PELAKSANAAN BIM DI

JABATAN KERJA RAYA

SYAMIL MUSADDIQ BIN MOHD.ASHHAR

GRADUATE ARCHITECT

BUILDING INFORMATION MODELING UNIT,

BPPK, CPAB,

JABATAN KERJA RAYA

29APRIL

2017

why

not

Typical Problems in Construction Project Delivery

Reasons• Lack of Proper Planning

• Lack of Coordination

• Lack of Professional Specialised Education

• Poor Decision Making

• Inefficient dispute resolution mechanism

• Lack of Mediation

• Diffculty in responsibility fixation

• Lack of Project Monitoring/ Programme Monitoring

• Reluctance in Adoption of New Technology

• Lack of Integrated Project Delivery

PWD’s Strategic Initiative for…

RMK-11

• Improving work process & system

• Driving productivity (IBS & BIM)

how

=

+ +Human

resourceKnowledge ICT

On-time

project

delivery

+ +Effective Cost

Management

Fulfilling the

Quality as per

Expected

CLIENT

MinistryEnd Users

Public

OF

BIM in JKR

2007BIM

diperkenalkan

di JKR

Pemilihan

Autodesk

sebagai

platform BIM di

JKR

2008

2010Penubuhan JK Teknikal BIM JKR

Projek BIM Reka dan Bina

- Institut Kanser Negara Putrajaya

2011Projek Perintis

BIM (In-house)

- Blok akademik

SMK Meru Raya

Ipoh Perak

•Penubuhan Unit BIM PROKOM

• Projek Perintis BIM II (In-house)

-SPRM Selangor

-Klinik Kesihatan Maran Pahang

2012

• Studio Latihan BIM

• JKR BIM Roadmap Engagement Day

•Projek BIM RP3 RMK10 (In-house)

- Kolej MARA Banting Selangor

2013

2014•Garis Panduan dan Piawaian BIM JKR

• Projek BIM Konvensional Perunding – MBKT

Terengganu

2015• Pengukuhan JK Teknikal BIM JKR

• JKR BIM Day

•Manual Proses Kerja BIM

• Perjanjian MoU BIM JKR-UMP

•Projek BIM Reka dan Bina

- Hospital Putrajaya

2017 -

2020

WAY FORWARD

2016•Garis Panduan Pengunaan Template JKR

• Projek BIM Konvensional Dalaman –

Hospital Parit Buntar

Autodesk was chosen as BIM

Platform Software in JKR

Disiplin Kegunaan model

RevitArchitecture, Structural, Mechanical &Electrical

Generate Virtual Building Model

Generate Drawing

Analyse and Design

Inter-discipline Coordination(Interference management)

Facility Management

Cost estimation

Disiplin Kegunaan model

AutoCAD Civil3D

Civil

Earth Work(Existing ground modeling, Site analysis,

Platform design and modeling & Volume calculation)

Road and Drainage (Profile design & Volume calculation)

Sanitary System(Gravity pipe network design)

Water Supply System (Pressure pipe network design)

Disiplin Kegunaan model

general

Design Validation and Verification (Model review)

Inter-Discipline Coordiantio (Interference management)

Model Visualisation (walkthrough)

4D Building Construction Simulation (Visualisasi 3D + Jadual

program kerja)

Other Software

STUDIO LATIHAN

BIM

JKR BIM

KEY

RESULT

AREAS

JKR BIM STANDARD & GUIDELINESJKR BIM standard and guidelines including processes developed

PEOPLEObjectives : Create awareness & buy in.Develop competent managers & designers / modelers

PROCESSObjective :Reengineer the processes for Integrated project delivery

TECHNOLOGYObjective : Provide adequate & sufficient software, hardware & infrastructure

Unit BIM

CPAB JKR

Construction

IndustryConstruction Industry (Sunway, Sime

Darby, Brunsfield & HSS)

• BIM

• Kaedah Konvensional

Model

Model

Analisis & Rekabentuk

Analisis & Rekabentuk

Koordinasi

Koordinasi

Lukisan

Lukisan

Faktor utama : Informasi dan keputusan yang tepat, awal dan mencukupi

ADVANTAGE

OFIMPLIMENTING

BIM FOR JKR

PROJECTS

Facilitate design review process as well as

managing clients expectation and needs through 3D

visualization.

Clearer Site Visualisation and Improving Earth Work

Calculation.

Helps to verify Contractor’s work programme

Minimising design conflicts, clashes and

construction errors.

Asset information can be recorded in the model.

