Transportation. Chapter 7. Sponsored by the National Science Foundation, Directorate for Education and Human Resources, project DRL-0733137. Chapter 6 Organization. A brief history of the transportation problem An engineering modeling approach to problem-solving using mathematics - PowerPoint PPT Presentation

TRANSCRIPT

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

TRANSPORTATION

Sponsored by the National Science Foundation, Directorate for Education and Human Resources, project DRL-0733137

CHAPTER 7

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

Chapter 6 Organization

• A brief history of the transportation problem• An engineering modeling approach to problem-

solving using mathematics• Modeling and engineering• A transportation problem from an engineering

modeling perspective• 7.1 Example Transportation Problem• 7.2 Integer Solutions• 7.4 Validating Models• 7.5 Sensitivity Analysis

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 Example Transportation Problem

• We need to transport oranges from California (CA) and Florida (FL) to Michigan (MI), Missouri (MO), and North Carolina (NC)

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 Example Transportation Problem

• Supply of oranges▪ CA – no more than 50.3 tons of oranges▪ FL – no more than 49.7 tons of oranges

• Demand of oranges▪ MI – at least 33.6 tons of oranges▪ MO – at least 36.3 tons of oranges▪ NC – at least 30.1 tons of oranges

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 Example Transportation Problem

• Since the oranges are shipped by truck, costs to consider include

• Shipping costs per tons of oranges

▪ diesel fuel ▪ wear and tear

▪drivers’ wage ▪ insurance

From/To MI MO NC

CA $10/ton $9/ton $12/ton

FL $8/ton $8/ton $6/ton

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 Example Transportation Problem

CA(50.3)

$12×NofTCA, NC

$6×NofTFL, NC

$8×NofTFL, MO

$9×NofTCA, MO

$10×NofTCA, MI

Shipping CostsNofT => Number of Tons

Demand in tonsSupply in tons

$9×NofTFL, MI

FL(49.7)

MI(33.6)

MO(36.3) NC

(30.1)

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 Example Transportation Problem

CA(50.3)

$12×NofTCA, NC

$6×NofTFL, NC$8×NofTFL, MO

$9×NofTCA, MO

$10×NofTCA, MI

Shipping Costs NofT => Number of Tons

Demand in tonsSupply in tons

$9×NofTFL, MI

FL(49.7)

MI(33.6)

MO(36.3) NC

(30.1)

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 Example Transportation Problem

CA(50.3)

$12×NofTCA, NC

$6×NofTFL, NC

$8×NofTFL, MO

$9×NofTCA, MO

$10×NofTCA, MI

Shipping CostsDemand in tons

Supply in tons

$9×NofTFL, MI

FL(49.7)

MI(33.6)

MO(36.3)

NC(30.1)

NofT => Number of Tons

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – LP Formulation

• Define ▪ Decision Variables, Objective Function,

Constraints• Create Excel Spreadsheet

▪ Input decision variables, objective function, constraints, RHS constraint values

• Use Solver to find the solution▪ Output final values, objective function value,

LHS constraint values• Analyze results using Answer and Sensitivity Reports

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Decision Variables

• Let xij be the number of tons of oranges shipped from supply state i to demand state j

▪ i = 1 (CA) or 2 (FL)▪ j = 1 (MI), 2 (MO), 3 (NC)

• Much better than the notation NofTCA, MI

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Objective Function

• Total Shipping Costs per route

• Minimize Shipping Cost

▪ z = $10x11 + $9x12 + $12x13 +

$9x21 + $8x22 + $6x23

From/To MI MO NC

CA $10x11 $9x12 $12x13

FL $9x21 $8x22 $6x23

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Supply Constraints

• CA and FL have a limited number of tons of oranges to distribute to demand states

▪ CA has a maximum supply of 50.3 tons

x11 + x12 + x13 ≤ 50.3 tons

▪ FL has maximum supply of 49.7 tons

x21 + x22 + x23 ≤ 49.7 tons

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Demand Constraints

• MI, MO, and NC have a minimum number of tons of oranges to receive from the supply states

▪ MI has minimum demand of 33.6 tons

x11 + x21 ≥ 33.6 tons

▪ MO has minimum demand of 36.3 tons

x12 + x22 ≥ 36.3 tons

▪ NC has minimum demand of 30.1 tons

x13 + x23 ≥ 30.1 tons

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – NonNegativity Constraints

• Cannot have a negative amount of oranges

▪ xij ≥ 0 where i = 1, 2 and j = 1, 2, 3

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Excel Formulas

= SUMPRODUCT($B$7:$G$7,B9:G9)

= SUMPRODUCT($B$7:$G$7,B12:G12)

= SUMPRODUCT($B$7:$G$7,B16:G16)

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Excel Solver

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.1 EX Transportation Problem – Solution

• The minimum cost for shipping 100 tons of oranges from the supply states to the demand states is $823.70

• More specifically

From/To MI MO NC

CA 14 tons 36.3 tons 0 tons

FL 19.6 tons 0 tons 30.1 tons

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.2 Integer Solutions

• What if we wanted our number in tons to be an integer value?

• How would our LP formulation change?

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.2 Integer Solutions - Objective Function

• Total Shipping Costs per route

• Minimize Shipping Cost

▪ z = $10x11 + $7x12 + $15x13

+ $8x21 + $10x22 + $5x23

From/To MI MO NC

CA $10x11 $7x12 $15x13

FL $8x21 $10x22 $5x23

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.2 Integer Solutions - Solution

• The minimum cost for shipping 100 tons of oranges from the supply states to the demand states is $790

• More specifically

From/To MI MO NC

CA 10 tons 7 tons 15 tons

FL 8 tons 10 tons 5 tons

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

7.4 Validate Our Model

• Use data from government websites to validate the shipping costs per ton

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

In Summary

• Transportation problems are specific types of linear programming problems that address moving products from supply to demand

• The problems in chapter 7 are all balanced transportation problems

MINDSET (Mathematics INstruction using Decision Science and Engineering Tools)

www.MINDSETproject.org

Practicing Transportation

• Optional – Read pp. 1 – 5 for background information

• Work on problems 7.17 – 7.23 (pp. 6-10 – 6-12), Cape Fear River Basin Water Supply Plan, individually or in pairs

▪ In the HW solutions, the answer to 7.21 is incorrect. The optimal solution should be $32,000 - not $36,000.

▪ When solving these problems, make sure to increase your precision (add more zeros)