Environmental Monitoring Report Bi Annual Environmental Monitoring Report January – June 2015
AZE: Water Supply and Sanitation Investment
Program – Tranche 1 and 2
Prepared by AZERSU, Government of Azerbaijan for the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
Bi-Annual EMR No-5 January 01 - June 30-2015
Bi Annual Environmental Monitoring Report
Period: January01 – June30, 2015
REPUBLIC OF AZERBAIJAN
WATER SUPPLY AND SANITATION INVESTMENT PROGRAM
Tranche 1 Project
Project No. L-42408-ICB-2.01
- COMPLETION OF CONSTRUCTION OF WATER INTAKE FACILITIES AND
REHABILITATION OF PART OF WATER SUPPLY AND SEWERAGE NETWORKS IN
GOYCHAY TOWN – PACKAGE 1
Tranche 2 Projects
Project No. MFF032-T2-ICB-1.01
- COMPLETION OF CONSTRUCTION OF WATER INTAKE FACILITIES AND
REHABILITATION OF WATER SUPPLY AND SEWERAGE NETWORKS IN AGDASH
TOWN
Project No. MFF032-T2-ICB-1.02
- CONSTRUCTION OF WATER INTAKE FACILITIES AND REHABILITATION OF
WATER SUPPLY AND SEWERAGE NETWORKS IN BEYLAGAN TOWN
Project No. MFF032-T2-ICB-1.03
- COMPLETION OF CONSTRUCTION OF WATER INTAKE FACILITIES AND
REHABILITATION OF WATER SUPPLY AND SEWERAGE NETWORKS IN
GOYCHAY TOWN – PACKAGE 2
Prepared by AZERSU, Government of Republic of Azerbaijan for the Asian Development Bank
ABBREVIATIONS
ADB - Asian Development Bank
CSC - Construction Supervision Consultant
EA - Environmental Assessment
EA&OC - Environmental Assessment and Organization Chart
HSE - Health, Safety and Environment
EIA - Environmental Impact Assessment
EMP - Environmental Management Plan
EMS - Environmental and Monitoring Sector
EP - Environmental Protection
HIV/AIDS - Human Immune deficiency virus and Acquired immune Deficiency
syndrome
IBA - Important Bird Areas
IDB - Islamic Development Bank
IUCN - International Union for Control of Nature
LACMA - Law on administrative Control over Municipality Activity
MAC - Maximum Allowable Concentration
MENS - Ministry of Ecology and Natural Resources
MH - Ministry of Health
NGO - Non-governmental Organization
OP - Operation Policy
PIU - Project Implementation Unit
ERV - Environmental Regional Visit
RP - Resettlement Policy
SFF - State Forest Fund
SD - Sexual diseases
STP - Sewage Treatment Plant
TA - Technical Assessment
UNDP - United Nations Development Program
WR - Water Reservoir
WSS - Water Supply and Sanitation
Measurement units
°C - Celsius degree
km - kilometre
km/s - km/hour
km2 - Square kilometre
m - meter
m3 - Cubic meter
mg/l - Milligram per litre
mg∙ekv - Equivalent to milligram
m/san - meter/second
m3/san - cubic meter/second
mm - Millimetre
106m3 - Million cubic meter
mb - Millibar
Table of Contents
I. INTRODUCTION ...................................................................................................... 1
A. Construction works and project progress during 6 months............................................... 2
B. Ecological Management Team ........................................................................................ 3
C. Project organization ......................................................................................................... 4
II. ECOLOGICAL MONITORING.................................................................................. 5
D. Noise ............................................................................................................................... 5
E. Water quality ................................................................................................................... 5
F. Air quality ........................................................................................................................ 6
G. Flora and fauna ............................................................................................................... 6
H. Waste disposal ................................................................................................................ 9
I. Final Monitoring Report ................................................................................................... 6
III. ECOLOGICAL MANAGEMENT ............................................................................... 7
J. Site inspection ................................................................................................................. 7
K. Reporting ......................................................................................................................... 7
L. Non-compliance notices ................................................................................................ 13
M.Reformatory Action Plan ..................................................................................................... 7
N. Recommendations and grievances .................................................................................. 7
APPENDICES
Appendix 1: Monitoring data
Appendix 2: Photographs of the Project Sites
Appendix 3: Grievance records of the towns
List of Tables
Table 1: Project Organization ..................................................................................................... 4
Table 2: Monitoring Table .......................................................................................................... 6
I. INTRODUCTION
1. The Azerbaijan Water Supply and Sanitation Investment Program is being co-financed
by the Government of Azerbaijan and the Asian Development Bank through a multitranche
financing facility (MFF) involving several tranches.
