film schedule, risk assessment, contingency plan
Post on 31-Jul-2015
186 Views
Preview:
TRANSCRIPT
FILM SCHEDULE, RISK ASSESSMENT, CONTINGENCY PLANPre-Production
Film Schedule
Shot No.
Date and Time Location Action/Content Shot Types Costume/ Make Up
Iconography/ Props
Equipment
1 15/12/14—10.00 Bedroom Batrane awakes from nightmare
Close-up, Mid Shot, Extreme Close Up, Focus Pull.
Plan Brown T-Shirt
Photographs Dog Tags
Camera, Tripod
2 15/12/14--10.20 Bedroom Batrane prepares for run
Close-up, Mid Shot, Extreme Close Up, Tracking Shot
Running gear Photographs Dog TagsPDST Pill Bottles
Camera,Tripod
4 15/12/14—10.40 Street Batrane begins run
Close-up, Mid Shot, Extreme Close Up, Tracking ShotLong Shot, Over the Shoulder Shot
Running gear Dog Tags Camera, Tripod, Skate Board
8 15/12/14—11.05 Street Batrane suffers panic attack due to his flashbacks
Close-up, Mid Shot, Extreme Close Up, Tracking ShotLong Shot, Over the Shoulder Shot
Running Gear Dog Tags Camera, Tripod
6 04/01/15-10.00 Street Further shots of Batrane running
Close-up, Mid Shot, Extreme Close Up, Tracking ShotLong Shot, Over the Shoulder Shot
Running Gear Dog Tags Camera, Tripod
3 04/01/15-10.20 Kitchen Batrane leaves Paige in kitchen for run
Close up, Over the Shoulder Shot, Mid Shot
Running GearJumper and Leggings
Dog Tags Camera, Tripod
10 04/01/15-10.30 Kitchen Batrane attacks Paige in Post Traumatic State
Close up, Over the Shoulder Shot, Mid Shot, Extreme Close up, Focus Pull
Running GearJumper and Leggings
Dog Tags, Kitchen Knife
Camera, Tripod
5 04/01/15-11.25 Heathland Forest
Flashback of Batrane running
Close-up, Mid Shot Army Clothing Dog Tags, Prop Weapon
Camera, Tripod, Skate board
7 04/01/15-11.35 Heathland Forest
Flashback of Batrane fighting in war
Close-up, Mid Shot Army Clothing Dog Tags, Prop Weapon
Camera, Tripod, Skate board
9 04/01/15-11.45 Heathland Forest
Flashback of Sam Dawes
Close-up, Mid Shot Army Clothing Dog Tags, Prop Weapon
Camera, Tripod, Skate board
Risk AssessmentLocation Potential Hazards People who may be at Risk Precautions taken to
alleviate riskLevel of Risk
Bedroom Falling over, colliding with furniture, electrical sockets,
Actors, Director/Cinematographer
Area well lit, Risks made aware of to crew, Surfaces cleaned to prevent slipping
Low
Kitchen Slipping over, cutting oneself on equipment, electrical appliances, hitting head on sharp corners
Actors, Director/Cinematographer
Area well lit, Risks made aware of to crew, Surfaces cleaned to prevent slipping, Equipment stores securely
Low-Medium
Street Falling over, Dangerous weather, Cutting oneself on broken glass or sharp stone, Slippery terrain
Actors, Director/Cinematographer
Risks made aware of to crew, Protocol of ceasing filming during dangerous weather, Appropriate footwear to be worn, Area surveyed before filming to remove foreign objects
Medium
Forest Falling over, Dangerous weather, Cutting oneself on broken glass or sharp stone, Slippery terrain
Actors, Director/Cinematographer
Risks made aware of to crew, Protocol of ceasing filming during dangerous weather, Appropriate footwear to be worn, Area surveyed before filming to remove foreign objects
Medium
Contingency PlanPossible Issue: Actions to be Undertaken:
Bad weather during filming Reschedule filming to a later date. If impossible, move filming to indoors entirely, using a possible set or venue.
Locations unavailable Look at using other potential locations; this can include the New Forest (forest scenes) and Bedrooms in 15 Cogdean Walk (bedroom scenes)
Actors becomes ill/unavailable Look at drafting in understudy/back up actors:Sam Allen, Jason Palmer, Angel Beckford
Equipment becomes damaged Use back up camera and tripod, located at home. Both of these are readily available for use.
Props become unavailable Look at using back props. This can include substituting the prop gun for a prop knife. Back up Dog Tags are available. Back up army clothing also available if necessary.
top related