14th February 2020 | Final Auction Report 0
Final Auction Report 2019 one year ahead Capacity Auction (T-1) Delivery year 2020/21
14th February 2020
V1.0
Final Auction Results T-1 Auction 2019 (DY 20/21)
Table of Contents
Executive summary Page 1 Results summary Page 2 Capacity awarded by generating type and primary fuel Page 3 to 4 Capacity procured by delivery year Page 5 Results by CMU Pages 6 to 10
Final Auction Results T-1 Auction 2019 (DY 20/21)
Disclaimer
This document has been prepared by National Grid Electricity System Operator Limited (NGESO) and is provided voluntarily and without charge. Whilst NGESO has taken all reasonable care in preparing this document, no representation or warranty either expressed or implied is made as to the accuracy or completeness of the information that it contains and parties using information within the document should make their own enquiries as to its accuracy and suitability for the purpose for which they use it. Neither NGESO nor any other companies in the National Grid plc group, nor any Directors or employees of any such company shall be liable for any error or misstatement or opinion on which the recipient of this document relies or seeks to rely other than fraudulent misstatement or fraudulent misrepresentation and does not accept any responsibility for any use which is made of the information or the document or (to the extent permitted by law) for any damages or losses incurred.
In the event of any conflict or inconsistency between this document and the Capacity Market Rules, the Electricity Capacity Regulations or the Auction Guidelines, the latter documents take precedence. Capitalised terms used in this document shall have the same meanings given in the Capacity Market Rules.
Confidentiality
This guidance document, and its contents should be considered as confidential in nature, and this document is supplied on this basis. No part of this document may be reproduced in any material form (including photocopying and restoring in any medium or electronic means and whether transiently or incidentally) without the written permission of NGESO.
Copyright National Grid ESO 2020, all rights reserved.
Final Auction Results T-1 Auction 2019 (DY 20/21)
Page 1
Executive Summary
National Grid ESO in its role as EMR Delivery Body is required by the Capacity Market Rules 2014 (Rule 5.10.2) to notify the Secretary of State of the Final Results of the Capacity Market Auction as soon as reasonably practicable following the conclusion of the Capacity Auction. This report discharges that obligation.
The T-1 Capacity Auction for delivery in 2020/21 concluded on 7th February 2020, 13:00 BST. The results of the auction are as follows, where any capacity figure refers to de-rated capacity, unless otherwise stated.
The CMUs to which a Capacity Agreement has been awarded and the duration of those Capacity Agreements are listed in the CMU results section (page 5).
In addition to the results presented above, National Grid ESO is required under Capacity Market Rule 5.10.3 to report any CMUs that were removed from the IT Auction System under Capacity Market Rule 5.3.3. The Auction concluded without any CMUs being removed from the system by National Grid.
The remainder of this report gives further detail on the Capacity Market Auction Clearing, how the Clearing Price was reached and what makes up the capacity that has been procured.
The results of the auction are provisional for the period of 8 working days after the completion of the Capacity Market Auction, during which time the Secretary of State may annul the auction on the grounds specified in Regulation 27 of the Electricity Capacity Regulations 2014. Following the close of the 19th of February 2020, the Auction Results are final.
Any T-1 (delivery year 2020/21) data shown within this document originates from the latest Capacity Market Register available at the time this document was published.
Final Auction Results T-1 Auction 2019 (DY 20/21)
Auction Results
Auction and Delivery Year T-1 Auction, Delivery Year 2020/21
Date and time auction cleared 13:00, 07th February 2020
Clearing Price £1.00
Aggregate Capacity of CMUs awarded Capacity Agreements 1024.409 MW
Target Capacity (demand at clearing price) 300 MW
Capacity entering auction and proportion awarded an agreement 3027.229 MW (33.84% awarded an agreement)
Number of CMUs awarded an agreement 33
Number of applicant companies awarded an agreement 86
Number of parent companies awarded an agreement 63
The high level auction results are summarised below including a round by round summary graph. As shown within the round summary, the auction cleared in round 15.
The awarded and exited capacity are summarised below by technology type. Existing CMUs made up 68.48% of the capacity entering the auction and formed both the largest
capacity to exit the auction (58.40%) and the largest capacity to be awarded an agreement (41.60%). Of the total 320.276MW of new build generation (10.58% of capacity
entering the auction), 23.58% of this capacity was successful in gaining an agreement.
