community meeting at new market elementary school feasibility study · 2016-07-05 · feasibility...
Post on 27-Jul-2020
1 Views
Preview:
TRANSCRIPT
FEASIBILITY STUDYSouth Montgomery Community School Corporation
April 12, 2016
Community Meeting at New Market Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Presentation Outline
School Facilities Review
Elementary Schools- January 26, 2016
Southmont Junior High and High School- February 16, 2016
* Site/Circulation
* Safety/Security
* Building Envelope
* Building Environment
* Building Interior/Systems
District-wide needs
Preliminary Costs
Questions and Answers
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Site/Circulation
1. Dual stripe for
handicap parking
2. Improve security
camera coverage
3. Selective playground
equipment
replacement /
improve accessibility
4. Replace sewage
treatment plant
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Building Envelope
1. Replace exterior doors
and windows
2. Replace main1995 roof
3. Create wind screen/
overhang at main entry
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Walnut Elementary School
Building Interior/Systems
1. Expanded secure entry
vestibule
2. Improve office visibility/
function
3. Renovate main restrooms
4. Repurpose music room
5. Combine music/ band
6. Would gain four classrooms
with 6th grade relocation
7. Consider potential for life
skills classroom
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
All Elementary Schools
Building Interior/Systems
1. Replace HVAC system
2. Selective technology
improvements
3. Finishes improvements
4. Replace chalkboards
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Site/Circulation
1. Improve control/flow at
drop-off/pick-up
2. Improve creek flow at
culvert to eliminate
basement flooding
3. Expand sidewalk for bus
loading
4. Selective playground
equipment replacement/
improve accessibility
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Building Envelope
1. Replace exterior doors
and windows
2. Replace 1998 shingle
and 2009 gym roofs
3. Add vestibule to main
entry
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Ladoga Elementary School
Building Interior/Systems1. Provide new secure entry
vestibule
2. Relocate administrative offices to
larger/more functional location
3. Repurpose existing office for small
group/other
4. Improve restroom ADA
compliance
5. Improve flexibility for team
collaboration
6. Selective kitchen equipment
replacement
7. Replace seating handrails/stage
curtain
8. Would gain one classroom with
6th grade relocation
* Generally improve acoustics in all
classrooms
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Site/Circulation
1. Create new bus loading
lot
2. Change existing bus
loading to parking
3. Selective playground
equipment replacement/
improve accessibility
4. Remove portable unit
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Building Envelope
1. Replace 1995 metal
roof and 1999
shingle roof
2. Resolve fascia/leak
problems
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
New Market Elementary School
Building Interior/Systems
1. Expanded secure
vestibule
2. Expanded secure office
waiting
3. Replace bleachers
4. Add second set of
restrooms
5. Improve serving line
flow/ replace seating
6. Renovate staff lounge
7. Add story areas
8. Would gain three
classrooms with 6th
grade relocation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont Junior High
Building Interior/Systems
1. Secure corridor near cafeteria
2. Repurpose Corp. Admin. to
accommodate 6th Grade
3. Repurpose lower level storage
for JH wrestling
4. Add time-out room at SE
classroom
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont Junior High
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont Junior High
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
Building Interior/Systems
1. Replace door hardware
as needed
2. New digital cameras
3. Replace 1996 HS and
2007 JH gym roofs
4. Remodel CTE, Woods
Lab, Ag./Hort. and
Culinary Arts
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Southmont High School
Campus Master Plan
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
District Needs
Administrative Offices
1. New freestanding facility
at JH/HS Campus
Transportation Center
1. New facility located at
JH/HS Campus
Administrative Offices
1. Provide fiber optic
connections from three
elementary schools
JH/HS Campus
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Project Cost
Site/Circ. Safety/Sec. Building Env. Building Int. Building Sys. Total
High School 5,696,500 95,000 487,200 1,410,500 7,689,200
Junior High School 45,000 281,350 326,350
Walnut ES 300,000 102,066 993,396 1,063,995 1,313,369 3,772,826
Ladoga ES 520,956 673,692 860,736 1,292,306 3,697,690
New Market ES 207,500 313,154 1,369,809 1,066,770 2,082,440 5,039,673
Administrative Offices 1,476,000
Transportation Center 3,731,250
District-wide Needs 926,640
Construction Costs 6,554,000 1,076,176 3,524,097 4,683,351 4,688,115 26,659,629
Soft Costs 6,664,907
Total Project Costs $ 33,324,537
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Schedule/Major Milestones
April 12 New Market ES Community Meeting
20 Ladoga ES Community Meeting
26 Walnut ES Community Meeting
June 13 Board Meeting- Final Study Presentation
SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION
Feasibility Study
top related