eosc 547: tunnelling & underground design 547: tunnelling & underground design ... cells...
Post on 25-Apr-2018
264 Views
Preview:
TRANSCRIPT
1
EOSC 547EOSC 547::
Tunnelling & Tunnelling & Underground DesignUnderground Design
Topic 3:
1 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Tunnelling Methods Tunnelling Methods ––Soft Ground TBMsSoft Ground TBMs
Excavation MethodsExcavation MethodsSelection of a tunnelling system (i.e. tunnelling method with/without additional measures, e.g. ground conditioning) involves choosing a method that is suitable for and
Consideration is generally given to:
compatible with the given ground and project constraints.
• the ground conditions and its variability;
• the geometry, diameter and length of the tunnel; th t l r nc f n rb
2 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
• the tolerance of nearby structures to ground movement;
• the consequences of ground losses;
• the tunnelling cost; • the safety of tunnel workers.
2
Cut & CoverCut & CoverFor shallow tunnels, cut & cover provides one of the most cost effective means of tunnelling (in terms of direct construction costs and operating economics, although incidental costs can change the balance completely).
Construction typically involves excavating a yp y gtrench and placing pre-cast concrete tunnel segments in the trench. The trench is then backfilled and the road restored.
3 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Bracing & ShoringBracing & ShoringShoring: involves any method used to prevent the collapse of ground surrounding an excavation, built top-down as excavation proceeds.
Sheet Piling
Lagging
Toronto (Sheppard Subway)
Shotcrete CaissonWall
4 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
3
RichmondRichmond--AirportAirport--Vancouver Rapid TransitVancouver Rapid Transit
Approximately 75% of the Vancouver segment of the Canada Line will be built by “cut and cover” method. cover method.
5 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Canada Line Canada Line –– Cut & CoverCut & CoverCut and cover is generally quicker than tunnel boring and more predictable in terms of scheduling.
6 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Plans are to vertically stack the two operating tunnels along Cambie St. in order to narrow the footprint of the cut & cover construction site and to help minimize disruption to traffic.
4
Canada Line Canada Line –– Cut & CoverCut & CoverIt is believed that most of the cut & cover tunnel will be excavated in tills with boulders, and in places, some marine sandstones, siltstones and mudstones.
However, near Queen Elizabeth park, the tunnel will encounter basalts, which will require blasting.
7 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Canada Line Canada Line –– Vancouver GeologyVancouver Geology
8 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Clague & Turner (2003)
5
Tunnel Excavation in Soft Ground ConditionsTunnel Excavation in Soft Ground ConditionsTunnelling in soft, water saturated ground began with Marc Brunel in the early 19th
century, when he invented the principle of shield tunnelling and undertook a contract to tunnel under the Thames.
His shield consisted of 12 independent cells with three floors in each cell, in which workers hand excavated the ground behind a secure wall of ‘poling boards’. One board would be removed to provide access for digging, after which it would be replaced and pushed forward by hydraulic jacks to re-engage the face support.
9 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Brunel’s shield was 22’3” high and 37’6” wide, and enabled 36 miners to work the tunnel face at one time. The brickwork built right behind the ‘shield’ served as an abutment for the whole frame. On average, progress was 8’-14’/week.
Harding (1981)
Tunnel Excavation in Soft Ground ConditionsTunnel Excavation in Soft Ground ConditionsStarted in 1825, flooding was a constant problem for Brunel in tunnelling under the Thames. In one such flood 6 men drowned. Brunel’s complaint to those offering advice on tunnelling in such difficult conditions, “In every case they make the ground to suit the plan and case they make the ground to suit the plan and not the plan to suit the ground”.
Completed in 1843, Brunel’s tunnel is still in fulluse as part of London’s Underground railway system, exactly as built!
10 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
James Greathead’s tunnel under the Thames (the 1869 Towers Subway) was built using a 7’1¾” (?) diameter circular shield propelled by screw jacks, that employed the first use of cast iron segments for the lining. Greathead’s circular shield became the model for later open-face shields.
6
Shield TunnellingShield TunnellingAdvantages of shield tunnelling in soft ground:
1.Tunnel construction can be performed as one step at its full dimensions.2.Constant support is provided to the advancing tunnel even though it takes
the form of a moving system.3.Omission of temporary support is compensated for by virtue of the er
& F
rith
(199
0)
p y pp p yimmediate installation of the permanent lining.