The Auction did not clear with an exact match of Offered Capacity and target capacity (“Clearing Capacity”) and so the Net Welfare Algorithm was used to determine price and
volume.
The Net Welfare Algorithm evaluates the integral specified in Rule 5.9.6 to determine whether to include the marginal unit.
The algorithm subtracts the additional cost of procuring the marginal unit from the welfare gained by procuring the marginal unit. If the result is positive i.e. the welfare
gained by procuring the additional unit outweighs the cost, the unit is included, and the Clearing Price is set to the Exit Bid Price of that unit.
The result of the Net Welfare Algorithm was positive and the marginal unit was procured hence the aggregate Capacity of CMU’s awarded Capacity agreements exceeds the
Target Capacity.
A fuller explanation of the Net Welfare Algorithm can be found on page 8 of the Capacity Market Auction User Guide.
Round 15
Round 14
Round 13
Round 12
Round 11
Round 10
Round 9
Round 8
Round 7
Round 6
Round 5
Round 4
Round 3
Round 2
Round 1
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
0 500 1,000 1,500 2,000 2,500 3,000 3,500
Price (£/kW/y)
Capacity (MW)
Supply and Demand Curve
Demand Curve Remaining Capacity
Page 2
Final Auction Results T-1 Auction 2019 (DY 20/21)
Capacity MW % No. CMU Capacity MW % No. CMU
Existing Generating CMU 42.39 4.14% 9 1210.641 60.45% 105
Coal 0 0.00% 0 0 0.00% 0
Combined Cycle Gas Turbine (CCGT) 0 0.00% 0 54 2.70% 1
Combined Heat and Power (CHP) 19.192 1.87% 4 564.068 28.16% 65
DSR 0 0.00% 0 0 0.00% 0
Energy from Waste 12.872 1.26% 1 22.789 1.14% 1
Hydro 0 0.00% 0 0 0.00% 0
Nuclear 0 0.00% 0 0 0.00% 0
OCGT and Reciprocating Engines (Fuel Type - Gas) 0 0.00% 0 0 0.00% 0
Onshore Wind 0 0.00% 0 0 0.00% 0
Open Cycle Gas Turbine (OCGT) 0 0.00% 0 237.396 11.85% 1
Reciprocating engines 6.648 0.65% 2 327.077 16.33% 34
Solar Photovoltaic 0 0.00% 0 0 0.00% 0
Storage 0 0.00% 0 0 0.00% 0
Storage (Duration 0.5h) 3.678 0.36% 2 3.065 0.15% 1
Storage (Duration 1h) 0 0.00% 0 2.246 0.11% 2
Storage (Duration 2h) 0 0.00% 0 0 0.00% 0
Storage (Duration 3h) 0 0.00% 0 0 0.00% 0
Storage (Duration 4h) 0 0.00% 0 0 0.00% 0
Storage (Duration 5.5h) 0 0.00% 0 0 0.00% 0
Storage (Duration 6h) 0 0.00% 0 0 0.00% 0
Storage (Duration 12h) 0 0.00% 0 0 0.00% 0
New Build Generating CMU 75.519 7.37% 14 244.757 12.22% 10
Coal 0 0.00% 0 0 0.00% 0
Combined Cycle Gas Turbine (CCGT) 0 0.00% 0 0 0.00% 0
Combined Heat and Power (CHP) 1.804 0.18% 1 3.969 0.20% 1
DSR 0 0.00% 0 0 0.00% 0
Energy from Waste 14.588 1.42% 1 84.008 4.19% 2
Hydro 0 0.00% 0 0 0.00% 0
Nuclear 0 0.00% 0 0 0.00% 0
OCGT and Reciprocating Engines (Fuel Type - Gas) 0 0.00% 0 0 0.00% 0
Onshore Wind 0 0.00% 0 0 0.00% 0
Open Cycle Gas Turbine (OCGT) 0 0.00% 0 0 0.00% 0
Reciprocating engines 59.127 5.77% 12 113.958 5.69% 3
Solar Photovoltaic 0 0.00% 0 0 0.00% 0
Storage 0 0.00% 0 0 0.00% 0
Storage (Duration 0.5h) 0 0.00% 0 0 0.00% 0
Storage (Duration 1h) 0 0.00% 0 42.822 2.14% 4
Storage (Duration 2h) 0 0.00% 0 0 0.00% 0
Storage (Duration 3h) 0 0.00% 0 0 0.00% 0
Storage (Duration 4h) 0 0.00% 0 0 0.00% 0
Storage (Duration 5.5h) 0 0.00% 0 0 0.00% 0
Storage (Duration 6h) 0 0.00% 0 0 0.00% 0
Storage (Duration 12h) 0 0.00% 0 0 0.00% 0
Pre-Refurbishment CMU 0 0.00% 0 0 0.00% 0
Refurbishing Generating CMU 0 0.00% 0 0 0.00% 0
Existing Interconnector CMU 820 80.05% 1 0 0.00% 0
New Build Interconnector CMU 0 0.00% 0 0 0.00% 0
Proven DSR CMU 18.438 1.80% 2 163.696 8.17% 17
Unproven DSR CMU 68.062 6.64% 7 383.726 19.16% 35
Awarded and exited capacity by technology type
Breakdown of awarded capacity Breakdown of capacity exiting the auction
Page 3
Final Auction Results T-1 Auction 2019 (DY 20/21)
Please note in the above charts, "Refurbishing Generating CMU" includes bidders who may have aquired either a pre-refurbishing agreement or a post-refurbishing
agreement.