2. Tranche 1 considers completion of construction of water intake facilities and
rehabilitation of part of water supply and sewerage network in Goychaytown.Construction of
remaining part of water supply and sanitation systems and wastewater treatment plant
inGoychay, and WSSsystems and WWTPs in AghdashandBeylagantowns are included into
tranche II, while construction of WSS systems and WWTPs in AghjabediandBalakanis included
into tranche III .
3. Goychay- “Completion of construction of water intake facilities and rehabilitation of
partofwater supply and sewerage networks in Goychay – Package 1” (L-42408-ICB-2.01) and
”Completion of water intake facilities and rehabilitation of water supply and sewerage networks
in Goychay - Package-2” (MFF032‐T2‐ICB‐1.03).The initial contract includes the construction of
water intake facilities – drilling 2 units of artesian wells, laying HDPEtransmission main (4175 m
Ø450 mm), installation of HDPE pipeline (1002 m Ø400 mm), two units of 2000 m3 water
reservoir, checkpoints and lavatory, including polyethylene water distribution network (54 300 m
length with different diameters) with fire hydrants and house connections and construction of
sewerage network from corrugated pipes (49 120 m length ) with manholes and house
connections.Both contracts were awarded to ATINAK Construction and Trading Co. in
November 2011 and September 2012. The construction works for Package 1 commenced on
January 2012, while for Package 2 on November 2012. The initial contract duration forPackage
1 was 540days.The contract duration for Package 1 was extended two times, for 200 days for
the first extension and 150 days for the second extension. The initial contract duration for
Package 2 was 548 days. The contract duration for Package 2 has been extended threetimes,
for 230 daysfor the first extension and 181 days for the second extension and 184 days for the
third extension
4. Agdas-The contract of “Completion of construction of water intake facilities and rehabilitation of water supply and sewerage networks in Agdash town (MFF 032-T2-ICB-1.01)” was awarded to ALKE InşaatSanayiveTicaret A.Ş. in July of 2012. The construction works commenced in November. The initial contract duration was 548 days. The contract duration for
Agdash was extended two times, for 243 daysfor the first extension and 240 days for the
second extension.
The initial contract consists of;
5. Water intake facilities:2 units of artesian wells(Depth: 140m, Diameter: Ø400 mm, also
water pumps),construction of 5 units of wellhead cubicles, installation of power lines and
transformer, construction of steel pipeline (271 m, Ø159x6 ) from water collection site to water
reservoirs field, construction of gravel roads (5,000 m²), construction of new pumps (3 set,
each 45 kW and 150 m³/hour, H=70 m), construction of two units of water reservoirs (each
2,000 m³).
6. Water Supply system:total length: about 134,000 m, pipe diameter: 110 - 400 mm,
length of roads to be reinstated: around 107,000 m², house connections: 7,616 units, fire
hydrants: 594 units, valves: 789 units
7. Valve chambers: 109units, pressure and chlorine measuring points: 5 units, crossings: 5
units.
8. Sewerage network: Total length: app. 121,000 m, pipe diameters: 200 - 800 mm, length
of roads to be reinstated: app. 110,000 m², crossings: 6 units.
