TRANSPORTATION &

CAPITAL IMPROVEMENTS

(TCI)2012 – 2017 Bond Projects

–1

2012 – 2017 Bond Projects

MAIN/SOLEDAD: COMMERCE TO

PECAN STREET

MAIN/SAN PEDRO/NAVARRO

ROUNDABOUT UPDATE

September 27, 2016

Presenter: Peter Rodriguez

Capital Project Officer

Location: Central Library

600 Soledad

Agenda

• TCI Introductions

• Main/Soledad: Commerce to Pecan Street Project

– Project Map

– Existing Conditions

– Planned improvements

– Sequence of Work

– Schedule

–2

– Schedule

• Main/San Pedro/Navarro Roundabout Project Update

– Project map

– Project scope

– Planned improvements

– Schedule

• TCI Commitments

• Public Comments and Questions

22

• City Council District 1

• Office of Councilman Roberto C. Treviño

• TCI Design/Construction Team

David Mc Beth P.E. – Project Manager

Florencio Rodriguez P.E. – Project Engineer

Peter Rodriguez – Capital Projects Officer

• Steven Cordell - TCI Inspector

TCI Introductions

–3

• Steven Cordell - TCI Inspector

• Main Ave. & Soledad

Design Consultant – Poznecki Camarillo – Fernando Camarillo P.E. – Project Manager

• Contractor

E-Z Bel Construction – Randy Hood

• Main/San Pedro/Navarro Roundabout

Design Consultant – CDM Smith – Matt Hunter P.E. – Project Manager

3

Main/Soledad: Commerce to Pecan St.

Main Street Soledad Street

–4

Project Construction Cost: $9.5 million allocated in the 2012 – 2017 Bond

Project Location Map

WESTON CENTRE

ROBERT E. LEE

HOTEL

–5 5

EMBASSY SUITES

FROST BANK

RIVERVIEW

TOWERS

HOTEL

Existing Conditions Main Ave. & Soledad

–6 66

Main Ave. & Soledad Streets:

• One-way streets

• Outdated drive approaches

• Cracks on street pavement

• Broken and cracked sidewalks

• Outdated sidewalk ADA wheel ramps

• Lack of pedestrian and bicycle connectivity

• Outdated storm drainage system

• Curbside Parallel Parking

•Main Ave.• Total roadway reconstruction (Commerce St. to Pecan St.)

• Conversion from one-way to two-way traffic operations.

• 10’ foot wide traffic lanes in each direction

• Variable width sidewalks and paver bands

• 5’ foot wide bike lanes in each direction

Planned Improvements

–7

• 5’ foot wide bike lanes in each direction

• Bulb-outs for street side parallel parking

• Install new storm drain inlets to reduce localized flooding

• Curb and gutter, sidewalks and incidental driveway construction

• Landscaping plan

• Street and pedestrian lighting and amenities (bike-racks, benches)

• ADA compliant wheelchair ramps

• Main: Pecan to Navarro (fog seal /restriping)

7

• Soledad Street• Total roadway reconstruction (Commerce St. to Pecan St.)

• Conversion from one-way to two-way traffic operations

• 10’ foot wide traffic lanes in each direction

• Continues left turn lane

• Variable width sidewalks and paver bands

Planned Improvements

–8

• Variable width sidewalks and paver bands

• Bulb-outs for street side parallel parking

• Install new storm drain inlets to reduce localized flooding

• Curb and gutter, sidewalks and incidental driveway construction

• Landscaping plan

• Pedestrian lighting and amenities (bike racks, benches)

• ADA compliant wheelchair ramps

• Soledad: Pecan to San Pedro (fog seal/restriping)

8

Planned Improvements

–9 9

Planned Improvements

–10 10

Planned Improvements

–11 11

Planned Improvements

–12 12

Traffic Control Plan/Sequence of Work

Sequence of Work (*all durations are weather permitting)

Phase 1– Soledad: Commerce to Pecan Street – duration approx. 3 months (mid Oct 2016- mid Jan 2017)Construct CPS gas and SAWS sewer mains and laterals

Phase 2 – Soledad: Commerce to Pecan Street (West Side) – duration approx. 5-1/2 months (mid Nov 2016-end of Mar 2017)*