The below charts show the breakdown by the primary fuel type of CMUs that were awarded an agreement and those CMUs who exited the auction above the clearing price.
The below charts show the breakdown by the generating type of CMUs that were awarded an agreement and those CMUs who exited the auction above the clearing price.
9
1
14
2
7
42.39
820
75.519
18.438
68.062Capacity awarded
Existing Generating CMU Existing Interconnector CMU New Build Generating CMU New Build Interconnector CMU
Proven DSR CMU Refurbishing Generating CMU Unproven DSR CMU
Capacity awarded:1,024.409 MW
CMUs awarded:33
105
10
17
35
1210.641244.757
163.696
383.726
Capacity exited
Capacity exited:2,002.820 MW
CMUs exited:167
8
20
1
2 2
83.992
89.279
820
3.678
27.46Capacity awarded
Coal Coal mine methane Diesel Distillate DSR
Gas Hydro Interconnector Nuclear Onshore Wind
Capacity awarded:1,024.409 MW
CMUs awarded:33
2
52
103
7
3
547.422
1294.399
48.133
106.797
Capacity exited
Capacity exited:2,002.820 MW
CMUs exited:167
Page 4
Final Auction Results T-1 Auction 2019 (DY 20/21)
Parent Company Applicant Company CMU ID Capacity AG CMU Classification Capacity (MW) Duration (Years) Fuel Type
RWE Generation UK plc RWE Generation UK plc SEAL19 No Existing Generating CMU 54 1 Gas
AEROSPACE ENERGY UK LIMITED AEROSPACE ENERGY UK LIMITED AeroCM Yes Unproven DSR CMU 2.508 1 Gas
Alkane Energy Limited Alkane Energy UK Limited AUKCM2 No Existing Generating CMU 2.023 1 Coal mine methane
Alkane Energy Limited Alkane Energy UK Limited AUKWHT No Existing Generating CMU 2.066 1 Gas
AMPIL 2 ASSET LIMITED AMPIL 2 ASSET LIMITED VILLA3 Yes Existing Generating CMU 2.849 1 Gas
Anesco Bidco 2 Limited Anesco Battery Solutions Limited ADABS2 Yes Unproven DSR CMU 4.481 1 DSR
Anesco Bidco 2 Limited Anesco Battery Solutions Limited ADABS1 Yes Unproven DSR CMU 4.652 1 DSR
APEX ENERGY LTD APEX ENERGY LTD PB2019 No Existing Generating CMU 7.745 1 Gas
Zenobe Energy Limited BESS Aylesford Limited DSRA19 No Proven DSR CMU 24.981 1 DSR
Zenobe Energy Limited BESS Claredown Limited DSRC19 No Proven DSR CMU 17.228 1 DSR
British Sugar plc British Sugar plc BSWI20 No Existing Generating CMU 41.4 1 Gas
Welsh Power Group Limited Bury Power Limited BURY19 No Existing Generating CMU 18.711 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES31 No Existing Generating CMU 38.7 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES-2 No Existing Generating CMU 4.693 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES-4 No Existing Generating CMU 6.351 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES-3 No Existing Generating CMU 1.997 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES-5 No Existing Generating CMU 7.131 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES17 No Existing Generating CMU 7.399 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES20 No Existing Generating CMU 35.919 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES-8 No Proven DSR CMU 2.988 1 DSR
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES32 No Unproven DSR CMU 10.337 1 DSR
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES22 No Existing Generating CMU 5.711 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES21 No Existing Generating CMU 5.391 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES25 No Existing Generating CMU 5.36 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES26 No Existing Generating CMU 5.731 1 Gas