9. Beylagan-The initial contract includes construction of water intake facilities – drilling 5
artesian wells, pumping systems, construction ofsteeltransmissionmain, laboratory, water
reservoirs, administrative building, workshop, checkpoints, lavatory, including water distribution
network 70905 m in length with fire hydrants and house connections and construction of
sewerage network from corrugated pipes 78828 m in length with manholes and house
connections. The contract was awarded by TTS Construction & Ludwig Pfieffer GmbH Co JV in
August 2012. The construction works commenced on November 2012.The initial contract
duration was 548 days. The contract duration for Beylagan was extended two times, for 243
daysfor the first extension and 365 days for the second extension.
10. This ecological monitoring report was prepared based on data for the months of
JanuarytoJune, 2015.
11. Ecological Impact Monitoring is performed according to Ecological Management Plan
prepared by Project Implementation Unit. The environmental impacts during construction are
indicated below:
1. Excavation
2. Land replacement
3. Pipe installation
4. Backfilling and compaction
5. Installation of asphalt/concrete roads
6. Road protection and other works
12. The following are monitored during project implementation:
1. Noise
2. Water quality
3. Air quality
4. Flora-fauna
5. Waste disposal
A. Construction activity and project progress during last six months
13. In Goychay–During last six months(January 01 – June 30), in “Tranche 1 project –
Completion of construction of water intake facilities and rehabilitation of part of water supply and
sewerage networksinGoychay – Package 1, the contractorhascompleted all works
andtemporary acceptance has been realized.
“Tranche 2 project – Completion of construction of water intake facilities and
rehabilitationofwater supply and sewerage networksinGoychay– Package 2” commencedonNovember 13, 2012, the works started in January of 2013. The contractor has
installed water lines Ø160 mm and Ø110 mm connected by valves, hydrants and fittings. In
addition, sewerage line with different diameters was installed. The works have beencompleted
around 95%.
14. InAghdash–Works in water and sewerage networks have been continued. The scope of the
contract has been changed and reduced by cancelling the middle part of the city
Water Network – excavation works, pipe lying, backfilling, and installation of fittings have been
continued. House connections have been constructed in parallel to pipe lying. During this period
the installation of water meters have been increased.
Sewerage network–excavation works, pipe lying, backfilling, and construction of inspection
manholes have been continued. House connections have been constructed in parallel to pipe
lying.
15. In Beylaqan–Works in water intake area, water and sewerage networks have been
continued in accordance with new approved projects.
Water intake area - The Contractor has mostly completed the water intake facilities such as
water wells, piping between water wells, water intake structure, 500 m3 two reservoirs and
pump station. The transmission main has already been completed and it is also connected to
the existing reservoirs. By rehabilitating the reservoirs and by constructing a new pump station
and installation new pumps into the pump station, water has pumped to the new network. By
this way the project objective has been realized.
Water network - excavation works, pipe lying, backfilling, and installation of fittings have been
continued. House connections have been constructed in parallel to pipe lying.During this period
the installation of water meters have been increased.
Sewerage network– excavation works, pipe lying, backfilling, and construction of inspection
manholes have been continued. House connections have been constructed in parallel to pipe
lying in sewerage network.
B. Ecological Management Team
16. Construction Specialist and Site Inspectors of Consultant assist Mr Abbas Əliyev, the
ecological expert of Azersu JSC, to perform monitoring of Ecological Management Plan.
The below mentioned are fulfilled by Ecological Management Team:
Inform contract parties, site workers, inspectors and other related personnel on
Ecological Management Plan;
Attend the site daily to control ecological process emerged during construction;
Review and implement Ecological Management Plan;
Inform contract parties about implemented works in order to solve the problems
raised during monitoring
C. Project organization
17. The Project Organization for above mentioned contracts are shown in the following
Table1.
