    Secant Pile ConstructionOSIS Augmentation & Relief Sewer (OARS) Phase 2 Shafts # 3, 4 & 5

    DFI ADSC Drilled Shaft SeminarSupport with Confidence

    July 11-12, 2013

    SecantPilesConstruction

    Structuralfoundationelementconsistingofoverlappingpilesformingacontinuouswall.

    Reinforcedconcrete(rebarcagesorsoldierpiles). Depthdependsuponfinaldesign&soilandequipment

    characteristics. Pilesdiametersusuallybasedonmetrictoolingsize.Typically

    760,880,1000and1180mmareused.Othersizesareavailable.

    Secantpileswallstobecantileveredorbraced.Anygeometricshapeispossible.Themoreuniquetheshapethemoredifficultthebracingsystembecomes.

  • 2

    SecantPilesConstruction

    Selectionofsecantpilesvs.otherearthretentionsupportsystemsisbasedon: Availableworkspace/sitelogistics Layoutofwall Impactrestrictionsonadjacentstructures Designparameters(stiffnessofwall,cutoffrequirements)

    Materialhandlingrequirements Excavationcapabilitiesindifficultsoilconditions

    SecantPilesConstruction

    Sequenceofconstruction Guidewallsinstallation Primaryorlaggingpilesinstallation

    Sectionalcasingrotationinadvanceofaugerremovingsoilinsideofthecasing

    Dryorwetdrillingdependinguponsoilsconditions

    Atdrillingcompletion,cleaningofpilebottom&placementofconcrete Freefallplacementindryconditionandwithatremie pipeinwetconditions

    Extractionofcasingatpourcompletion Secondaryorclosingpilesinstallation

    Sectionalcasingrotationinadvanceofaugerremovingsoilinsideofthecasing

    Dryorwetdrillingdependinguponsoilsconditions

    Atdrillingcompletion,cleaningofpilebottom&placementofreinforcementfollowedbyconcrete

    Freefallplacementindryconditionandwithatremie pipeinwetconditions

    Extractionofcasingatpourcompletion

  • 3

    SecantPilesConstruction

    Sequenceofconstruction Guidewallsinstallation

    SecantPilesConstruction

    Sequenceofconstruction Primaryorlaggingpilesinstallation

    Pilestypicallyunreinforced Lowerstrengthconcretecanbeused.Dependentondesignandfinal

  • 4

    SecantPilesConstruction

    Sequenceofconstruction Primaryorlaggingpilesinstallation

    Sectionalcasingrotatedaheadofaugercleaninginsideofcasing

    SecantPilesConstruction Sequenceofconstruction

    Primaryorlaggingpilesinstallation Sectionalcasingrotationaheadofaugercleaninginsideofcasing

  • 5

    SecantPilesConstruction Sequenceofconstruction

    Secondaryorclosingpilesinstallation Pilesarereinforcedusingrebarcagesorsoldierpiles Highstrengthconcreteistypicallyused

    Secondary Piles

    Primaryiles

    SecantPilesConstruction Sequenceofconstruction

    Secondaryorclosingpilesinstallation Designmayrequiredallpilestobereinforced,inthatcasethelaggingpileswillbe

    pouredusingstructuralconcrete

  • 6

    SecantPilesConstruction

    Sequenceofconstruction Secondaryorclosingpilesinstallation

    Pilesoverlapiscriticaltoguaranteecontinuityofwall Overlapisdependingofdepthofdrilledpilesanddrillingverticalitytolerance

    SecantPilesConstruction Sequenceofconstruction

    Secondaryorclosingpilesinstallation Loadbearingcaissonscanbeeasilyincorporatedintosecantwall

  • 7

    SecantPilesConstruction

    CaseHistory

    Project: OSISAugmentation&ReliefSewer(OARS)Phase2Shafts#3,4&5

    ProjectInformation: 397Each 1180mmShafts

    3independentsiteslocatedapproximatelymilefromeachother

    Eachsecantpilewallsystemcomprisedofandropshaftandapproachchannel.

    Eachsecantpilefortheaccessshaftwaskeyed5intoshalebedrock.

    AverageSecantPileDrillLengthwas62.

    OARSPhase2CaseHistory ShaftLocations

  • 8

    OARSPhase2Project SubsurfaceProfile

    DropShafts: SecantPileCompressionRingDesign

    All4,500psiConcrete

    Noreinforcementrequiredfordesignaslongverticalitytolerancemet,

  • 9

    OARSPhase2Project Shaft3Layout

    85 each Secant Piles @ 53 Long

    OARSPhase2Project Shaft4Layout

    173 each Secant Piles @ 64 Long

  • 10

    OARSPhase2Project Shaft5Layout

    139 each Secant Piles @ 65 Long

    OARSPhase2Project KODENUltrasonicDeviceVerticalityControl

  • 11

    OARSPhase2Project JeanLutzGyroscopeVerticalityControl

    OARSPhase2Project KODENUltrasonicDeviceOutput

    Pile #17B:Pile Depth = 57.83ftDeviation in x' direction = .78inDeviation in y direction = 1.57inTotal deviation = 1.75 < 7.08in = accepted

  • 12

    OARSPhase2ProjectPhotos

    OARSPhase2ProjectPhotos

  • 13

    OARSPhase2ProjectPhotos

    OARSPhase2ProjectPhoto

  • 14

    OARSPhase2ProjectPhoto

    OARSPhase2ProjectPhoto

  • 15

    OARSPhase2ProjectPhoto

    QUESTIONS?