COMMON

BIM

OBJECTIVES IN

JKR PROJECTS

OPTIMIZED EARTHWORK QUANTITIES

Detailed site model

FACILITATE DESIGN REVIEW PROCESS & MANAGE

CLIENT’S EXPECTATIONS THROUGH VISUALIZATIONS

VERIFY WORK PROGRAM VIA 4D CONSTRUCTION

SIMULATION

Construction model

Architectural model Structural model

Mechanical model Electrical model

Architecture detailed model

Structure detailed model

Mechanical detailed model

Electrical detailed model

Combined detailed model

MINIMISE CONFLICTS & REWORKS AT CONSTRUCTION

SITE

Interference checking

Structural component vs

Mechanical component

Electrical component vs

Mechanical component

Visualize designs more clearly through 3D visualization ofBIM model

Institut Kanser Negara, Putrajaya

(a)Clash detection between structure with M&E system (b) Clash detection between structure with architecture

(c) Clash detection between M&E system with M&E system

CASE STUDIES

CLASH ANALYSIS REPORTS

CLASH ANALYSIS REPORTS

AIR TERMINAL vs LIGHTING FIXTURES

DUCT vs CABLE TRAY

MECH. EQUIPMENT vs CABLE TRAY

DUCT vs ELECTRICAL FIXTURES

Pengubahsuaian perabot dapat ditentukan di peringkatawal sebelum kerja pembinaan dimulakan

FURNITURES vs COLUMN

Kedudukan ruang bukaan (opening) yang perlu disediakan padarasuk dapat ditentukan di peringkat awal rekabentuk sebelum kerjapembinaan dimulakan

PIPE vs GROUND BEAM

- Punching through beam structure during construction work can be avoided when the opening/sleeve in the beam are provided earliear

- Structural integrity is assured

3D coordination conducted

Family Type : Structural Column

Family Type : Structural Framing-Beam

Family Type : Structural Framing-Slab

Family Type : Structural Framing-Others

Family Type : Structural Foundation

Family Type : Structural Trusses

Parameter

Record Modeling

Architectural –Family Type

Electrical – Family Type

Mechanical –Family Type

Record

Modeling

• 4D simulation allow monitoring of actual physical progress vs planned

• Stumps is constructed earlier than pile cap

• Staircase construction at Level 3 starts earlier than the frame structure

FINDINGS

• Furniture assembly at each level starts early than structural framework

• Construction of columns at level 7 is not included in contractor’s work program

FINDINGS

SPATIAL ANALYSIS & ROOM SCHEDULE GENERATION

COMMON BIM OBJECTIVES

JKR PROJECTS

Quantity

Estimation

Drawing documentation

Structure Drawing

Mechanical Drawing

Electrical Drawing

BAB 1 : PENGENALAN

BAB 2 : KEGUNAAN BIM

BAB 3 : PERANAN DAN TANGGUNGJAWAB

BAB 4 : PELAN PELAKSANAAN PROJEK BIM

BAB 5 : MODEL BIM

BAB 6 : PROSES KERJA

BAB 7 : PENGURUSAN DATA

BAB 1 : TEMPLATE

BAB 2 : KONVENSYEN PENAMAAN

BAB 3 : SYARAT PEMATUHAN

WAY FORWARD1. Menyediakan beberapa dokumen rujukan seperti berikut :

Manual Proses Kerja BIM

Penggunaan Template Perisian

Kaedah Konvensyen Penamaan

JABATAN KERJA RAYA MALAYSIA

2. Menghasilkan Revit Apps (JBIM Library)

3. Mengurus pengumpulan komponen families dari masa kesemasa

4. Menambahbaik JKR Revit Template mengikut keperluan danteknologi semasa

https://www.jkr.gov.my/cawarkitek/paprmk11/

B I M &

BEYOND

Maintenance Scheduling

Maintenance Scheduling

B I M

INDUSTRY

FEEDBACK

BIM users (38)

165respondents

Advantages

• Improve quality

• Improve

communication

• reduce time

BIM non users (127)

Why

•No requirement

•Unaware

•Not competent

When

• 73% plan to use BIM

within 1-3 years

Difficulties:

• lack of trained personnel

•high cost of technology

AVOID FRUSTRATION

Source: Internet

INCREASESATISFACTION

Source: Internet

BIMTHE FUTURE IS HERE

T H A N K Y O U© 2017 Unit BIM CPAB JKR

Malaysia

Syamil Musaddiq bin Mohd.AshharGraduate Architect