Table 1: Project Organization
Project Employer Contractor Engineer
Goychay P1
L-42408-ICB-
2.01
Azersu JSC Atinak A.S. AYKO-ART-NKUK
Aghdash
MFF032-T2-ICB-
1.01
Azersu JSC AlkeInsaatSanayiveTicaret
A.S.
AYKO-ART-NKUK
Beylagan
MFF032-T2-ICB-
1.02
Azersu JSC TTSInsaat MMC and
Ludwig Pfeiffer JV
AYKO-ART-NKUK
Goychay P2
(MFF 032-T2-
ICB-1.03)
Azersu ASC Atinak A.S. AYKO-ART-NKUK
II. ECOLOGICAL MONITORING
18. In order to assess environmental impacts during construction works in Aghdash,
Goychay and Beylagan, site visits were conducted at different times to the areas with ongoing
construction-installation works. The monitoring revealed that the construction of water supply
and sewer systems in the downtown were accompanied by massive excavation of land. The
contractor plans work phases and takes necessary measures to manage excavated material
since it impedes normal movement of local people and vehicles.
19. Machinery with disturbing noise is applied at minimum. Dusty materials and other
wastes from construction are prevented through temporary fences and covers. In order to
prevent pollution of the downtown, the excavated materials are transported more through
alternative secondary roads, which are not considered the central streets of the town, rather
than the main roads of the town. There are not any cultural premises and archaeological
monuments in the project area. If the cultural and historical areas are spotted in the project
area in the future, appropriate measures will be taken with regard to the Environmental
Management Plan (EMP).
20. The contractors noted down to consider the health of contract parties, environment of
the construction site; manage noise and wastes; public grievance.
D. Noise
21. The contractors minimized the noise from construction works. All construction works
were carried out during unrestricted hours (09.00 to 18.00), excluding weekends and general
holidays. All heavy vehicles and mechanical equipment used for the purpose of the works
were fitted with exhaust silencers. No diesel heavy construction equipment is kept running idle
for more than five minutes. Special consideration have been provided to protect workers from
harmful and long exposures to noise from construction machinery such as wearing of earmuffs
for operators. The use of vehicles and mechanical equipment resulting in noise and vibration
is minimized in densely populated areas. There is no complaint about noise but it should be
kept under strict control.Listed grievances are connected with other issues.However,
residential buildings were damaged in Beylagan as a result of noise-vibration. By this way,
conducted regular monitoring of pollution should be kept under strict control.
E. Water quality
22. No construction works are conducted around any river side. The executed works were
apart from water resources and there was no pollution.All the works were implemented
considering minimization of sediment in water basin, prevention of wreckage, trees, natural
wastes, oil, diesel and hazardoussubstancesto enter the water basins.
23. Stable construction materials and damaged parts were covered to avoid loss and flow of
material. Storage sites are located at 200 m from water basins.
24. Natural drainage models were under control to minimize sludge disposal into rivers and
water basins as a result of construction. Construction works are nearly conducted in parallel to
existing system. Since existing water pipelines are very old, there are many accidents on
existing line during excavation works and they are eliminated in a very short period by the
Contractor. Accordingly, the water quality gets worse.
F. Air quality
25. Naturally, some wastes, dust from excavation and harmful gases from fuel used by
machinery affect air quality during construction. The construction site is watered especially in
hot and dry weather in order to prevent the dust. Temporary fence and covers are installed to
prevent spread of dusty materials and other wastes from construction. This method is applied
to minimize the dust. Speed limit for heavy construction vehicles was limited at 30 km/hour. All
the excavation, uploading/unloading works have been stopped when wind velocity is more
than 12 km/hour. All construction works were executed in such a way that will minimize if not
totally eliminate the spreading of dust or any inconvenience and nuisance to nearby
communities.
G. Flora and fauna
26. The environmental damage is almost minimized in this stage of construction.
H. Waste disposal
27. All solid wastes were properly packaged and disposed at the designated dumpsite of the
town. This site was determined by MENR. Waste containers were placed in every construction
site and camps. These containers are collected and disposed on a daily basis.
