By: Tamer Farid Rev. 6
G1201Adams Challenge
Event Description [Contract] Key Date
Effective Date of Agreement 5-Nov-14
Start of Cutting Project Steel 15-Dec-14
Mobilization of Sleeper / Riser Installation Marine Spread 14-Aug-15
Completion of Full Deck Main Structure + Full Jacket Fabrication 7-Sep-15
Mobilization of Pipeline / Platform Installation Marine Spread 8-Sep-15
Installation of Jacket at the Worksite 10-Oct-15
Completion of Installation of All Pipelines 21-Nov-15
Installation of the Rashid-C Deck at the Work Site 24-Nov-15
Pre-Commissioning of All Pipelines 26-Dec-15
Mechanical Completion of All Facilities 26-Dec-15
Handover of All Project Documentation 4-Feb-16
DSV Adams Challenge
Sleepers Installation
SMART Flange Preparation
Risers Installation
Bowstring Installation
Production Spools
Metrology, Closing Spools, Jacket Grouting, Crossing
Completion, Susea Protection Frames & Bowstring Removal
Pre-commissioning Support
DSV Oceanic Installer
Subsea FCG of 14" & 20" Replacement Pipelines
Metrology, Fixed & Closing Spools Installation
G1201
Rashid C Jacket & Boat Landing Installation
Pipelines Installation (30", 20" & 14")
Pipelines Installation (18", 10" & 12")
Deck Installation
Pre-Commissioning
30", 20" & 14"
18", 12" & 10"
Feb-16 Mar-16Jan-16May-15 Dec-15Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15
Jacket
Topsides
Piles
Risers
Tie-in Spools
Installation AidsPre-Engineering
Survey
Geophysical & ROV Jacket Face
Surveys
Bowstring Installation (4 nos.)
Concrete Sleepers Installation102 Km of Pipelines; 30", 20", 18", 14",
12" & 10"In-line Barred Tees (6 nos.)
Risers (8 nos.) + Riser Clamps (29 nos.)
Free Span Corrections
Tie-in / Closing Spools
Production Spools
Smart Flanges (8 nos.)
Valve Assemblies
Subsea Protection Frames (6 nos.)FCG & Hydrotest of all Pipeline
Systems.De-watering & Nitrogen Purging of 10"
Gas Lift Pipeine System.As-Built Survey ROV & CP Potential Surveys
Pre-Commissioning
Fabrication
(Dubai Dry Docks)
DSV Preparatory
Works
Scope of Work
DSV Works
Pipelying