New Ringgold Middle School

Project SlideshowSeptember 24, 2016

Aerial Photo from Northwest

Provided by Hudson Group

Aerial Photo from Northeast

Provided by Hudson Group

Aerial Photo from East

Provided by Hudson Group

Aerial Photo from South

Provided by Hudson Group

Building Areas

Foundation Installation Continues

Layout & Excavation – Area C

Foundation Installation Continues

Footers Poured – Area C

Concrete Wall Installation

Setting Panels

Concrete Wall Installation

Reinforcement

Concrete Wall Installation

Concrete Pour

Concrete Wall Installation

Forms Stripped

Front Entrance Piers – Area A

Excavation

Reinforcement

Front Entrance Piers – Area A

Concrete Pour

Building Areas - Progress

Masonry Installation – Area A

Masonry Installation – Area D

Monday

Friday

Placing Steel Lintels

Steel Bearing Plates – Area A Wall

Grout Masonry Walls – Area D

Stone Backfill & Compaction – Area A

Stone Backfill & Compaction – Area B

Prep for Concrete Floors

Spreading #57 Stone

Prep for Concrete Floors

Pouring Concrete Floors

Masonry, Backfill and Concrete Floor Progress

Retaining Wall #2 Installation

Retaining Wall #2 Installation Complete

Retaining Wall #1 Installation

Layout for Inlets North of Building

Stormwater Management at Tennis Courts

Spreading Topsoil at Tennis Courts

Installing Floor Drains – Area A

Underground Plumbing – Area D

Underground Electrical Conduit Installation Continues

Underground Electrical Conduit Installation Continues

• Complete Footer Installation• Continue Retaining Walls• Foundations at Fitness Center• Continue Masonry Installation – Areas A, B, C & D• Continue Backfill to Subgrade Inside Bldg – Area A, B & D• Continue Plumbing Underground• Finish Sidewalk at Southwest Corner of High School• Seed Areas Between HS & Sidewalks• Tennis Court Installation• Complete Infiltration Basin• Continue Electrical Underground• Continue Concrete Slabs on Grade

Scheduled Work for Next Few Weeks