Centrica plc Centrica Business Solutions UK Optimisation Limite 5RES27 No Existing Generating CMU 9.781 1 Gas
Centrica plc Centrica PB Limited 5RES15 No Existing Generating CMU 237.396 1 Gas
Anesco Asset Management Limited Clayhill Solar Limited ADSCHL Yes Unproven DSR CMU 5.168 1 DSR
Welsh Power Group Limited Clyne Power Limited CLYN19 No Existing Generating CMU 15.007 1 Gas
COGENERATION SOLUTIONS LIMITED COGENERATION SOLUTIONS LIMITED Cavrd5 No Existing Generating CMU 7.598 1 Gas
Conrad (Ampthill) Limited Conrad (Ampthill) Limited CDAMP2 Yes New Build Generating CMU 5.699 1 Gas
Conrad (Calne) Limited Conrad (Calne) Limited CDCAL2 Yes New Build Generating CMU 5.699 1 Gas
Conrad (Flint) Limited Conrad (Flint) Limited CDFLI2 Yes New Build Generating CMU 4.749 1 Gas
Conrad (Matching) Limited Conrad (Matching) Limited CDMAT2 Yes New Build Generating CMU 5.699 1 Gas
Conrad (Sandycroft) Limited Conrad (Sandycroft) Limited CDSDC2 Yes New Build Generating CMU 4.749 1 Gas
CONRAD ENERGY (DEVELOPMENTS) LIMITED CONRAD ENERGY (DEVELOPMENTS) LIMITED CDFLB2 Yes New Build Generating CMU 2.375 1 Gas
CONRAD ENERGY (DEVELOPMENTS) LIMITED CONRAD ENERGY (DEVELOPMENTS) LIMITED CDHAW2 Yes New Build Generating CMU 2.375 1 Gas
CONRAD ENERGY (DEVELOPMENTS) LIMITED CONRAD ENERGY (DEVELOPMENTS) LIMITED CDLAG2 Yes New Build Generating CMU 4.037 1 Gas
CONRAD ENERGY (DEVELOPMENTS) LIMITED CONRAD ENERGY (DEVELOPMENTS) LIMITED CDPLY2 Yes New Build Generating CMU 4.749 1 Gas
Welsh Power Group Limited Culvery Power Limited CULV19 No Existing Generating CMU 13.107 1 Gas
Distributed Generators Limited Distributed Generators Limited elms03 No Existing Generating CMU 4.749 1 Gas
E.ON UK Plc E.ON UK Plc BVC001 No Existing Generating CMU 3.471 1 Gas
E.ON UK Plc E.ON UK Plc CEN007 No Existing Generating CMU 2.241 1 Gas
E.ON UK Plc E.ON UK Plc AGG001 No Existing Generating CMU 2.598 1 Gas
Page 6
Final Auction Results T-1 Auction 2019 (DY 20/21)
Parent Company Applicant Company CMU ID Capacity AG CMU Classification Capacity (MW) Duration (Years) Fuel Type
EDF Energy Customers Limited EDF Energy Customers Limited DR201A No Proven DSR CMU 5.338 1 DSR
EDF Energy Customers Limited EDF Energy Customers Limited DR201B No Proven DSR CMU 7.5 1 DSR
EELPOWER (OPCO6) LIMITED EELPOWER (OPCO6) LIMITED WORM20 No Unproven DSR CMU 6.891 1 DSR
Enel X UK Limited Enel X UK Limited NDSR03 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR04 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR05 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR06 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR07 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR08 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR09 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR10 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR11 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR12 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR35 No Proven DSR CMU 10.752 1 DSR
Enel X UK Limited Enel X UK Limited NDSR36 No Proven DSR CMU 10.752 1 DSR
Enel X UK Limited Enel X UK Limited NDSR37 No Proven DSR CMU 10.766 1 DSR
