Newlands Cross Upgrade Scheme
South Dublin County Council
Strategic Policy Committee
5th September 2013
Introductions
Description of the Works
Traffic Management Phasing
Speed Limits
Road Safety Audits
Emergency Arrangements
2
BAM PPP
3
4
5
Description of Newlands Cross Upgrade Works
Grade Separated Junction at Newlands Cross
3 Lane Dual Carriageway from M50 to west of Boot Road
Signalised junction on R113 Belgard / Fonthill Road
Signalised Junction at Newlands Golf Club
Utility Diversions
Bus Lanes
Pedestrian / cyclist facilities
Fencing / Safety barrier / Drainage
ITS Equipment / Traffic Signalling
6
Programme
Construction carried out in 6 major TM phases
Phase 1 – June to Nov‘13
Phase 2 – Nov‘13 to Feb‘14
Phase 3 – Feb‘14 to Aug ‘14
Phase 4 – Aug ‘14 to Oct ‘14
Phase 5 – Oct ‘14 to Dec ‘14
Phase 6 – Dec ‘14 to Jan ‘15
7
Phase 1
8
Phase 1 (cont.)
9
Dublin
Naas
Phase 1 Works looking East
Temporary Lanes under
Construction
Bewleys Hotel
10
Phase 1 Works looking West
Temporary Lanes under
Construction
Dublin
Naas
Joels / Louis
Fitzgerald Hotel
11
Phase 1 Works looking West
Temporary Lanes under
Construction
N7
Naas
12
Phase 2
13
Phase 2 (cont.)
Phase 2 N7 Westbound
14
N7 Naas
Phase 2 Westbound
15 N7 Naas
N7 Dublin
Phase 2 Westbound
16
N7 Naas
N7 Dublin
Phase 2 Eastbound
17
N7 Dublin
Phase 2 Eastbound
18
N7 Dublin
Phase 2 Eastbound
19
N7 Dublin
N7 Naas
Phase 2 Eastbound
20
N7 Dublin N7 Naas
21
Phase 3
22
Phase 3 (cont.)
Phase 3 looking eastbound
23
N7 Dublin
/ Fonthill
Road
Dublin /
Belgard
Road
N7 Naas
Newlands Golf Club
Bewleys Hotel
Phase 3 looking eastbound
24
N7 Dublin
/ Fonthill
Road
Dublin /
Belgard
Road
N7 Naas
Phase 3 looking westbound
25
N7 Naas
N7 Dublin
N7 Dublin
Newlands Golf Club
Phase 3 looking eastbound
26
Dublin /
Belgard
Road
N7 Naas
Bewleys Hotel
Phase 3 looking eastbound
27
N7 Dublin
N7 Naas
Joels / Esso
Phase 3 looking eastbound
28
N7 Dublin
N7 Naas
29
Phase 4
30
Phase 4(cont.)
31
Phase 5
32
Phase 6
Final Junction Layout
33 Newlands Golf Club
34
Statutory Orders Applications in progress
Liaison / Consultation with:
Kildare County Council
South Dublin County Council
An Garda Siochana
Authority’s Representative
Statutory Orders to be renewed every 12 months
Enforcement
Temporary Speed Limits
35
Road Safety Audits (RSA)
Stage 2 RSA carried out by Arup, in consultation with
relevant parties
Stage 3 RSA may be attended by representatives of
Kildare County Council
South Dublin County Council
An Garda Siochana
Authority’s Representative
Certification by Authority prior to implementation of any
TTMS