I. Final Monitoring Report
28. The Table 2 was prepared based on monthly report of Contractors of Trench 2. P1
project 'n Trench 1 is expired a year ago.
Table 2: Monitoring Table for the projects in Trench 2
Months (2015)
January
February
March April May June
Noise Under control
Under control
Under control
Under control
Under control
Under control
Water quality Satisfactory Satisfactory Satisfactory N/A N/A Satisfactory
Air quality Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory
Flora-fauna Protected Protected Protected Protected Protected Protected
Waste disposal Checked Checked Checked Checked Checked Checked
Public grievance
Health and safety N/A N/A
III. ECOLOGICAL MANAGEMENT
J. Site inspection
29. Official ecological inspectors of Project Implementation unit conducted daily site visits. In
addition, the consultants’ site inspectors were on site to observe safeguard measures. PMO’s environmental manager paid weekly visits to the construction site.
The names of Environmental specialists of each Contractor are;
Goychay, ATINAK, ElnurCaferov
Agdas, ALKE, Alay Azizov
Beylagan, TTS Ins., Amin Mammadov
K. Reporting
30. Contractors submitted monthly reports to the PMO describing their environmental
monitoring activities and health and safety management.
L. Non-compliance notices
31. Not any non-compliance notice has been issued in the project. The environmental team
of “ATINAK” and “AlkeInsaatSanayiveTicaret A.S” Companies of Turkey and “TTŞ İnşaat MMC And Ludwig Pfeiffer” company of Azerbaijan has not changed. The team is very well trained in preventing or minimizing environmental impacts and how to implement them according to their
management plan. They have not been warned for anything.
M. Reformatory Activity Plan
32. No reformatory activity has been performed during the report period, 2014.
N. Recommendations and grievances
33. During the reporting period, grievance letters of IlhamImanovand the other resident
IbrahimovMammadYunisoglu that live in R.Akhundov street,108 in Beylagan were received
by the construction company. Private residential buildings belonging to ImanovIlham and
IbrahimovMammadwere looked at and cracks were identified in the walls of their houses as
a result of the vibration during the construction. In order to calculate the damage to
IlhamImanovMaharramoglu who lives in R.Akhundov street,108 in Beylagan, the
Construction company applied toMinistry's State Agency for Construction Safety Control and
received opinions and recommendations. According to the recommendations the problems
will be solved soon.
10 people have been registered on the complaint in Goychay. The complaints mainly dealt
with not installation of sewer lines and meters and the coverage of roads with asphalt where
the work has done. One issue is resolved, others are expected to be resolved in the near
future.
39 complaints were registered in Agdash in connection with the non-provision of water with
line and elimination of sewage manholes and investigations were conducted at ways of
solving problems and most were resolved in short period, others are expected to be
eliminated.
Appendix 1: Monitoring Data For All Cities :Goychay, Agdash and Beylegan
№ Site Issue Recommended Implemented Note 1
Con
str
uction
site
Use of health-care items (protective glasses, gloves, cloth, shoes, helmet)
Availability of health-care matters in construction site
Health-care items to be provided by the contractor to the workers
Satisfactory
Temporary sites and signals for construction works
Information boards. Warning alarms, identification signs and other important signs should be provided along the pipe
Information boards and warning signals are to be installed during the construction
Satisfactory
Dust Watering the site in order to avoid the dust during vehicle and facility movement; Limiting the speed Covering the completed roads with asphalt
Though the site is watered regularly, there is dust problem in hot and dry weather in the areas not covered with asphalt; The speed is limited at 30 km/hour
Non Satisfactory(1)
Noise contamination
Minimization of noise from vehicle and facilities; Minimization of total construction noise
Use of noise eliminators for heavy vehicle and machinery; Construction activity creating much noise is minimized.