Enel X UK Limited Enel X UK Limited NDSR38 No Proven DSR CMU 6.404 1 DSR
Enel X UK Limited Enel X UK Limited NDSR39 No Proven DSR CMU 6.405 1 DSR
Enel X UK Limited Enel X UK Limited NDSR40 No Proven DSR CMU 4.104 1 DSR
Enel X UK Limited Enel X UK Limited NGEN18 No Existing Generating CMU 6.991 1 Gas
Enel X UK Limited Enel X UK Limited NGEN31 No Existing Generating CMU 22.789 1 Waste
Enel X UK Limited Enel X UK Limited NGEN20 No Existing Generating CMU 6.535 1 Gas
Enel X UK Limited Enel X UK Limited NGEN30 No Existing Generating CMU 5.022 1 Gas
Enel X UK Limited Enel X UK Limited NGEN32 No Existing Generating CMU 5.5 1 Gas
Enel X UK Limited Enel X UK Limited NGEN33 No Existing Generating CMU 3.997 1 Gas
Enel X UK Limited Enel X UK Limited NGEN34 No Existing Generating CMU 3.6 1 Gas
Enel X UK Limited Enel X UK Limited NGEN24 No Existing Generating CMU 5.261 1 Gas
Enel X UK Limited Enel X UK Limited NGEN25 No Existing Generating CMU 5.208 1 Gas
Enel X UK Limited Enel X UK Limited NGEN21 No Existing Generating CMU 8.003 1 Gas
Enel X UK Limited Enel X UK Limited NGEN22 No Existing Generating CMU 10.001 1 Gas
Enel X UK Limited Enel X UK Limited NGEN02 No Existing Generating CMU 4.506 1 Gas
Enel X UK Limited Enel X UK Limited NGEN03 No Existing Generating CMU 4.916 1 Gas
Enel X UK Limited Enel X UK Limited NGEN04 No Existing Generating CMU 4.401 1 Gas
Enel X UK Limited Enel X UK Limited NGEN06 No Existing Generating CMU 4.008 1 Gas
Enel X UK Limited Enel X UK Limited NGEN07 No Existing Generating CMU 4.001 1 Gas
Enel X UK Limited Enel X UK Limited NGEN11 No Existing Generating CMU 11.003 1 Gas
Enel X UK Limited Enel X UK Limited NGEN16 No Existing Generating CMU 8.023 1 Gas
Enel X UK Limited Enel X UK Limited NGEN17 No Existing Generating CMU 6.201 1 Gas
Enel X UK Limited Enel X UK Limited NDSR01 No Unproven DSR CMU 21.535 1 DSR
Enel X UK Limited Enel X UK Limited NDSR02 No Unproven DSR CMU 21.535 1 DSR
ESB SOLAR (NORTHERN IRELAND) LIMITED ESB SOLAR (NORTHERN IRELAND) LIMITED MFARM1 No Existing Generating CMU 1.729 1 Storage - Battery
ESSO PETROLEUM COMPANY,LIMITED ESSO PETROLEUM COMPANY,LIMITED EMD-19 No Existing Generating CMU 71.816 1 Gas
FCC Recycling (UK) Limited FCC (E&M) Limited FCCMI1 Yes Existing Generating CMU 12.872 1 Waste
Ferrybridge MFE 2 Limited Ferrybridge MFE 2 Limited FM2-23 No New Build Generating CMU 66.074 1 Waste
Flexitricity Limited Flexitricity Limited F18033 No Existing Generating CMU 4.21 1 Gas
Flexitricity Limited Flexitricity Limited F18034 No Existing Generating CMU 3.02 1 Gas
Flexitricity Limited Flexitricity Limited F18036 No Existing Generating CMU 3.658 1 Gas
Page 7
Final Auction Results T-1 Auction 2019 (DY 20/21)
Parent Company Applicant Company CMU ID Capacity AG CMU Classification Capacity (MW) Duration (Years) Fuel Type
Flexitricity Limited Flexitricity Limited F19039 No Existing Generating CMU 3.012 1 Gas
Flexitricity Limited Flexitricity Limited F18007 No Existing Generating CMU 3.25 1 Gas
Flexitricity Limited Flexitricity Limited F19108 No Existing Generating CMU 3.51 1 Gas
Flexitricity Limited Flexitricity Limited F18025 No Existing Generating CMU 15.111 1 Gas
Flexitricity Limited Flexitricity Limited F19029 No Existing Generating CMU 3.077 1 Gas
