1

Newlands Cross Upgrade Scheme

South Dublin County Council

Strategic Policy Committee

5th September 2013

Introductions

Description of the Works

Traffic Management Phasing

Speed Limits

Road Safety Audits

Emergency Arrangements

2

BAM PPP

3

4

5

Description of Newlands Cross Upgrade Works

Grade Separated Junction at Newlands Cross

3 Lane Dual Carriageway from M50 to west of Boot Road

Signalised junction on R113 Belgard / Fonthill Road

Signalised Junction at Newlands Golf Club

Utility Diversions

Bus Lanes

Pedestrian / cyclist facilities

Fencing / Safety barrier / Drainage

ITS Equipment / Traffic Signalling

6

Programme

Construction carried out in 6 major TM phases

Phase 1 – June to Nov‘13

Phase 2 – Nov‘13 to Feb‘14

Phase 3 – Feb‘14 to Aug ‘14

Phase 4 – Aug ‘14 to Oct ‘14

Phase 5 – Oct ‘14 to Dec ‘14

Phase 6 – Dec ‘14 to Jan ‘15

7

Phase 1

8

Phase 1 (cont.)

9

Dublin

Naas

Phase 1 Works looking East

Temporary Lanes under

Construction

Bewleys Hotel

10

Phase 1 Works looking West

Temporary Lanes under

Construction

Dublin

Naas

Joels / Louis

Fitzgerald Hotel

11

Phase 1 Works looking West

Temporary Lanes under

Construction

N7

Naas

12

Phase 2

13

Phase 2 (cont.)

Phase 2 N7 Westbound

14

N7 Naas

Phase 2 Westbound

15 N7 Naas

N7 Dublin

Phase 2 Westbound

16

N7 Naas

N7 Dublin

Phase 2 Eastbound

17

N7 Dublin

Phase 2 Eastbound

18

N7 Dublin

Phase 2 Eastbound

19

N7 Dublin

N7 Naas

Phase 2 Eastbound

20

N7 Dublin N7 Naas

21

Phase 3

22

Phase 3 (cont.)

Phase 3 looking eastbound

23

N7 Dublin

/ Fonthill

Road

Dublin /

Belgard

Road

N7 Naas

Newlands Golf Club

Bewleys Hotel

Phase 3 looking eastbound

24

N7 Dublin

/ Fonthill

Road

Dublin /

Belgard

Road

N7 Naas

Phase 3 looking westbound

25

N7 Naas

N7 Dublin

N7 Dublin

Newlands Golf Club

Phase 3 looking eastbound

26

Dublin /

Belgard

Road

N7 Naas

Bewleys Hotel

Phase 3 looking eastbound

27

N7 Dublin

N7 Naas

Joels / Esso

Phase 3 looking eastbound

28

N7 Dublin

N7 Naas

29

Phase 4

30

Phase 4(cont.)

31

Phase 5

32

Phase 6

Final Junction Layout

33 Newlands Golf Club

34

Statutory Orders Applications in progress

Liaison / Consultation with:

Kildare County Council

South Dublin County Council

An Garda Siochana

Authority’s Representative

Statutory Orders to be renewed every 12 months

Enforcement

Temporary Speed Limits

35

Road Safety Audits (RSA)

Stage 2 RSA carried out by Arup, in consultation with

relevant parties

Stage 3 RSA may be attended by representatives of

Kildare County Council

South Dublin County Council

An Garda Siochana

Authority’s Representative

Certification by Authority prior to implementation of any

TTMS

36