community airport partnership (cap) program project and … · 2019-01-10 · -rehabilitation of...

Post on 03-Aug-2020

1 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Maple Creek

Shaunavon

Swift Current

Leader

Eston

Kyle

Big River

Assiniboia

Gravebourg

Lucky Lake

Outlook

Kindersley

Luseland

Macklin

Unity

Rosetown

Biggar

Maidstone

North Battleford

Frontier

Shellbrook

Weyburn

Moose Jaw

Estevan

Carlyle

Oxbow

Kipling

Moosomin

Esterhazy

Yorkton

Humboldt

Wynyard

Birch Hills

MelfortTisdale

Kamsack

G:\GIS_Work\RWU_GIS\CAP\Cap.gws

Big River - $3,850 -Lighting upgrades

North Battleford - $651,404 -Lighting upgrades/engineer report -Runway rehibilitation -Rehabilitation of drainage system -Storm sewer replacement

Kamsack - $61,452 -Patch runway -Upgrade taxiway apron -Lengthen runway and lighting

Esterhazy - $273,356 -Asphalt overlay of runway, taxiway andapron -Beacon, tipdown,windsock, crack/slurryseal -Runway lighting

Moosomin - $9,631 -Rehabilitate and expand runway ends

Carlyle - $360,868 -Site survey and granular/runway paving -Runway extension & line painting -Runway edge lighting -Redesign WASS &Crack sealing -Widen taxi way & expand apron

Estevan - $378,152 -Lighting upgrades and runway surface rejuvenation -Repair runway cracks

Moose Jaw - $316,113 -Rehabilitate runway, taxiway and apron -Crack seal, lighting -Lighting wiring system -Taxiway crack sealing

Assiniboia - $55,546 -Repair major runway crack -AWOS -Engineering services report

Frontier - $62,259 -Rehabilitate runway cracks andtarmac -Repaint runway lines -Lighting upgrades

Swift Current - $401,927 -Asphalt upgrades and lighting -Primeter fencing -PAPIs -Pavement load ratings updates -Runway markings -Beacon refurbishment

Maple Creek - $136,290 -Sealing runway and tarmac -GPS -Repaint runway lines -Resurface tarmac

Lucky Lake - $54,312 -Rehabilitate runway -Repaint runway lines

Luseland - $55,234 -Rehabilitate runway cracks & line painting -Crackfilling deteriorating runway

Unity - $130,454 -Recap and extension of apron -Repave runway -Runway chip sealand asphalt patching

Wynyard - $45,678 -Lighting replacement/runway repairs

Humboldt - $90,136 -Rehabilitate runway -Runway and taxiway sealing -Engineering drainage and grading plan

Yorkton - $1,021,996 -Resurface apron and taxiway -Drainage system and runway rehabilitation -Runway surface and lighting repairs -Airside Fencing -Runway taxiway repairs -Line marking

Rosetown - $74,017 -Runway lighting -Crack and slurry seal runway -Repaint the runway lines

Shaunavon - $56,367 -Upgrade to AWOS system -Slurry Seal -Repaint runway lines

Kindersley - $93,499 -Repaving taxiway and apron - line painting -Drainage improvements -Pavement assessment and geotechnical -Crack sealing & beacon replacement -ARCAL navigation system -Upgarde runway lighting

Kipling - $106,299 -Runway crack sealing -Engineer study to assess runway and lighting -Taxiway and apron rehabiliation -Line painting

Weyburn - $332,133 -Engineering design -Hydraulic/drainage -Lighting, grading -Recap runway

Biggar - $74,485 -Runway Reparis -Paving airort apron & taxi areas

Gravelbourg - $225,427 -Runway/taxi lighting -Taxiway/apron repairs -Repave airstrip

Melfort - $22,396 -GPS

Birch Hills - $15,675 -Runway and apron crack sealling

Shellbrook - $211,214 -Reshape runway and improve drainage -Drainage repairs -Upgrade easterly half of runway -Crushed rock, levelling runway -Move lights

Tisdale - $47,673 -GPS/WASS -Replace lighting -Crack Sealing -Drainage imporvement

Kyle - $49,500 -Crack sealing

Leader - $50,000 -Runway + taxi pad crack sealing -Paint runway lines -Beacon

Maidstone - $24,386 -GPS/WAAS -Fencing

Project and Payment Summary

Community Airport Partnership (CAP) Program

2007/08-2016/17

Total CAP Payments - $5,718,451

Outlook - $20,720 -Replace runway lighting

Macklin - $64,052 -Crack Repair and resurface runway -Taxiway and apron

Oxbow - $18,500 -Land purchase for runway expansion

Eston - $123,450 -Rehabilitate runway