FLINT TO CELL LIMITED FLINT TO CELL LIMITED Finwy3 No Existing Generating CMU 4.749 1 Gas
FS NEVENDON LIMITED FS NEVENDON LIMITED NEV462 Yes Existing Generating CMU 1.226 1 Storage - Battery
P3P Partners LLP Glass Leaf Power Limited BRAN19 Yes Existing Generating CMU 3 1 Gas
Gloucestershire County Council Gloucestershire County Council JAVP19 No New Build Generating CMU 17.934 1 Waste
GREEN PEAK GENERATION LIMITED GREEN PEAK GENERATION LIMITED Lilly5 No Existing Generating CMU 7.124 1 Gas
Greenspan Contractors Limited Greenspan Contractors Limited ABCN03 Yes Existing Generating CMU 3.799 1 Gas
Greenspan Nifty Fifty Limited Greenspan Nifty Fifty Limited WPKB03 Yes New Build Generating CMU 3.799 1 Gas
Greenspan Nifty Fifty Limited Greenspan Nifty Fifty Limited WPKA03 Yes New Build Generating CMU 3.799 1 Gas
GridBeyond Limited GridBeyond Limited END027 No Unproven DSR CMU 4.947 1 DSR
GridBeyond Limited GridBeyond Limited END028 No Unproven DSR CMU 6.017 1 DSR
GridBeyond Limited GridBeyond Limited END029 No Unproven DSR CMU 5.817 1 DSR
GridBeyond Limited GridBeyond Limited END030 No Unproven DSR CMU 9.107 1 DSR
GridBeyond Limited GridBeyond Limited END031 No Unproven DSR CMU 4.347 1 DSR
GridBeyond Limited GridBeyond Limited END032 No Unproven DSR CMU 3.062 1 DSR
GridBeyond Limited GridBeyond Limited GBD001 No Proven DSR CMU 2.84 1 DSR
GridBeyond Limited GridBeyond Limited END014 No Unproven DSR CMU 3.446 1 DSR
GridBeyond Limited GridBeyond Limited END015 No Unproven DSR CMU 3.446 1 DSR
GridBeyond Limited GridBeyond Limited GBD010 No Existing Generating CMU 5.001 1 Gas
Welsh Power Group Limited Hull Reserve Power Limited HULL19 No Existing Generating CMU 19.756 1 Gas
Anesco Asset Management Limited Hulley Road Energy Storage Limited ADSHU2 Yes Unproven DSR CMU 17.228 1 DSR
Ethical Power Group Limited Huthwaite Solar Farm Limited HUT019 No Unproven DSR CMU 4.135 1 DSR
Welsh Power Group Limited Immingham Power Limited IM2019 No Existing Generating CMU 15.007 1 Gas
ENGIE UK HOLDING (SERVICES) LIMITED Industrial Energy Services Limited CES0C3 No Existing Generating CMU 5.38 1 Gas
Infinis Alternative Energies Limited Infinis Alternative Energies Limited AVELEN No Existing Generating CMU 4.329 1 Gas
Infinis Alternative Energies Limited Infinis Alternative Energies Limited AVELEF No Existing Generating CMU 3.818 1 Gas
Infinis Alternative Energies Limited Infinis Alternative Energies Limited OTGS19 No Existing Generating CMU 3.299 1 Gas
Infinis Alternative Energies Limited Infinis Alternative Energies Limited ADGS18 No Existing Generating CMU 3.455 1 Gas
Welsh Power Group Limited Irwell Power Limited IRWE19 No Existing Generating CMU 14.912 1 Gas
Keekle Power Limited Keekle Power Limited KeNur2 No New Build Generating CMU 11.935 1 Storage - Battery
E.ON UK Plc Kemsley CHP Limited DSK102 No Existing Generating CMU 54.391 1 Gas