Satisfactory
Water pollution Provision of sediment syphons for erosion control
Barriers and siphons shall be installed in the places shown by Official Ecological Control
Satisfactory
Solid waste Provision of closed (with cap) waste boxes to the construction site; Dispose construction waste to determined site
Waste boxes were provided to each construction site; The waste is transported to the site determined MENR
Satisfactory
2
Con
str
uction
ca
mp
Water quality Provision of water tap in bathroom, lavatory, kitchen and canteen
Reservoir, bathroom, lavatory, kitchen, canteen are supplied with taps.
Satisfactory
Lavatory Provision of lavatory and bathroom with shower system.
Water is available in all the lavatories
Satisfactory
Transportation of sewage waters with septic cranes, its treatment and use for watering mine well
Camp drainage Provision of water drainage bear the ditch far from the camp Prevention of water stagnation in the camp
Water drainage is installed and water is disposed into the ditch. There is no water stagnation in the site
Satisfactory
Solid wastes Placement of waste bins in the camp and modernisation with cap and handles
Each room is provided with waste box When they are full, they are collected and transported.
Satisfactory
Fire-fighting items should be available in the camp and office.
Fire-fighting items which are used in emergency situations shall be visible
Firefighting items shall be visible.
Satisfactory
3
Ma
teria
l re
se
rve
ının
topl
anıld
ığıs
ahə
The dust will pollute the site full of materials
Provision of gravel to earth roads to avoid the dust
The earth is strengthened in the material storage sites. Dust was minimized.
Satisfactory
(1)This issue was solved by consultation with Contractor.
Appendix 3: Grievance records of the towns Records in Goychay :
№ Date/receiv
ing
grievances
Name/Employe
r’s contact number
Kind of
grievance
Categor
y
Place Situatio
n
waiting-
solved
Organi
zation
s
Further
comments
1 03.05.2015
direct
051 502 60 48 Controllin
g sewer
connectio
ns
Sewer M.Mura
daov
Dalan 2,
h 4
solved
2 06.06.2015
direct
Azadov İl a
050 592 63 95
No sewer Sewer Z.Bunya
dov
waiting
3 12.06.2015
direct
Ma ılov Mahi 050 465 72 69
No sewer
No water
Sewer
and
water
Xaqani
str.
H 2
waiting
4 15.06.2015
direct
Şı ali ev Etiba
050 304 77 22
No sewer
laying
Sewer Potu,
back of
Vusal
market
waiting
5 17.06.2015
direct
Abdullayev
Rüstəm
050 744 50 00
No water
meter
installatio
n
Water Z.Bunya
dov
waiting
6 21.06.2015
direct
İsma ılov Bəxtiyar
050 556 08 77
No
asphalt
laying
Asphalt Kurt
village
waiting solved
7 26.06.2015
direct
İsma ılov Azad
050 343 32 49
No meter Meter Ataturk
7, h 7
waiting
8 01.07.2015
direct
Əliyeva Raida
051 981 61 57
Water
problem
Habibi
str. 22
waiting
Records in Agdash :
№ Name /date The subject of
the grieavance
Address Situation Waiting/solved
1 Qadirov Mehman
01.06.2015
The old sewer
line was
damaged.
Samad
Vurgun,6
The work is
ongoing/
050 343 35 10
Solved
05.06.2015
2 Mammadov Intiqam
01.06.2015
There is no
water
connection.
There is no
sewer and
house
connection
Evez str.,
Opposite the
school
051 746 16 86 Solved
07.06.2015
3 Afandiyev Vidadi
Musayev Bahram
01.06.2015
No house -
water
connection
was given both
of them
Back of the old
hospital
050 314 47 52
050 367 85 75
Solved
07.06.2015
4 Ezmammadov Saffar New house,
but no water
connection.
Ibrahim
Qaradagli str.
051 313 81 00 Solved
07.06.2015