Whi
ttak
e
11 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Shield TunnellingShield TunnellingOpen- & Closed-Face Shields – When the tunnel face is free standing and does not require continuous support, the shield is operated in ‘Open Mode’. The face is mechanically supported by the cuttinghead while the flood control doors regulate muck flow from the face to the cuttinghead chamber. The excavated muck is rapidly extracted by the conveyor. With a closed-face, an airlock and bulkhead are used to allow the “excavation chamber” to be pressurized with compressed air are used to allow the excavation chamber to be pressurized with compressed air or a slurry to aid face support.
Open-face shields
Closed face
12 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Closed-face shields
7
Shield Tunnelling Shield Tunnelling –– Compressed AirCompressed AirJames Greathead solved the problem of containing groundwater during the construction of subaqueous tunnels in loose soil, by combining shield tunnelling with the use of compressed air during his 1886 construction of the London Underground.
This led to a considerable increase in the number of increase in the number of shield driven tunnels world-wide. At the beginning of the 20th century, the majority of the tunnels were built with Greathead shields.
13 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Shield Tunnelling Shield Tunnelling –– Compressed AirCompressed AirFactors to account for when tunnelling with compressed air:
• Air pressure must be kept in balance with the hydrostatic pressure; p ;
• Maximum pressure cannot exceed 4 bar (or 400 kPa), i.e. 3 bar excess pressure;
• Earth pressure cannot be resisted directly, it has to be withstood by natural or mechanical support;
• Ability to maintain pressure may be compromised by the air
bili f h d (i • Shorter working hours result from loss
Maidl et al. (1996)
14 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
permeability of the ground (i.e. leakage);
• Cover above the tunnel must be 1-2 tunnel diameters (depending on ground type) to avoid blow-outs;
of time during compression and decompression;
• Reduced performance of miners (danger of caisson’s disease);
• Increased danger of fire (due to increased oxygen content).
8
Slurry ShieldsSlurry ShieldsDue to problems regarding health and safety as well as operational aspects (in highly permeable ground, maintaining air pressure at the tunnel face is difficult), compressed air shields are being used less and less. Instead, slurry shields and earth-pressure balance shields are being favoured more.
Slurry shield operating principle:
• Tunnel face is supported by bentonite slurry (i.e. tunnel is free from compressed air);
• The slurry is mixed and pumped into a closed
15 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
pumped into a closed excavation chamber;
• The slurry enters the ground, sealing it (filter cake) and enabling pressure to be built up and balanced with the earth and water pressure.
Slurry ShieldsSlurry Shields
As the ground is excavated, it is mixed with the slurry in the excavation chamber. The ground/suspension mixture is then pumped to the surface. In a p pseparation plant, the slurry is sparated from the ground. New bentonite is added as required, and the fluid is pumped back to the tunnel face.
Overall, slurry shields provide a safe tunnelling method causing low
ttl t A li ti i ibl i ll
16 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Mai
dl e
t al
.(19
96)
settlements. Application is possible in all kinds of loose ground with/without groundwater. Disadvantages include the separation plant (cost, space, energy requirements) and environmental hazards related to tailings (non-separable bentonite slurry containing fines).
9
Earth Pressure Balance ShieldsEarth Pressure Balance ShieldsWith a growing percentage of fines, slurry shield tunnelling requires an increasing degree of sophistication and cost for separation (and increasing frequency of slurry renewal). Apart from the high costs and environmental hazards involved, the confined space in most major cities makes the installation of a separation plant on surface difficult. Such were the conditions encountered in the early 70’s in Japan, which led to the development of Earth-Pressure Balance shields (EPB). p ( )
EPB Shields: provide continuous support to the face by balancing earth pressure against machine thrust. As the cutterhead rotates and the shield advances, the excavated earth is mixed with foams in the cutterhead chamber
17 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
in the cutterhead chamber to control its viscosity. The pressure is then adjusted by means of the rate of its extraction (by screw conveyor).
Earth Pressure Balance ShieldsEarth Pressure Balance Shields
The key advantages of EPB Shields are that no separation plant is required and that the method is economically favourable in ground with a high percentage of silt/clay.
clay foam injector
When using EPB tunnelling mode, no bentonite and special treatment plants are necessary and the outcoming soil is
18 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
are necessary and the outcoming soil is nearly natural. If additives like Foam or Polymers are used, highly biodegradable versions exist which can be 95% destroyed after 28 days.