Welsh Power Group Limited Kiln Power Limited KILN19 No Existing Generating CMU 15.006 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG35 No Existing Generating CMU 1.8 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG36 No Existing Generating CMU 1.8 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG45 No Existing Generating CMU 9.765 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG46 No Existing Generating CMU 1.8 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG47 No Existing Generating CMU 3.638 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG48 No Existing Generating CMU 3.306 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG49 No Existing Generating CMU 3.013 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG42 No Existing Generating CMU 1.863 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG29 No Existing Generating CMU 5.137 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG38 No Existing Generating CMU 5.378 1 Gas
KiWi Power Ltd KiWi Power Ltd KPEG44 No Existing Generating CMU 2.696 1 Gas
Page 8
Final Auction Results T-1 Auction 2019 (DY 20/21)
Parent Company Applicant Company CMU ID Capacity AG CMU Classification Capacity (MW) Duration (Years) Fuel Type
KiWi Power Ltd KiWi Power Ltd KPB104 No Existing Generating CMU 0.517 1 Storage - Battery
KiWi Power Ltd KiWi Power Ltd KPB005 No New Build Generating CMU 6.237 1 Storage - Battery
Anesco Asset Management Limited Larport Energy Storage Limited ADSLA2 Yes Unproven DSR CMU 16.797 1 DSR
Anesco Asset Management Limited Lascar Battery Storage Limited ADSLS1 Yes Unproven DSR CMU 17.228 1 DSR
Limejump Ltd Limejump Ltd DSR319 No Unproven DSR CMU 3.446 1 DSR
Limejump Ltd Limejump Ltd DSR321 No Unproven DSR CMU 3.446 1 DSR
Limejump Ltd Limejump Ltd DSR322 No Unproven DSR CMU 16.367 1 DSR
Limejump Ltd Limejump Ltd DSR304 No Proven DSR CMU 2.585 1 DSR
Limejump Ltd Limejump Ltd DSR300 No Proven DSR CMU 2.584 1 DSR
Limejump Ltd Limejump Ltd DSR301 No Unproven DSR CMU 3.455 1 DSR
Limejump Ltd Limejump Ltd EXL101 No Existing Generating CMU 13.239 1 Gas
Limejump Ltd Limejump Ltd EXL103 No Existing Generating CMU 3.015 1 Gas
Limejump Ltd Limejump Ltd EXL102 No Existing Generating CMU 7.47 1 Gas
Limejump Ltd Limejump Ltd EXL100 No Existing Generating CMU 2.52 1 Gas
Limejump Ltd Limejump Ltd DSR306 No Unproven DSR CMU 5.168 1 DSR
Limejump Ltd Limejump Ltd DSR310 No Unproven DSR CMU 3.446 1 DSR
Limejump Ltd Limejump Ltd DSR311 No Unproven DSR CMU 1.723 1 DSR
Limejump Ltd Limejump Ltd DSR313 No Unproven DSR CMU 1.723 1 DSR
Limejump Ltd Limejump Ltd DSR314 No Unproven DSR CMU 2.584 1 DSR
Limejump Ltd Limejump Ltd DSR317 No Unproven DSR CMU 5.168 1 DSR
Limejump Ltd Limejump Ltd DSR318 No Unproven DSR CMU 8.614 1 DSR
Welsh Power Group Limited Loddon Power Limited LODD19 No Existing Generating CMU 15.007 1 Gas
LOWER MINETY ENERGY LIMITED LOWER MINETY ENERGY LIMITED LMES01 No New Build Generating CMU 12.325 1 Storage - Battery
Welsh Power Group Limited Marden Power Limited MARD19 No Existing Generating CMU 18.711 1 Gas
MINETY BATTERY STORAGE LIMITED MINETY BATTERY STORAGE LIMITED MBSS01 No New Build Generating CMU 12.325 1 Storage - Battery
National Grid Holdings One plc (NGH1) NEMO LINK LIMITED NEMO19 Yes Existing Interconnector CMU 820 1 Interconnector
Welsh Power Group Limited Northwich Power Limited NORT19 No Existing Generating CMU 5.509 1 Gas
Welsh Power Group Limited Ogmore Power Limited OGMO19 No Existing Generating CMU 15.007 1 Gas
PARC ADFER LIMITED PARC ADFER LIMITED PaAd19 Yes New Build Generating CMU 14.588 1 Waste
G2 Energy Limited POWER UP GENERATION LIMITED PUG002 No Existing Generating CMU 5.494 1 Gas