–13 13

5-1/2 months (mid Nov 2016-end of Mar 2017)*Construct storm sewer inlets, roadway, curb and gutter, sidewalks and drive approachesConstruct Travis Street

Phase 3 – Soledad: Commerce to Pecan Street (East Side) – duration approx. 2-1/2 months (end of Mar – mid-June 2017)*Construct SAWS water main and laterals storm sewer inletsConstruct roadway, curb and gutter, sidewalks and drive approaches

Traffic Control Plan/Sequence of Work

Sequence of Work (*all durations are weather permitting)

Phase 4 – Main Ave.: Commerce to Houston St. – duration approx. 1 month ( Jan – Feb 2017)*o Construct CPS gas and SAWS water mains and sewer laterals.

Phase 5 – Step 1 Main Ave.: Commerce to Pecan (West Side) – duration approx. 4-1/2 months (mid May-Oct 2017)*o SAWS water work construction

–14 14

o SAWS water work constructiono Construct storm sewer inlets, roadway, curb and gutter, sidewalks and

drive approacheso Construct Travis Street and Salinas Street intersections

Phase 6 – Step 1 Main Ave.: Commerce to Pecan (East Side) – duration approx. 2-1/2 months (end of Aug-mid Nov 2017)*o Storm drain inlet worko Construct storm drain inlets, roadway, curb and gutter, sidewalks and

drive approaches

Traffic Control Plan/Sequence of Work

Sequence of Work (*all durations are weather permitting)

Phase 7 – Soledad: Commerce to Pecan Street – duration approx. 6-1/2 months (May - mid Nov 2017)*o Install Traffic signals on Soledad from Commerce to Martino Install traffic signals on Main Ave for Commerce to Martin

Install small signs

–15 15

o Install small signso Install final riding surface of asphalto Install final stripingo Final Clean up

Main Ave. & Soledad

• Contractor shall provide access at all times to include pedestrian

access, drop off and deliveries

• TCI has notified all affected services (EMS, USPS, etc.), Council

Office

TCI Project Commitments

–16

Office

• Any property owners or stakeholders with special needs will be

identified

• Contractor to notify property owners 48 hour in advance of

driveway construction

• Message boards will be installed to notify public of upcoming

construction

• TCI has coordinated with other TCI divisions and B-Cycle

16

Historic Tiled Entryways

Robert E. Lee Hotel

Alpha Hotel

–17 17

Project Schedule

Main Ave. & Soledad ScheduleMain Ave. & Soledad Schedule

Construction start October 17th 2016

Estimated construction

completion*

November 2017

* Weather permitting

–18 18

For information in regards to the project during the Construction Phase: Please contact: Pete Rodriguez – TCI Capital Projects Officer at 210-207-8154

Pete.Rodriguez@sanantonio.gov

If you would like to be added to an e-mail list for project updates or future meeting

announcements, please ensure you fill out the sign-in sheet and check the permission

block.

Main/Navarro/San Pedro Roundabout Update

–19

Project Location Map

BAPTIST

CENTRAL CHRISTIAN

CHURCH

–20 20

CENTRAL LIBRARY

FOX TECH H. S.

BAPTIST

HOSPITAL

A.P.I.

Project Scope:

Main/San Pedro/Navarro Roundabout

This project includes full reconstruction of the intersection of San Pedro Ave and N. Main

Ave. This is a 5-leg intersection, two of the legs being N. Main, the other three being San

Pedro Ave., Camden, and Navarro. The reconstruction will include raised medians to better

Project Scope

–21 21

facilitate traffic and pedestrians. Included in this project will be a 10’ share use path to

improve bicycle and pedestrian connectivity, curb and gutter, incidental driveway

construction, landscaping, pedestrian lighting and amenities, and this project will include a

public art component.

SAWS sewer and water work

CPS Gas and over head adjustments

Project Budget:

$6,000,000 allocated in the 2012 – 2017 General Obligation Bond

Planned Improvements

–22 22

Roundabout (Rendering – Plan View)

Project Schedule

Main/San Pedro/Navarro Design ScheduleMain/San Pedro/Navarro Design Schedule

Project Bidding November 2016

Construction start January 2017

–23 23

Construction start January 2017

Estimated construction

completion*

October 2017

* Weather permitting

Questions or Comments

–24

TCI Thanks You for Your Attendance