10
Earth Pressure Balance ShieldsEarth Pressure Balance Shields
19 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Maidl et al. (1996)
Canada Line Canada Line –– EPB Bored TunnelEPB Bored TunnelAn Earth Pressure Balanced system will be used on for the RAV. The TBM will be launched from 2nd Ave., advance under False Creek, along Davie and Granville St. A TBM exit shaft will be constructed on Granville south of Dunsmuir to extract the TBM. The TBM will then e brought back to 2nd Ave. to be launched again to construct the second bored tunnel.
20 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
11
Canada Line Canada Line –– EPB Bored TunnelEPB Bored Tunnel
Th TBM ill h
The TBM entry shaft.
The TBM will then move northwards excavating the 1st
tunnel.
21 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Canada Line Canada Line –– EPB Bored TunnelEPB Bored Tunnel
The TBM will then excavate under False Creek.
22 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
12
Canada Line Canada Line –– EPB Bored TunnelEPB Bored Tunnel
23 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Once the TBM reaches the end, it will be lifted out on an exit shaft, transported back to the entry shaft, so that it can excavate the 2nd parallel tunnel.
Canada Line Canada Line –– EPB Bored TunnelEPB Bored Tunnel
24 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
13
Canada Line Canada Line –– EPB Bored TunnelEPB Bored Tunnel
25 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Tunnel Excavation in Soft Ground ConditionsTunnel Excavation in Soft Ground Conditions
Open shields are favoured where the ground is free standing.
Cl d hi ld f d h th d i k Closed shields are favoured where the ground is very weak, such as soft clay, silt or running sand.
Slurry shields are favoured for water saturated sandy soils and gravels (<10% clay and silt content; e.g. running sand).
26 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
EPB shields are favoured for water saturated silty soils (>7% clay and silt content; <70% gravel content).
14
Tunnel Excavation in Soft Ground ConditionsTunnel Excavation in Soft Ground Conditions
27 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Special Cases Special Cases –– Immersed/Floating TunnelsImmersed/Floating Tunnels
Immersed tunnels can be constructed in otherwise difficult/expensive conditions (e.g. soft alluvial deposits characteristic of large river estuaries). They can also be designed to deal with the forces and movements in earthquake conditions.
28 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
Submerged floating tunnels allow for construction in extremely deep water, where alternatives are technically difficult or prohibitively expensive. Likely applications include fjords, deep, narrow sea channels, and deep lakes.
15
Lecture ReferencesLecture ReferencesBarla, G & Pelizza, S (2000). TBM Tunneling in difficult conditions. In GeoEng2000, Melbourne.Technomic Publishing Company: Lancaster, pp. 329-354.
Harding, H (1981). “Tunnelling History and My Own Involvement”. Golder Associates: Toronto,258pp.
Hudson, JA & Harrison, JP (1997). “Engineering Rock Mechanics – An Introduction to the Principles” Elsevier Science: Oxford 444pp. Elsevier Science: Oxford, 444pp.
Maidl, B, Herrenknecht, M & Anheuser, L (1996). “Mechanised Shield Tunnelling”. Ernst & Sohn:Berlin, 428pp.
NTNU (1995). “Tunnel: Blast Design”. Department of Building and Construction Engineering,Norwegian University of Science and Technology (NTNU), Trondheim, Project Report 2A-95.
NTNU-Anleggsdrift (1998). “Hard Rock Tunnel Boring: The Boring Process”. Norwegian University ofScience and Technology (NTNU), Trondheim, Project Report 1F-98.
Thuro, K & Plinninger, RJ (2003). Hard rock tunnel boring, cutting, drilling and blasting: rockparameters for excavatability In: Proc 10th ISRM Congress Johannesburg SAIMM: Johannesburg
29 of 29 Tunnelling Grad Class (2012) Dr. Erik Eberhardt
parameters for excavatability. In: Proc., 10th ISRM Congress, Johannesburg. SAIMM: Johannesburg,pp. 1227-1234.
UNIT-NTH (1995). “Tunnel: Prognosis for Drill and Blast”. Department of Building and ConstructionEngineering, Norwegian University of Science and Technology (NTNU), Trondheim, Project Report 2B-95.
Whittaker, BN & Frith, RC (1990). “Tunnelling: Design, Stability and Construction”. Institution ofMining and Metallurgy: London, 460pp.
top related