PUTNEY POWER LIMITED PUTNEY POWER LIMITED Copse4 No Existing Generating CMU 8.073 1 Gas
Alkane Energy Limited Regent Park Energy Limited ARPMLT No Existing Generating CMU 4.046 1 Coal mine methane
Alkane Energy Limited Regent Park Energy Limited ARPDC1 No Existing Generating CMU 9.178 1 Gas
Alkane Energy Limited Regent Park Energy Limited ARP023 No Existing Generating CMU 5.042 1 Gas
Rock Energy Storage Limited Rock Energy Storage Limited ROCK20 Yes Proven DSR CMU 16.438 1 DSR
Suncredit Solutions Limited Rossington Power Limited ST-114 No Existing Generating CMU 3.799 1 Gas
Statera Energy Limited Saltholme North Power Limited SEL055 No New Build Generating CMU 47.481 1 Gas
Statera Energy Limited Saltholme South Power Limited SEL056 No New Build Generating CMU 47.481 1 Gas
Shovel Ready 6 Limited Shovel Ready 6 Limited amyjn2 No Existing Generating CMU 6.649 1 Gas
Shovel Ready 7 Limited Shovel Ready 7 Limited vent03 No Existing Generating CMU 8.073 1 Gas
Sittingbourne Power Limited Sittingbourne Power Limited SITTI2 Yes New Build Generating CMU 11.398 1 Gas
Speciality Steel UK Limited Speciality Steel UK Limited SS2019 No Proven DSR CMU 33.469 1 DSR
Welsh Power Group Limited St Asaph Power Limited STAS19 No Existing Generating CMU 15.007 1 Gas
Tata Steel UK Limited Tata Steel UK Limited TS19_3 No Proven DSR CMU 7 1 DSR
Tata Steel UK Limited Tata Steel UK Limited TS19_1 No Proven DSR CMU 8 1 DSR
Tata Steel UK Limited Tata Steel UK Limited TS19_4 No Existing Generating CMU 18.356 1 Gas
Teesside Hire Limited Teesside Hire Limited TEES19 No Existing Generating CMU 5.94 1 Gas
Page 9
Final Auction Results T-1 Auction 2019 (DY 20/21)
Parent Company Applicant Company CMU ID Capacity AG CMU Classification Capacity (MW) Duration (Years) Fuel Type
TYNEMOUTH ENERGY STORAGE LIMITED TYNEMOUTH ENERGY STORAGE LIMITED ENEL02 No Existing Generating CMU 3.065 1 Storage - Battery
UK Energy Storage Services Limited UK Energy Storage Services Limited BRES2X Yes Existing Generating CMU 2.452 1 Storage - Battery
Utility I Ltd Utility I Ltd LhoH19 Yes New Build Generating CMU 1.804 1 Gas
Veolia UK Limited Veolia UK Limited VES005 Yes Proven DSR CMU 2 1 DSR
Veolia UK Limited Veolia UK Limited ELIL03 Yes Existing Generating CMU 6.126 1 Gas
Veolia UK Limited Veolia UK Limited BHRLH5 Yes Existing Generating CMU 6.508 1 Gas
Veolia UK Limited Veolia UK Limited SGH005 Yes Existing Generating CMU 3.558 1 Gas
VITAL ENERGI SOLUTIONS LIMITED VITAL ENERGI SOLUTIONS LIMITED VIT201 No New Build Generating CMU 3.969 1 Gas
VITAL ENERGI SOLUTIONS LIMITED VITAL ENERGI SOLUTIONS LIMITED VIT207 No Existing Generating CMU 3.339 1 Gas
VITAL ENERGI SOLUTIONS LIMITED VITAL ENERGI SOLUTIONS LIMITED VIT208 No Existing Generating CMU 3.506 1 Gas
Welsh Power Group Limited Warrington Power Limited WARR19 No Existing Generating CMU 15.007 1 Gas
Welsh Power Group Limited Westwood Power Limited WEST19 No New Build Generating CMU 18.996 1 Gas
Welsh Power Group Limited Wharf Power Limited WHAR19 No Existing Generating CMU 15.007 1 Gas
Winchester Power Limited Winchester Power Limited WINP20 No Unproven DSR CMU 8.614 1 DSR
Welsh Power Group Limited Wolverhampton Power Ltd WOLV19 No Existing Generating CMU 15.007 1 Gas
Page 10