Wyoming DOT Connected Vehicle Pilot Deployment Program

PROJECT STATUS UPDATEAUGUST 27, 2019

Project Background

2

I-80 Corridor

Runs 402 miles along Wyoming’s southern borderMore than 32 million tons of freight per year Truck volume is 30-55% of the total traffic stream on an annual basis• Seasonal peaks as high as 70%

3

System Deployment

4

Application Overview

5

6

On-Board ApplicationsDistress Notification

Vehicle 2

Vehicle 2

Vehicle 1

• Generation and broadcast of distress message • CV and RSU within vicinity receive and forward message

7

On-Board ApplicationsDistress Notification

Vehicle 2

Vehicle 2

Vehicle 3

Vehicle 1

• CV and RSU within vicinity receive and forward message

Project Team Members

8

WYDOT Team

9

No Boundaries

Equipment Traffic Telecom

Patrol GIS/ITSDistrict

Personnel

Rigging Shop IT Public

Affairs

Operations Systems Update

10

System Design

11

Leverage Open Source Software

Use Standards

Integrate with Existing Systems Agile Development

Acceptance Testing

TMC Integration

12

Pikalert

13

Pikalert

14

RSU Management

15

Next Steps for Deployment

169/19/2019

Equip 400 partner vehicles with CV

TechnologyDriver training

Operate the system for

demonstration period

Collect data and assess

performance

Plan for long-term sustainability

Connected Vehicle Pilot

17

visit the Wyoming Connected Vehicle Pilot websitehttps://wydotcvp.wyoroad.info