presented to: by: date: federal aviation administration national airport pavement test facility...

Post on 02-Jan-2016

216 Views

Category:

Documents

1 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Presented to:

By:

Date:

Federal AviationAdministration

National Airport Pavement Test Facility Update

Airport Pavement Working Group

Don Barbagallo

April 24, 2012

2Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Acknowledgement

• This presentation overview represents the work of many individuals including:– FAA Pavement Group– SRA International– Gemini Technology– McQueen Associates

3Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Current Ongoing Projects at NAPTF• Construction Cycle 5 (Flexible Pavement).• Construction Cycle 6 (Rigid Pavement).• High Tire Pressure Testing on HMA.• Reflective Cracking of HMA Overlay Testing.• Alkali-Silica Reactivity Slabs.• Single Wheel Module Instrumentation.• Engineered Material Arresting System (EMAS)

Testing.• Runway Friction Test. • Upgrades to the Test Vehicle.• Future Tests.

4Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Post Traffic Testing

• CC5 examines the effect of multiple gear configurations on low strength subgrade flexible pavement life.

5Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

CC5 TRENCH AREA

6Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

CC5 TRENCH SUBGRADE CHARACTERIZATION

Nuclear Density LWD

CBR Measurement Profiles

7Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Preliminary CC 5 Trench Findings

CBR Summary

0

5

10

15

20

25

30

3.0 3.5 4.0 4.5 5.0 5.5 6.0

De

pth

fro

m T

op

of

Su

bg

rad

e

CBR

Average CBRin Dupont Clay Post Traffic Subgrade

Series1

Pre-

Traffi

c CBR

8Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

CC 6 Rigid Pavement• CC6 tests to determine the effect of concrete flexural strength

on rigid pavement life (AC 150/5320-6E) specification.

North

Asphalt Stabilized Base

South

Econocrete Base

MRS 1 = 500 psi TFS Total Passes = 17,500 @ 45K

MRS 2 = 750 psi TFS Total Passes = 20,000 @ 45 + 13,529 @ 52K + 5,200 @70K

MRS 3 = 1000 psi TFS Total Passes = 20,000 @ 45K + 11,000 @ 52K + 7,729 @ 70K

9Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

CC6 Rigid Pavement Tests

• Dr. David Brill & Mr. Josh Davis will present update on CC6 testing.

10Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

HMA High Tire Pressure Tests

• Ran tests over the winter of 2010/11.• Rutting failure in the PG 64-22 mix.• Will continue testing the PG 76-22 mix

at 17 ºF higher temperature than for the PG 64-22 mix.– High temperature can only be achieved during

the summer.– Delayed because of CC6 testing.– Plan to partially groove section of heated

pavement vs unheated pavement.

11Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Reflective Cracking Test Rig

• Goal: Develop design guidance for asphalt overlay of concrete pavements based upon full scale testing.

• AC 150/5320 - 6D purely empirical solution• AC 150/5320 – 6E FAARFIELD does not address

problem.

• Cracking of asphalt overlays is a complex problem.– Environmental temperature expansion/contraction.– Thermal induced warping– Load induced fatigue

12Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Reflective Cracking Test Rig

13Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Reflective Cracking Test Rig• Environmental temperature change

simulation. – Interface temperature 32F– Movement = Sinusoidal 0 to 15 mils– Total Cycle Time = 6 minutes– Total # of cycles completed to date ≈ 2600

• Instrumentation includes:– Strain gages: concrete, asphalt, and surface – LVDT’s measuring concrete movement– Thermistors

• Crack length monitored with photos.• Dr. Hao Lin of Gemini Technologies will

present data.

14Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Alkali-Silica Reactivity Testing

• Indoor, outdoor, & control slabs.• Periodic dosing with potassium acetate solution whenever

slabs dry out; about every 6 - 8 weeks.• On–going testing of slabs continues with little visual

evidence of ASR. • Planned grooving of slabs to expose aggregate to

potassium acetate.

15Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Single Wheel Module Instrumentation

Bending, Shear, & Torque Strain Gages Wheel Encoder

16Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

EMAS Testing• Work performed under a CRDA between the FAA

and Zodiac Aerospace (formerly ESCO).• Comparison testing of new block design.• Additional tests planned for May 2012.

17Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Aircraft Tire Friction Braking Testing

• Measure forces and friction coefficient for snow covered surface.

• Single wheel module with locked wheel

18Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Aircraft Tire Friction Strain Gage

Ave Horizontal Force

Sliding Friction Coefficient : µ ≈ 0.13

Ave Vertical Force

19Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Planned Facility Upgrades

• Replace fiber optic data communication line – SPUs to control room.

• Add wireless access point for east end of building.

• Charging station for electric vehicles.• 200,000 lb in-ground scale to facilitate

calibration of test vehicle wheel loads.

20Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Test Vehicle Projects*

• Study to upgrade vehicle traction drives to incorporate dynamic braking.

• Procure and install hydraulic oil heating system.

• On-going load control system upgrade - Delta controllers and digital servo valves.

* Ryan Rutter to further discuss

21Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Future NAPTF Schedule

• Continue Traffic CC6.• Finish testing on CC5 HMA sections that were

suspended due to cold weather.• Remove/reinistall HMA overlay on reflective

cracking rig.• Plan and construct CC7 on the low-strength

subgrade. Proposed testing to look at overload on flexible pavements.

• CC7 to also look at perpetual HMA pavements.

22Federal AviationAdministration

Airport Pavement Working GroupApr 24, 2012

Future NAPTF Schedule (continued)

• Repave the HTP pavement with warm-mix asphalt in conjunction with CC7 HMA construction.

• CC8 concrete pavement test planning beginning. Joint design – load transfer of dowels for thick

slabs on moderate strength subgrades. Joint design – sinusoidal keyways vs. dowels. As-built slab strength vs. predicted slab strength. Slab aspect ratios.

top related