Structural Designer and Design Supervisor: Prof. Franco Mola

ECSD Srl Staff: L.M. Pellegrini, P. Banti, G. D’Agostino, G. Sconocchia, G.

Matessi, A. Da Campo, F. Palma, E. Mola, C. Pozzuoli

University of Patras

16 May 2014 – h. 11:00-18:00

Technical-scientific seminar on

Analysis and design of tall building structures

NUOVA TORRE REGIONE PIEMONTE: THE NEW

HEADQUARTES FOR REGIONE PIEMONTE (2010-14)

ECSD S.r.l.

Via Goldoni, 22 Milano

Ph. +390273954653

Fax. +390270008547

www.ecsd.it

mailto: info@ecsd.it

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER, TORINO

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER: ARCHITECTURAL PROJECT

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • Foundations

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • Foundations

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • Foundation pile load test

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Diagrams of the vertical subsidence of the foundation

plate in the two orthogonal directions passing through

the central node of the plate

Envelope of the plate

deformation in the z direction

(vertical displacement) - Dir

South-West - under

permanent load

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • Foundation analysis

• Modelling

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • SCC in massive element

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Massive foundation:

12000 m3

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• The effects of the heat of hydration

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Temperature

Stresses

+ +

-

REGIONE PIEMONTE HEADQUARTER

CONSTRUCTION PROJECT • The effects of the heat of hydration

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • Vertical bearing elements: the core

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER

CONSTRUCTION PROJECT • Vertical bearing elements: columns with

composite steel and concrete sections

section up to Liv.06

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Vertical bearing elements: columns of

reinforced concrete above the Liv.06

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• II Order Analysis and structural safety

results

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• II Order Analysis and structural safety

results

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Standard Floor: lightened slab, h = 34 cm,

prestressed with unbounded cables

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Standard Floor: lightened slab, h = 34 cm,

prestressed with unbounded cables

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Standard Floor: structural analysis for

ultimate and service limit state

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Maximum analytical vertical

displacement: 3 mm

Maximum measured

displacement: 2.14 mm

Residual displacement: 0.06

mm

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Standard Floor: Load Test

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • The cantilevered prestressed concrete floor structures (“Jump-deck floors”)

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Joint Sections

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• The cantilevered prestressed concrete floor structures (“Jump-deck floors”)

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Finite Element Model

implemented in

MidasGen

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Core

elements

East

Facade

elements Global

Model

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Finite Element

Model implemented

in MidasGEn

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Finite Element Model

implemented in MidasGEn

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Design actions: permanent

loads, live loads and façade

weight

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Design action: wind load Eurocode

Wind tunnel test

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Lateral displacements of the core

and of a central column of the tall

building, including foundation

deformation, in the service load

condition.

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Finite Element Model

implemented with MidasGEn

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Vertical Elastic Displacement s(dir. Z)

of a central column and of the core,

under the load combination:

Gk + 0.3 Qk

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• Finite Element Model

implemented with MidasGEn

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • The Steel Structure of the East Façade

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT • The Steel Structure of the East Façade

Details of the connections to the “Jump-Deck Floors”

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Wind y-direction: acting

on the long side

Displacements of the supporting structure of the facade

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• The Steel Structure of the East Façade

Service Limit State: Compatibility of Deformations

ECSD S.r.l. Via Goldoni, 22 Milano – www.ecsd.it – mailto: info@ecsd.it

Design Steps

Tolerances:

• +10.2, -16.8 mm, vertical

joint, Control 1, in plane;

• 11.5 mm horizontal joint,

Control 2, in plane;

• 5 mm, Control 3, out of

plane;

• 10 mm, Control 4, pairs of

plates out of plane (V);

• 5 mm, Control 5, pairs of

plates out of plane;

• 5 mm, Control 6, vertical

delta.

REGIONE PIEMONTE HEADQUARTER – CONSTRUCTION PROJECT

• The Steel Structure of the East Façade

Service Limit State: Compatibility of Deformations