/security

c. Building permit & special permits

d. Printing costs

e. Insurance - Builders risk & general liability

f. Performance bonds

g. Material & special testing

h. Test & balance of HVAC system

i. Hook up or connection fees to City services

Typically budgeted at 12% of construction costs